A dynamic partition scheduling method for water delivery system based on hydraulic blockage effect
By using a linear analysis model of the hydraulic process of rivers and canals based on the hydraulic blocking effect, the propagation range of water diversion disturbances is dynamically identified, and dynamic scheduling zones are constructed. This solves the problems of delayed scheduling response and high computational complexity in traditional scheduling methods, and realizes efficient and accurate scheduling of river and canal water conveyance systems.
Patent Information
- Application Number
- CN202611588975.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-14
- Publication Date
- 2026-11-10
AI Technical Summary
Traditional river and canal water conveyance system scheduling methods are difficult to achieve accurate scheduling when faced with disturbances such as hydraulic process lag and dynamic fluctuations in water demand, resulting in delayed scheduling response and low efficiency. Furthermore, existing hydraulic simulation methods have high computational complexity and serious distortion in complex rivers and canals.
Based on the hydraulic blocking effect, a linear analysis model of the hydraulic process of rivers and canals is established. Historical monitoring data is used to quantify the hydraulic blocking coefficient and static coefficient, dynamically identify the propagation range of water diversion disturbance, construct dynamic scheduling zones, and optimize the scheduling model of the control gate to achieve precise scheduling.
Dynamic partitioned scheduling of the river and canal water conveyance system was realized, reducing the system optimization dimensions, improving scheduling calculation efficiency and response speed, and reducing computational complexity and scheduling distortion.
Smart Images

Figure CN123070657A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of river and canal water conveyance scheduling technology, and in particular to a dynamic zone scheduling method for water conveyance systems based on the hydraulic blocking effect. Background Technology
[0002] River and canal water conveyance projects have become a core measure for optimizing the spatial allocation of water resources. Currently, river and canal water conveyance systems face various disturbances in actual operation, such as hydraulic process lag and dynamic fluctuations in water demand. Traditional scheduling adopts unified or fixed-zone control along the entire line, which is difficult to implement in real-time scheduling in high-dimensional scenarios, resulting in scheduling response lag and an imbalance between efficiency and accuracy.
[0003] Specifically, traditional unified scheduling across the entire line requires high-dimensional calculations across the entire region, which results in problems such as large computational redundancy, slow response, and low control efficiency. Fixed zonal scheduling does not consider the dynamic characteristics of hydraulic propagation, cannot achieve precise dimensionality reduction and decoupling, and is difficult to adapt to short-term dynamic changes such as fluctuations in water flow and water level disturbances, which can easily lead to over- or under-control and imbalance between global and local scheduling.
[0004] In the field of river and canal hydraulic simulation, traditional hydrodynamic simulation methods based on the Saint-Venant equations can accurately depict hydraulic processes, but they suffer from high computational complexity and stringent requirements for basic data, making it difficult to meet the high-efficiency requirements of real-time scheduling. Integrator-Delay (ID) models have become one of the mainstream tools due to their simple structure and strong applicability. However, they are based on idealized channel assumptions and are difficult to apply to actual rivers and canals with complex cross-sectional shapes and variable boundary conditions. Directly applying these assumptions to simulations can easily lead to significant distortions.
[0005] Therefore, it is necessary to provide a scheduling method for river and canal water conveyance systems that can accurately quantify the hydraulic blocking effect and achieve dynamic scheduling. Summary of the Invention
[0006] The purpose of this invention is to provide a dynamic zoning scheduling method for water conveyance systems based on the hydraulic blocking effect.
[0007] The present invention provides a dynamic zoning scheduling method for a water conveyance system based on the hydraulic blocking effect, comprising: establishing a linear mapping relationship between changes in river and canal flow and water conveyance losses in the water conveyance system to obtain a linear analysis model of the hydraulic process of the river and canal; calibrating the hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process using historical monitoring data of the water conveyance system to quantify the hydraulic blocking effect; and determining the propagation range of the water-dividing disturbance based on the hydraulic blocking effect when a water-dividing disturbance occurs during the scheduling of the water conveyance system, thereby dynamically zoning the water conveyance system, including: obtaining the location of the water-dividing disturbance, the amount of flow disturbance, and the duration of the disturbance, and setting a dynamic zoning water level change threshold. Using the canals where water diversion disturbances occur as the initial dynamic scheduling zones, a linear hydraulic process analysis model is used to calculate the water level changes in front of the control gates of the associated canals. It is then determined whether the water level changes in front of the control gates of the associated canals exceed the water level change threshold. If the water level changes exceed the threshold, the associated canals are included in the dynamic scheduling zones. An optimized scheduling model is constructed with the optimization objectives of minimizing the deviation between the water level in front of the gates and the target water level, and minimizing the number of gate actions in the dynamic scheduling zones. Upper and lower limits of water level, flow rate, and water level fluctuation constraints for the control gates are set. An augmented objective function is constructed based on the degree of violation of each constraint by the current scheduling scheme. The optimized scheduling model is then solved using the augmented objective function to obtain the final scheduling result.
[0008] The beneficial effects of the dynamic partition scheduling method for water conveyance systems based on hydraulic blocking effect provided by this invention are as follows: applying this method can accurately quantify the hydraulic blocking effect of rivers and canals, dynamically identify the dynamic scheduling partition boundaries according to the propagation range of water diversion disturbances, realize dynamic partition scheduling of water conveyance systems, significantly reduce system optimization dimensions, and improve scheduling calculation efficiency and response speed.
[0009] In one possible embodiment, the expression of the linear analysis model of the hydraulic process satisfies: ,in, express Changes in water level in front of the control gate during a given time period. Indicates the hydraulic blocking coefficient. express The change in average flow rate of the river or canal over a given period of time. express Loss of water flow during the river and canal transport period Indicates the duration of the calculation period. Represents static coefficients. express Water level in front of the canal control gate during a certain period of time express The water level in front of the canal control gate during a certain period.
[0010] In another possible embodiment, the hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process are calibrated using historical monitoring data of the water conveyance system, including: defining the objective function for calibration as minimizing the mean square error between the simulated water level and the measured water level; quantifying the mean square error of the historical simulation period of the linear analysis model of the hydraulic process using historical monitoring data according to the objective function; and calibrating the hydraulic blocking coefficient and static coefficient by minimizing the mean square error.
[0011] In other possible embodiments, determining whether an associated canal should be included in a dynamic scheduling zone based on whether the change in water level in front of the control gate of the associated canal exceeds a water level change threshold includes: obtaining the location of the water diversion disturbance, the amount of flow disturbance, and the duration; setting a dynamic zone water level change threshold; using the canal where the water diversion disturbance occurs as the initial dynamic scheduling zone; calling a linear hydraulic process analysis model to calculate the change in water level in front of the control gate of the upstream and downstream associated canals; from the downstream perspective, determining whether the change in water level in front of the control gate of the adjacent canal downstream of the current dynamic scheduling zone exceeds the water level change threshold; if it does not exceed the threshold, stopping the downstream expansion; if it exceeds the threshold, including the adjacent downstream canal in the dynamic scheduling zone, and targeting... The updated dynamic scheduling partition determines whether the water level change in front of the control gate of the downstream adjacent river or canal exceeds the water level change threshold, until the dynamic scheduling partition stops expanding downstream. From the upstream perspective, it determines whether the water level change in front of the control gate of the upstream adjacent river or canal of the current dynamic scheduling partition exceeds the water level change threshold. If it does not exceed the threshold, it stops expanding upstream. If it exceeds the threshold, the upstream adjacent river or canal is included in the dynamic scheduling partition. The updated dynamic scheduling partition then determines whether the water level change in front of the control gate of the upstream adjacent river or canal exceeds the water level change threshold, until the dynamic scheduling partition stops expanding upstream. The river or canal range determined when expansion stops is taken as the final dynamic scheduling partition corresponding to the current water diversion disturbance.
[0012] The hydraulic process linear analysis model is used to calculate the change in water level in front of the control gates of the associated river and canal. This includes: inputting the flow rates of the upstream and downstream control gates, diversion gates and drainage gates of the river and canal at various time periods, and estimating the water storage capacity of the river and canal at various time periods; and combining the water conveyance loss of the river section, using the calibrated hydraulic process linear analysis model to estimate the change in water level in front of the control gates of the associated river and canal.
[0013] An augmented objective function is constructed based on the degree of violation of various constraints by the current scheduling scheme. This includes: calculating the over-limit amount of each constraint of the current scheduling scheme for each canal, and obtaining the degree of violation of each constraint by the current scheduling scheme; using the pre-set penalty factors corresponding to each constraint to perform a weighted summation of the degree of violation of each constraint, and adding the weighted summation result to the original objective function value to obtain the augmented objective function value.
[0014] The augmented objective function is combined to perform successive approximation-stepwise optimization of the optimization scheduling model to obtain the final scheduling result. This includes: setting optimization solution engineering parameters, determining the initial flow and initial water level of each canal control gate; after optimizing the flow of all control gates in all time periods within the target time for all control gates in the dynamic scheduling zone, determining whether the optimization result meets the convergence termination condition; when the optimization result meets the convergence termination condition, outputting the optimization scheduling process and scheduling scheme. Attached Figure Description
[0015] Figure 1 A flowchart illustrating a dynamic zoning scheduling method for a water conveyance system based on the hydraulic blocking effect, provided in an embodiment of the present invention;
[0016] Figure 2 This is a schematic diagram of an electronic device structure provided in an embodiment of the present invention. Detailed Implementation
[0017] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions in the embodiments of this invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this invention. All other embodiments obtained by those skilled in the art based on the embodiments of this invention without inventive effort are within the scope of protection of this invention. Unless otherwise defined, the technical or scientific terms used herein should have the ordinary meaning understood by those skilled in the art. The terms "comprising" and similar expressions used herein mean that the element or object preceding the word covers the element or object listed following the word and its equivalents, but do not exclude other elements or objects.
[0018] This embodiment provides a dynamic zoning scheduling method for a water conveyance system based on the hydraulic blocking effect.
[0019] See Figure 1 The method includes:
[0020] S101: Based on the changes in river and canal flow and water loss in the water conveyance system, a linear mapping relationship between the changes in storage capacity and the changes in water level in front of the control gate is established to obtain a linear analysis model of the hydraulic process of the river and canal.
[0021] In a specific embodiment, historical monitoring data such as inflow, outflow, diversion flow, and downstream water level of the river channel are first acquired, and the flow rate is selected as the core driving factor affecting the downstream water level based on the information entropy-mutual information method. Based on this, according to the principle of river channel water balance, a linear mapping relationship is established between the change in river channel storage capacity over a period of time (determined by the difference between inflow, outflow, and diversion flow rates and the duration of the period) and the change in water level in front of the control gate. Simultaneously, a parameterized water loss term is introduced to characterize the impact of water losses such as evaporation and seepage on the water level response. A linear analysis model of the hydraulic process is constructed according to the logic of input flow rate change and loss → output water level fluctuation. The core formula of the linear analysis model of the hydraulic process is: ,in, express Changes in water level in front of the control gate during a given time period. This represents a linear mapping function for the hydraulic process of a river or canal based on changes in storage capacity. Indicates the hydraulic blocking coefficient. express The change in average flow rate of the river or canal over a given period of time. express Loss of water flow during the river and canal transport period Indicates the duration of the calculation period. Represents static coefficients. express Water level in front of the canal control gate during a certain period of time express The water level in front of the canal control gate during a certain period.
[0022] In the linear analysis model of hydraulic processes, the duration of the calculation period is... The sampling interval was set based on actual monitoring data, using the time period length corresponding to the conventional monitoring frequency in engineering; the parameters to be optimized in the model include the hydraulic blocking coefficient. and static coefficients Water conveyance loss refers to the amount of water lost during water conveyance due to evaporation, leakage, and other reasons. It is closely related to the channel flow state and channel bed boundary conditions. In the linear analysis model of the hydraulic process described above, the water conveyance loss term can be characterized as a functional relationship between the inflow, outflow, distribution flow, and downstream water depth of the canal. Specifically, it can be calculated using the water conveyance loss calculation function. Characterization. For example, the general functional expression for the water conveyance loss term is: ,in, The function representing the water conveyance loss can be characterized by any of the following forms: constant function, linear function, or nonlinear function. It is used to calculate the water conveyance loss flow rate of rivers and canals caused by evaporation, leakage, and structural operating losses per unit time, with the unit being m³ / s. This indicates the inflow rate into the river or canal, specifically the flow rate entering the river or canal from the upstream control gate. The unit is m³ / s. The larger the value, the greater the total amount of seepage and evaporation loss along the river or canal. The outflow rate of a river or canal is the flow rate that flows out of the river or canal from the downstream control gate. The unit is m³ / s. Together with the inflow rate, it determines the residence time of water in the river or canal and the average water depth, which in turn affects the amount of water loss. The total water distribution flow at each branch point along the canal is expressed in m³ / s. It represents the change in the water volume and hydraulic state of the canal caused by water users taking water, and indirectly affects water transport losses. The water level upstream of the downstream control gate of the canal, expressed in meters (m), reflects changes in the cross-sectional area, wetted perimeter, and hydraulic radius of the canal. It is a key hydraulic element affecting canal leakage and surface evaporation losses. The parameters to be optimized in the model (hydraulic blocking coefficient and static coefficient) and the parameters of the water conveyance loss term are determined by minimizing the calibration objective function.
[0023] S102: Use historical monitoring data of the water conveyance system to calibrate the hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process in order to quantify the hydraulic blocking effect.
[0024] The hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process are calibrated using historical monitoring data of the water conveyance system. This includes: defining the objective function for calibration as minimizing the mean square error between the simulated water level and the measured water level; quantifying the mean square error of the linear analysis model of the hydraulic process during the historical simulation period using historical monitoring data based on the objective function; and calibrating the hydraulic blocking coefficient and static coefficient by minimizing the mean square error.
[0025] The hydraulic blocking effect refers to a natural hydraulic phenomenon in river and canal water conveyance systems where water level fluctuations gradually decrease and their propagation range is limited due to the resistance along the canal and the obstruction and regulation of hydraulic structures such as gates, aqueducts, and inverted siphons.
[0026] In this embodiment, the intensity of the hydraulic blocking effect is used to define the propagation range of water level fluctuations; the hydraulic process linear analysis model constructed in S101 is used as a quantitative tool for the hydraulic blocking effect, and the hydraulic blocking coefficient and static coefficient in the hydraulic process linear analysis model together constitute the key index system for quantifying the hydraulic blocking effect.
[0027] Specifically, the design hydraulic blocking coefficient It reflects the dynamic response sensitivity of river and canal water levels to changes in flow rate. The smaller the value, the lower the rate of water level change caused by a unit flow change, and the less sensitive the water level in front of the downstream control gate of the canal is to changes in the canal flow, that is, the stronger the hydraulic blocking effect of the canal. The value does not change with operating conditions such as flow rate and water level; it is only closely related to the inherent characteristics of the canal, such as its length, roughness, and bottom width. (Design static coefficient) It reflects the baseline water level of the river or canal when there is no change in flow. The smaller the value, the stronger the river and canal's ability to maintain its own balance under static conditions, that is, the better the static stability of the river and canal system. The value is also only related to the characteristics of the canal itself and does not change with the operating conditions.
[0028] Hydraulic blocking coefficient With static coefficients The values were obtained through differential evolution algorithm, synchronously calibrated based on actual historical monitoring data (including inflow, outflow, diversion flow, and downstream water level) of each river channel. , The value is uniquely determined.
[0029] In one specific embodiment, the differential evolution (DE) algorithm is used to synchronously calibrate the hydraulic blocking coefficient. and static coefficients The objective function is to minimize the mean square error between the simulated water level and the measured water level. The expression of the objective function satisfies: ,in, Represents the objective function value; The length of the training data refers to the total number of valid samples in the historical observation data sequence used for parameter calibration (including inflow, outflow, diversion flow, and water level in front of the downstream control gate). express The measured water level in front of the control gate of the canal at any time, in meters; express The water level upstream of the control gate of the canal, obtained from the linear analysis model of the hydraulic process at any given time, is expressed in meters (m). The mechanism by which the objective function affects parameter optimization is as follows: As the sole quantitative indicator of individual fitness in the DE algorithm, for each set of candidate parameters The candidate parameters are substituted into the linear analysis model of the hydraulic process to calculate the simulated water level for each time period. and the measured water level at the same time Calculate the mean square error after taking the difference; The smaller the value, the higher the agreement between the simulated and measured water level processes under the candidate parameters, and the better the fitness of the corresponding individual. The DE algorithm drives the population towards [a higher fitness level] through iterative evolution via mutation, crossover, and selection operations. The direction of decrease continues to evolve, when When it converges to a stable minimum, the corresponding set This represents the globally optimal parameter combination for the canal under the current operating conditions. The objective function guides the calibration process. and The value of , under the premise of clear physical meaning, enables the linear analysis model of hydraulic process to have the optimal water level simulation accuracy.
[0030] S103: When a water diversion disturbance occurs during the scheduling of the water conveyance system, the propagation range of the water diversion disturbance is determined based on the hydraulic blocking effect to dynamically partition the water conveyance system. This includes: obtaining the location of the water diversion disturbance, the amount of flow disturbance, and the duration; setting a dynamic partition water level change threshold; taking the river or canal where the water diversion disturbance occurs as the initial dynamic scheduling partition; calling the hydraulic process linear analysis model to calculate the water level change in front of the control gate of the associated river or canal; determining whether the water level change in front of the control gate of the associated river or canal exceeds the water level change threshold; and including the associated river or canal that exceeds the threshold in the dynamic scheduling partition.
[0031] A dynamic zone water level change threshold is set. In water conservancy project scheduling and control, the water level control accuracy generally does not exceed 0.01m; therefore, the water level change threshold can be determined to be 0.01m. The location, flow disturbance amount, and duration of the water diversion disturbance are obtained. The dynamic zone water level change threshold is set, with the canal where the water diversion disturbance occurs as the initial dynamic scheduling zone. A linear hydraulic process analysis model is used to calculate the water level change in front of the control gates of the upstream and downstream connected canals. From the downstream perspective, it is determined whether the water level change in front of the control gates of the adjacent downstream canals of the current dynamic scheduling zone exceeds the water level change threshold. If it does not exceed the threshold, the downstream expansion stops. If it exceeds the threshold, the downstream adjacent canals are included in the dynamic scheduling zone. For the updated dynamic scheduling zone, it is determined whether the water level change in front of the control gates of the downstream adjacent canals exceeds the water level change threshold, until the dynamic scheduling zone stops expanding downstream. From the upstream perspective, it is determined whether the water level change in front of the control gate of the adjacent upstream canal in the current dynamic scheduling zone exceeds the water level change threshold. If it does not exceed the threshold, the upstream expansion stops. If it exceeds the threshold, the adjacent upstream canal is included in the dynamic scheduling zone, and the water level change in front of the control gate of the adjacent upstream canal is checked against the updated dynamic scheduling zone to see if it exceeds the water level change threshold, until the dynamic scheduling zone stops expanding upstream. The canal range determined when expansion stops is taken as the final dynamic scheduling zone corresponding to the current water diversion disturbance.
[0032] The hydraulic process linear analysis model is used to calculate the changes in water level upstream of the control gates of the associated canals. This includes inputting the flow rates of the upstream and downstream control gates, diversion gates, and drainage gates of the canals at various time periods, and estimating the canal storage capacity at each time period. Combined with the water conveyance loss of the river section, the calibrated hydraulic process linear analysis model is used to estimate the changes in water level upstream of the control gates of the associated canals.
[0033] Based on the above calculation method, the change in water level in front of the control gate of each canal in the entire water conveyance system can be obtained by calculating the water level of each canal separately.
[0034] During the scheduling of the river and canal water conveyance system, the water consumption at the branch outlets along the route often changes. In this embodiment, when the flow rate at the branch outlet changes, the water level response of each river and canal along the route is simulated using a linear hydraulic process analysis model. Based on the simulated change in the water level in front of the control gate corresponding to the flow rate change at the branch outlet, the boundary of the branch outlet fluctuation is determined to divide the dynamic scheduling zones.
[0035] Specifically, the core of the dynamic scheduling zoning design lies in the following: when a flow change occurs at a certain water diversion point, simulation calculations are performed using a linear hydraulic process analysis model. The simulated changes in the water level upstream of the control gate of each canal are compared with a set water level change threshold. If the water level change upstream of the control gate exceeds the water level change threshold, the impact of the flow fluctuation at that water diversion point is considered to have propagated to the corresponding canal; otherwise, the impact is considered negligible. The canal at which the impact propagation is determined to be the furthest point is used as the boundary of the fluctuation at that water diversion point, and dynamic scheduling zones are delineated accordingly.
[0036] In a specific embodiment, the specific judgment process for dynamic scheduling phases is as follows:
[0037] The location, flow disturbance amount, and duration of the water diversion disturbance are obtained. The river or canal where the disturbance occurs is used as the initial dynamic scheduling zone, and a dynamic zone water level change threshold is set. The water level change threshold can be manually set according to project requirements; if not manually set, a pre-set default value will be used. For example, the default value can be a water level monitoring tolerance error of 0.01m.
[0038] The hydraulic process linear analysis model is used to calculate the water level changes in the upstream and downstream canals of the dynamic scheduling zone at the gates. Specifically, the calculations performed by the hydraulic process linear analysis model include: determining the specific canal number in the entire canal where the water-dividing disturbance occurs based on the location of the disturbance, then setting that canal as the initial dynamic scheduling zone, and clarifying the range of related canals for which the water level change to be calculated is currently being determined. The flow disturbance is substituted into the hydraulic process linear analysis model to determine the average flow change in the canal; specifically, the average flow change in the canal is taken as the algebraic sum of the flow disturbance and other flow changes (such as inflow and outflow changes) in the canal during the corresponding time period. When the water-dividing disturbance is a single disturbance source and the flow at the upstream and downstream gates has not been adjusted, the average flow change in the canal is directly taken as the value of the flow disturbance. The duration period is used to define the time domain range of the hydraulic process linear analysis model calculation; the hydraulic process linear analysis model takes the starting time of the water-dividing disturbance as the starting point and the duration period as the total calculation time, and calculates the duration period. (The data sampling interval is consistent with that used in the calibration model.) The calculation is divided into several continuous calculation periods, and the model is called in turn to extrapolate the water level change for each period. When the water diversion disturbance lasts for multiple periods, the hydraulic process linear analysis model uses the actual flow disturbance in each period as input to recursively calculate the water level change in front of the control gate of the canal, thus obtaining the water level response process during the duration of the water diversion disturbance and after the disturbance ends. It should be noted that the hydraulic process linear analysis model must ensure that the time scale of each input parameter is consistent, that is, the flow disturbance, the time step, and the water level change all use a unified time base (such as hour or day) to ensure the physical consistency and comparability of the calculation results.
[0039] Determine whether the change in water level in front of the control gate of the adjacent downstream river in the current dynamic scheduling zone exceeds the water level change threshold. If it does, add the adjacent downstream river to the dynamic scheduling zone, recalculate the change in water level in front of the control gate of the adjacent downstream river in the updated dynamic scheduling zone, and determine whether to expand the dynamic scheduling zone until the dynamic scheduling zone stops expanding downstream.
[0040] Determine whether the change in water level in front of the control gate of the upstream adjacent river in the current dynamic scheduling zone exceeds the water level change threshold. If it does, add the upstream adjacent river to the dynamic scheduling zone, recalculate the change in water level in front of the control gate of the upstream adjacent river in the updated dynamic scheduling zone, and determine whether to expand the dynamic scheduling zone until the dynamic scheduling zone stops expanding upstream.
[0041] The canal extent determined when expansion ceases is used as the final dynamic scheduling zone corresponding to the water diversion disturbance. During scheduling, only local optimization scheduling is performed on the control gates and water diversion outlets within the determined dynamic scheduling zone; no unified calculation across the entire line is required.
[0042] It should be noted that if the water level in the boundary canals of the dynamically managed zone still poses a risk of exceeding the limit after local optimization scheduling, the zone should be expanded outwards until the water level fluctuations in all boundary canals do not exceed the water level change threshold. Conversely, if the water level fluctuations in the boundary canals of a zone are far below the water level change threshold (e.g., less than 50% of the threshold), the scheduling zone can be considered for contraction to reduce unnecessary control range. Furthermore, during local optimization scheduling, water level changes in canals outside the zone should be monitored simultaneously. When the water level fluctuations caused by water diversion disturbances accumulate in canals outside the zone and exceed the water level change threshold, the corresponding canals should be included in the zone in the next scheduling cycle to ensure the safety of water transfer along the entire line.
[0043] S104: An optimized scheduling model is constructed with the goal of minimizing the deviation between the water level in front of the gate and the target water level and minimizing the number of gate actions in the dynamic scheduling zone. The upper and lower limits of the water level of the control gate, the flow rate and the water level fluctuation constraints are set. An augmented objective function is constructed based on the degree of violation of each constraint by the current scheduling scheme. The optimized scheduling model is solved by combining the augmented objective function to obtain the final scheduling result.
[0044] An augmented objective function is constructed based on the degree of violation of various constraints by the current scheduling scheme. This includes: calculating the over-limit amount of each constraint of the current scheduling scheme for each canal, and obtaining the degree of violation of each constraint by the current scheduling scheme; using the pre-set penalty factors corresponding to each constraint to perform a weighted summation of the degree of violation of each constraint, and adding the weighted summation result to the original objective function value to obtain the augmented objective function value.
[0045] The final scheduling result is obtained by solving the optimization scheduling model by combining the augmented objective function, including: setting the optimization solution engineering parameters, determining the initial flow and initial water level of each river and canal control gate; after optimizing the flow of all control gates in all time periods within the target time for all control gates in the dynamic scheduling zone, judging whether the optimization result meets the convergence termination condition; when the optimization result meets the convergence termination condition, outputting the optimization scheduling process and scheduling scheme.
[0046] In a specific embodiment, with the optimization objectives of minimizing the deviation between the water level in front of the gate and the target water level and minimizing the number of gate actions, an optimized scheduling model is constructed for the dynamic scheduling zone. The upper and lower limits of the water level of the control gate, the flow rate, and the water level fluctuation constraints are set to ensure the safe and stable operation of the canal.
[0047] Specifically, the water level control target can be expressed as the following formula: ,in, This represents the average deviation between the water level upstream of each control gate and the target water level. Indicates the number of time periods in the scheduling period. Indicates the number of control gates. express Time period The water level upstream of each control gate express Time period The target water level upstream of each control gate.
[0048] The target number of gate actuations can be expressed by the following formula: ,in, This represents the total number of times all gates have been activated. Indicates the first A control gate in Number of actions during a given time period.
[0049] The upper and lower limits of the water level at the control gate can be expressed by the following formula: ,in, and These are the lower and upper limits of the water level at the control gate, respectively, in meters. They are determined based on the safety elevation of the channel lining structure (upper limit) and the minimum water level requirement for downstream water intake (lower limit) in the engineering design, and are inherent design parameters of the project.
[0050] The overcurrent constraint can be expressed as the following formula: ,in, and These are the lower and upper limits of the overcurrent flow rate, respectively, in m³ / s. They are determined based on the maximum overcurrent capacity (upper limit) and minimum adjustable flow rate (lower limit) of the control gate and are inherent design parameters of the project. This represents the overcurrent flow rate of the control gate during time period t.
[0051] The water level fluctuation constraint can be expressed by the following formula: , The threshold for controlling the change in gate water level, in meters, is set manually by the engineering operation and management unit based on the safety requirements of the channel lining structure and the accuracy requirements of gate control. In the absence of specific engineering regulations, the value can be adopted based on engineering operation experience or by referring to the value of similar projects. This represents the change in water level at the control gate during time period t.
[0052] A penalty function strategy can be used to transform different types of constraints into computable violation indices, thus converting nonlinear constrained optimization problems into unconstrained optimization problems. The specific processing procedure is as follows:
[0053] Calculate the degree of violation of each constraint by the current scheduling scheme, including the extent of exceeding the upper and lower water level limits, the extent of exceeding the flow rate constraints, and the extent of exceeding the water level fluctuation constraints, to obtain the degree of violation of each constraint by the current scheduling scheme. For example, the extent of exceeding the upper and lower water level limits is calculated as follows: Calculation; Over-limit amount of overcurrent constraint according to Calculation; the overrun of water level fluctuation constraints is calculated according to... Calculate; use the calculated excess amount as the degree of violation of the corresponding constraints by the current scheduling scheme.
[0054] Multiply the exceedance amount of each constraint by its corresponding penalty factor to obtain the penalty term for each constraint. Sum all penalty terms and add them to the original objective function value to form the augmented objective function. The augmented objective function can be expressed as follows: ,in, This represents the value of the augmented objective function. F represents the original objective function value. , This indicates the total number of constraints. Indicates the first Penalty factor for the constraint, Indicates the first The degree of constraint violation. When the scheduling scheme satisfies all constraints, the degree of violation is zero, and the augmented objective function value equals the original objective function value. When the scheduling scheme violates any constraint, the augmented objective function value will be penalized and increase accordingly. In the process of optimizing the scheduling scheme, it will naturally tend to choose the scheme with a smaller degree of violation or even zero, thus transforming the constrained problem into an unconstrained problem for processing.
[0055] For example, the optimized scheduling model can be solved using the Dynamic Programming Successive Approximation-Planetary Optimization Algorithm (DPSA-POA), and the solution process is as follows:
[0056] First, the parameters of the successive approximation-stepwise optimization algorithm are initialized, and the initial solution and the initial flow and initial water level of each canal control gate are determined. The initialized parameters include the scheduling period, time period length, number of gates, dimension of decision variables, discretization precision, and convergence criteria. The initial solution is determined by either introducing an initial solution or randomly generating an initial solution within the range of decision variable values.
[0057] First, the outer loop iterates through successive approximations to progressively optimize the control gates: each time, a control gate is selected as the target control gate for optimization calculation. After determining the target control gate, the gate flow of the remaining control gates is fixed, and the target control gate is progressively optimized. In the inner loop of progressive optimization of the target control gate, the flow of the target control gate is optimized in time periods. When optimizing the flow of each time period, the flow of the remaining time periods is fixed, and the feasible region under the constraints of the current optimization time period is derived. The number or precision of discrete points within the search range of the feasible region is set, and the scheduling process corresponding to all discrete flow points in the feasible region is traversed. The augmented objective function value is calculated, and the flow scheduling process that minimizes the augmented objective function value is selected to obtain the optimal scheduling scheme to complete the flow optimization of that time period. The time period flow optimization of the target control gate is progressively optimized in the same way for all time periods.
[0058] After optimizing the gate flow of a control gate, the next control gate with unoptimized gate flow is selected as the target control gate, and the time-period flow of the target control gate is optimized according to the above optimization scheme for all time periods until the gate flow of all control gates in the dynamic scheduling partition is optimized and the optimization result is obtained, then the convergence verification stage is entered. Specifically, the convergence verification includes: determining whether the optimization result meets the convergence termination condition. If the determination result is yes, the final scheduling result is output; otherwise, the successive approximation-stepwise optimization solution is repeated to continue the optimization process. For example, the convergence termination condition may be that the change in the augmented objective function value is less than a preset convergence threshold or the number of iterations reaches a set upper limit.
[0059] In a specific embodiment, the dynamic zonal scheduling method for water conveyance systems based on the hydraulic blocking effect of this invention and the traditional unified scheduling method for the entire line are applied for verification. A case study is conducted using the daily short-term scheduling of a water transfer project within a ten-day period, specifically covering the area from control gate No. 2 to control gate No. 61, with a total length of approximately 1183 kilometers. This section is a crucial component of the water conveyance scheduling of the aforementioned water transfer project, characterized by its long distance, complex structure, and close hydraulic connections. Within the study area, the main canal has 60 control gates, 75 branch outlets, and 52 drainage gates. These control gates divide the continuous canal into 59 independent canal pools connected in series, forming a typical cascade series open channel water conveyance system. Verification results show that dynamic zonal scheduling has significant advantages over unified scheduling across the entire line: under the condition of reduced branch flow, the model solution time can be reduced from 46375.55s to 22.26s, and the number of gate actions in the core area decreases by 33.3%; under the condition of increased branch flow, the model solution time can be reduced from 48716.73s to 1107.11s, and the number of gate actions in the core area decreases by 14.3%. The maximum water level deviation under both conditions is controlled within 0.1m, with no drainage phenomenon and meeting water supply requirements. The flow and water level of all control gates meet operational constraints.
[0060] The dynamic zoning scheduling method for water conveyance systems based on the hydraulic blocking effect provided by this invention designs a linear analysis model of the hydraulic process that can accurately quantify the hydraulic blocking effect of rivers and canals. It can dynamically identify the dynamic scheduling zoning boundary according to the propagation range of water diversion disturbance, realize local targeted scheduling of the water conveyance system, and improve scheduling calculation efficiency and response speed.
[0061] The linear hydraulic process analysis model of this invention abandons the idealized cross-section assumption of traditional integral time-delay models, directly establishing a linear relationship between flow rate changes, water loss, and water level response over time periods, significantly improving simulation accuracy. The linear hydraulic process analysis model designs hydraulic blocking coefficients and static coefficients to quantitatively characterize the hydraulic blocking effect and provides a physical basis for the division of dynamic scheduling zones, enabling accurate identification of the actual propagation range of water diversion disturbances. Based on the results of dynamic scheduling zone division, the optimized scheduling scheme transforms traditional full-line scheduling into local scheduling, significantly reducing the solution scale of the scheduling problem while ensuring scheduling accuracy, improving scheduling computational efficiency and response speed, and achieving a balance between scheduling accuracy and engineering operating costs.
[0062] In other embodiments of this application, an electronic device is disclosed, such as... Figure 2As shown, the electronic device 200 may include: one or more processors 201; a memory 202; a display 203; one or more application programs (not shown); and one or more computer programs 204. These devices can be connected via one or more communication buses 205. The one or more computer programs 204 are stored in the memory and configured to be executed by the one or more processors 201. The one or more computer programs 204 include instructions that can be used to perform actions such as... Figure 1 And the steps in the corresponding embodiments.
[0063] Through the above description of the embodiments, those skilled in the art will clearly understand that, for the sake of convenience and brevity, only the division of the above functional modules is used as an example. In practical applications, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device can be divided into different functional modules to complete all or part of the functions described above. The specific working process of the system, device, and unit described above can be referred to the corresponding process in the foregoing method embodiments, and will not be repeated here.
[0064] In the embodiments of this application, the functional units can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit.
[0065] If the integrated unit is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solutions of the embodiments of this application, essentially, or the parts that contribute to the prior art, or all or part of the technical solutions, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) or processor to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned storage medium includes various media capable of storing program code, such as flash memory, portable hard disk, read-only memory, random access memory, magnetic disk, or optical disk.
[0066] The above description is merely a specific implementation of the embodiments of this application, but the protection scope of the embodiments of this application is not limited thereto. Any changes or substitutions within the technical scope disclosed in the embodiments of this application should be covered within the protection scope of the embodiments of this application. Therefore, the protection scope of the embodiments of this application should be determined by the protection scope of the claims.
Claims
1. A dynamic zonal scheduling method for a water conveyance system based on the hydraulic blocking effect, characterized in that, include: Based on the changes in river and canal flow and water loss in the water conveyance system, a linear mapping relationship between the changes in storage capacity and the changes in water level in front of the control gate is established to obtain a linear analysis model of the hydraulic process of the river and canal. The hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process are calibrated using historical monitoring data of the water conveyance system to quantify the hydraulic blocking effect. When a water diversion disturbance occurs during the scheduling of the water conveyance system, the propagation range of the water diversion disturbance is determined based on the hydraulic blocking effect to dynamically partition the water conveyance system. This includes: obtaining the location of the water diversion disturbance, the amount of flow disturbance, and the duration; setting a dynamic partition water level change threshold; taking the river or canal where the water diversion disturbance occurs as the initial dynamic scheduling partition; calling the hydraulic process linear analysis model to calculate the water level change in front of the control gate of the associated river or canal; determining whether the water level change in front of the control gate of the associated river or canal exceeds the water level change threshold; and including the associated river or canal that exceeds the threshold in the dynamic scheduling partition. An optimized scheduling model is constructed with the optimization objectives of minimizing the deviation between the water level in front of the gate and the target water level and minimizing the number of gate actions in the dynamic scheduling zone. The upper and lower limits of the water level of the control gate, the flow rate and the water level fluctuation constraints are set. An augmented objective function is constructed based on the degree of violation of each constraint by the current scheduling scheme. The optimized scheduling model is solved by combining the augmented objective function to obtain the final scheduling result.
2. The method according to claim 1, characterized in that, The expression of the linear analysis model of the hydraulic process satisfies: ,in, express Changes in water level in front of the control gate during a given time period. Indicates the hydraulic blocking coefficient. express The change in average flow rate of the river or canal over a given period of time. express Loss of water flow during the river and canal transport period Indicates the duration of the calculation period. Represents static coefficients. express Water level in front of the canal control gate during a certain period of time. express The water level in front of the canal control gate during a certain period.
3. The method according to claim 1, characterized in that, The hydraulic blocking coefficient and static coefficient in the linear analysis model of the hydraulic process are calibrated using historical monitoring data of the water conveyance system, including: The objective function for calibration is defined as minimizing the mean square error between the simulated water level and the measured water level. Based on the objective function, using historical monitoring data, the mean square error of the linear analysis model of the hydraulic process during the historical simulation period is quantified; the hydraulic blocking coefficient and static coefficient are calibrated by minimizing the mean square error.
4. The method according to claim 1, characterized in that, Whether a related river or canal should be included in the dynamic scheduling zone is determined based on whether the change in water level upstream of the control gate exceeds the water level change threshold, including: The location, flow disturbance amount, and duration of the water diversion disturbance are obtained, and a dynamic zone water level change threshold is set, with the river or canal where the water diversion disturbance occurs as the initial dynamic scheduling zone. The linear analysis model of the hydraulic process is used to calculate the change in water level in front of the control gate of the upstream and downstream related canals; From the downstream perspective, it is determined whether the change in water level in front of the control gate of the adjacent river channel downstream of the current dynamic scheduling zone exceeds the water level change threshold. If it does not exceed the threshold, the downstream expansion stops. If it exceeds the threshold, the adjacent river channel downstream is included in the dynamic scheduling zone. The updated dynamic scheduling zone is then used to determine whether the change in water level in front of the control gate of the adjacent river channel downstream exceeds the water level change threshold until the dynamic scheduling zone stops expanding downstream. From the upstream perspective, it is determined whether the change in water level in front of the control gate of the adjacent river channel upstream of the current dynamic scheduling zone exceeds the water level change threshold. If it does not exceed the threshold, the upstream expansion stops. If it exceeds the threshold, the adjacent river channel upstream is included in the dynamic scheduling zone. The updated dynamic scheduling zone is then determined whether the change in water level in front of the control gate of the adjacent river channel upstream exceeds the water level change threshold until the dynamic scheduling zone stops expanding upstream. The extent of the canal determined when the expansion stops is used as the final dynamic scheduling partition corresponding to the current water diversion disturbance.
5. The method according to claim 2, characterized in that, The linear analysis model of the hydraulic process is used to calculate the change in water level upstream of the control gate of the associated river channel, including: Input the flow rates of upstream and downstream control gates, diversion gates and drainage gates of the river and canal at various time periods, and calculate the water storage capacity of the river and canal at various time periods; Based on the water conveyance loss of the river section, the water level change in front of the control gate of the associated river channel is calculated using a calibrated linear hydraulic process analysis model.
6. The method according to claim 1, characterized in that, An augmented objective function is constructed based on the degree to which the current scheduling scheme violates various constraints, including: Calculate the extent to which the current scheduling scheme violates each constraint condition for each canal, thus obtaining the degree of violation of each constraint condition by the current scheduling scheme; The degree of violation of each constraint is weighted and summed using the penalty factors corresponding to the preset constraints. The weighted sum is then added to the original objective function value to obtain the augmented objective function value.
7. The method according to claim 1, characterized in that, The final scheduling result is obtained by solving the optimized scheduling model using the augmented objective function, including: Set optimization solution parameters to determine the initial flow rate and initial water level of each river and canal control gate; After optimizing the flow of all control gates within the dynamic scheduling partition for all time periods within the target time, determine whether the optimization result meets the convergence termination condition. When the optimization result meets the convergence termination condition, output the optimized scheduling process and scheduling scheme.