Modular combined support construction method and system for cast-in-place bridge sidewall construction
By combining a multi-point distributed anchoring system and a modular support system of cantilever load-bearing structures, the problems of high cost, insufficient rigidity and poor adaptability in traditional cast-in-place construction of bridge sidewalls have been solved, realizing construction without grounding and efficient and safe bridge construction.
Patent Information
- Application Number
- CN202611579588.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-13
- Publication Date
- 2026-11-17
AI Technical Summary
In the existing cast-in-place construction of bridge sidewalls, the traditional support system lacks modular design, resulting in high construction costs, insufficient overall rigidity, low elevation control accuracy, poor adaptability to complex bridge types, and the inability to achieve groundless construction when crossing roads and waterways, affecting traffic and waterway navigation.
A modular combined support system is constructed by combining a multi-point distributed anchoring system with a cantilever load-bearing structure. The system forms an integrated rigid connection through the layered assembly of standardized modules. Combined with a multi-point synchronous adjustment system and real-time monitoring technology, the integrated stress and precise control of the template and support are achieved.
It enables the in-situ construction of bridge sidewalls without interrupting traffic and waterway navigation, reducing construction costs, improving construction efficiency and safety, adapting to the construction needs of complex bridge types, and allowing modular components to be reused, thus reducing material waste.
Smart Images

Figure CN123109077A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of bridge construction technology, and in particular relates to a modular combined support construction method and system for cast-in-place construction of bridge sidewalls. Background Technology
[0002] Cast-in-place construction of bridge sidewalls is a crucial step in the construction of urban rail transit, highways, and bridge projects. With the rapid development of infrastructure construction, more and more bridges need to cross existing roads, rivers, railways, or viaducts. These special construction scenarios place extremely high demands on the support system. Traditional ground-based support systems, such as full-span scaffolding and Bailey bridges, cannot be constructed without interrupting traffic or affecting river navigation because they require ground space.
[0003] While existing steel bracket cantilever support systems enable construction without ground contact, they suffer from several technical drawbacks in practical applications: First, the support systems are often custom-designed, lacking standardization and modularization, making them difficult to apply across different projects, resulting in low component reuse rates and high construction costs. Second, the overall structural stiffness and stability are insufficient, making them prone to significant deformation under construction loads, affecting construction quality and safety. Third, the formwork system and support system are independent of each other, failing to form an integrated load-bearing structure, leading to unclear load transfer paths and potential localized stress concentrations. Fourth, they only offer localized adjustment capabilities, with low precision in elevation and alignment control, and poor adaptability to complex bridge types such as curved bridges and bridges with varying widths. Fifth, in special scenarios such as crossing roads and rivers, there is a lack of targeted safety protection and emergency measures, resulting in higher construction risks.
[0004] Especially during construction projects spanning urban arterial roads and BRT lanes, traffic disruptions can cause significant social impacts and economic losses. Therefore, developing an efficient, safe, and economical support system for in-situ cast-in-place bridge sidewall construction without interrupting traffic or affecting river navigation has become a pressing technical challenge for the industry. Summary of the Invention
[0005] This application addresses the problems existing in the prior art by proposing a modular combined support construction method and system for cast-in-place bridge sidewall construction. It involves constructing multi-point distributed anchored cantilever foundations on the existing main structure, and using standardized modules for layered assembly to form a stable load-bearing structure with a spatial truss effect. This achieves integrated rigid connection and continuous load transfer between the formwork and the support. A multi-point synchronous adjustment system precisely controls the construction alignment and elevation, while layered pouring and real-time monitoring technologies ensure construction safety. Ultimately, the modular support system can be modularly dismantled and reused. This method is suitable for construction scenarios without ground supports across roads, rivers, or viaducts. It enables cast-in-place bridge sidewall construction without interrupting traffic or affecting river navigation, improving construction efficiency, reducing overall costs, and minimizing traffic congestion. It solves the technical problems of existing support systems, such as non-modularity, insufficient overall stiffness, low elevation control accuracy, and poor adaptability to complex bridge types and special construction environments, and has broad engineering application value.
[0006] To achieve the above objectives, this application provides the following technical solution:
[0007] Firstly, a modular combined support construction method for cast-in-place construction of bridge sidewalls includes the following steps: S1, setting up a multi-point distributed anchoring system on the existing main structure to form a cantilever load-bearing foundation; S2, rigidly connecting the prefabricated cantilever load-bearing structure with the multi-point distributed anchoring system to construct a cantilever construction platform that is completely independent of ground support; S3, on the cantilever construction platform, assembling and connecting standardized vertical bearing modules, oblique stabilization modules, and telescopic adjustment modules in layers through multi-degree-of-freedom connection node modules to form a modular support system with a spatial truss effect; S4, rigidly connecting the formwork system and the modular support system in an integrated manner to form a system from the formwork system and modular support system to the existing main structure. S5. Continuous and uninterrupted load transfer path; S6. Through multi-point adjustable units set at key nodes between the modular support system and the formwork system, the elevation, alignment, and inclination of the formwork system are synchronously adjusted to the design allowable deviation range using an overall coordination-local correction algorithm; S7. Based on the concrete lateral pressure calculation model, the layered pouring thickness and pouring speed parameters are determined, and the side wall concrete is poured using a layered controlled pouring process according to the determined parameters. The formwork displacement, support deformation, anchor point stress, and node loosening status of the modular support system are monitored in real time based on the load-deformation prediction model; S8. After the concrete reaches the design strength, the modular support system is dismantled in modules, and each dismantled module is transferred to the next construction section for reuse.
[0008] Optionally, in step S1, the cantilevered foundation can simultaneously transmit vertical loads, horizontal loads, and overturning moments; the multi-point distributed anchoring system arranges at least two rows of anchor points along the height direction of the existing main structure, with each row of anchor points evenly distributed longitudinally to form a spatial stress grid; the anchoring system selects any one of chemical anchors, pre-embedded steel plates, or clamping clamps according to the structural conditions.
[0009] Optionally, in step S1, the layout parameters and bearing requirements of the multi-point distributed anchoring system are calculated based on the spatial force system equilibrium model. The formulas for the spatial force system equilibrium model are shown below:
[0010]
[0011]
[0012] in, To prevent overturning safety factor; This is the design value for single-point anchoring force; This is the design value for the overturning moment; This is the design value for the overturning moment; V is the structural importance coefficient; L is the design value of the total vertical load; n is the vertical distance between the upper and lower rows of anchor points; and n is the number of anchor points in a single row. This represents the design value for the pull-out bearing capacity of a single anchor point.
[0013] Optionally, in step S3, the layered assembly includes:
[0014] S31. Install the first main load-bearing layer, and connect the vertical load-bearing module with the cantilever load-bearing structure through flanges to form the main vertical force transmission system;
[0015] S32. Install the second stabilizing layer, and set the inclined stabilizing module and the vertical bearing module to form a triangular stabilizing structure. The included angle between the inclined stabilizing module and the vertical bearing module is controlled between 30° and 75°.
[0016] S33. When the height of the side wall is greater than 4m, an intermediate reinforcement layer shall be added.
[0017] Optionally, in step S3, the multi-degree-of-freedom connection node module is a two-stage hinged and locking structure, which can realize rotation around the X-axis from 0° to 90° and rotation around the Z-axis from ±45°; the node uses a pin shaft, an arc-shaped dial, and a locking bolt to achieve angle reading and precise locking, and the telescopic adjustment module uses a threaded adjustment rod, a sleeve-type telescopic rod, or a hydraulic adjustment component.
[0018] Optionally, in step S5, the formula for the global coordination-local correction algorithm is as follows:
[0019]
[0020]
[0021] in, Let be the elevation adjustment amount for the i-th node; Let the target elevation of the i-th node be _____. Let be the current elevation of the i-th node.
[0022] Optionally, in step S6, the concrete lateral pressure calculation model is calculated using the following two formulas, and the smaller value is taken:
[0023]
[0024]
[0025] Where F is the maximum pressure exerted by the newly poured concrete on the side formwork, taken as... and The smaller value in; The unit weight of concrete; The initial setting time of freshly poured concrete; This is the correction factor for the influence of admixtures; is the correction factor for the effect of concrete slump; v is the concrete pouring speed; H is the total height of concrete pouring.
[0026] Optionally, in step S6, the formula for the load-deformation prediction model is as follows:
[0027]
[0028] in, Let be the deformation value at time t; t represents the maximum deformation value; k represents the deformation development coefficient; and t represents the pouring time.
[0029] Optionally, in step S6, if the displacement of the modular support system template is greater than 10mm or the force on the anchor point exceeds the design value of the pull-out bearing capacity of a single anchor point or the node becomes loose, the pouring should be stopped immediately, and emergency measures such as adding temporary supports, slowing down the pouring speed, or partially unloading should be taken.
[0030] In a second aspect, the present invention provides a modular combined support construction system for cast-in-place construction of bridge sidewalls, used to implement the modular combined support construction method for cast-in-place construction of bridge sidewalls as described in the first aspect, comprising:
[0031] A multi-point distributed anchoring system is used to connect with the existing main structure and transfer vertical loads, horizontal loads and overturning moments;
[0032] The cantilever load-bearing structure is fixedly connected to the multi-point distributed anchoring system to form a cantilever construction platform that is completely independent of ground support.
[0033] The modular support system is assembled from vertical load-bearing modules, oblique stabilizing modules, multi-degree-of-freedom connection node modules, and telescopic adjustment modules, and is installed on the cantilever load-bearing structure.
[0034] The template system is rigidly connected to the modular support system in an integrated manner;
[0035] Multi-point adjustable units are set at key nodes of the modular support system to adjust the template elevation, alignment and inclination angle;
[0036] The monitoring and control unit is used to monitor the template displacement, support deformation, anchor point stress and node loosening status of the modular support system in real time, and control the synchronous adjustment of multiple adjustable units.
[0037] The beneficial effects of this application are as follows:
[0038] (1) This application constructs a cantilever construction platform that does not rely on ground support at all through a multi-point distributed anchoring system and a cantilever load-bearing structure. In construction scenarios that cross roads, rivers or viaducts, it does not occupy the lanes and pedestrian spaces below, and can ensure normal vehicle passage, avoiding the huge social costs and economic losses caused by traffic interruption. When constructing across rivers, it does not affect the normal navigation of ships and protects the navigation function of the river.
[0039] (2) The modular support system of this application is composed entirely of standardized modules, which are manufactured in factories and quickly assembled on site, reducing installation and dismantling time and shortening the construction period. The modular components have good interchangeability and versatility and can be reused more than 10 times across projects. Compared with traditional customized steel brackets, it reduces material usage and lowers the overall cost.
[0040] (3) This application integrates the formwork system and the modular support system into a rigid connection, forming a clear and continuous load transfer path, which completely solves the problem of unreasonable stress caused by the separation of formwork and support in the traditional system, and effectively avoids quality problems such as formwork bulging and concrete cracking.
[0041] (4) This application adopts multi-degree-of-freedom connection nodes and telescopic adjustment modules, and the support spacing, angle and height can be flexibly adjusted. It can adapt to the construction of various bridge sidewalls with sidewall heights of 2.0-6.0m and thicknesses of 0.3-0.8m, and is particularly suitable for the construction of curved bridges, bridge decks with varying widths and areas with limited space. This variable arrangement capability allows a modular support system to be applied to a variety of different engineering scenarios, greatly improving the utilization rate of the equipment.
[0042] (5) This application reduces the time spent working at heights through modular rapid assembly, improves structural stability through integrated stress design, and ensures safety during construction through real-time monitoring and emergency measures. In particular, it has set up a comprehensive safety protection system to address the special risks of construction across roads and rivers, which reduces the accident rate compared with traditional construction methods and provides reliable safety assurance for high-altitude cantilever construction. Attached Figure Description
[0043] Figure 1 This is a schematic diagram illustrating a modular combined support construction system for cast-in-place construction of bridge sidewalls, according to some embodiments of this application.
[0044] Figure 2 This is a schematic diagram of a modular combined support construction method for cast-in-place construction of bridge sidewalls according to Embodiment 1 of this application;
[0045] Figure 3 This is a schematic diagram of a modular combined support construction system for cast-in-place construction of bridge sidewalls, according to Embodiment 2 of this application. Detailed Implementation
[0046] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description of this application is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely one preferred embodiment of this application and are only used to explain this application. They do not limit the scope of protection of this application. All other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0047] like Figure 1 The diagram illustrates a scenario application of a modular combined support construction system for cast-in-place bridge sidewall construction. In the construction of the sidewall of an elevated bridge above a major urban road, a combined support system of customized steel frames and ground-mounted steel pipe supports is used. The ground-mounted supports directly occupy the lanes below, allowing vehicles to pass slowly. Warning signs are placed on the road surface, resulting in severe traffic congestion and potential traffic accident hazards. In this traditional solution, the steel frame is a customized component for the project and cannot be reused across projects; the formwork and support system are designed separately, leading to discontinuous stress and potential deformation; simultaneously, the amount of high-altitude work is substantial, and the construction period is long, completely failing to meet the requirement of uninterrupted construction in the core urban area.
[0048] Example 1:
[0049] like Figure 2 As shown, a modular combined support construction method for cast-in-place bridge sidewall construction includes the following steps:
[0050] S1. Set up a multi-point distributed anchoring system on the existing main structure to form a cantilever foundation during construction;
[0051] S2. The prefabricated cantilever load-bearing structure is rigidly connected to the multi-point distributed anchoring system to construct a cantilever construction platform that does not rely on ground support at all.
[0052] S3. On the cantilever construction platform, standardized vertical bearing modules, oblique stabilizing modules and telescopic adjustment modules are assembled and connected in layers through multi-degree-of-freedom connection node modules to form a modular support system with spatial truss effect.
[0053] S4. Integrate the formwork system and the modular support system into a rigid connection to form a continuous and uninterrupted load transfer path from the formwork system and the modular support system to the existing main structure.
[0054] S5. By setting up multi-point adjustable units at key nodes between the modular support system and the template system, the elevation, alignment and inclination of the template system are synchronously adjusted to the design allowable deviation range using the overall coordination-local correction algorithm.
[0055] S6. Based on the concrete lateral pressure calculation model, determine the layered pouring thickness and pouring speed parameters, and use the layered controlled pouring process to pour the side wall concrete according to the determined parameters. Based on the load-deformation prediction model, monitor the template displacement, support deformation, anchor point stress and node loosening status of the modular support system in real time.
[0056] S7. After the concrete reaches the design strength, the modular support system is dismantled in sections, and each dismantled module is transferred to the next construction section for reuse.
[0057] Specifically, in step S1, the existing main structure includes bridge piers, the web of a continuous steel bridge beam, or a cast-in-place beam. A multi-point distributed anchoring system is installed on the existing main structure to form a cantilever foundation capable of reliably transmitting vertical loads, horizontal loads, and overturning moments. The cantilever foundation can simultaneously transmit vertical loads, horizontal loads, and overturning moments. The multi-point distributed anchoring system is arranged with at least two rows of anchor points along the height direction of the existing main structure, with each row of anchor points evenly distributed longitudinally to form a spatial stress grid. The multi-point distributed anchoring system selects any one of the following methods based on structural conditions: chemical anchors, embedded steel plates, or clamping clamps. This ensures that the load can be evenly transmitted to the existing main structure, avoiding damage to the existing structure caused by local stress concentration.
[0058] This application establishes a design model for a multi-point distributed anchorage system based on the spatial force system equilibrium theory, considering the combined effects of vertical loads, horizontal loads, and overturning moments. Specifically, based on the spatial force system equilibrium model, the layout parameters and bearing requirements of the multi-point distributed anchorage system are calculated. The overturning safety factor of the multi-point distributed anchorage system should meet the following requirements:
[0059]
[0060] in, To prevent overturning safety factor; This is the design value for the overturning moment; This is the design value for the overturning moment.
[0061] The design value of single-point anchorage force should meet the following requirements:
[0062]
[0063] in, This is the design value for single-point anchoring force; V is the structural importance coefficient; L is the design value of the total vertical load; n is the vertical distance between the upper and lower rows of anchor points; and n is the number of anchor points in a single row. This represents the design value for the pull-out bearing capacity of a single anchor point.
[0064] By overturning safety factor and single-point anchorage force design value The dual control ensures that the anchoring system has sufficient safety margin under the combined action of vertical load, horizontal load and overturning moment, avoiding the risk of cantilever system instability due to insufficient anchoring force.
[0065] In some embodiments, this application uses a multi-point distributed anchoring system to fix the main load-bearing nodes to the side web or bottom plate of the main beam / cap beam. Depending on different structural conditions and construction requirements, the multi-point distributed anchoring system can flexibly select the following three methods:
[0066] Chemical anchors are suitable for pre-formed concrete structures. The specifications of chemical anchors are M20-M30, the anchoring depth is not less than 12d, and the single-point pull-out bearing capacity is not less than 120kN.
[0067] Pre-embedded steel plate anchoring is suitable for new structures. During the construction of the main structure, 16-20mm thick steel anchor plates are pre-embedded. The anchor plates are connected to the main structure reinforcement by double-sided welding, and the weld length is not less than 10d. It has high anchoring strength and good reliability.
[0068] The clamping and anchoring method is suitable for special structures where drilling is prohibited. It clamps the main structure with two semi-circular clamps and uses the friction generated by the preload to transfer the load. The preload of the clamps is not less than 80kN, and the shear resistance of the transverse connectors is not less than 100kN.
[0069] After the multi-point distributed anchoring system is completed, an on-site pull-out test must be conducted. A hydraulic jack can be used for graded loading to verify whether its bearing capacity meets the design requirements, ensuring that the single-point pull-out bearing capacity is not less than 80kN and the safety factor is not less than 1.5, thus ensuring the stability of subsequent cantilever construction.
[0070] Specifically, in step S2, a cantilever load-bearing structure is installed on the multi-point distributed anchoring system to construct a cantilever construction platform that is completely independent of ground support. The cantilever load-bearing structure is the main load-bearing component of the entire modular support system, bearing the entire load of the formwork, reinforcing steel, concrete, and construction personnel, and transferring these loads to the multi-point distributed anchoring system and the existing main structure. The modular support system is fixed to the existing main structure entirely by the multi-point distributed anchoring system and the cantilever load-bearing structure, without any contact with the ground, thus not occupying the space of roads, waterways, or viaducts below. This ensures normal vehicle traffic when constructing across urban arterial roads and BRT lanes; ensures normal navigation for ships when constructing across waterways; and does not affect the underlying bridge structure when constructing across existing viaducts.
[0071] Specifically, this application simplifies the cantilever load-bearing structure into a cantilever beam mechanical model with one end fixed and the other end free, and its maximum bending moment and maximum deflection are as follows:
[0072]
[0073]
[0074] in, This represents the design value for the maximum bending moment of the cantilever beam. q represents the maximum deflection of the cantilever beam; P represents the design value of the uniformly distributed load; L represents the design value of the concentrated load; E represents the cantilever length of the cantilever beam; E represents the elastic modulus of the steel; and I represents the moment of inertia of the section. The cantilever load-bearing structure uses standardized steel components, and H-beams, double-channel steel spliced beams, or box-section steel beams can be selected according to the load-bearing capacity.
[0075] The cantilever load-bearing structure is rigidly connected to the connection nodes of a multi-point distributed anchoring system using high-strength bolts of grade 8.8 or higher, and anti-slip pads are installed to prevent slippage. To prevent upward deformation of the cantilever end under construction loads, Φ16-Φ25 steel tie rods or 50-100kg counterweight components are installed at the cantilever end. The cantilever length of the cantilever load-bearing structure can be adjusted within the range of 1.0-3.0m according to construction needs to accommodate the construction requirements of sidewalls of different widths.
[0076] Specifically, in step S3, a modular support system is assembled in layers on the cantilever construction platform to form a stable load-bearing structure with a spatial truss effect. The modular support system consists of four categories of standardized modules: vertical load-bearing modules, oblique stabilizing modules, multi-degree-of-freedom connection node modules, and expansion and contraction adjustment modules. All modules are factory-produced, have good interchangeability and versatility, and can be reused across projects.
[0077] Furthermore, this application treats the modular support system as a space truss structure and employs the matrix displacement method for internal force analysis. Its overall stiffness matrix is:
[0078]
[0079] in, The overall stiffness matrix of the modular support system; Let be the coordinate transformation matrix of the e-th element; is the local stiffness matrix of the e-th element; n is the total number of elements in the modular support system.
[0080] Specifically, layered assembly includes:
[0081] S31. Install the first main load-bearing layer, connect the vertical load-bearing module and the cantilever load-bearing structure through flanges to form the main vertical force transmission system; the vertical load-bearing module adopts steel pipe columns or H-beams, which can withstand large vertical loads.
[0082] S32. Install the second stabilizing layer, and set up the inclined stabilizing module and the vertical bearing module to form a triangular stabilizing structure to improve the system's resistance to lateral displacement. The inclined stabilizing module adopts adjustable diagonal braces or tie rods, and the included angle between the inclined stabilizing module and the vertical bearing module is controlled between 30° and 75° to obtain the best stabilizing effect.
[0083] S33. When the sidewall height exceeds 4m, an intermediate reinforcing layer is added. This further improves the overall stiffness and stability of the system, preventing excessive deformation of the modular support system under concrete lateral pressure. The intermediate reinforcing layer consists of transverse connecting rods and diagonal support rods, forming a grid-like stable structure.
[0084] In step S3, the multi-degree-of-freedom connection node module adopts a two-stage hinged and locking structure, with the longitudinal direction of the cantilever beam as the X-axis, the vertical direction as the Y-axis, and the transverse direction as the Z-axis. The first stage rotates around the X-axis with an angle range of 0°-90° to adapt to changes in the longitudinal slope of the bridge. The second stage rotates around the Z-axis with an angle range of ±45° to adapt to changes in the transverse slope and curve of the bridge.
[0085] The nodes are equipped with pins, arc-shaped dials, and locking bolts to achieve angle reading and precise locking. The locking torque is not less than 120 N·m, and the allowable axial force of a single node is not less than 150 kN and the bending moment is not less than 20 kN·m.
[0086] The telescopic adjustment module uses threaded adjusting rods, sleeve-type telescopic rods, or hydraulic adjusting components. Through this module, the longitudinal spacing of the support units can be adjusted within the range of 1.0-4.0m, the lateral spacing within the range of 0.5-3.0m, and the column inclination angle within the range of 0°-15°, perfectly adapting to the construction requirements of curved bridges and bridges with varying widths. For curved bridges, by adjusting the lateral spacing of support units at different locations, the spacing between inner supports is smaller, and the spacing between outer supports is larger, forming a support arrangement that matches the curve. For bridges with varying widths, the lateral spacing of the support units is continuously adjusted to adapt to changes in bridge width.
[0087] In step S4, the formwork system and the modular support system are rigidly connected in an integrated manner to form a continuous, uninterrupted load transfer path from the formwork panel to the existing main structure. The formwork system includes main beams, secondary beams, and formwork panels. The main beams are VT20K or GT24 type standard steel beams, the secondary beams are square steel or channel steel, and the formwork panels can be made of 3-5mm thick steel plates or 12-18mm thick film-coated boards.
[0088] The formwork system and modular support system are rigidly connected by M16-M24 high-strength bolts or welding, with a connection spacing of 0.3-0.6m. This integrated connection method transforms the traditional point-contact force transmission into continuous structural force transmission, and the dispersed system into a whole-body force-bearing system, so that the lateral pressure of the concrete can be evenly transmitted to each support unit, significantly reducing local stress concentration.
[0089] The continuous load transfer path established by this invention is as follows: concrete lateral pressure → formwork panel → back brace → transverse support beam → vertical support → cantilever load-bearing beam → anchorage node → existing main structure. This clear and continuous force transfer path ensures that the load can be efficiently and safely transferred to the existing main structure, avoiding node failure and formwork deformation problems caused by unclear force transfer in traditional systems. Finite element analysis and engineering verification show that this integrated design can reduce local stress peaks by 15%-30%, reduce lateral deformation of the formwork by 10%-25%, and improve overall stability by 20%-30%.
[0090] In step S5, the elevation, alignment, and inclination of the formwork system are simultaneously adjusted to the design requirements using multi-point adjustable units located at key nodes of the modular support system. The multi-point adjustable units include screw-type or hydraulic adjustment devices. The formwork support is connected to the distribution beam via sliding guide rails, enabling lateral sliding of 0-200mm and vertical fine-tuning of ±20mm.
[0091] This application employs a multi-point synchronous adjustment algorithm combining overall coordination and local correction. First, the target elevation and position of all nodes are calculated based on the design alignment. Then, all nodes are synchronously adjusted to 95% of the target elevation using unified commands. Finally, nodes with deviations exceeding 2mm are locally corrected until all node deviations meet the requirements. During the adjustment process, the displacement of each node should satisfy the following formula:
[0092]
[0093]
[0094] in, Let be the elevation adjustment amount for the i-th node; Let the target elevation of the i-th node be _____. Let be the current elevation of the i-th node.
[0095] By employing a two-stage adjustment strategy of "first adjusting the overall elevation to 95% of the target elevation, and then making local corrections to nodes with deviations exceeding 2mm", the synchronization and efficiency of multi-point adjustment are ensured. At the same time, the residual deviations caused by module manufacturing errors, installation errors and elastic deformation of the support system are eliminated through local corrections. Ultimately, high-precision control is achieved with template elevation error ≤ ±5mm and cantilever end position deviation ≤ ±10mm.
[0096] Unlike existing technologies that only use adjustment devices in specific locations, this application incorporates multi-point adjustable units at all major support nodes, forming a multi-point synchronous adjustment system. Through unified adjustment commands, the height and position of all nodes can be adjusted simultaneously, achieving precise overall control of the formwork system. This multi-point synchronous adjustment method not only significantly improves adjustment efficiency but also effectively avoids formwork deformation and stress concentration caused by localized adjustments.
[0097] During the adjustment process, real-time measurements were taken using a level and total station to ensure that the adjustment accuracy met the design requirements. After the adjustment was completed, the template elevation error and cantilever end position deviation were effectively controlled, fully meeting the requirements of current bridge construction specifications. For curved bridges and bridges with varying widths, by adjusting the height and spacing of support units at different locations, the changes in the bridge's alignment can be precisely matched, achieving high-quality construction of complex bridge types.
[0098] Specifically, in step S6, a layered controlled pouring process is used for the sidewall concrete pouring, and the deformation, stress, and stability of the modular support system are monitored in real time. The thickness of each layer is controlled at 0.3-0.5m, and the pouring speed is no more than 2m / h to prevent excessive lateral pressure from the concrete from causing formwork bulging and support deformation. The pouring process follows the principles of symmetry, uniformity, and continuity to avoid the unbalanced load generated by unilateral pouring from adversely affecting the modular support system.
[0099] In step S6, the layered pouring thickness and pouring speed parameters are determined based on the concrete lateral pressure calculation model. The standard value of the maximum lateral pressure is calculated using the following two formulas, and the smaller value is taken:
[0100]
[0101]
[0102] Where F is the maximum pressure exerted by the newly poured concrete on the side formwork, taken as... and The smaller value in; The unit weight of concrete; The initial setting time of freshly poured concrete; This is the correction factor for the influence of admixtures; is the correction factor for the effect of concrete slump; v is the concrete pouring speed; H is the total height of concrete pouring.
[0103] By simultaneously calculating the lateral pressure considering the pouring speed. And considering the lateral pressure of the pouring height By taking the smaller value, we can avoid both excessive lateral pressure due to excessive pouring speed and excessive bottom lateral pressure due to excessive pouring height, thus providing a scientific basis for determining the parameters of layered pouring thickness and pouring speed.
[0104] In step S6, this application establishes a deformation prediction model for a modular support system based on the load-deformation relationship, which can predict the deformation trend of the modular support system in real time according to the pouring progress. The specific formula is as follows:
[0105]
[0106] in, Let be the deformation value at time t; t represents the maximum deformation value; k is the deformation development coefficient, and the range of k values is determined based on the stiffness of the modular support system and the rate of increase in concrete strength; t is the pouring time.
[0107] An exponential growth model is used to describe the deformation development of the modular support system during concrete pouring. It can predict the deformation trend in real time according to the pouring progress. When the predicted deformation value approaches the warning threshold, measures such as slowing down the pouring speed or adding temporary supports can be taken in advance, realizing the transformation from passive monitoring to active early warning.
[0108] During concrete pouring, laser measurement, leveling instruments, or total stations are used to monitor the modular support system in real time. Monitoring includes formwork displacement, support deformation, anchor point stress, and joint loosening. Monitoring is conducted every 30 minutes, and can be increased to every 15 minutes during peak pouring periods.
[0109] When the displacement of the modular support system template is greater than 10mm, the stress on the anchor point exceeds the design value of the pull-out bearing capacity of a single anchor point, or the node becomes loose, pouring should be stopped immediately, and emergency measures such as adding temporary supports, slowing down the pouring speed, or partially unloading should be taken to ensure construction safety.
[0110] In step S7, after the concrete strength reaches more than 75% of the design strength, the modular support system is dismantled in reverse order according to the modular units and transferred to the next construction section for reuse. The dismantling sequence strictly follows the principle of "installed first, dismantled later" and "installed last, dismantled first": first, the formwork system and multi-point adjustable units are dismantled, then the upper support, middle support and lower support are dismantled from top to bottom, then the cantilever load-bearing structure is dismantled, and finally the multi-point distributed anchoring system is dismantled.
[0111] The dismantling process employs a modular, integrated dismantling method, hoisting and transporting each module as a whole, thus avoiding component damage and loss caused by piecemeal dismantling in traditional methods. After simple cleaning and maintenance, the dismantled modular components can be transferred to the next construction section for reuse. The modular components of this invention are designed with a long service life, capable of being reused more than 10 times, greatly improving material utilization and reducing construction costs.
[0112] Example 2:
[0113] like Figure 3 As shown, this embodiment provides a modular combined support construction system for cast-in-place bridge sidewall construction, used to implement the modular combined support construction method for cast-in-place bridge sidewall construction as described in Embodiment 1, including:
[0114] A multi-point distributed anchoring system is used to connect with the existing main structure and transfer vertical loads, horizontal loads and overturning moments;
[0115] The cantilever load-bearing structure is fixedly connected to a multi-point distributed anchoring system to form a cantilever construction platform that is completely independent of ground support.
[0116] The modular support system is assembled from vertical load-bearing modules, oblique stabilizing modules, multi-degree-of-freedom connection node modules, and telescopic adjustment modules, and is installed on the cantilever load-bearing structure.
[0117] The template system is rigidly connected to the modular support system.
[0118] Multi-point adjustable units are set at key nodes of the modular support system to adjust the template elevation, alignment and inclination angle;
[0119] The monitoring and control unit is used to monitor the template displacement, support deformation, anchor point stress and node loosening status of the modular support system in real time, and control the synchronous adjustment of multiple adjustable units.
[0120] The above-described specific embodiments are preferred embodiments of a modular combined support construction method and system for cast-in-place construction of bridge sidewalls according to this application. They are not intended to limit the specific scope of this application. The scope of this application includes but is not limited to the specific embodiments described above. All equivalent changes made in accordance with the shape and structure of this application are within the protection scope of this application.
Claims
1. A modular composite support construction method for cast-in-situ construction of bridge side walls, characterized in that, Includes the following steps: S1. Set up a multi-point distributed anchoring system on the existing main structure to form a cantilever foundation during construction; S2. The prefabricated cantilever load-bearing structure is rigidly connected to the multi-point distributed anchoring system to construct a cantilever construction platform that does not rely on ground support at all. S3. On the cantilever construction platform, standardized vertical bearing modules, oblique stabilizing modules and telescopic adjustment modules are assembled and connected in layers through multi-degree-of-freedom connection node modules to form a modular support system with spatial truss effect. S4. Integrate the template system with the modular support system to form a continuous and uninterrupted load transfer path from the template system and the modular support system to the existing main structure. S5. By using multi-point adjustable units set at key nodes between the modular support system and the template system, the elevation, alignment and inclination of the template system are synchronously adjusted to the design allowable deviation range using an overall coordination-local correction algorithm. S6. Based on the concrete lateral pressure calculation model, determine the layered pouring thickness and pouring speed parameters, and use the layered controlled pouring process to pour the side wall concrete according to the determined parameters. Based on the load-deformation prediction model, monitor the template displacement, support deformation, anchor point stress and node loosening status of the modular support system in real time. S7. After the concrete reaches the design strength, the modular support system is dismantled in sections, and each dismantled module is transferred to the next construction section for reuse.
2. The modular composite support construction method for cast-in-situ construction of bridge side walls according to claim 1, characterized in that, In step S1, the cantilevered foundation can simultaneously transmit vertical loads, horizontal loads, and overturning moments; the multi-point distributed anchoring system arranges at least two rows of anchor points along the height direction of the existing main structure, with each row of anchor points evenly distributed longitudinally to form a spatial stress grid; the anchoring system selects any one of chemical anchors, pre-embedded steel plates, or clamping clamps according to the structural conditions.
3. The modular composite support construction method for cast-in-situ construction of bridge side walls according to claim 1, characterized in that, In step S1, the layout parameters and bearing requirements of the multi-point distributed anchoring system are calculated based on the spatial force system equilibrium model. The formulas of the spatial force system equilibrium model are as follows: in, To prevent overturning safety factor; This is the design value for single-point anchoring force; This is the design value for the overturning moment; This is the design value for the overturning moment; V is the structural importance coefficient; L is the design value of the total vertical load; n is the vertical distance between the upper and lower rows of anchor points; and n is the number of anchor points in a single row. This represents the design value for the pull-out bearing capacity of a single anchor point.
4. The modular combined support construction method for cast-in-place bridge sidewall construction according to claim 1, characterized in that, In step S3, the layered assembly includes: S31. Install the first main load-bearing layer, and connect the vertical load-bearing module with the cantilever load-bearing structure through flanges to form the main vertical force transmission system; S32. Install the second stabilizing layer, and set the inclined stabilizing module and the vertical bearing module to form a triangular stabilizing structure. The included angle between the inclined stabilizing module and the vertical bearing module is controlled between 30° and 75°. S33. When the height of the side wall is greater than 4m, an intermediate reinforcement layer shall be added.
5. The modular combined support construction method for cast-in-place bridge sidewall construction according to claim 1, characterized in that, In step S3, the multi-degree-of-freedom connection node module is a two-stage hinged and locking structure, which can realize rotation around the X-axis from 0° to 90° and rotation around the Z-axis from ±45°. The node uses a pin shaft, an arc-shaped dial, and a locking bolt to achieve angle reading and precise locking. The telescopic adjustment module uses a threaded adjustment rod, a sleeve-type telescopic rod, or a hydraulic adjustment component.
6. The modular composite support construction method for cast-in-place construction of bridge side walls according to claim 1, characterized in that, In step S5, the formula for the global coordination-local correction algorithm is as follows: wherein, is an elevation adjustment amount for the i-th node; is a target elevation for the i-th node; is a current elevation for the i-th node.
7. The modular composite support construction method for cast-in-place construction of bridge side walls according to claim 1, characterized in that, In step S6, the concrete lateral pressure calculation model is calculated using the following two formulas, and the smaller value is taken: Wherein, F is the maximum pressure of the new pouring concrete to the side formwork, taking the smaller value in ; is the specific gravity of the concrete; is the initial setting time of the new pouring concrete; is the admixture influence correction coefficient; is the concrete slump influence correction coefficient; v is the pouring speed of the concrete; and H is the total height of the concrete pouring.
8. The modular combined support construction method for cast-in-place bridge sidewall construction according to claim 1, characterized in that, In step S6, the formula for the load-deformation prediction model is as follows: in, Let be the deformation value at time t; t represents the maximum deformation value; k represents the deformation development coefficient; and t represents the pouring time.
9. The modular combined support construction method for cast-in-place bridge sidewall construction according to claim 1, characterized in that, In step S6, when the displacement of the modular support system template is greater than 10mm, or the force on the anchor point exceeds the design value of the pull-out bearing capacity of a single anchor point, or the node becomes loose, the pouring should be stopped immediately, and emergency measures such as adding temporary supports, slowing down the pouring speed, or partially unloading should be taken.
10. A modular combined support construction system for cast-in-place construction of bridge sidewalls, characterized in that, A modular combined support construction method for cast-in-place bridge sidewall construction as described in any one of claims 1-9 includes: A multi-point distributed anchoring system is used to connect with the existing main structure and transfer vertical loads, horizontal loads and overturning moments; The cantilever load-bearing structure is fixedly connected to the multi-point distributed anchoring system to form a cantilever construction platform that is completely independent of ground support. The modular support system is assembled from vertical load-bearing modules, oblique stabilizing modules, multi-degree-of-freedom connection node modules, and telescopic adjustment modules, and is installed on the cantilever load-bearing structure. The template system is rigidly connected to the modular support system in an integrated manner; Multi-point adjustable units are set at key nodes of the modular support system to adjust the template elevation, alignment and inclination angle; The monitoring and control unit is used to monitor the template displacement, support deformation, anchor point stress and node loosening status of the modular support system in real time, and control the synchronous adjustment of multiple adjustable units.