A method for real-time identification and analysis of safety risks at power engineering construction sites
By identifying the impact paths of newly added risk factors and forming unknown risk evolution chains in real time at the power engineering construction site, the problem of identifying unknown risks caused by new equipment has been solved, and construction safety has been improved.
Patent Information
- Application Number
- CN202611568786.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-12
- Publication Date
- 2026-11-10
AI Technical Summary
Existing risk identification methods based on historical construction data are insufficient to identify combinations of unknown risk factors caused by new construction equipment and processes. In particular, with the application of new equipment such as flexible lifting tools, it is impossible to identify the continuous transmission relationship between multiple construction changes in a timely manner, leading to the accumulation of safety hazards.
By matching the current construction characteristics with the risk model, continuous analysis is performed when mismatches are identified, the impact paths of newly added risk elements are screened, an unknown risk evolution chain is formed, and the construction risk model is updated with a new comparison benchmark to generate adjustment plans.
It enables real-time risk identification of construction site changes, timely identification of unknown risk formation processes, reduces the impact of repeated verification of risk evolution direction, and improves construction safety.
Smart Images

Figure CN123070640A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of power engineering analysis technology and relates to a method for real-time identification and analysis of safety risks at power engineering construction sites. Background Technology
[0002] In the safety management of power engineering construction sites, to achieve real-time identification and analysis of potential safety risks during construction, risk identification methods based on historical construction data are commonly used. These methods collect data on personnel locations, equipment operating parameters, environmental parameters, and construction procedures at the construction site, and combine this information with historical construction cases to establish risk models. Based on the matching between the current construction status and existing risk patterns, safety risks during construction are assessed.
[0003] However, in actual power engineering construction, with the application of new construction equipment, new construction techniques, and new temporary structures, combinations of risk factors that are not covered by historical risk models may occur at the construction site. For example, in the expansion construction of large substations, when a new flexible hoisting system is used for the first time, its stress response differs from that of traditional hoisting equipment due to the greater structural deformation capacity of the flexible hoisting equipment. Traditional hoisting equipment typically exhibits increased overall sway when wind speed increases, while flexible hoisting equipment may exhibit increased local deformation caused by wind speed changes, further leading to equipment center of gravity shift and intensified rotational sway.
[0004] Since the aforementioned risk changes are not present in historical construction data, existing methods based on historical risk models struggle to establish corresponding risk impact paths in a timely manner. This is especially true when the local deformation of flexible lifting equipment, the offset of the equipment's center of gravity, and the equipment's rotational sway angle have not yet exceeded their respective allowable ranges, but have been continuously changing sequentially relative to the initial stable stage of hoisting. Simply judging whether each collected quantity exceeds its allowable range may still lead to the current construction status being deemed acceptable for continued construction, failing to promptly identify the continuous transmission relationships between multiple construction changes. As these changes continue to accumulate, they may further lead to safety issues such as instability of large equipment in mid-air, hoisting path deviation, equipment collisions, and untimely personnel avoidance. Therefore, to address the problem that historical risk models cannot cover new risk element combinations due to the application of new equipment and processes in power engineering construction, and that relying solely on the allowable range of a single collected quantity makes it difficult to promptly identify the formation process of unknown risks, a real-time identification and analysis method for safety risks at power engineering construction sites is urgently needed. This method can discover new risk impact paths based on real-time changes at the construction site, construct unknown risk evolution chains, and achieve early identification of the formation process of new construction risks. Summary of the Invention
[0005] In view of this, in order to solve the problems mentioned in the background technology, a real-time identification and analysis method for safety risks at power engineering construction sites is proposed.
[0006] The objective of this invention can be achieved through the following technical solution: a method for real-time identification and analysis of safety risks at power engineering construction sites, comprising the following steps: Acquire current construction characteristics and match them item by item with existing construction characteristics in the construction risk model; when there are mismatches, continuously analyze the real-time data collected at the construction site, and identify construction changes that have not yet exceeded the corresponding allowable range of change but have been continuously changing and whose transmission relationship with other risk elements is not recorded in the current risk record as new risk elements. Candidate connections are formed according to the order in which the new risk factors occur. The degree of influence is determined based on the time interval between occurrences, spatial distance, and the dimensionless change magnitude of the subsequent new risk factors. When the degree of influence reaches the influence threshold, an influence path is formed. An unknown risk evolution chain is formed according to the aforementioned impact path and the chronological order of occurrence of newly added risk elements; After the unknown risk evolution chain is formed, the current collected values of each newly added risk element are used as a new comparison benchmark to re-obtain the subsequent change sequence; when the subsequent change sequence is consistent with the order of occurrence in the unknown risk evolution chain, the risk evolution direction is determined, the construction risk model is updated according to the unknown risk evolution chain, and a construction adjustment plan is generated.
[0007] Compared with the prior art, the beneficial effects of the present invention are as follows: (1) When there are mismatches in the current construction features, the present invention performs continuous analysis on the real-time collected data so that construction changes that have not yet reached the allowable change boundary but have formed continuous changes can be included in the subsequent risk relationship analysis.
[0008] (2) This invention uses the time interval, spatial distance and dimensionless change amplitude to screen the influence path between newly added risk elements, and forms an unknown risk evolution chain according to the order of occurrence. It can identify the continuous transmission relationship formed when multiple construction changes have not yet exceeded the limits.
[0009] (3) After the unknown risk evolution chain is formed, the present invention uses a new comparison benchmark to re-obtain the subsequent change sequence, thereby confirming the risk evolution direction and writing the confirmed risk transmission process into the construction risk model, thereby reducing the impact of repeatedly verifying the risk evolution direction at the same occurrence time. Attached Figure Description
[0010] Figure 1 This is a schematic diagram of the overall process of steps S1 to S4 in this invention; Figure 2This is a schematic diagram of the process for matching construction features and determining new risk factors in this invention; Figure 3 This is a schematic diagram of the process in this invention for obtaining the order of subsequent changes and identifying the direction of risk evolution based on a new comparison benchmark; Figure 4 This is a schematic diagram showing the time sequence comparison of changes in wind speed, local deformation of the flexible lifting tool, equipment center of gravity shift, and equipment rotation and swing angle during the flexible hoisting process in this invention. Detailed Implementation
[0011] The following will describe, with reference to the accompanying drawings, a method for real-time identification and analysis of safety risks at power engineering construction sites according to the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0012] Unless otherwise defined, the technical terms used herein have the same meaning as commonly understood by one of ordinary skill in the art.
[0013] The following description, in conjunction with the accompanying drawings, details the specific scheme of the real-time identification and analysis method for safety risks at power engineering construction sites provided by this invention.
[0014] Example 1: like Figure 1 As shown, the real-time identification and analysis method for safety risks at power engineering construction sites according to the present invention includes steps S1 to S4 in sequence. Step S1 is used to obtain the current construction characteristics and match them item by item with the existing construction characteristics in the construction risk model. When there are mismatches, new risk elements are determined by continuous change judgment. Step S2 is used to form candidate connections according to the order of occurrence of new risk elements, and determine the degree of influence based on the degree of temporal proximity, spatial proximity, and dimensionless change amplitude, and screen the influence path. Step S3 is used to form an unknown risk evolution chain according to the influence path and the order of occurrence. Step S4 is used to re-obtain the subsequent change sequence using a new comparison benchmark after the unknown risk evolution chain is formed, match it with the order of occurrence in the chain, confirm the risk evolution direction, update the construction risk model, and generate a construction adjustment plan.
[0015] This embodiment takes the hoisting of GIS equipment units in a substation expansion project as an example. The construction risk model is established based on historical construction records under existing construction equipment, construction technology, and construction environment conditions. Each risk record includes the type of construction equipment, the type of construction technology, construction environment conditions, risk factors, the impact path, the risk transmission sequence, and construction adjustment measures. Existing records mainly correspond to risk factor combinations under traditional rigid lifting conditions. After switching to a flexible hoisting system on site, local deformation of the lifting equipment will change the stress state of the hoisting and may continue to cause equipment center of gravity shift and equipment rotational sway. The above-mentioned collected quantities may still be within the allowable variation range specified in the hoisting-specific construction plan when forming a continuous variation relationship. Therefore, it is necessary to continuously analyze their variation sequence and interaction relationship.
[0016] In this embodiment, first according to Figure 1 Step S1 involves matching construction equipment type, construction process type, and construction environmental conditions item by item. If mismatches exist, a continuous change judgment is performed on the real-time collected data to identify new risk elements. Then, according to step S2, the influence path is screened based on the time interval between occurrences, the spatial distance between the locations of construction changes, and the dimensionless change amplitude. Step S3 connects the retained influence paths to form an unknown risk evolution chain. Finally, according to step S4, the comparison benchmark is reset when the chain is formed, the subsequent change sequence is obtained, the risk evolution direction is confirmed, the construction risk model is updated, and a corresponding construction adjustment plan is generated.
[0017] S1. Obtain the current construction characteristics and match them item by item with the existing construction characteristics in the construction risk model; if there are mismatches, perform a continuous change judgment on the real-time collected data to determine the new risk elements.
[0018] like Figure 2 As shown, step S1 specifically includes steps S101 to S103: S101. Obtain the construction equipment type, construction process type, and construction environment conditions corresponding to the current construction characteristics.
[0019] In practice, the construction equipment type is retrieved from the hoisting operation task and equipment configuration records, the construction process type is retrieved from the hoisting-specific construction plan, and the construction environmental conditions are obtained from the on-site environmental monitoring unit and work area information. In this embodiment, the construction equipment type is recorded as a flexible hoisting system, the construction process type is recorded as GIS equipment unit hoisting, and the construction environmental conditions are recorded as the current wind speed, the spatial range of the hoisting area, and the work period. This information is written into the current construction feature according to the same construction task identifier for subsequent matching with existing records in the construction risk model.
[0020] S102. Match the construction equipment type, construction process type, and construction environmental conditions with the construction equipment type, construction process type, and construction environmental conditions corresponding to the existing risk element combinations in the construction risk model.
[0021] The construction equipment type, construction process type, and construction environmental conditions obtained in step S101 are compared item by item with the three types of construction features corresponding to existing risk element combinations in the construction risk model. When both the construction equipment type and construction process type are consistent with existing records, and the construction environmental conditions are within the applicable range of the corresponding existing records, the current construction feature is determined to be a match, and monitoring continues according to the existing risk element combination; if any one of these conditions is not met, the current construction feature is determined to be a mismatch, and the process proceeds to step S103. In this embodiment, a flexible hoisting system is used, while the existing records in the construction risk model mainly correspond to traditional rigid hoisting equipment; therefore, it is determined that the current construction feature is not completely covered by the existing risk element combination. Figure 2 As shown, if there are no mismatches in the matching results, continue monitoring along the "no" branch according to the existing risk element combination; if there are mismatches, proceed to step S103 along the "yes" branch.
[0022] S103. When there are construction feature mismatches, the data collected during the current construction process will be continuously analyzed. Construction changes that have not yet exceeded the corresponding allowable range of change but have shown continuous changes and whose transmission relationship with other risk factors is not recorded in the current risk record will be identified as new risk factors.
[0023] After entering step S103, the displacement detection unit continuously collects the local deformation of the flexible lifting device; it determines the initial center of gravity coordinates of the equipment based on the equipment design data, and uses the three-dimensional coordinates of multiple non-collinear detection points arranged at different positions on the equipment in the initial and current states to determine the attitude transformation relationship of the equipment, converts the initial center of gravity coordinates to obtain the current center of gravity coordinates, and then determines the equipment center of gravity offset based on the position difference between the two; the attitude detection unit continuously collects the rotation and swing angles of the equipment. Each acquisition unit uses a unified clock to output the acquisition results. The initial stable stage of the current construction task refers to the continuous period before formal construction in which all real-time acquisition quantities remain stable and without directional drift; in this embodiment, GIS equipment is being hoisted, so the continuous period before formal hoisting where the equipment attitude is stable is selected as the initial stable stage of hoisting, and the stable values of each acquisition quantity in this stage are used as the benchmark to determine the stable fluctuation range based on the fluctuation boundary during stable operation.
[0024] After hoisting begins, each data acquisition quantity is continuously assessed periodically. The continuous assessment period is determined by the low-speed commissioning results before the formal hoisting: the number of consecutive periods during which the instantaneous fluctuation of each data acquisition quantity continuously exceeds the stable fluctuation range is counted, and the maximum number of consecutive periods is taken as the next consecutive period number. When a data acquisition quantity continuously exceeds the stable fluctuation range within the continuous assessment period, maintains the same direction of change relative to the benchmark value, and still does not exceed the allowable change range, the construction change is considered to have formed a continuous change; then, the current risk record is checked to see if the transmission relationship between this construction change and other risk factors has been recorded. If not, it is identified as a new risk factor, and the start time of the continuous change is recorded. Data acquisition quantities that have exceeded the allowable change range directly enter the over-limit safety handling procedure specified in the hoisting-specific construction plan.
[0025] S2. Form candidate connections according to the order of occurrence of the new risk factors, and determine the degree of influence based on the time interval between occurrences, spatial distance, and dimensionless change magnitude, and screen the influence paths between the new risk factors.
[0026] After identifying new risk factors, they are sorted according to their occurrence time. New risk factors occurring earlier are considered candidate upstream factors, and those occurring later are considered candidate downstream factors. The degree of influence is then calculated by combining the temporal and spatial proximity of the two factors, as well as the dimensionless change magnitude of the later-occurring risk factor. Candidate connections are retained when the degree of influence reaches a threshold. In this embodiment, the flexible spreader first experiences continuous local deformation, followed by a shift in the equipment's center of gravity, and then rotational oscillation of the equipment. Therefore, candidate connections are formed from the local deformation of the flexible spreader to the shift in the equipment's center of gravity, and from the shift in the equipment's center of gravity to the rotational oscillation of the equipment.
[0027] To avoid distortion in the assessment of the degree of impact caused by direct comparison of different units such as millimeters and angles, this embodiment converts the change range of each newly added risk element into a dimensionless change range. The calculation formula is:
[0028] In the formula, Indicates the first The dimensionless change range of each newly added risk element; The number indicating the newly added risk element; Indicates the first The current collected value of each newly added risk element; Indicates the first The baseline value corresponding to each newly added risk element in the initial stable phase of the current construction task; Indicates the first The permissible range of change corresponding to each newly added risk element. The determination is based on the baseline value of the current data collection and the corresponding allowable variation boundary specified in the hoisting-specific construction plan; , and Using the same units, therefore the formula above yields... It is a dimensionless numerical value.
[0029] The permissible variation range of each newly added risk element is determined based on the current construction equipment commissioning records and the hoisting-specific construction plan, taking the variation range of the corresponding collected quantity from the benchmark value to the permissible variation boundary. After normalizing the permissible variation range of local deformation of flexible lifting equipment, equipment center of gravity offset, and equipment rotation and sway, the degree of change of each construction change relative to its own permissible boundary can be compared, while avoiding the direct participation of different dimensions such as deformation, displacement, and angle in the same calculation.
[0030] The spatial relationships between newly added risk elements are determined by the location of the corresponding construction changes. For construction changes obtained through direct detection, the actual location represented by the detection point is used; for construction changes calculated from multiple detection points, the spatial reference location corresponding to the calculation result is used. The maximum effective influence distance is determined based on the size of the hoisting equipment, the range of motion of the hoisted equipment, and the arrangement of guiding constraints. When the actual spatial distance is less than the maximum effective influence distance, the spatial proximity is determined according to the following formula; when the actual spatial distance reaches or exceeds the maximum effective influence distance, the spatial proximity is set to zero, and the corresponding candidate connection is not retained:
[0031] In the formula, Indicates newly added risk factors With new risk factors The degree of spatial proximity between them; Indicates the number of the newly added risk element that occurred first; Indicates the number of any newly added risk element; Indicates newly added risk factors With new risk factors The actual spatial distance between the locations corresponding to the changes in construction; Indicates newly added risk factors With new risk factors The maximum effective influence distance under the corresponding working conditions. and Use the same length unit; when Less than When, the result obtained from the above calculation formula It is a dimensionless numerical value.
[0032] The maximum effective influence distance is determined from the specific hoisting construction plan, taking the boundary of the area that covers the hoisting equipment, the hoisted equipment, and the force transmission area of the guiding constraints. When the construction equipment, hoisting path, or guiding constraint arrangement changes, it is re-determined according to the corresponding specific hoisting construction plan, and the fixed value under other construction conditions is not used.
[0033] Furthermore, the time proximity is determined based on the time intervals between the occurrences of newly added risk factors. First, the occurrence times of adjacent newly added risk factors are obtained, and time intervals are divided according to the data collection period. Within each time interval, the number of times a subsequent construction change occurs in the same order and the corresponding number of adjustments are counted. The formula for calculating the time proximity is:
[0034] In the formula, Indicates newly added risk factors With new risk factors The degree of time proximity between them; Indicates the number of the newly added risk element that occurred first; Indicates the number of any newly added risk element; Indicates newly added risk factors With new risk factors The time interval between occurrences, and ; Indicates newly added risk factors The moment when continuous change begins; Indicates newly added risk factors The moment when continuous change begins, and Later ; Indicates the time interval Within, the number of times each subsequent construction change occurs in the same order; Indicates the corresponding time interval The number of debugging attempts included in the statistics. In this embodiment, a time decay table is established based on the response delay of adjacent construction changes during the low-speed debugging process before the formal hoisting of the flexible hoisting system. The effective response period is divided into continuous time intervals according to the acquisition cycle. The time proximity corresponding to each time interval is obtained according to the above calculation formula, and a time decay table is formed in the order of the time intervals. After the effective response period confirmed by the low-speed debugging is exceeded, the corresponding candidate connection is not retained.
[0035] Based on this, the degree of influence is obtained by combining the temporal proximity, spatial proximity, and the dimensionless change magnitude of the subsequently added risk factors. The calculation formula is:
[0036] In the formula, Indicates newly added risk factors New risk factors The extent of the impact; Indicates the number of the newly added risk element that occurred first; Indicates the number of any newly added risk element; Indicates newly added risk factors To new risk factors The degree of time proximity; Indicates newly added risk factors New risk factors Spatial proximity; Indicates the dimensionless change in the magnitude of newly added risk factors; , , These represent the weights corresponding to temporal proximity, spatial proximity, and dimensionless variation amplitude, respectively. Each weight is calibrated based on the low-speed commissioning results before formal hoisting. For each candidate weight combination, the minimum impact of continuous response construction changes and the maximum impact of stable construction changes are determined, retaining candidate weight combinations where the former is greater than the latter. When multiple candidate weight combinations exist, the candidate weight combination with the largest difference between the two is selected, and each candidate weight is normalized by dividing by the sum of the weights; the result is used as the corresponding weight.
[0037] The impact threshold is calibrated through low-speed testing before the formal hoisting. When the minimum impact of continuous construction changes is greater than the maximum impact of stable construction changes, the midpoint between the two is taken as the impact threshold of the current construction equipment and hoisting conditions; if this condition is not met, the candidate weights are readjusted and calibrated.
[0038] According to the above rules, the degree of influence between local deformation of the flexible lifting device and equipment center of gravity shift, and between equipment center of gravity shift and equipment rotation and oscillation, are determined. During the current lifting process, the sequence of occurrence of the two sets of adjacent construction changes is consistent with the response sequence confirmed during low-speed commissioning. The corresponding locations of the construction changes are all within the effective range, and the degree of influence reaches the influence threshold. Therefore, the two sets of candidate connections are retained to form influence paths. The degree of influence is only used to screen the connection relationships between newly added risk elements and is not used as a direct basis for determining whether a single construction parameter requires work stoppage.
[0039] During a flexible hoisting commissioning process, the attitude data collected remained stable at the beginning of the hoisting phase. As the crosswind intensified, the displacement detection unit first detected a continuous increase in the local deformation of the flexible hoisting equipment; subsequently, the center of gravity position calculated based on the coordinates of the equipment's detection points showed a continuous shift; while this stress state continued, the attitude detection unit detected an increase in the equipment's rotational sway. None of the above data collected reached the allowable variation boundaries specified in the hoisting construction plan, but the changes occurred consecutively in a fixed sequence.
[0040] The controller records the starting time of each construction change that continuously deviates from the stable fluctuation range and determines the corresponding position of the construction change. Local deformation of the flexible lifting device is detected at the position where the continuous deformation occurs; equipment center of gravity offset is calculated using the current equipment center of gravity position; equipment rotation and oscillation are calculated using the corresponding equipment reference position. If the time interval between adjacent construction changes exceeds the effective response period confirmed during low-speed commissioning, or if the corresponding position is not within the current lifting range, the candidate connection is not retained.
[0041] Based on the assessment of the degree of impact, both the local deformation of the flexible spreader leading to the shift of the equipment's center of gravity, and the shift of the equipment's center of gravity leading to the equipment's rotation and swaying, reached the threshold of impact, and maintained this condition within the continuous assessment period, forming a continuous impact path. The unknown risk evolution chain only uses the impact path that meets the above continuity condition, and does not use connections formed by isolated changes or single fluctuations.
[0042] like Figure 4 As shown, the horizontal axis represents the construction time, and the vertical axis represents the degree of change of each collected quantity relative to its own baseline state; the red solid line represents wind speed, the blue dashed line represents local deformation of the flexible lifting device, the green dotted line represents the equipment center of gravity shift, and the purple dotted line represents the equipment rotation and sway angle. After the lateral wind effect intensifies, the wind speed changes first; t1, t2, and t3 represent the times when the local deformation of the flexible lifting device, the equipment center of gravity shift, and the equipment rotation and sway angle first meet the continuous change conditions of step S103, respectively. Based on this, the controller determines the initial order of occurrence of the three newly added risk elements and uses the time interval between adjacent occurrence times to determine the time proximity in step S2. The vertical height of the different curves in the figure only represents the trend of change of each relative to its own baseline state, and does not represent the magnitude relationship between the absolute values of collected quantities of different dimensions. Figure 4 The blue dashed line, green dotted line, and purple dotted line enter the continuous change segment at the corresponding times t1, t2, and t3, respectively, so that the three occurrence times correspond to the continuous change starting points of the corresponding newly added risk elements.
[0043] S3. Connect the impact paths and the order in which the new risk factors occur to form an unknown risk evolution chain.
[0044] Specifically, the influence paths retained in step S2 are connected according to the order of occurrence of the newly added risk elements. The local deformation of the flexible spreader and the shift of the equipment's center of gravity form the first influence path, and the shift of the equipment's center of gravity and the rotation and sway of the equipment form the second influence path. After the two influence paths are connected with the shift of the equipment's center of gravity as a common node, the risk transmission process of the local deformation of the flexible spreader, the shift of the equipment's center of gravity, and the rotation and sway of the equipment is obtained, and this risk transmission process is written into the unknown risk evolution chain.
[0045] Before incorporating an impact path into the unknown risk evolution chain, its continuity is confirmed. The controller uses the continuous judgment period determined in step S103 to judge the impact degree of adjacent newly added risk elements cycle by cycle. When the corresponding impact degree reaches the impact degree threshold within the continuous judgment period, the adjacent impact paths are connected in chronological order to form a risk transmission process and written into the unknown risk evolution chain. If a collection result does not reach the impact degree threshold, it is not written temporarily, and subsequent collection results are read.
[0046] S4. After the unknown risk evolution chain is formed, the current collected values of each newly added risk element are used as the new comparison benchmark to re-acquire the subsequent change sequence, identify the risk evolution direction in the current construction process, update the construction risk model according to the unknown risk evolution chain, and generate a construction adjustment plan.
[0047] like Figure 3 As shown, the risk evolution direction identification process in step S4 specifically includes steps S401 to S403: S401. After the unknown risk evolution chain is formed, the current collected value of each newly added risk element is used as a new comparison benchmark to re-obtain the subsequent change sequence of each newly added risk element.
[0048] When an unknown risk evolution chain is formed, the controller records the current acquired values of the flexible spreader's local deformation, the equipment's center of gravity offset, and the equipment's rotational sway angle, and uses these as new comparison benchmarks. Subsequently, it continues to read each acquired value according to the acquisition cycle used in step S103, and re-executes the continuous change determination relative to the new comparison benchmark. When a newly added risk element first meets the continuous change condition after the chain is formed, it records the start time of its continuous change relative to the new comparison benchmark; the subsequent change sequence is formed according to the order of these start times. This subsequent change sequence is obtained using the new acquisition process after the chain is formed, and does not use the original occurrence time when the unknown risk evolution chain was constructed.
[0049] S402. Match the subsequent sequence of changes with the order in which each new risk element occurs in the unknown risk evolution chain.
[0050] The order of newly added risk elements written into the unknown risk evolution chain in step S3 is read, and the subsequent change order obtained in step S401 is compared item by item. In this embodiment, the unknown risk evolution chain is recorded as follows: local deformation of the flexible spreader, shift of the equipment's center of gravity, and rotational oscillation of the equipment occur sequentially. When the three newly added risk elements in the subsequent data collection process also undergo continuous changes in this order, it is determined that the subsequent change order is consistent with the order of occurrence in the unknown risk evolution chain. If there are missing elements, reversed order, or the corresponding data collection quantity does not undergo continuous changes, it is determined that the two are inconsistent. Figure 3 As shown, if the matching results are consistent, the "yes" branch proceeds to step S403; if the matching results are inconsistent, the "no" branch continues to collect each newly added risk element and returns to step S401.
[0051] S403. When the subsequent change sequence is consistent with the order of occurrence, determine the risk evolution direction corresponding to the unknown risk evolution chain of the current construction process.
[0052] When the matching result of step S402 is consistent, the risk evolution direction of the current construction process is determined to be from the local deformation of the flexible lifting tool to the shift of the equipment's center of gravity, and then to the rotation and swing of the equipment, and the construction risk model update and construction adjustment scheme generation process is entered; when the matching result is inconsistent, it is not confirmed that the current construction process develops along the unknown risk evolution chain, and the newly added risk elements are collected and steps S401 to S403 are re-executed.
[0053] After confirming the direction of risk evolution, the newly added risk elements, impact paths, and risk transmission processes in the unknown risk evolution chain are read and compared with existing records in the construction risk model. During the comparison, the order of the newly added risk elements and the connection relationships of the impact paths are checked separately. If both are consistent, it is determined that the same risk transmission process exists and is not written repeatedly; otherwise, the corresponding newly added risk element, impact path, and risk transmission process are stored as a new risk record. If the same construction feature subsequently exhibits the same sequence of changes, the already written risk transmission process is directly invoked for identification.
[0054] The construction adjustment plan is determined based on the construction stages involved in the unknown risk evolution chain and the specific hoisting construction plan. The construction stages to be adjusted are identified in the order from upstream to downstream of the unknown risk evolution chain, with the construction stage corresponding to the newly added risk element at the very upstream being prioritized for adjustment. Then, the safety measures corresponding to the construction stages to be adjusted are retrieved from the current specific hoisting construction plan and a construction adjustment plan is formed. The implemented measures and the corresponding risk transmission process are recorded together in the construction risk model.
[0055] In this embodiment, once the local deformation of the flexible lifting device, the shift of the equipment's center of gravity, and the rotational swaying of the equipment sequentially form an unknown risk evolution chain and the direction of risk evolution is confirmed, lifting is stopped. Lateral guiding constraints are added to the lifted equipment, and unrelated personnel are removed from the area where the equipment may sway. Lifting operations resume once the on-site wind conditions return to the operating conditions permitted by the lifting-specific construction plan, and the acquired attitude data re-enter the fluctuation range corresponding to the initial stable stage of the lifting and remain stable.
[0056] After completing the above processing, the newly added risk elements, impact paths, risk transmission processes, and construction adjustment measures corresponding to the flexible hoisting system are written into the construction risk model. When the same construction characteristics reappear, the construction risk model identifies the risks according to the recorded risk transmission process and invokes the corresponding construction adjustment measures.
[0057] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the real-time identification and analysis method for safety risks at power engineering construction sites and its inventive concept, should be covered within the scope of protection of the present invention.
Claims
1. A method for real-time identification and analysis of safety risks at power engineering construction sites, characterized in that, Includes the following steps: Acquire current construction characteristics and match them item by item with existing construction characteristics in the construction risk model; when there are mismatches, continuously analyze the real-time data collected at the construction site, and identify construction changes that have not yet exceeded the corresponding allowable range of change but have been continuously changing and whose transmission relationship with other risk elements is not recorded in the current risk record as new risk elements. Candidate connections are formed according to the order in which the new risk factors occur. The degree of influence is determined based on the time interval between occurrences, spatial distance, and the dimensionless change magnitude of the subsequent new risk factors. When the degree of influence reaches the influence threshold, an influence path is formed. An unknown risk evolution chain is formed according to the aforementioned impact path and the chronological order of occurrence of newly added risk elements; After the unknown risk evolution chain is formed, the current collected values of each newly added risk element are used as a new comparison benchmark to re-obtain the subsequent change sequence; when the subsequent change sequence is consistent with the order of occurrence in the unknown risk evolution chain, the risk evolution direction is determined, the construction risk model is updated according to the unknown risk evolution chain, and a construction adjustment plan is generated.
2. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 1, characterized in that, Current construction characteristics include the type of construction equipment, the type of construction technology, and the construction environment conditions; Before formal construction, a continuous period in which each real-time data acquisition remains stable and without directional drift is selected as the initial stable phase of the current construction task, and the benchmark value and stable fluctuation range of each data acquisition are determined. When the collected data continuously exceeds the stable fluctuation range within a continuous determination period, maintains the same direction of change relative to the reference value, and does not exceed the corresponding allowable change range, it is determined that the collected data has formed a continuous change.
3. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 1, characterized in that, Candidate impact directions are determined according to the order in which new risk factors occur, and the degree of impact of candidate connections is determined based on temporal proximity, spatial proximity, and the dimensionless change magnitude of the later-occurring new risk factors. When the degree of influence reaches the influence threshold, the candidate influence direction is determined as the connection direction of the influence path.
4. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 3, characterized in that, The dimensionless variation range is determined by the ratio of the change in the current collected value of the newly added risk element relative to the benchmark value of the initial stable stage of the current construction task to the corresponding allowable variation range; Spatial proximity is determined by the actual spatial distance and the maximum effective impact distance between the locations where the construction changes corresponding to the newly added risk elements take effect; The degree of time proximity is determined by the time interval between the occurrence of newly added risk factors and the preset time decay relationship.
5. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 1, characterized in that, Connect the impact paths between adjacent newly added risk factors in chronological order to form a risk transmission process; When the degree of influence between adjacent newly added risk elements reaches the influence threshold within a continuous judgment period, the risk transmission process is written into the unknown risk evolution chain.
6. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 1, characterized in that, After the unknown risk evolution chain is formed, the collected values of each newly added risk element at the time of chain formation are used as the new comparison benchmark, and the continuous change judgment is re-executed. Record the starting time when each newly added risk element begins to change continuously relative to the new benchmark, and record the subsequent changes in order of the starting time; The subsequent sequence of changes is compared item by item with the sequence of occurrence recorded in the unknown risk evolution chain. If they match, the direction of risk evolution is confirmed. If they do not match, data is collected and compared again.
7. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 6, characterized in that, The subsequent changes are ordered according to the starting moment when each newly added risk element first meets the condition for continuous change after the formation of the unknown risk evolution chain.
8. The method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 6, characterized in that, After confirming the direction of risk evolution, extract the newly added risk elements, impact paths, and risk transmission processes from the unknown risk evolution chain, and compare them with the existing records in the construction risk model. When there is no identical risk transmission process, the corresponding newly added risk element, impact path and risk transmission process will be written into the construction risk model as the same risk record; A construction adjustment plan is generated based on the updated construction risk model.
9. A method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 8, characterized in that, The order of new risk elements to be written into the risk transmission process and the connection of their impact paths are compared with the existing risk transmission process. If the order of arrangement and the connection relationship of the impact path are consistent, they will not be written repeatedly; otherwise, the corresponding newly added risk elements, impact paths and risk transmission processes will be stored as new risk records.
10. A method for real-time identification and analysis of safety risks at power engineering construction sites according to claim 8, characterized in that, The construction stages to be adjusted are determined in the order from upstream to downstream of the unknown risk evolution chain, and the construction stages corresponding to the newly added risk elements at the very upstream are identified as the priority construction stages to be adjusted. Read the safety measures corresponding to the construction phase to be adjusted from the specific construction plan corresponding to the current construction task; Based on the aforementioned safety measures, a construction adjustment plan is formulated.