Safety control methods and related equipment for hydrostatic testing of long-distance pipelines
By constructing a virtual pipeline model using digital twin technology and the Internet of Things, and combining it with drones and sensor monitoring, intelligent and unmanned operation of long-distance pipeline hydrostatic testing has been achieved, solving the risk of high-pressure energy release and improving safety and efficiency.
Patent Information
- Application Number
- CN202611014524.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-09
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2046-07-09
AI Technical Summary
There is a risk of high-pressure energy release during the hydrostatic test of long-distance pipelines, which could lead to casualties and environmental disasters. Existing technologies are unable to achieve accurate measurement and intelligent monitoring, and cannot effectively prevent leaks or pipe bursts.
A virtual pipeline model is constructed using digital twin technology. Combined with the Internet of Things and big data analysis, the pipeline status is monitored in real time. Data is acquired through drones and sensors to achieve remote unmanned operation and automated safety control, including measures such as pressure grading, venting, monitoring and inspection, quality control, and energy release assessment.
It has realized risk pre-control, accurate measurement and remote unmanned monitoring of hydrostatic testing of long-distance pipelines, and transformed into an intelligent and unmanned operation mode, which has improved safety and efficiency and reduced the risks of manual operation.
Smart Images

Figure CN122524586B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of safety control for long-distance pipelines, and in particular to a safety control method and related equipment for hydrostatic testing of long-distance pipelines. Background Technology
[0002] As oil and gas field development extends into deeper layers, deserts, and oceans, long-distance pipelines face a development trend towards higher pressure, larger diameters, and higher steel grades (X80 and above). Hydrostatic testing is not only a strength test but also a comprehensive examination of pipeline materials, welding quality, and terrain adaptability. Because the testing process involves high-pressure energy release, the operation of large machinery, and complex terrain environments, leaks or pipe bursts can easily cause casualties or environmental disasters. Therefore, establishing a safety technology system based on risk pre-control, precise measurement, and intelligent monitoring is the core of safety management in current long-distance pipeline hydrostatic testing. Summary of the Invention
[0003] In view of this, this application provides a safety control method and related equipment for hydrostatic testing of long-distance pipelines to solve or partially solve the above problems.
[0004] The first aspect of this application provides a safety control method for hydrostatic testing of long-distance pipelines, applied to a central control system. The central control system is electrically coupled to a monitoring system. The method includes: constructing a virtual model corresponding to the long-distance pipeline in the central control system. The parameters used to construct the virtual model include at least the pipeline length, diameter, wall thickness, pipe material, number of bends, and elevation difference of the long-distance pipeline; determining the current stage of the hydrostatic test of the long-distance pipeline, the hydrostatic test being used to verify the pipeline's strength and sealing performance, the stages including water injection and venting, pressurization, early warning mechanism, emergency response, test judgment, and termination; acquiring relevant parameters of the long-distance pipeline through the monitoring system, and calculating predicted safety parameters of the long-distance pipeline based on the relevant parameters and the virtual model. The relevant parameters of the long-distance pipeline include the inner diameter of the long-distance pipeline, the length of the pipeline test section, and the test pressure. The predicted safety parameters include the total potential energy stored in the long-distance pipeline; acquiring relevant parameters of the long-distance pipeline through the monitoring system, and calculating predicted safety parameters based on the relevant parameters and the virtual model... The calculation of predicted safety parameters for long-distance pipelines further includes: obtaining the inner diameter of the pipeline, the length of the pipeline test section, and the test pressure; calculating the total volume of fluid involved in compression based on the inner diameter and the length of the pipeline test section; calculating the total potential energy stored in the pipeline based on the test pressure, the total volume of fluid involved in compression, and the bulk modulus of the liquid in the pipeline; determining the safety status of the pipeline and corresponding safety measures based on the predicted safety parameters and the current stage of the hydrostatic test; further, determining the safety status of the pipeline and corresponding safety measures based on the predicted safety parameters and the current stage of the hydrostatic test includes: in response to the total potential energy stored in the pipeline exceeding a first threshold and the current stage of the pipeline being a pressurization stage, determining the safety status of the pipeline as unsafe and triggering corresponding energy release preventive measures; wherein, the preventive measures include pressure grading, venting, monitoring and inspection, quality control, pressure detection, and energy release assessment.
[0005] In a second aspect, this application provides a safety control system for hydrostatic testing of long-distance pipelines. The safety control system is a central control system electrically coupled to a monitoring system. The safety control system includes: a model building unit configured to build a virtual model corresponding to the long-distance pipeline within the central control system. Parameters used to build the virtual model include at least the pipeline length, diameter, wall thickness, pipe material, number of bends, and elevation difference of the long-distance pipeline; a stage determination unit configured to determine the current stage of the hydrostatic test of the long-distance pipeline, including water injection and venting, pressurization, early warning mechanism, emergency response, test judgment, and termination stages; and a parameter acquisition unit configured to acquire relevant parameters of the long-distance pipeline via the monitoring system and, based on these parameters and the virtual model, calculate predicted safety parameters of the long-distance pipeline. The relevant parameters of the long-distance pipeline include the inner diameter, length of the test section, and test pressure. The predicted safety parameters include the total potential energy stored within the long-distance pipeline. The calculation of predicted safety parameters for long-distance pipelines using a virtual model further includes: obtaining the inner diameter of the pipeline, the length of the pipeline test section, and the test pressure; calculating the total volume of fluid involved in compression based on the inner diameter and the length of the pipeline test section; and calculating the total potential energy stored in the long-distance pipeline based on the test pressure, the total volume of fluid involved in compression, and the bulk modulus of the liquid within the pipeline. A safety control unit is configured to determine the safety status of the long-distance pipeline and corresponding safety measures based on the predicted safety parameters and the current stage of the hydrostatic test. This determination further includes: in response to the total potential energy stored in the pipeline exceeding a first threshold and the current stage of the pipeline being a pressurization stage, determining the safety status of the long-distance pipeline as unsafe and triggering corresponding energy release preventative measures; wherein the preventative measures include pressure grading, venting, monitoring and inspection, quality control, pressure detection, and energy release assessment.
[0006] This application provides a safety control method and related equipment for hydrostatic testing of long-distance pipelines. The method includes determining the current stage of the hydrostatic test, acquiring relevant parameters of the pipeline through a monitoring system, and calculating predicted safety parameters based on these parameters and a virtual model. Based on the predicted safety parameters and the current stage of the hydrostatic test, the method determines the safety status of the pipeline and corresponding safety measures. This method achieves risk pre-control, accurate measurement, and remote unmanned monitoring in hydrostatic testing of long-distance pipelines, fundamentally transforming the hydrostatic testing process from traditional manual operation to intelligent and unmanned operation. Attached Figure Description
[0007] To more clearly illustrate the technical solutions of the embodiments of this application, the drawings used in the embodiments of this application will be briefly introduced below. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort, and these are all within the protection scope of this application.
[0008] Figure 1 A schematic diagram of an exemplary electronic device 100 according to an embodiment of this application is shown.
[0009] Figure 2 A flowchart illustrating an exemplary safety control method for hydrostatic testing of a long-distance pipeline according to an embodiment of this application is shown.
[0010] Figure 3 An exemplary digital and intelligent procedure flowchart for hydrostatic testing of long-distance pipelines according to an embodiment of this application is shown.
[0011] Explanation of reference numerals in the attached figures: 100, electronic device; 110, memory; 120, processor; 130, computer program. Detailed Implementation
[0012] The technical solution of this application will be clearly and completely described below with reference to the embodiments of this application. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0013] It should be particularly noted that similar substitutions and modifications made to this application are obvious to those skilled in the art, and they are all considered to be included in this application. Those skilled in the art can obviously make modifications or appropriate alterations and combinations to the methods and applications described herein without departing from the content, spirit, and scope of this application to implement and apply the technology of this application. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments.
[0014] Long-distance pipelines, as vital arteries for energy transportation, are directly related to national energy security and public safety in terms of construction quality. Hydrostatic testing, a crucial process for verifying the overall strength of the pipeline, detecting leaks, and eliminating residual stress, is a high-risk operation. This application's embodiments systematically elucidate the entire safety technology system for hydrostatic testing of long-distance pipelines from multiple dimensions, including test preparation, media control, pressure grading, safety isolation, digital and intelligent safety monitoring, safety analysis and innovative methods, and emergency response. The aim is to achieve inherent safety through technological means and management innovation.
[0015] Traditional manual inspections can no longer meet the safety requirements of modern high-pressure pipeline testing. Therefore, this application incorporates Internet of Things (IoT) and big data analytics technologies, which are key to enhancing the innovation of safety technologies.
[0016] Traditional hydrostatic testing requires a large number of personnel to patrol the pipeline, read meters, and record data on-site. If a high-pressure pipeline bursts, the shockwave and flying debris can cause serious injuries or fatalities instantly. Furthermore, manual assessment of pressure changes and temperature effects is often delayed, making it difficult to detect potential hazards in advance. The core objective of the digital and intelligent safety monitoring method provided in this application is to keep people away from high-pressure areas, allowing machines and systems to replace humans in "seeing, hearing, judging, and acting."
[0017] Figure 1 A schematic diagram of an exemplary electronic device 100 according to an embodiment of this application is shown.
[0018] like Figure 1 As shown, the electronic device 100 includes a processor 120 coupled to a memory 110. The memory 110 stores at least one computer program 130, which is loaded and executed by the processor 120 to enable the electronic device 100 to implement any of the methods of the embodiments of this application. Specifically:
[0019] The electronic device 100 can vary considerably due to differences in configuration or performance. It may include one or more processors 120 (Central Processing Units, CPUs) and one or more memories 110. The one or more memories 110 store at least one computer program 130, which is loaded and executed by the one or more processors 120 to enable the electronic device 100 to implement the safety control method for hydrostatic testing of long-distance pipelines provided in this application embodiment. Of course, the electronic device 100 may also have wired or wireless network interfaces, a keyboard, and input / output interfaces for input and output. The electronic device 100 may also include other components for implementing device functions, which will not be elaborated upon here.
[0020] This application provides a remote, unmanned monitoring system. Before pressure testing, wireless pressure sensors, tilt sensors, and video surveillance are deployed at key nodes along the test section (e.g., high points, crossings, valve chambers) and connected to the network for testing. This monitoring system can transmit data such as pressure, temperature, displacement, and vibration back to the central control system (SCADA) at the command center in real time via a wireless network. Operators can monitor the entire line's status from their screens and remotely control the pressure pumps and pressure relief valves. Operators must remotely control the system from the pressure test command center via the central control system (SCADA). During pressure increase and stabilization, the test area (within 50-100 meters on either side of the pipeline centerline) is under fully enclosed, unmanned management, with all inspections conducted via drones equipped with thermal imagers.
[0021] When using the monitoring system, all personnel within a 50-100 meter radius on both sides of the pipeline must be cleared, and electronic fences must be erected. The operator initiates water injection and pressurization via a mouse click from the central control system at the command center. During pressurization, the central control system screen displays real-time pressure curves, temperature curves, and pipeline deformation. If any abnormality is detected (sudden pressure drop, excessive displacement), the system automatically issues an alarm and opens the emergency shut-off valve, releasing pressure within seconds. Drones are available at any time to scan the entire pipeline with thermal imagers to confirm no unauthorized entry or abnormal leaks.
[0022] In some embodiments, digital twin technology can be used to create a virtual model in a computer that perfectly corresponds to the physical pressure test section. Pressure, temperature, and flow data are injected in real time, and the model can predict changes in pipe wall stress distribution in real time. When the monitored data deviates abnormally from the model prediction (such as a sudden pressure drop or abnormal vibration), the system automatically triggers an emergency shut-off valve (ESD) to achieve "second-level" pressure relief, controlling risks at an early stage. In the computer, an identical "virtual pipeline" model (digital twin) is created based on the actual dimensions, material, and terrain of the pipeline. Then, real-time data (pressure, temperature, etc.) from field sensors are input into this virtual pipeline model, allowing it to synchronously "simulate" the stress and deformation trends at each current point. The results output by the virtual pipeline model are then compared with the real sensor data—if the deviation exceeds the normal range, it indicates a potential problem with the real pipeline, and the system issues an early warning.
[0023] When creating a virtual pipeline model, the pipe length, diameter, wall thickness, material, number of bends, elevation difference, etc., need to be input to build the virtual model. Next, historical data or small-scale pressure test data are used to teach the virtual model "how to react under normal conditions." During the test, sensor data is simultaneously sent to the virtual model. The virtual model calculates "what pressure and stress should be at this moment" based on physical laws and then compares it with the sensor's measured values. If the measured pressure is more than 5% lower than the model's predicted value, the system judges that the pipeline "may have a leakage problem"; if the measured stress is close to the material's yield strength, the system judges that the pipeline pressure is too high and "will be crushed." Once an emergency risk is determined (such as an impending pipe burst), the system automatically triggers the emergency shut-off valve, without waiting for manual intervention.
[0024] This application's embodiments are driven by digital and intelligent technologies. By constructing a technical system of "precise perception, intelligent early warning, automatic control, rapid execution, and safety assurance," it achieves a fundamental transformation of long-distance pipeline hydrostatic testing from traditional manual operation to intelligent and unmanned operation. Its core features are shown in Table 1:
[0025] Table 1: Intelligent Safety Measures for Long-Distance Pipeline Hydrostatic Testing from Preparation to Completion
[0026] Hydrostatic testing of long-distance pipelines is a crucial step in verifying pipeline strength and sealing. Under high-pressure testing conditions, a large amount of potential energy is stored within the pipeline. If this energy is explosively released due to pipeline defects, insufficient strength, or other unknown factors, it could cause multiple hazards, including projectile injuries, water jet impacts, and pressure wave impacts. This application's embodiments, based on quantitative analysis and formula derivation, systematically study the safety risks, prevention and control measures, and restricted area settings of hydrostatic testing, providing technical support for engineering practice.
[0027] Under test pressure, pipeline hydrostatic testing involves high levels of stored energy within the pipeline. All precautions must be taken to prevent explosive energy release. Unknown factors exist during pressure testing, such as pipeline damage, residual defects, insufficient pipeline strength, incorrect wall thickness, and fitting defects. These factors can lead to pipeline leaks or ruptures during any operation involving the use of internal pressure. If an underground pipeline ruptures during the test, the escaping fluid can accelerate backfill soil (including stones) into the air, creating projectiles that can cause property damage and personal injury. The embodiments of this application provide guidance for determining the initial velocity of such projectiles and the maximum projection distance of water as the test fluid.
[0028] This application does not address quantitative probabilities and risks, but it discusses qualitative issues and precipitating factors related to maximum projectile distance. When assessing and estimating prohibited areas for activities related to stress testing, precipitating factors and available controllable factors for the relevant projects and specific locations should also be considered.
[0029] Regarding energy risks and prevention in pressure testing: First, there's the analysis of stored energy levels (potential energy stored within a closed pipeline). During pressure testing, the potential energy stored within the pipeline system reaches dangerous levels. The potential energy stored in a pipeline under high pressure (i.e., released elastic energy) is a core indicator for assessing its potential destructive power. This energy primarily originates from the compressed liquid (water) and the elastic expansion of the pipe itself due to pressure.
[0030] The elastic potential energy (compression potential energy) of water inside a closed pipe. The calculation formula is derived based on the theory of fluid compressibility, and the expression is:
[0031]
[0032] Typically, the energy stored by liquid compression is much greater than the energy stored by tube expansion (approximately 95% vs. 5%). For simplicity and conservative estimation, the liquid compression energy is often used as a representative of the total stored energy.
[0033]
[0034] in, This represents the total potential energy stored in the pipe, measured in joules (J). It represents the potential energy stored in a compressed liquid, measured in joules (J). This represents the potential energy stored by the elastic deformation of the tube, measured in joules (J). Indicates test pressure (absolute pressure), unit: Pascal (Pa); The total volume of the fluid involved in compression is represented by (m³); D is the inner diameter of the pipe (m), which affects the stress and deformation of the pipe wall; t represents the pipe wall thickness (m), the thicker the wall, the more rigid it is, the smaller the deformation, and the less energy it stores; K represents the bulk modulus of the liquid, for water (K≈2.2×10⁻⁶). 9 Pa) is more than air (K≈1.4×10) 5 The energy storage density of a Pascal (Pa) is about 15,000 times lower, but still considerable. This represents the elastic modulus of the pipe material (for steel, ...). ≈2.1×10 11 Pa), unit: Pascal (Pa). It should be noted that absolute pressure (gauge pressure + atmospheric pressure) must be used in the calculation.
[0035] Total volume of fluid involved in compression The calculation formula is:
[0036]
[0037] Where D represents the inner diameter of the pipe, in meters (m); Indicates the length of the pipeline test section, in meters (m).
[0038] For example, a section = 10 km long, diameter D1 = 0.711 m, wall thickness t assumed to be 0.012 m (common X70 steel grade), P (test pressure) = 10 MPa. Stored energy is approximately 9.64 × 10⁻⁶ m. 7 Joules. This is equivalent to the energy released by the explosion of approximately 23 kilograms of TNT (trinitrotoluene) explosive (1 kg TNT ≈ 4.184 × 10⁻⁶). 6 J). If this energy were released instantaneously, it would be extremely destructive. It can be understood that the inner diameter of the pipe is the pipe diameter minus two wall thicknesses t.
[0039] If the stored energy is calculated using the above formula If the pressure exceeds a preset threshold (e.g., the first threshold), appropriate energy release preventative measures must be taken. It should be noted that the first threshold can be determined based on engineering experience. These preventative measures include: a) graded pressure ramping: using a "step-by-step pressurization method," stabilizing the pressure for 30 minutes at each stage, strictly following requirements (e.g., 25% / 50% / 75% / 90% / 100% in stages) to identify potential leaks or deformation. This avoids sudden pressure changes that could lead to energy accumulation imbalance; b) venting: ensuring complete removal of air from the pipeline to prevent the formation of compressible air chambers, which could cause pressure instability and "water hammer" effects, leading to two-phase flow hazards; c) monitoring and inspection: real-time monitoring of pressure-volume changes. Any abnormal pressure drop or volume increase may be a precursor to leakage or yielding. d. Quality Control: Strictly review pipe certificates, welding records, and non-destructive testing reports before pressure testing to ensure the strength of the pipeline body; e. Pressure Monitoring System: Install multiple calibrated pressure gauges (accuracy no less than Class 1) and pressure balances; f. Energy Release Assessment: Pressure testing should be conducted after a hazard assessment. The biggest problem in conducting a pressure test hazard assessment is the velocity and size of the jet and material that may be accelerated due to a malfunction, including debris and the explosion itself.
[0040] Regarding risk control for two-phase flow and temporary piping: During pressure testing, sections of piping may contain a mixture of air and water. This mixture is typically drained through temporary piping. This two-phase flow (slug flow) can exert extremely high pressure on the piping, especially at bends. Several fatal and serious injury incidents have occurred during drainage operations due to failures in temporary piping. Pressure surges in temporary crossings have also led to accidents.
[0041] If the pipeline is not adequately vented, residual air will dissolve in the water under high pressure. When the pipeline ruptures and the pressure drops sharply, the dissolved gas will rapidly precipitate, forming a two-phase flow of "gas-water". The air-water mixture generates slug flow during discharge, which has the following hazards: a) Unstable flow: triggering severe pressure fluctuations and impact loads, exacerbating pipeline vibration and rupture propagation; b) Accelerated projectiles: gas expansion provides additional thrust, giving projectiles such as soil and rocks higher initial velocities; c) Affected pressure relief efficiency: when the two-phase flow passes through the pressure relief valve, it reduces the valve's discharge capacity and delays pressure reduction; d) Impact loads on pipe fittings: elbows and tees are subjected to alternating stresses, easily leading to fatigue failure; e) Temporary pipeline vibration: may cause connection failure.
[0042] Temporary test pipelines shall be made of steel of the same or higher grade as the main pipeline, and shall be seamless steel pipes. Connection method: Welded connections shall be used, and welds shall be 100% radiographically inspected (Level II qualified). Threaded or flanged connections are prohibited in high-pressure sections (due to the high risk of leakage under high pressure). Discharge end design: Fixed tees or 90° elbows shall be installed for downward discharge to reduce backlash. Support and fixation: All temporary pipelines must be firmly supported and fixed to prevent displacement or breakage due to vibration, water hammer, or accidental impact. Sturdy supports shall be installed every 1.5-2 meters, and anti-thrust supports shall be added at corners to prevent whiplash caused by displacement vibration during faults. Isolation valves: Isolation valves shall be installed at the connection between the temporary pipeline and the main pipeline to quickly shut off the main pipeline in case of leakage. Protection: Temporary pipelines should be located as far away from areas of human activity as possible, or explosion-proof barriers shall be installed.
[0043] Regarding hazard assessment and failure mechanism analysis: When a pipeline ruptures, high-pressure water is rapidly ejected and mixes with the surrounding air to form a two-phase "gas-water" flow. The hazard originates from three aspects:
[0044] a. Projectile Kinetic Energy Damage: Assume the soil / rock above the rupture is accelerated and ejected by a high-pressure fluid. Based on Bernoulli's equation and a simplification of energy conversion, it is assumed that the fluid pressure potential energy is completely converted into the projectile's kinetic energy. Calculation formula (projectile initial velocity estimation - simplified model):
[0045]
[0046] in, Indicates the initial velocity of the projectile, in meters per second (m / s); The fluid pressure (gauge pressure) at the moment of rupture, in Pascals (Pa). : Density of soil / projectile, unit: kg / m³, typical value is 2000 kg / m³.
[0047] For example, the fluid pressure at the moment of rupture. = 10 × 106 Pa, At a velocity of 2000 kg / m³, the initial velocity of the projectile can reach 100 m / s (approximately 360 km / h) (e.g., the second threshold), which is equivalent to the velocity of a bullet and has lethality.
[0048] b. Water jet impact damage: Momentum mutation: When a pipe ruptures, water is released from its confined state, and its velocity suddenly increases from 0 to supersonic speed, forming a strong high-speed jet that can directly impact the human body or structures. This is based on the fluid mechanics orifice outflow theory (Torricelli's theorem) and the momentum theorem.
[0049] The formula for calculating jet velocity is:
[0050]
[0051] in, This indicates the jet exit velocity (i.e., jet speed), with units of meters per second (m / s). This represents the flow velocity coefficient (considering frictional losses, it is usually taken as 0.85-0.95). This indicates the density of water, 1000 kg / m³. This indicates the fluid pressure (gauge pressure) at the moment of rupture.
[0052] Water jet impact damage is the impact force of the jet on a vertical plane, and the formula for calculating this impact force is:
[0053]
[0054] Where F represents the impact force of the jet on the vertical plane, in Newtons (N); A represents the area of the rift, in square meters (m²). Assume it is a circular orifice with a diameter of d.
[0055] For example, suppose the tear diameter d = 0.1m (about 4 inches). =0.9. The jet velocity is as high as 127 m / s, and the impact force is about 12.7 tons (e.g., the third threshold), which is enough to knock a person away or cause serious internal organ damage and destroy most temporary structures.
[0056] c. Pressure wave damage: Cavitation effect: During the decompression process of high-pressure water, cavitation bubbles are generated. When these bubbles collapse, they release instantaneous high pressure (up to 5-10 times the test pressure), exacerbating secondary pipeline rupture. The pipeline ruptures instantaneously, and the pressure is released rapidly, generating a shock wave in the air.
[0057] Calculation formula (estimating peak overpressure): Empirical formulas for high-energy gas explosions (such as the TNT equivalent method) can be used as approximate references. Here, a more relevant empirical model of pipeline rupture shock waves (simplified from the Baker formula) is used:
[0058] Shock wave overpressure Relationship with distance r:
[0059]
[0060] in, This indicates the shock wave overpressure (unit: Pascal, Pa). Constants related to the medium and the properties of explosion (unit: ). The energy released by the explosion (i.e., the total potential energy stored in the pipe) represents the available energy (potential energy) carried by the fluid (water) rapidly released from the rupture point when the pipe ruptures (the unit is usually joules J); r represents the distance from the rupture point (the unit is meters, m).
[0061] For example, the pipeline test pressure P = 10 MPa, the pipeline diameter D1 = 0.711 m, and the pipeline length... =10000m, the shock wave overpressure at 100m from the explosion point is approximately 26.9kPa (e.g., the fourth threshold).
[0062] This is a pre-calculated example, derived from the formula:
[0063]
[0064] The pipe's diameter and length are not specified here, but The representative is energy, and the formula is:
[0065]
[0066] Here, V represents the volume of the pipeline test section (i.e., the total volume of the fluid involved in compression), formula:
[0067]
[0068] This formula originates from the shock wave attenuation model of a point-source explosion in explosion mechanics (similar to TNT equivalent estimation). At the instant a pipe ruptures, the high-pressure water rapidly expands and does work; the released energy E can be approximately estimated using the following two methods:
[0069] The formula for potential energy (i.e., the total potential energy stored in the pipe) based on fluid compressibility (more accurate, applicable to water) (same as the "Stored Energy Level Analysis Formula" above):
[0070]
[0071] in, Indicates the test pressure (absolute pressure). This represents the total volume (m³) of the fluid involved in compression. Note: This is usually not the volume of the entire pipe section, but rather the volume of fluid that can flow towards the rupture point within the characteristic time of pressure wave propagation, approximately the pipe cross-sectional area multiplied by a certain length (e.g., several tens of times the pipe diameter). This is a crucial and conservative estimation parameter. K represents the bulk modulus (Pa) of the liquid.
[0072] In applied thermodynamics, isothermal expansion does work, based on a simplified formula for the work done during isothermal expansion:
[0073]
[0074] Where E is the released energy (i.e., the total potential energy stored in the pipe) (unit: joule, J). The average pressure during the expansion process (unit: Pascals, Pa) is usually taken as the average of the initial pressure and the final pressure. This refers to the volume change of a fluid during expansion (unit: cubic meters, m³), that is, the increase in volume when it expands from high pressure to atmospheric pressure.
[0075] formula This indicates that the shock wave overpressure (ΔP) is directly proportional to the cube root of the released energy and inversely proportional to the distance (r). (Coefficient) It depends on the propagation medium (air or water) and the rupture geometry.
[0076] This formula is used to estimate the overpressure of shock waves (pressure waves) at medium to long distances to assess the risk of damage to people's auditory system, lungs, building glass, etc.
[0077] For the near field (such as within a few meters of the rupture), the situation is extremely complex, with fluid jets and debris impacts being the main hazards, and this formula is not applicable.
[0078] d. Risk probability assessment
[0079] Fault tree analysis: Taking "pipeline pressure test rupture" as the top event, it is decomposed into intermediate events and basic events such as "material defect", "welding defect", and "pressure runaway". The probability of the basic events is estimated by historical data, and the probability of the top event is obtained by combining the results.
[0080] Historical data: According to industry databases (such as PARLOC), modern pipelines constructed and tested according to regulations have an extremely low probability of catastrophic rupture during strength testing (<10). -3(Short-term pressure test), but the probability of localized leaks is relatively high. The main risks are concentrated in welds, fittings, and temporary systems. It should be noted that the PARLOC (Pipeline and Riser Loss of Containment) database is the most authoritative statistical database of North Sea subsea pipeline leaks in the global oil and gas industry. Its core purpose is to identify potential hazards in operating pipelines and quantify historical loss frequencies (i.e., leakage or rupture frequencies), providing data support for pipeline safety assessments.
[0081] Conclusion: Although the overall probability of failure is low, the consequences are extremely serious, and considering factors such as personnel density and environmental sensitivity, the highest level of protective measures must be implemented.
[0082] Restricted area setting and influencing factors; calculation method for restricted area radius; basic projection distance formula derived from motion analysis of projectiles during pipeline rupture and accident data regression (applicable to buried pipelines):
[0083]
[0084] Where R is the radius of the restricted area (unit: meters, m). For soil type coefficients (dimensionless, 1.0 for sandy soil, 0.7 for clay, and 1.3 for rock). This is the burial depth coefficient (dimensionless, depending on the ratio of burial depth to pipe diameter; the coefficient decreases as burial depth increases (1.0-2.0)). Test pressure (rupture point pressure, i.e., gauge pressure) (unit: Pascal, Pa). D1 is the pipe diameter (unit: meter, m). The length of a pipe rupture (unit: meter, m) is usually taken as the possible axial length of the rupture or the length of the pipe segment. Typical stone mass (unit: kilogram).
[0085] According to the above formula: =10MPa, D1 =0.711m, =0.1m、 =10kg (hypothetical) =1.0 (sand) =1.0 (burial depth / pipe diameter ratio < 1.0); when the rupture length L = 0.1m, the restricted area radius R ≈ 112.4m.
[0086] Analysis of the impact of backfill type: Sand backfill: Maximum projectile distance, stones achieve high initial velocity. Clay backfill: High viscous resistance, projectile distance reduced by 30-40%. Graded crushed stone: Maximum stone size determines maximum projectile mass. Overburden depth: Deeper overburden layer has a stronger binding effect on projectiles, but may increase projectile size. Loose sand produces more projectiles that travel farther than hard clay.
[0087] Analysis of the impact of fracture location: 10 o'clock - 2 o'clock position: maximum horizontal ejection distance. 6 o'clock position: mainly upward ejection, horizontal distance halved. 12 o'clock position: virtually no horizontal ejection, mainly vertical ejection. Fracture mode and direction: longitudinal tearing is more dangerous than circumferential fracture; ejection direction affects the shape of the hazardous area.
[0088] Regarding the accumulation of air at high points, when the air accumulation point ruptures, the projectile characteristics are similar to those of a pneumatic pressure test:
[0089]
[0090] According to industry databases (such as PARLOC), barometric testing The bursting and ejection distance is determined by the hydrostatic test. 2.5 times that of [previous data]. It should be noted that the PARLOC (Pipeline and Riser Loss of Containment) database is the most authoritative statistical database of North Sea subsea pipeline leakage accidents in the global oil and gas industry. Its core purpose is to identify potential hazards in operating pipelines and quantify historical loss frequencies (i.e., leakage or rupture frequencies), providing data support for pipeline safety assessments.
[0091] The hydrostatic test setup is designed to minimize cavitation within the tube. Failures at these locations can lead to excessive cavitation, potentially causing the maximum calculated throwing distance to approach the pneumatic test distance. Therefore, careful attention must be paid to venting to reduce the amount of air present within the tube.
[0092] Other influences include pressure and pipe diameter: positively correlated, these are the main factors affecting energy and projectile velocity. Environment: wind speed and terrain (mountains, plains) affect projectile impact point and jet diffusion.
[0093] It should be noted that regarding the calculation of E: In actual engineering safety assessments, the estimation of energy E is often the most conservative. Sometimes, the total potential energy of the entire test pipe section under the test pressure is simply taken as E, which leads to a very large calculated exclusion radius. A more reasonable approach is to combine pipe fracture mechanics to estimate a possible rupture length (L), and then take the fluid energy within that length of pipe section as E. Specific methods should refer to relevant industry standards or be based on historical failure data.
[0094] The two formulas mentioned above (pressure wave, projection distance) are highly simplified engineering estimation models. They provide a quick and conservative reference for delineating the initial safety exclusion zone. The final exclusion zone boundary still needs to be determined through a professional, risk-based assessment, taking into account the specific terrain, obstructions, and location of residential areas, and incorporating a safety margin.
[0095] Safety first principle: Regardless of the calculated theoretical distance, strict on-site control must be implemented during stress testing to ensure that all unrelated personnel are evacuated to a safe command post outside the calculation restricted area, and the test section is remotely observed through monitoring equipment.
[0096] In one specific embodiment, based on historical accident statistics, the average actual launch distance is approximately 45-55% of the theoretical maximum. 90% of projectiles fall within 0.7Rmax. A restricted area radius of 1.2 × Rmax is recommended.
[0097] This application also provides the following security recommendations:
[0098] I. Personnel Training Requirements
[0099] Test personnel should understand the stored potential energy, the effects of the explosion release, and anticipate these effects when planning tests and setting up test sites.
[0100] Operators: Training in equipment operation, emergency response, and signal recognition.
[0101] Assessment and certification: Candidates must be certified to work, and each project requires separate assessment and retraining.
[0102] II. Written Procedure Requirements
[0103] Safety requirements that should be included in pressure testing procedures:
[0104] Pre-test checklist: Key safety checkpoints.
[0105] Boosting procedure: Boost the voltage in at least multiple stages, maintaining each stage for 30 minutes.
[0106] Emergency procedures: a three-tiered response mechanism.
[0107] III. Contents of Hazard Assessment
[0108] A written hazard assessment must include:
[0109] (a) Hazard identification: based on Hazard and Operability Analysis (HAZOP).
[0110] (b) Risk quantification: Failure Mode and Effects Analysis (FMEA) or Fault Tree Analysis is used.
[0111] (c) Control measures: engineering controls, management controls, and personal protective equipment.
[0112] IV. Operational Procedures
[0113] (a) Design phase: Conduct quantitative risk analysis to determine the theoretically prohibited area. Prioritize segmented pressure testing to reduce the energy storage capacity of a single segment.
[0114] (b) Construction phase: Strictly adhere to welding and testing procedures. Ensure thorough venting. Use certified pressure testing equipment and instruments.
[0115] (c) Before pressure testing: Prepare a detailed pressure testing plan and emergency response plan, and conduct a thorough briefing for all personnel. Accurately calculate and set up restricted areas.
[0116] (d) During pressure testing: Implement closed management and strictly prohibit unauthorized personnel from entering. Remotely monitor pressure and flow. Install explosion-proof shelters in critical areas (near the pressure test head and temporary pipelines).
[0117] (e) Emergency Response: Establish clear emergency depressurization procedures. Equip the area with medical rescue teams and equipment. Communicate with local emergency services in advance.
[0118] It is recommended to establish a restricted area around the pipeline test section and prohibit unauthorized personnel from entering during the test operation.
[0119] (a) Physical isolation: The calculated restricted area shall be completely closed off using fences, warning tapes and roadblocks, and a clear safety warning sign shall be set up every 50 meters.
[0120] (b) Access control: A single registration checkpoint shall be established, and all personnel entering the area must be authorized, registered and informed of emergency signals and evacuation routes.
[0121] (c) Clearance and Patrol: Before pressurization, security personnel will thoroughly clear the restricted area, removing all personnel and animals. During pressurization, continuous patrols will be conducted around the perimeter.
[0122] (d) Communication and early warning: Establish a reliable wireless communication network. Early warnings will be given in advance through methods such as horn sounding during each stage of voltage boosting, stabilization, and depressurization.
[0123] (e) Time range: from the start of pressurization until the pressure is completely released.
[0124] The safety of hydrostatic testing for long-distance pipelines is based on systematic engineering analysis and rigorous process control. Key conclusions are as follows:
[0125] a. Energy risk is controllable: Energy storage levels can be reduced by 2-3 orders of magnitude through hydrostatic testing (rather than air pressure).
[0126] b. Scientific setting of restricted areas: Based on theoretical calculations and actual data, the restricted area radius with a safety factor of 1.2 can provide sufficient safety margin.
[0127] c. Strict process management: The whole-process quality control of the test head from design, manufacture, installation to testing is the foundation of safety.
[0128] d. Sufficient emergency preparedness: A complete emergency response plan and response mechanism is the final safety barrier.
[0129] e. Recommendations for practical engineering applications:
[0130] Adopt a risk-based approach to determine specific safety measures.
[0131] Establish a pressure test database to continuously improve safety standards.
[0132] Although the probability of rupture can be reduced to an extremely low level through strict quality control and standardized operation, safety management and control must never be relaxed due to its risk characteristics of low probability and high consequence. The core conclusion of this analysis is that "energy isolation" and "distance protection" must be taken as the primary safety strategies. That is, on the one hand, technical and management measures shall be taken to prevent accidental energy release; on the other hand, a sufficiently large restricted safety zone must be established and strictly implemented based on scientific calculation and the conservative principle, to ensure that all irrelevant personnel and key facilities are located outside the potential hazard area.
[0133] The safety guarantee of the hydrostatic test is a systematic project, which relies on rigorous design, qualified materials, standardized construction, scientific schemes, thorough implementation and the awareness of safety prudence of all personnel. Negligence in any link may lead to catastrophic consequences. The calculation results in this report provide a key quantitative basis for formulating a specific pressure test safety plan. Through the above systematic measures, the risk of the hydrostatic test for long-distance pipelines can be reduced to the level of As Low As Reasonably Practicable (ALARP), so as to ensure the safety of personnel, environment and assets.
[0134] Figure 2 shows a schematic flow chart of an exemplary safety control method for hydrostatic testing of long-distance pipelines according to an embodiment of the present application. The method can be applied to a central control system, which is electrically coupled to a monitoring system, as shown Figure 2 shown in the figure, the method may include the following steps.
[0135] In step 202, a virtual model corresponding to the long-distance pipeline is constructed in the central control system, and the parameters used for constructing the virtual model at least include the pipeline length, pipe diameter, wall thickness, pipeline material, number of elbows and elevation difference of the long-distance pipeline.
[0136] In step 204, the current stage of the hydrostatic test of the long-distance pipeline is determined, and the stages include water injection and exhaust, pressure boosting, early warning mechanism, emergency disposal, test judgment and final stage.
[0137] In step 206, relevant parameters of the long-distance pipeline are obtained through the monitoring system, and the predicted values of safety parameters of the long-distance pipeline are calculated based on the relevant parameters and the virtual model.
[0138] In some embodiments, the inner diameter of the long-distance pipeline, the length of the pipeline test section, and the test pressure are obtained; the total volume of the fluid involved in compression is calculated based on the inner diameter of the long-distance pipeline and the length of the pipeline test section; and the total potential energy stored in the long-distance pipeline is calculated based on the test pressure, the total volume of the fluid involved in compression, and the bulk modulus of the liquid in the long-distance pipeline.
[0139] In step 208, the safety status of the long-distance pipeline and corresponding safety measures are determined based on the predicted values of safety parameters and the current stage of the hydrostatic test of the long-distance pipeline.
[0140] In some embodiments, in response to the total potential energy stored in the long-distance pipeline being greater than a first threshold and the current stage of the long-distance pipeline being a pressurization stage, the safety status of the long-distance pipeline is determined to be unsafe and corresponding energy release preventive measures are triggered; wherein, the preventive measures include pressure grading, venting, monitoring and inspection, quality control, pressure detection and energy release assessment.
[0141] In some embodiments, the fluid pressure at the moment of rupture of the long-distance pipeline is obtained; the kinetic energy damage of the projectile is calculated based on the fluid pressure and the density of the soil / projectile; and an emergency shut-off valve on the long-distance pipeline is triggered in response to the projectile kinetic energy damage being greater than or equal to a second threshold.
[0142] In some embodiments, the fluid pressure at the instant of the rupture of the long-distance pipeline is obtained; the water jet impact damage is calculated based on the fluid pressure and the density of water; the impact force of the water in the long-distance pipeline is calculated based on the water jet impact damage, the density of water and the preset pipeline rupture area; and an emergency shut-off valve on the long-distance pipeline is triggered in response to the impact force of the water in the long-distance pipeline being greater than or equal to a third threshold.
[0143] In some embodiments, the energy released by the explosion of the long-distance pipeline and the distance from the rupture point are obtained; pressure wave damage is calculated based on the energy released by the explosion, the distance from the rupture point, and constants related to the medium and the nature of the explosion; and an emergency shut-off valve on the long-distance pipeline is triggered in response to the pressure wave damage being greater than or equal to a fourth threshold.
[0144] In some embodiments, the fluid pressure, pipe diameter, pipe rupture length, and burial depth coefficient of the long-distance pipeline at the moment of rupture are obtained; the restricted area radius of the long-distance pipeline is calculated based on the fluid pressure, pipe diameter, pipe rupture length, rock mass, soil type coefficient, and burial depth coefficient; and an emergency shut-off valve on the long-distance pipeline is triggered in response to the detection of relevant personnel within the restricted area radius.
[0145] This application also provides a safety control system for hydrostatic testing of long-distance pipelines, the specific technical solution of which is as follows:
[0146] The model building unit is configured to build a virtual model corresponding to the long-distance pipeline in the central control system. The parameters used to build the virtual model include at least the pipeline length, pipe diameter, wall thickness, pipe material, number of bends, and elevation difference of the long-distance pipeline.
[0147] The phase determination unit is configured to determine the current phase of the hydrostatic test of the long-distance pipeline, which includes water injection and venting, pressurization phase, early warning mechanism, emergency response, test judgment and closing phase.
[0148] The parameter acquisition unit is configured to acquire relevant parameters of the long-distance pipeline via the monitoring system, and calculate the predicted values of safety parameters of the long-distance pipeline based on the relevant parameters and the virtual model.
[0149] The safety control unit is configured to determine the safety status of the long-distance pipeline and corresponding safety measures based on predicted safety parameters and the current stage of the hydrostatic test of the long-distance pipeline.
[0150] It should be noted that the beneficial effects of the safety control system for hydrostatic testing of long-distance pipelines provided in the above embodiments are the same as those of the above-described safety control method for hydrostatic testing of long-distance pipelines, and will not be repeated here. Furthermore, the system provided in the above embodiments is only illustrated by the division of the above functional modules. In practical applications, the above functions can be assigned to different units as needed, that is, the system can be divided into different units according to the actual situation to complete all or part of the functions described above. In addition, the system and method embodiments provided in the above embodiments belong to the same concept, and their specific implementation process is detailed in the method embodiments, and will not be repeated here.
[0151] An embodiment of this application provides a computer-readable storage medium storing at least one computer program, which is loaded and executed by a processor to enable a computer to implement any of the above methods.
[0152] Alternatively, the computer-readable storage medium may be a read-only memory (ROM), a random access memory (RAM), a compact disc read-only memory (CD-ROM), magnetic tape, a floppy disk, and an optical data storage device, etc.
[0153] In an exemplary embodiment, a computer program product or computer program is also provided, which includes computer instructions stored in a computer-readable storage medium. A processor of an electronic device reads the computer instructions from the computer-readable storage medium and executes the computer instructions, causing the electronic device to perform any of the methods described above.
[0154] Figure 3 An exemplary digital and intelligent procedure flowchart for hydrostatic testing of long-distance pipelines according to an embodiment of this application is shown. Figure 3 This demonstrates digital and intelligent safety monitoring, driven by digital and intelligent technologies. By constructing a technical system of "precise perception, intelligent early warning, automatic control, rapid execution, and safety assurance," it has achieved a fundamental transformation of long-distance pipeline hydrostatic testing from traditional manual operation to intelligent and unmanned operation mode.
[0155] like Figure 3As shown, the first step is to develop and approve the pressure test plan, install and calibrate equipment and instruments, and deploy and test sensors and communications. The safety isolation zone can be set up using an electronic fence and video surveillance. Then, personnel are cleared from the area, and a drone patrol is conducted to determine if it is a closed, uninhabited zone. If the determination is negative, personnel are remotely broadcast to evict them; if positive, water injection is remotely initiated, and automatic venting and flow rate and pressure are monitored at the end of the injection. After water injection, thermal balancing is performed for 24-96 hours. System self-checks can be performed using sensors, communication devices, and actuators. After the system self-check, the automatic pressure increase program is initiated. When the pressure is increased to 30% of the test pressure in stages, it is stabilized for 30 minutes. A digital twin comparison is used to check if the deviation is less than 5%. If it is greater than or equal to 5%, a level three warning is activated: increased monitoring is initiated; if it is less than 5%, the pressure is increased to 60% of the test pressure in stages and stabilized for 30 minutes. Next, determine if the deviation is less than 5%. If the deviation is greater than or equal to 5%, initiate a level two warning: pause pressurization and use a drone for thermal imaging inspection to check for leaks. If no leaks are found, return to the step of determining if the deviation is less than 5%. If a leak is found, remotely depressurize and repair the defect. After defect repair, return to the system self-check step. If the deviation is less than 5%, gradually increase the pressure to 100% of the test pressure and stabilize for 30 minutes, then continue to determine if the deviation is less than 5%. If it is greater than or equal to 5%, return to the level two warning step. If it is less than 5%, conduct a strength test and stabilize for 4 hours. It should be noted that if a level one warning (deviation greater than or equal to 10% or acoustic emission / displacement abnormality) is detected at any time, the ESD emergency shut-off valve will be automatically triggered. After the strength test, determine if the pressure drop rate is qualified and if there are no abnormal alarms. If the result is no, perform remote depressurization. If the result is yes, slowly depressurize to the design pressure rate of 0.2~0.3MPa / h. Then, conduct a tightness test and stabilize for 24 hours, automatically calculate the pressure-temperature correction, and determine ΔP. 实际 Is it less than △P? 理论 If the result is negative, check for leaks and return to the step of slowly depressurizing to the design pressure. If the result is positive, the test is qualified, and the pressure is remotely depressurized to normal. Finally, drain the water, dry the pipes, and remove the seal from the sealed area.
[0156] The above description of the embodiments is only for the purpose of helping to understand the method and core ideas of this application. It should be noted that, for those skilled in the art, several improvements and modifications can be made to this application without departing from the principles of this application, and these improvements and modifications also fall within the protection scope of the claims of this application.
Claims
1. A safety control method for hydrostatic testing of long-distance pipelines, characterized in that, Applied to a central control system electrically coupled to a monitoring system, the method includes: A virtual model corresponding to the long-distance pipeline is constructed in the central control system. The parameters used to construct the virtual model include at least the pipeline length, pipe diameter, wall thickness, pipe material, number of bends, and elevation difference of the long-distance pipeline. The current stage of the hydrostatic test of the long-distance pipeline is determined. The hydrostatic test is used to verify the pipeline's strength and sealing performance. The stage includes water injection and venting, pressurization stage, early warning mechanism, emergency response, test judgment, and closing stage. The monitoring system acquires relevant parameters of the long-distance pipeline, and based on these parameters and the virtual model, calculates predicted safety parameters for the pipeline. The relevant parameters include the pipeline's inner diameter, the length of the test section, and the test pressure. The predicted safety parameters include the total potential energy stored within the pipeline, the kinetic energy damage from projectiles, the impact force of water within the pipeline, and the pressure wave damage. The process of acquiring the relevant parameters of the long-distance pipeline through the monitoring system and calculating the predicted safety parameters based on these parameters and the virtual model further includes: acquiring the pipeline's inner diameter, the length of the test section, and the test pressure; calculating the total volume of fluid involved in compression based on the pipeline's inner diameter and the length of the test section; and calculating the total potential energy stored within the pipeline based on the test pressure, the total volume of fluid involved in compression, and the bulk modulus of the liquid within the pipeline. Based on the predicted safety parameters and the current stage of the hydrostatic test of the long-distance pipeline, the safety status of the long-distance pipeline and corresponding safety measures are determined; the determination of the safety status of the long-distance pipeline and corresponding safety measures based on the predicted safety parameters and the current stage of the hydrostatic test of the long-distance pipeline further includes: in response to the total potential energy stored in the long-distance pipeline being greater than a first threshold and the current stage of the long-distance pipeline being a pressurization stage, determining the safety status of the long-distance pipeline as unsafe and triggering corresponding energy release preventive measures; wherein, the preventive measures include pressure grading, venting, monitoring and inspection, quality control, pressure detection, and energy release assessment.
2. The safety control method for hydrostatic testing of long-distance pipelines according to claim 1, characterized in that, The relevant parameters of the long-distance pipeline include the fluid pressure at the moment of rupture of the long-distance pipeline, and the method further includes: Obtain the fluid pressure at the moment of rupture of the long-distance pipeline; The kinetic energy damage of the projectile is calculated based on the fluid pressure and the density of the soil / projectile. In response to the projectile kinetic energy damage being greater than or equal to a second threshold, an emergency shut-off valve on the long-distance pipeline is triggered, wherein the projectile kinetic energy damage is the initial velocity of the projectile.
3. The safety control method for hydrostatic testing of long-distance pipelines according to claim 1, characterized in that, The relevant parameters of the long-distance pipeline include the fluid pressure at the moment of rupture of the long-distance pipeline, and the method further includes: Obtain the fluid pressure at the moment of rupture of the long-distance pipeline; Calculate the water jet velocity based on the fluid pressure and water density; The impact force of the water in the long-distance pipeline is calculated based on the jet velocity, water density, and preset pipe rupture area. The impact force is the impact force of the jet on the vertical plane. In response to the impact force of water in the long-distance pipeline being greater than or equal to a third threshold, the emergency shut-off valve on the long-distance pipeline is triggered.
4. The safety control method for hydrostatic testing of long-distance pipelines according to claim 1, characterized in that, The relevant parameters of the long-distance pipeline include the energy released by the explosion and the distance from the rupture point. The method further includes: Obtain the energy released by the explosion of the long-distance pipeline and the distance from the rupture point; The pressure wave damage is calculated based on the energy released by the explosion, the distance from the rupture point, and constants related to the medium and the nature of the explosion. In response to the pressure wave damage being greater than or equal to a fourth threshold, the emergency shut-off valve on the long-distance pipeline is triggered.
5. The safety control method for hydrostatic testing of long-distance pipelines according to claim 1, characterized in that, The method further includes: Obtain the fluid pressure, pipe diameter, pipe rupture length, and burial depth coefficient of the long-distance pipeline at the instant of rupture; The restricted area radius of the long-distance pipeline is calculated based on the fluid pressure, the pipeline diameter, the pipeline rupture length, the mass of the rocks, the soil type coefficient, and the burial depth coefficient. In response to the detection of relevant personnel within the restricted area radius, the emergency shut-off valve on the long-distance pipeline is triggered.
6. A safety control system for hydrostatic testing of long-distance pipelines, characterized in that, The safety control system is a central control system, electrically coupled to the monitoring system, and includes: The model building unit is configured to build a virtual model corresponding to the long-distance pipeline in the central control system. The parameters used to build the virtual model include at least the pipeline length, pipe diameter, wall thickness, pipe material, number of bends and elevation difference of the long-distance pipeline. The stage determination unit is configured to determine the current stage of the hydrostatic test of the long-distance pipeline, the hydrostatic test being used to verify the pipeline's strength and sealing performance, the stage including water injection and venting, pressurization stage, early warning mechanism, emergency response, test judgment, and closing stage; The parameter acquisition unit is configured to acquire relevant parameters of the long-distance pipeline via the monitoring system, and calculate predicted safety parameters of the long-distance pipeline based on the relevant parameters and the virtual model. The relevant parameters of the long-distance pipeline include the inner diameter of the pipeline, the length of the pipeline test section, and the test pressure. The predicted safety parameters include the total potential energy stored in the long-distance pipeline, the kinetic energy damage from projectiles, the impact force of water in the long-distance pipeline, and the pressure wave damage. The step of acquiring the relevant parameters of the long-distance pipeline via the monitoring system and calculating the predicted safety parameters of the long-distance pipeline based on the relevant parameters and the virtual model further includes: acquiring the inner diameter of the long-distance pipeline, the length of the pipeline test section, and the test pressure; calculating the total volume of fluid involved in compression based on the inner diameter of the long-distance pipeline and the length of the pipeline test section; and calculating the total potential energy stored in the long-distance pipeline based on the test pressure, the total volume of fluid involved in compression, and the bulk modulus of the liquid in the long-distance pipeline. A safety control unit is configured to determine the safety status and corresponding safety measures of the long-distance pipeline based on the predicted safety parameters and the current stage of the hydrostatic test of the long-distance pipeline. The determination of the safety status and corresponding safety measures based on the predicted safety parameters and the current stage of the hydrostatic test of the long-distance pipeline further includes: in response to the total potential energy stored in the long-distance pipeline being greater than a first threshold and the current stage of the long-distance pipeline being a pressurization stage, determining the safety status of the long-distance pipeline as unsafe and triggering corresponding energy release preventive measures; wherein the preventive measures include pressure grading, venting, monitoring and inspection, quality control, pressure detection, and energy release assessment.
7. An electronic device, characterized in that, The electronic device includes a processor coupled to a memory, the memory storing at least one computer program, which is loaded and executed by the processor to enable the electronic device to implement the safety control method for hydrostatic testing of long-distance pipelines as described in any one of claims 1 to 5.
8. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores at least one computer program, which is loaded and executed by a processor to enable the computer to implement the safety control method for hydrostatic testing of long-distance pipelines as described in any one of claims 1 to 5.
Citation Information
Patent Citations
Long-distance pipe network safety monitoring method, system and equipment based on Internet and medium
CN119475635A
Intelligent control method and system for stability of deep and long tunnel under complex geological conditions
CN121902475A