A sequential construction method and system for a sluice gate system under complex riverside conditions
By adopting a phased construction method for the gate and pumping station system under complex river conditions, gates and pumping stations were constructed sequentially for each individual river channel. This solved the problem of the disconnection between the flood storage and detention area and the external river during the construction period, thus meeting the needs of safe flood control and drought relief in the basin, and improving construction efficiency and flood control capabilities.
Patent Information
- Application Number
- CN202611427212.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-15
- Publication Date
- 2026-11-17
AI Technical Summary
During the construction of the Linjiang multi-channel sluice gate project, the simultaneous closure of the entire river channel resulted in the complete severing of the hydraulic connection between the flood storage and detention area and the outer river, causing the loss of natural flood discharge and drainage capacity, forming a "closed flood" phenomenon, which seriously threatens flood control safety.
The sequential construction method is adopted, and gate stations are constructed on individual river channels in sequence to maintain the connectivity of at least one river channel. Through the sequential construction mode and various construction methods (such as multi-sequence parallel combined with reverse sequence gate installation, process resetting, and sequential multi-track, etc.), the flood control and drainage functions of the basin are maintained during the construction process, and the basin water regulation system for daily water flow and flood control and storage during the flood season is finally constructed.
It effectively avoids the drawbacks of losing flood passage in the flood storage and detention area under the synchronous interception mode of the whole river channel, solves the flood control risk during the construction period, improves construction efficiency and safety, and ensures the flood control and drainage capacity and drought resistance and water regulation function of the basin.
Smart Images

Figure CN123109113A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of water conservancy gate and pumping station construction technology, and in particular to a sequential construction method and a sequential construction system for a gate and pumping station system under complex conditions near a river. Background Technology
[0002] Riverside lake-type flood storage and detention areas are usually connected to the outer rivers through multiple waterways. The control gates, pumping stations and other gate facilities on the waterways are the core components of the basin's flood control, drainage and water resource allocation system, and undertake the key functions of lake water level regulation, flood discharge during the flood season and water replenishment during the dry season.
[0003] During the current water conservancy upgrade and renovation process in the Linjiang River Basin, there are two types of new gate and pumping station needs: First, some waterways connected to the river did not have supporting control facilities, resulting in a gap in the water system's control capacity, requiring the construction of new gate and pumping station projects to fill the functional gaps; Second, the existing facilities in flood storage and detention areas and their connected water systems are old, dilapidated, and lack sufficient flood control, drainage, and water regulation capacity, requiring the construction of new gate and pumping station projects to achieve system upgrades.
[0004] The current construction of sluice gate projects along multiple rivers in Linjiang generally adopts a construction organization method of simultaneous closure of all river channels, that is, closing all river channels leading to the river at the same time to carry out sluice gate construction. Due to the long construction period of sluice gate projects, they usually span two phases: the non-flood season and the flood season. During the non-flood season, the water level of the outer river is low and the regional water volume is small, so the impact of the closure of all river channels on the drainage and regulation of flood storage areas is relatively limited. However, after entering the flood season, the water level of the outer river rises and the region experiences frequent heavy rainfall. Under the condition of simultaneous closure of all river channels, the flood storage area is completely cut off from the outer river in terms of hydraulic connection, and the natural flood discharge and drainage channels are completely lost. The water in the lake area cannot be discharged in time, which can easily lead to the phenomenon of "closed flooding", seriously threatening the flood control safety of towns and farmlands along the river. The flood control risk during the construction period is extremely prominent.
[0005] Therefore, it is urgent to develop a construction organization method that is compatible with multiple river gates and pumping stations along the river, to ensure the hydraulic connectivity between the flood storage and detention area and the outer river during the construction process, maintain the basic flood discharge and drainage capacity during the construction period, and fundamentally avoid the flood control risks during the construction period caused by the simultaneous interception of the entire river. Summary of the Invention
[0006] To address the technical problem that existing multi-channel sluice gate projects along rivers, which employ a simultaneous closure of all river channels during construction, completely sever the hydraulic connection between the flood storage area and the outer river during the construction period across the flood season, resulting in the complete loss of natural flood discharge and drainage capabilities, this invention provides a sequential construction method and system for sluice gate systems under complex river conditions. By adopting a sequential construction mode for sluice gate systems located on two rivers connecting the flood storage area and the outer river, the corresponding control gates, pumping stations, and riverbank dikes and structures are constructed sequentially by closure of each river channel. Throughout the construction process, at least one river channel remains connected, maintaining the basic flood discharge and drainage functions of the basin during the flood season. Ultimately, this constructs a basin water regulation system that enables daily water flow and flood control and storage during the flood season.
[0007] To achieve the above objectives, the present invention provides the following technical solution: A method for sequential construction of a gate and pumping station system under complex riverside conditions, wherein the gate and pumping station system is laid out on two waterways connecting a flood storage area and the outer river, the two waterways being a first waterway on the upstream side and a second waterway on the downstream side. A first control gate and a first pumping station are installed on the first waterway, and a second control gate and a second pumping station are installed on the second waterway; the method includes the following steps: Construction has begun, and at least one river channel must be maintained to connect the flood storage and detention area with the outer river throughout the entire construction process to maintain the flood control and drainage functions of the basin. The upstream and downstream cofferdams were filled to block the first channel of the river, and the second channel took over the function of flood control and drainage of the basin. The construction of the first control gate and the first pumping station was completed in sequence, and the construction of the dikes and structures penetrating the dikes of the first channel was carried out in sections simultaneously. After the first control gate and the first pumping station were ready for water supply, the cofferdams of the first channel were removed to restore the flood control function of the river. The upstream and downstream cofferdams were filled to block the second channel, and the first channel took over the function of flood control and drainage of the basin. The construction of the second pumping station and the second control gate was completed in sequence, and the construction of the dikes and structures penetrating the dikes of the second channel was carried out simultaneously. After the completion of the construction of all control gates, pumping stations, dikes and structures penetrating the dikes, commissioning and acceptance will be carried out to form a watershed water regulation system for daily water supply and flood control and storage during the flood season.
[0008] As a further improvement to the above scheme: the first control gate adopts a construction method of multi-sequence parallel combined with reverse-sequence gate installation, as detailed below: After the upstream and downstream cofferdams of the first control gate corresponding to the building section are filled, the upstream and downstream cofferdams cross the entire cross section of the river channel to achieve the first river channel closure. Then, the deep foundation pit of the first control gate is excavated, and the underwater soft soil treatment, main gate chamber structure, upstream and downstream auxiliary structures of the gate chamber, left and right bank wing walls and embankment reinforcement are carried out in sequence and in parallel. After the main structure of the underwater gate pier is completed, the construction of the upper structure of the gate chamber will be temporarily suspended. The gate slots will be buried and the gates will be installed first, so that the gates can be opened and closed to block water and perform temporary flood control duty in advance. After the gate was put into temporary flood control duty, construction continued on the upper structure of the gate chamber, the hoisting equipment, the electromechanical system and the external power supply line.
[0009] As a further improvement to the above scheme: the first pumping station adopts a construction method that combines multi-sequence construction with process re-reset, as detailed below: The upstream cofferdam of the first pumping station was filled in, and the downstream section relied on the existing dike to block water, forming a dry construction area for the first pumping station. Within this dry construction area, the construction of the inlet gate and inlet culvert was carried out in parallel in sections and sequence. At the same time, the main foundation pit support system of the pumping station was constructed, dewatering wells were laid, and the layered excavation of the foundation pit was started. The construction of the upstream and downstream auxiliary structures of the pumping station was also carried out in parallel. When the water level of the outer river rises during the flood season to the point where the difference between the water levels inside and outside the foundation pit exceeds the safety threshold, and there is a risk of piping and slope instability, the process reset procedure shall be initiated: First, the excavation of the foundation pit was stopped, the existing support and enclosure system was preserved, all dewatering wells were sealed, and the original appearance of the dike and its toe was restored. Next, the excavated foundation pit was backfilled in layers to the original landform elevation, and the geological stability was restored by soil weight load. At the same time, a 24-hour inspection and safety monitoring mechanism was launched. Finally, construction resumed after the flood season when the water level of the outer river receded to a safe range. The existing support and enclosure system was used to redeploy dewatering wells to restore drainage. The foundation pit was excavated to the designed foundation surface, and the main structure of the pumping station was completed.
[0010] As a further improvement to the above plan: the inlet gate of the first pumping station and the downstream flood control gate both adopt a reverse construction method: After the substructure is completed, the gates will be installed first and used to seal off the water to ensure the safety of the pumping station pit. After the flood peak passes and the water level returns to normal, the construction of the superstructure, hoist and electromechanical installation will continue.
[0011] As a further improvement to the above scheme: the second pumping station adopts a phased, multi-track, and efficient construction method, employing corresponding construction techniques and local cofferdam forms for different construction sections of the pumping station: Riverbed cofferdam section: A partial construction cofferdam is constructed using a double-row steel sheet pile cofferdam structure, which is suitable for the complex geology of the riverbed silt layer and encloses the dry construction area. In the old dike seepage interception section: a construction method combining riprap grouting foundation reinforcement with plastic concrete cutoff wall is adopted to construct a permanent cutoff wall, reinforce the foundation and improve the stability of the dike. Downstream outlet section: A combination of rock dumping and silt removal, crushed stone cushion layer and gravity concrete buttress retaining wall is used to treat the deep silty soft foundation; the silt generated during construction is environmentally solidified and recycled for shoreline restoration.
[0012] As a further improvement to the above plan: the flood control gate on the riverside of the second pumping station adopts an underwater forward-sequence construction method combined with an upper reverse-sequence construction method. After the underwater section is completed in the correct order, the gate slots and gates will be installed first, so that the gates can be put into flood control duty status in advance, and then the above-water structure, equipment installation and electromechanical engineering construction will continue.
[0013] As a further improvement to the above scheme: the second control gate adopts a sequential construction method. First, the upstream and downstream cofferdams corresponding to the construction section of the second control gate are filled to form the water-retaining area for the construction of the second control gate. Then, the foundation pit excavation and dewatering construction are carried out. After excavation to the designed foundation surface, foundation treatment and structural construction are carried out. For the unfavorable geological conditions of the landfill layer and silt layer in the construction area, a combination of replacement and pile foundation treatment is adopted.
[0014] As a further improvement to the above plan: After construction is completed, the first control gate, the first pumping station, the second control gate, and the second pumping station will operate in conjunction with the existing old gates at the confluence of the two river channels and the supporting flood intake and discharge gates on the outer river side. Flood control and storage will be implemented in stages based on the water level relationship between the flood storage and detention area and the outer river. The specific operating mode is as follows: Operating Condition 1: When the water level in the flood storage and detention area is higher than that in the outer river, the two existing old gates are opened to discharge water into the outer river. The first and second control gates are kept open, and the water level regulation and normal flow between the flood storage and detention area and the outer river are achieved through the natural water level difference. Condition 2: When the water level of the outer river is higher than that of the flood storage area during the flood season and flood storage is not required, the two existing old gates are closed to prevent backflow of the outer river, while the first and second control gates remain open to maintain the flow and drainage of the river. Condition 3: During the flood season, when the water level of the outer river is higher than that of the flood storage area, the two existing old sluice gates are closed to block water. When the water level of the flood storage area rises to the elevation level but does not meet the flood storage conditions, both the first and second control gates are closed to block water, and local regulation and storage of floodwater are carried out within the flood storage area. When the water level in the two rivers rises to the elevation level, the first and second pumping stations are activated to discharge floodwater into the outer river to control the river water level from exceeding the elevation level and ensure the safety of villages and towns along the riverbanks on the safe side during the flood season. Operating Condition 4: When implementing basin-wide flood storage and dispatching, operate according to Operating Condition 3 mode; when the water level of the outer river continues to rise to above the warning level, open the supporting flood gate on the outer river side to divert the floodwater from the outer river to the flood storage and detention area for flood storage and peak regulation; simultaneously, when the water levels in the two rivers rise to the elevation level, start the first and second pumping stations to discharge floodwater into the outer river to control the river water level from not exceeding the elevation level; Condition 5: During the flood receding phase after the flood peak, the supporting flood discharge gates on the outer river side, the two existing old gates, as well as the first and second control gates will be opened. Flood discharge will be carried out as appropriate according to the water level of the outer river, and the floodwater in the flood storage and detention area will be discharged to the outer river. Condition 6: If rainfall continues after the water level in the flood storage area reaches the flood storage level, and the water level in the outer river is still higher than the river channel level and the flood storage level, partially open the first and second control gates. Under the condition that the river channel water level does not exceed the elevation level, start the first and second pumping stations to discharge floodwater into the outer river. After the water level in the outer river is lower than the river channel level, switch to the flood discharge mode of Condition 5 until the end of the flood season.
[0015] As a further improvement to the above plan: after the completion of construction, a gate-station coordinated drought relief and water diversion method will be adopted during the dry season: when the flood storage and detention area lacks water supply during the dry season, the existing old gates at the confluence of the two rivers with the first and second control gates will be jointly operated; when the water level of the outer river can meet the water replenishment needs, the existing old gates and the first and second control gates will be opened to divert water from the outer river to the flood storage and detention area and the river channel to ensure the water supply for production and daily life in the basin; when the water level of the outer river is too low to continuously replenish water, the existing old gates and the first and second control gates will be closed to impound and store water in the flood storage and detention area and the river channel to maintain the water supply of the basin.
[0016] A dual-channel cascade gate and pumping station system for complex riverside conditions includes a first channel and a second channel connecting a flood storage area with the outer river. A first control gate and a first pumping station are installed on the first channel, and a second control gate and a second pumping station are installed on the second channel. Embankments and structures penetrating the embankments are constructed along the banks of both channels. The gate and pumping station system is constructed using a sequential construction method for gate and pumping station systems under complex riverside conditions. Throughout the construction process, at least one channel is kept connected to the flood storage area and the outer river, ultimately forming a watershed water regulation system for daily water flow, flood control and storage during the flood season, and drought relief and water regulation during the dry season.
[0017] Compared with the prior art, the beneficial effects of the present invention are: 1. In the sequential construction method, an overall organizational scheme of alternating closure of two river channels and sequential construction is adopted, forming a construction mode of "one policy for each type, multiple tracks in sequence, and efficient breakthrough". By sequentially filling cofferdams to close the river and carrying out sluice gate construction on each individual river channel, at least one river channel is always kept connected to the flood storage area and the outer river throughout the entire construction process. This fundamentally avoids the drawback of the flood storage area completely losing its flood passage under the traditional synchronous closure mode of the entire river channel. It specifically solves the problems of multiple working conditions, tight construction organization and schedule, and conflicts between flood control and water storage faced by cascade water conservancy projects and comprehensive management of multiple river basins under complex conditions near the river. It effectively eliminates the risk of "flooding when the gate is closed" during the construction period, takes into account the needs of safe flood control and drought relief and drainage, and eliminates risks. At the same time, the sequential organization method of single river channel advancement not only facilitates the concentration of resources to ensure construction efficiency, but also adapts to the complex hydrological conditions of construction across the flood season near the river, and promotes the orderly progress of project construction under the premise of safe flood control.
[0018] 2. An unconventional construction approach of "installing the gates first and then building the superstructure" was adopted to specifically meet the construction needs of rushing to complete the project before the flood season along the river. On the one hand, by carrying out parallel construction of underwater soft foundation treatment, main gate chamber structure, upstream and downstream auxiliary structures, wing walls and dike reinforcement in sequence, and simultaneously advancing multi-section operations, the construction efficiency was effectively improved and the construction period of underwater projects was shortened. On the other hand, the conventional sequential construction process was broken. The underwater structure construction process was consistent with the conventional sequential process. After the underwater main structure of the gate pier was completed and before the upper structure such as the hoisting machine room was built, the gate slot was buried and the gate was installed in advance by taking advantage of the initial hoisting window, so that the gate could have the functions of opening and closing water and temporary flood control duty in advance. The subsequent upper structure adopted the detour construction method of avoiding the already installed gate with formwork and support system. After the structure was capped, the equipment could be directly commissioned. This eliminated the need to reserve hoisting holes in the roof of the upper structure, build a hoisting platform for the second time, and pour concrete to seal the hoisting holes for the second time. This not only simplified the process, shortened the construction period and improved the efficiency, but also reduced the construction joints because the roof was cast in one go, which is conducive to improving the overall structure and improving the waterproof and seepage prevention effect of the roof. This construction method significantly shortens the service life of the diversion cofferdam, reducing the risk of long-term water ingress and maintenance costs, and also creating diversion conditions in advance for the subsequent diversion construction of the second channel.
[0019] 3. By employing multiple methods, including "forward and reverse sequence" and "process resetting," the constraints of different working conditions were addressed, eliminating the risk of piping in deep foundation pits and ensuring safe flood control. During the normal construction phase, the project progress was efficiently advanced through parallel operations of the inlet section structure, foundation pit support, dewatering, main excavation, and auxiliary structures. When encountering the risk of piping and slope instability due to a surge in the external river water level during the flood season, a three-step process of "risk isolation—ballast stabilization—condition reconstruction" was used to quickly seal the dewatering wells and backfill the ballast pit while retaining the existing support system. This approach avoided the major safety risks of foundation pit instability and piping failure at a relatively low cost. Furthermore, the existing support system could be directly reused to resume construction after the flood season, minimizing the delays to the overall project schedule during the flood season and achieving a balance between safety and schedule.
[0020] 4. The inlet gate and downstream flood control gate of the first pumping station are constructed in reverse order. This is the core reverse order method for the pumping station project to cope with the risks of the flood season. After the substructure is completed and the external power supply and superstructure are not yet completed, the gate is installed first and the water blocking function is realized. The pumping station's inlet and outlet channels can be blocked in advance during the flood season to prevent the backflow of river water into the deep foundation pit of the pumping station. It can play the role of water blocking during the flood season without waiting for the superstructure, hoist and electromechanical system to be completed. It effectively seizes the pre-flood construction node, ensures the safety of the pumping station foundation pit construction during the flood season, and meets the urgent needs of the riverside pumping station project for flood control construction.
[0021] 5. The second pumping station adopted a "sequential, multi-track, high-efficiency breakthrough" construction mode. Addressing the unique geological conditions along the river, it tackled engineering challenges such as cofferdam construction in the riverbed section, cutoff wall construction in complex sections of the old dike, and soft soil foundation treatment for the downstream outlet pool. This eliminated safety hazards, improved construction efficiency, and ensured construction safety during the flood season. Based on the different geological conditions and construction difficulties of the riverbed cofferdam section, the old dike cutoff section, and the downstream outlet pool section, this mode adapted specialized technologies such as double-row steel sheet pile cofferdams, grouted plastic concrete cutoff walls, and grouted silt-dissipating composite soft soil foundation treatment. It addressed differentiated engineering challenges such as the difficulty of constructing cofferdams in silt layers, poor seepage interception effects of the old dike foundation, and settlement of deep soft soil foundations. Simultaneously, parallel operations were possible in each construction section, achieving efficient construction of the pumping station under complex geological conditions. Furthermore, the silt generated during construction was environmentally solidified and recycled for shoreline restoration, balancing engineering and ecological benefits.
[0022] 6. The underwater forward-sequence construction method combined with the upper reverse-sequence construction method for the flood control gate on the riverside of the second pumping station is a key aspect of ensuring the safety of the riverside side during the flood season in the multi-track construction method of the second pumping station. The underwater part is constructed in the conventional forward sequence to ensure the quality of structural forming. After the underwater structure is completed, the gate slot and gate are installed first, so that the flood control gate can enter the flood control duty state in advance. It can play its role in blocking water on the riverside without waiting for the completion of the above-water structure, equipment installation and electromechanical engineering. It forms a flood barrier on the riverside of the pumping station in advance, effectively reducing the risk of river flooding during the construction period of the pumping station and improving the overall flood season safety redundancy of the project.
[0023] 7. The second control gate adopted a phased construction mode. In response to unfavorable geological conditions such as landfill and silt layers in the construction area, a combination of replacement and pile foundation treatment was adopted. By replacing and improving the shallow miscellaneous fill soil and the pile foundation reaching deep into the stable bearing layer, the problems of insufficient foundation bearing capacity and uneven settlement under unfavorable geological conditions were effectively solved. This improved the overall stability and seismic performance of the control gate foundation. Under the premise of ensuring the water-retaining conditions during construction, the construction quality and long-term operational safety of the gate structure under complex site conditions were ensured.
[0024] 8. By coordinating the operation of newly built control gates and pumping stations with existing old gates and flood diversion gates on the outer river side, different dispatching strategies can be precisely adapted according to the water level difference between the flood storage and detention area and the outer river, as well as the flood season level. This covers all scenarios, including normal drainage, flood season water blocking, local regulation and storage, basin-wide flood diversion and storage, flood discharge after the flood peak, and strong discharge at extreme water levels. It realizes the refined hierarchical regulation of flood control resources in the basin, fundamentally improves the flood control and drainage capacity of the flood storage and detention area, and completely solves the "flooding when the gate is closed" problem under the traditional model.
[0025] 9. By jointly scheduling the existing old sluice gate and the two newly built control gates, the operation mode can be flexibly switched according to the water level of the outer river: when the water level of the outer river is sufficient, the gates and stations will be opened simultaneously to divert and replenish water to ensure the water needs of production and daily life in the basin; when the water level of the outer river is low, the gates will be closed simultaneously to impound water, retain water in the lake area and river channel, improve the water resource utilization efficiency during the dry season, improve the operation and control function of the gate and station system throughout the year and all time, and achieve dual protection of flood control and drought resistance. Attached Figure Description
[0026] Figure 1 This is a flowchart of the sequential construction method. Detailed Implementation
[0027] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0028] like Figure 1 As shown in the figure, this specific embodiment discloses a dual-channel cascade gate and pumping station system under complex river conditions and its sequential construction method. The system is deployed on the first and second channels connecting the flood storage area and the outer river. Each channel is equipped with a control gate and a pumping station, and is simultaneously equipped with a total of 19.3 km of riverside dikes and 18 dike-penetrating structures. The whole system can form a watershed water control system for daily water passage, graded flood control and storage during the flood season, and coordinated drought relief and water regulation during the dry season. The system is constructed using a sequential construction process. Throughout the construction process, at least one channel is always connected to the flood storage area and the outer river to maintain the basic flood control and drainage functions of the watershed. The construction sequence is to first intercept the first channel and then construct the first control gate and the first pumping station. The first control gate adopts a multi-sequence parallel operation combined with a reverse-sequence gate installation method, which significantly reduces the service life of the cofferdam and enables it to be ready for use in advance. To enhance flood control capabilities, the first pumping station employs a multi-stage construction method combining "risk isolation - ballast stabilization - condition reconstruction" to mitigate the risks of deep foundation pit piping and slope instability during the flood season at a low cost. Once the first river channel gate is ready for water flow, the second river channel will be diverted to construct the second pumping station and the second control gate in sequence. The second pumping station utilizes differentiated specialized technologies and local cofferdam forms for different sections of the riverbed, old dike, and outlet pool to achieve efficient multi-stage construction. The second control gate employs a combination of replacement and pile foundation to address unfavorable geological conditions such as landfill and silt layers. During construction, dike reinforcement and the construction of structures penetrating the dike will be carried out in stages. After the completion of all projects, the newly built gates, together with the existing old gates and the supporting flood inlet and outlet gates on the outer river side, will operate in coordination, fundamentally solving the problem of "flooding at the gate" in the riverside flood storage area.
[0029] I. Dual-channel cascade gate system under complex river conditions
[0030] This invention takes the construction of a dual-channel gate system in a riverside lake flood detention area as an example. This project simultaneously covers two types of gate construction needs: first, some rivers connecting to the river previously lacked supporting control gate facilities, resulting in a significant gap in the basin's water system control capacity, requiring new construction to address these shortcomings; second, some existing facilities in the flood detention area's connecting waterways were old and dilapidated, lacking sufficient flood control, drainage, and water resource allocation capabilities, necessitating system upgrades through new construction. The overall construction period spans both the non-flood season and the flood season. If the traditional simultaneous interception construction mode across the entire river channel is adopted, the impact on drainage during the non-flood season will be relatively limited, but during the flood season, the external drainage channels of the flood detention area will be completely cut off, easily triggering the risk of "flooding upon closure."
[0031] Under complex river conditions, the dual-channel cascade gate and pumping station system is deployed on two channels connecting the flood storage area and the outer river. These two channels are the first channel upstream and the second channel downstream. The first channel houses the first control gate and the first pumping station, while the second channel houses the second control gate and the second pumping station. Embankments and structures penetrating the embankments are constructed along both channels. The system is constructed using the following sequential construction method, ensuring that at least one channel remains connected to the flood storage area and the outer river throughout the construction process. Ultimately, the system together forms a watershed water regulation system for daily water flow, flood control and storage during the flood season, and drought relief and water transfer during the dry season.
[0032] (a) First River Channel Sluice Gate Facilities
[0033] 1. First control gate
[0034] The first control gate has a drainage capacity of 615 m³ / s and a designed flood discharge capacity of 615 m³ / s. The structure is classified as Class 1, with the main structures such as the gate chamber, bank wall, wing wall, and energy dissipation and scour prevention structure being Class 1, the secondary structures being Class 3, and the temporary structures being Class 4.
[0035] The first control gate is located at the starting point of the first channel's safety zone embankment, approximately 300 meters from the bend where the first channel enters the flood storage area. The gate chamber has a total width of 100.8 meters, with both the left and right bank walls being 20 meters wide. The gate chamber is a breast-wall structure, with the top elevation of the gate at 20.50 meters and the bottom elevation of the breast wall at 16.00 meters. The gate chamber has eight openings, arranged in pairs, with each opening being 10.00 meters wide. The gate bottom slab has an elevation of 6.00 meters, a total length of 22.5 meters downstream, and a thickness of 2 meters. Both the front and rear ends have 1.5-meter-deep toothed grooves. The central pier of the gate chamber is 2 meters thick, the joint piers are 1.6 meters thick, and the side piers are 1.6 meters thick.
[0036] A 0.6m thick reinforced concrete apron, 15m long, is constructed upstream of the sluice gate. Upstream of the reinforced concrete apron, a 30m long, 0.4m thick concrete block apron is constructed, and at the upstream end, a 10m long riprap scour channel is installed. The energy dissipation facility downstream of the sluice gate is a reinforced concrete stilling basin, with a 1.0m thick bottom slab, a 1.00m depth, a 1.00m sill height, and a total length of 20m. The sloping section is 4m long with a slope ratio of 1:4, the horizontal section is 15.5m long, and the basin bottom elevation is 5.00m. A 30m long concrete apron follows the stilling basin sill, followed by a 30m long, 0.6m thick Reno mattress. Downstream of the Reno mattress, a 15m long riprap scour channel is constructed, and a 0.3m thick coarse sand and gravel cushion layer serves as a filter layer.
[0037] The gate chamber has empty box-type abutments on both sides. The left and right abutments are both 20m wide and 22.5m long in the downstream direction. The bottom plate of the abutment is 2.0m thick and the top elevation of the bottom plate is 6.00m. The top plate is 0.5m thick and the surrounding walls are 1.0m thick. Two 1.0m thick partition walls are set in the downstream direction and two 0.6m thick partition walls are set in the perpendicular direction of the downstream direction.
[0038] Upstream reinforced concrete apron and downstream stilling basin are flanked by wing walls, which combine reinforced concrete buttress structures with gravity retaining wall structures. The wing wall panels are fitted with structures with a diameter of [missing information]. The 50mm drainage holes are spaced 2.0m x 2.0m apart and arranged in a quincunx pattern.
[0039] The embankment connecting to the bank wall is of the same standard as the embankment in the safety zone, with a top width of 6.0m and a top elevation of 18.15m. The inner and outer slope ratios are both 1:3. The inner platform has an elevation of 14.00m and a width of 5.0m, sloping down to the natural terrain. The outer platform has an elevation of 11.00 to 13.50m and a width of 5.0 to 31.5m, sloping down to the top of the toe retaining wall or the bottom of the river channel.
[0040] The foundations of the main structures, including the lock chamber, bank walls, wing walls, and dikes, are situated on a clay layer with high bearing capacity and weak expansibility. The lock gates are flat steel gates, operated by fixed winches, with one winch per gate. A traffic bridge is located downstream of the lock gates, with a bridge deck width equal to the width of the roads connecting the dikes on both banks. It is constructed using prestressed concrete hollow slabs and designed to Highway Class II standards.
[0041] 2. First pumping station
[0042] The main structures of the first pumping station are classified as Class 2, including the pump house, outlet pipeline, floodgate, and wing walls. The secondary structures are classified as Class 3, and the temporary structures are classified as Class 4. The pumping station adopts a dike-back layout and is designed for flood drainage, with a flow rate of 55 m³ / s.
[0043] The main structures of the first pumping station, from upstream to downstream, are as follows: intake canal, trash rack bridge, intake culvert, intake forebay, main pump house, outlet pressure pipeline, floodgate, outlet stilling basin, and outlet canal.
[0044] The main pump house adopts a block-foundation type and houses three vertical fully adjustable axial flow pumps, arranged in a straight line. The main pump house has a plan dimension of 28.4m × 26.4m (length × width) and is divided into two parts in the direction of water flow: the inlet and the main unit room.
[0045] The intake is 9.6m long along the water flow direction and has three intake channels. Each intake channel has a total width of 7.2m at the inlet, with a 1.1m wide partition in the middle, resulting in a net width of 6.1m for each intake channel. The intake is equipped with six inlet safety barriers and two inlet maintenance gates, which can meet the maintenance needs of one unit simultaneously. The maintenance gates are opened and closed by a gantry crane, and the maintenance platform for the gates is at an elevation of 16.50m.
[0046] The axis spacing between the three units in the main equipment room is 9.0m. Below the ground level of the main pump house, from top to bottom, there are the following layers: motor layer, coupling layer, well maintenance platform, pump layer, and flow channel layer: The motor layer has an elevation of 21.00m, and the width of the passage between the motor and the side wall of the plant is greater than 1.5m; the coupling layer has an elevation of 16.50m, level with the top of the concrete well shaft of the pump, and each unit has 8 columns on the coupling layer as motor foundations; the manhole layer has an elevation of 12.00m, 50cm lower than the bottom elevation of the manhole in the pump well shaft; the pump layer has an elevation of 7.60m, and houses 3 main water pumps, fire pumps, dehumidifiers, and other equipment; the top elevation of the inlet flow channel is 2.50-4.30m, and drainage corridors, drainage ditches, and collection wells are provided, with the collection wells located at units 1 and 2. A staircase is installed between the pump floor and the coupling floor in the main pump room to connect the vertical traffic of each floor; the water inlet channel under the pump room adopts an elbow-shaped channel.
[0047] The upper part of the main pump house adopts a reinforced concrete frame structure, and a gate hoist is arranged at the water inlet maintenance gate. An electric double girder bridge crane is installed in the main machine room. The lifting method is hook lifting, the span is 14.5m, and the top elevation of the bridge crane rail is about 13.0m above the indoor design floor.
[0048] The pump house floor is located on an alternating layer of sandy loam. The foundation uses bored cast-in-place piles with a diameter of 1.2m and an average length of 45m. The bearing layer is silty mudstone.
[0049] An installation room is located to the right of the main pump house. The installation room measures 15.6m × 16.8m and has an elevation of 16.50m, consistent with the elevation of the main pump house's coupling layer. The main pump house's double-bridge crane can operate to the installation room area. The installation room has two underground levels, both serving as auxiliary facilities: the first underground level has an elevation of 12.00m, with one doorway each upstream and downstream connecting to the main pump house; the second underground level has an elevation of 7.60m, consistent with the elevation of the main pump house's pump floor, with one doorway each upstream and downstream connecting to the main pump house. A staircase at the end of the installation room provides vertical access between the installation room and the main pump house. The installation room's floor is situated on alternating sandy and loam layers. The foundation uses bored cast-in-place piles with a diameter of 1.2m and a length of approximately 50m, with the bearing layer being medium-argillaceous siltstone.
[0050] The auxiliary plant is located to the left of the main pump house, with a plan dimension of 29.75m × 16.8m. It has two floors above ground and houses the central control room, unit control panel room, high and low voltage power distribution room, stairwell, and restrooms. The floor below ground is a cable mezzanine. The foundation of the auxiliary plant is located on backfill soil and uses bored cast-in-place piles with a pile diameter of 1.2m and a pile length of approximately 55m. The bearing stratum is silty mudstone.
[0051] The maximum excavation depth of the first pumping station's foundation pit reached 15 meters, classifying it as a deep foundation pit. The soil within the excavation area mainly consisted of fine sand, silt, silty clay, sandy loam, and alternating layers of sand and loam, exhibiting moderate permeability. The foundation pit was enclosed by a support system consisting of reinforced concrete retaining piles and cement mixing piles, with a total of 48 dewatering wells, including 4 spare wells and 7 observation wells. Of the 48 wells, 13 were steel pipe wells, and the remainder were sand-free pipe wells.
[0052] (ii) Second River Channel Sluice Gate Facilities
[0053] 1. Second pumping station
[0054] The second pumping station adopts a zoned, differentiated design, with specialized structures and technologies configured for different geological conditions: Riverbed cofferdam section: A double-row steel sheet pile cofferdam structure is adopted to adapt to the complex geology of the riverbed silt layer and to enclose and form a dry construction area; In the old dike seepage interception section: a permanent seepage interception wall combining riprap grouting and plastic concrete is installed to reinforce the foundation and improve the stability of the dike; Downstream outlet section: A combined structure of riprap for silt removal, crushed stone cushion layer, and gravity concrete buttress retaining wall is used to treat the deep silty soft foundation and ensure the stability of the foundation.
[0055] The second pumping station is equipped with a floodgate on the riverside, which can be put into flood control duty in advance; the silt generated during construction and cleaning is recycled for shoreline restoration after environmental solidification.
[0056] 2. Second control gate
[0057] The second control gate was constructed in sequence. To address the unfavorable geological conditions of the landfill and silt layers in the construction area, a combination of replacement and pile foundation treatment was adopted to ensure the bearing capacity of the foundation and structural safety.
[0058] (iii) Dikes and structures penetrating the dikes
[0059] The total length of the safety zone dikes along the two river channels is 19.30 km. All of them are old dikes that have been reinforced, and the dike level is Class 2. The dike top width is 6.0 m, and the inner and outer slope ratio is 1:3. When the vertical height of the dike body is greater than 6.0 m, a 2 m wide counterweight platform is set 4 m below the top of the dike on the back slope. For dike sections without counterweight platforms, a 5 m wide management platform is set.
[0060] The total length of the soft soil foundation treatment for the dike is 18.10 km, and four types of reinforcement measures are adopted: counterweight platform + drainage consolidation, composite foundation, counterweight platform + geogrid, and geogrid. Among them, the top elevation of the counterweight platform is 13-14 m, the width is 5-25 m, and the thickness is 1.0-3.5 m; the drainage consolidation and composite foundation treatment depth is 8-15 m.
[0061] The outer slope of the safety zone dike adopts a combination of Reno slope protection and concrete slope protection. Above the platform, the Reno slope protection is used, and below the platform, the concrete slope protection is used, with a total length of 19.30 km for the hard slope protection treatment. The Reno slope protection thickness is 17 cm or 23 cm, and the concrete slope protection thickness is 10 cm or 15 cm. For lake dike sections with large waves, the thickness is 23 cm and 15 cm respectively, while for river dike sections with smaller waves, the thickness is 17 cm and 10 cm respectively. The inner slope of the dike and the counterweight platform use turf slope protection, with a total length of 19.30 km.
[0062] Eighteen structures were built along the dike, which are small-scale dike-crossing gate stations and gate facilities, to realize segmented water diversion, drainage and refined management of the dike.
[0063] II. Sequential Construction Method for Sluice Gate System under Complex Riverside Conditions
[0064] The sequential construction method of the gate and pumping station system under complex river conditions in this embodiment is used to construct the above-mentioned dual-channel cascade gate and pumping station system. During the entire construction process, at least one channel is kept connected to the flood storage and detention area and the outer river to maintain the flood discharge, drainage and drought relief functions of the basin.
[0065] (I) Overall Construction Organization
[0066] First, we prepared an implementation-oriented construction organization design, a cofferdam diversion and closure plan, and various special construction plans. Then, we used BIM information technology to optimize the overall layout and schedule simulation control.
[0067] After demonstration, comparison and simulation, the overall construction sequence was determined as follows: first construct the first channel cascade gate system, then construct the second channel cascade gate system, and simultaneously carry out dike filling and construction of structures penetrating the dike in sections; the construction sequence within a single channel is as follows: the first channel is constructed in the order of "first control gate → first pumping station", and the second channel is constructed in the order of "second pumping station → second control gate".
[0068] During construction, at least one river channel will always be maintained to connect the flood storage area with the outer river: when the first river channel is being diverted, the second river channel will take over the function of flood control and drainage of the basin; when the second river channel is being diverted, the first river channel will take over the function of flood control and drainage of the basin.
[0069] (II) Sequential construction of the first channel
[0070] The first channel adopts an organizational model of one-time interception, sequential construction, and unified dismantling of cofferdams: First, the upstream and downstream full-section cofferdams of the construction section corresponding to the first control gate are filled to cut off the flow of the first channel in one go, serving as the main water-retaining barrier during the construction period of the entire channel; within the dry area protected by the main cofferdam, construction is organized sequentially in the order of the first control gate → the first pumping station, where the first pumping station only fills the upstream partial cofferdam in its own construction section (the downstream relies on the existing existing embankment for water retention), which is a secondary construction enclosure within the main cofferdam; after the first control gate and the first pumping station are all completed and ready for water flow, all construction cofferdams in the first channel are uniformly dismantled to restore the flood discharge of the entire channel.
[0071] 1. First control gate: Multi-sequence parallel combined with reverse sequence gate installation construction
[0072] First, the upstream and downstream cofferdams corresponding to the construction section of the first control gate are filled in, and the cofferdams cross the entire cross-section of the river channel to achieve the first channel closure.
[0073] After the cofferdam is filled, the deep foundation pit of the control gate will be excavated. The following operations will be carried out simultaneously in a sequential and parallel manner: underwater soft soil treatment (using cement-soil replacement technology), main gate structure construction, upstream and downstream auxiliary structure construction of the gate chamber, left and right bank wing wall construction, and soft soil treatment and filling reinforcement of the embankment connecting section of the wing wall (using counterpressure platform + drainage consolidation technology).
[0074] After the main structure of the underwater gate pier is completed, the construction of the upper structure of the gate chamber is temporarily suspended. The gate slots are buried and the gates are installed in reverse order, so that the gates can be put into operation for opening and closing water blocking and temporary flood control in advance. The specific process is as follows: (1) Gate slot installation: The total length of the gate slot embedded parts is 15m, which is prefabricated in 3 sections, each section is 5m long; the quick installation and dismantling top-mounted leveling and positioning lifting equipment is used to lift the sections, and vertical welding splices are performed in the gate slot; multiple sets of embedded connecting bars are welded on the back of the embedded parts, and the embedded connecting bars are corrected by the steel bar straightening device, and then overlapped and welded firmly with the embedded parts in the first phase of the poured gate pier concrete structure; during the construction process, measuring instruments and laser devices matching the lifting equipment are used to control the verticality, horizontality and installation spacing of the embedded parts in real time; finally, the joint surface and the surface of the embedded bars are cleaned, the template is installed, the concrete is poured and vibrated to compact, and cured to the design strength.
[0075] (2) Gate installation: The single gate is a flat sliding gate with a size of 10.3m×10.3m and a single gate weight of 71.4t; the gate is divided into 3 prefabricated sections in the factory, with the dimensions of each section being 10.3m×3.3m, 10.3m×3.7m, and 10.3m×3.3m respectively, and the average weight of a single section is 23.8t; after the prefabricated sections are transported to the site, they are assembled using high-strength bolts.
[0076] The assembled gate is hoisted into the slot using a truck crane. Temporary fixation and opening / closing are achieved through positioning locking beams and a quick-change platform vehicle. The gate locking beams are simply supported beams with an I-beam cross-section and a single beam weighs 0.13t. Each gate is equipped with two locking beams, placed at the top of the gate slot. Two cantilever wheels are installed on each side of each gate section. The gate is supported on the locking beams by the cantilever wheels on both sides, keeping it in a suspended, ready-to-go state. At this time, the distance between the bottom of the gate and the bottom plate of the gate chamber is about 8m, which does not affect the normal flow of the river.
[0077] When the gate needs to be closed, use a truck crane to lift the gate, use a special lifting tool and a quick conversion platform vehicle to remove the locking beam, and then lower the gate along the gate slot; when the gate needs to be opened, use a truck crane to slowly lift the gate along the gate slot, and then reset the locking beam to below the cantilever wheels on both sides of the gate, so that the gate is resuspended and fixed.
[0078] After the gate was put into temporary flood control duty, construction continued on the upper structure of the gate chamber, the hoisting equipment, the electromechanical system and the 35kV external power supply line.
[0079] By constructing in reverse order, the actual service life of the cofferdam of the first control gate was shortened from the original plan of 2 years to 1 year, enabling water flow and flood discharge ahead of schedule, and creating diversion conditions for the subsequent construction of the second channel.
[0080] 2. First pumping station: Multi-sequence construction combined with process re-reset construction
[0081] The upstream cofferdam of the first pumping station was filled in, and the downstream area relied on the existing dike to block water, thus forming a dry construction area for the first pumping station.
[0082] In the dry construction area, a multi-sequence parallel construction method is adopted: the construction of the inlet gate and inlet culvert of the inlet section is carried out in parallel in sections and sequences, the main foundation pit support system of the pumping station is constructed simultaneously, the dewatering wells are laid out and the layered excavation of the foundation pit is started, and the construction of the upstream and downstream auxiliary structures of the pumping station is promoted in parallel.
[0083] The foundation pit construction employed rotary drilling rigs for cast-in-place pile foundation construction, with crawler cranes hoisting and placing the reinforcing cages. The concrete for the cast-in-place piles was self-mixed at the mixing plant and transported to the site by mixer trucks. Earthwork excavation was carried out in layers, with wet excavators loading the excavators and dump trucks transporting the soil to the backfill area or temporary stockpile. During the excavation process, ground settlement monitoring of the surrounding area was strengthened.
[0084] When the water level of the outer river rises rapidly to an elevation of 14m during the flood season, and the deep foundation pit of the pumping station is excavated to an elevation of 5m, the water level difference between the inside and outside of the pit exceeds 8m. Since the foundation pit soil is mainly composed of fine sand and silt, with moderate permeability and low slope shear strength, there is a risk of piping and slope instability, endangering the safety of the surrounding area and the project. Therefore, the process resetting procedure should be initiated immediately, implemented in three steps: "risk isolation → ballast stabilization → condition reconstruction." (1) Risk isolation: Stop the excavation of the foundation pit, retain the existing cast-in-place pile + mixing pile enclosure support system, urgently seal all foundation pit dewatering wells, restore the original appearance of the dike and the toe of the dike, and eliminate the risks of support structure failure, foundation pit leakage and slope instability.
[0085] (2) Ballast stability: The excavated foundation pit is backfilled in layers with earthwork to the original landform elevation, and the geological stability is restored by the earth weight ballast. At the same time, a 24-hour shift patrol mechanism and safety monitoring are started to prevent sudden dangers and ensure safe flood season.
[0086] (3) Condition reconstruction: After the flood season, when the water level of the outer river drops to a safe range, apply for resumption of work again according to the procedure; reuse the cast-in-place pile + mixing pile enclosure support system that has been constructed in the early stage, re-drill dewatering wells to restore the foundation pit dewatering, continue to excavate the foundation pit to the designed foundation surface, and complete the construction of the main structure of the pumping station.
[0087] By resetting the construction process, the foundation pit support system and some upstream and downstream ancillary structures were completed ahead of schedule before the flood season, thus avoiding flood season risks at a lower cost and shortening the overall construction period.
[0088] In addition, the inlet gate of the first pumping station and the flood control gate of the downstream section both adopted the reverse construction method: after the substructure was completed, the gate was installed first before the external power was connected, and the gate was used to block the water and ensure the safety of the pumping station foundation surface; after the flood peak passed and the water level returned to normal, the construction of the superstructure, gate hoist, power supply and maintenance and decoration of the superstructure continued.
[0089] (III) Sequential construction of the second channel
[0090] Once the first control gate and the first pumping station on the first channel are ready for water flow, the cofferdam of the first channel will be removed to restore the channel's flood control function. Subsequently, a cofferdam will be built to block the second channel, and the first channel will assume the function of flood control and drainage in the basin. Construction of the second channel gate and station will then begin.
[0091] The second channel adopts a symmetrical approach to the first channel, involving a single interception, sequential construction, and unified weir removal: First, full-section cofferdams are constructed upstream and downstream of the corresponding construction section of the second control gate to cut off the flow of the second channel in one go, serving as the main water-retaining barrier during the construction period of the entire channel; within the dry area protected by the main cofferdam, construction is organized sequentially in the order of "second pumping station → second control gate," with the second pumping station only constructing a local dedicated cofferdam in its own construction section, which is a secondary construction enclosure within the main cofferdam; after the second pumping station and the second control gate are fully constructed and ready for water flow, all construction cofferdams in the second channel are uniformly removed to restore the flood discharge capacity of the entire channel.
[0092] 1. Second pumping station: Sequential multi-track, high-efficiency construction breakthrough
[0093] The second pumping station employs specific construction techniques and local cofferdam designs for different construction sections: (1) Riverbed cofferdam section: A double-row steel sheet pile cofferdam mechanism (such as the double-row steel sheet pile cofferdam mechanism for a highly stable riverbed silt layer described in the invention patent application with application number CN202511335391.7) was used to construct a local construction cofferdam, which solved the problem of cofferdam construction in complex riverbed silt geology, successfully constructed the cofferdam system, and ensured the safe construction of the pumping station.
[0094] (2) Old dike seepage interception section: The construction method of grouting and solidifying plastic concrete cut-off wall for the dike in the rock-filling emergency section (patent application number CN202511360288.8) is adopted to solve the construction problem of permanent cut-off wall under special geological conditions such as silt layer and rock-filling layer mixed with garbage and impurities at the bottom of the dike, to ensure the successful cut-off of the pumping station, to strengthen the bearing capacity of the foundation, and to improve the safety of the dike section.
[0095] (3) Downstream outlet pool section: For the deep silty soft foundation, the technical measures of riprap squeezing + crushed stone cushion layer + gravity concrete buttress retaining wall are adopted to solve the problem of soft foundation subsidence and ensure the stability of the foundation; the silt cleaned up during construction is recycled and reused for shoreline restoration of farmland along the river after environmental solidification.
[0096] The second pumping station's riverside flood control gate adopts a construction method that combines underwater forward sequence with upper reverse sequence: after the underwater part is completed in forward sequence, the gate slot and gate are installed first, so that the flood control gate can enter the duty flood control state in advance, and then the above-water part of the structure, equipment installation, power and weak current and decoration works are carried out.
[0097] 2. Second control gate: Sequential construction
[0098] First, the upstream and downstream cofferdams of the building section corresponding to the second control gate are filled to form the water-blocking area for the construction of the control gate. Then, the foundation pit support, excavation and dewatering construction are carried out. After excavation to the designed foundation surface, foundation treatment and structural construction are carried out.
[0099] In response to the unfavorable geological conditions such as garbage, debris, and silt buried by villagers in the construction area, a combined treatment scheme of replacement and pile foundation was adopted to solve the unfavorable geological problems and ensure the quality of the project and safe passage through the flood season.
[0100] During the construction of the second river channel, the construction of the remaining sections of the dike and the structures penetrating the dike will be carried out simultaneously.
[0101] (iv) System debugging and acceptance
[0102] After the completion of construction of all control gates, pumping stations, dikes, and structures penetrating the dikes, commissioning and acceptance will be organized according to procedures. Upon acceptance, the newly built gates, dikes, and their penetrating structures, together with the existing old gates, will form a system for daily water supply, flood control and drainage during the flood season, and water storage and regulation during the dry season, thus realizing the planned water storage and regulation functions.
[0103] (v) Operation and control methods after completion
[0104] 1. Flood storage and regulation mode during the flood season
[0105] After the system is completed, the first control gate, the first pumping station, the second control gate, and the second pumping station will work in conjunction with the existing old gates at the confluence of the two rivers and the supporting flood intake and discharge gates on the outer river side. Flood control and storage will be implemented in stages based on the water level relationship between the flood storage and detention area and the outer river. The specific operating conditions are as follows: Operating Condition 1: When the water level in the flood storage area is higher than that in the outer river, the two existing old gates are opened to discharge water into the outer river. The first and second control gates are kept open, and the water level regulation and normal flow between the flood storage area and the outer river are achieved through the natural water level difference.
[0106] Condition 2: When the water level of the outer river is higher than that of the flood storage area during the flood season and there is no need for flood storage, the two existing old gates are closed to prevent backflow of the outer river, while the first and second control gates remain open to maintain the flow and drainage of the river.
[0107] Scenario 3: During the flood season, when the water level of the outer river is higher than that of the flood storage area, the two existing old sluice gates are closed to block water. When the water level of the flood storage area rises to an elevation of 14.86m but does not meet the flood storage conditions, both the first and second control gates are closed to block water, and local regulation and storage of floodwater are carried out within the flood storage area. When the water level in the two rivers rises to an elevation of 14.86m, the first and second pumping stations are activated to discharge floodwater into the outer river, controlling the river water level to not exceed the elevation of 14.86m, and ensuring the safety of villages and towns along the river during the flood season.
[0108] Operating Condition 4: When implementing basin-wide flood storage and dispatching, it operates according to Operating Condition 3 mode; when the water level of the outer river continues to rise to the level exceeding the warning level, the supporting flood gate with a design flow of 800 m³ / s on the outer river side is opened to divert the floodwater from the outer river to the flood storage and detention area for flood storage and peak regulation. The designed flood storage level of the flood storage and detention area is 17.35 m, corresponding to a dike elevation of 18.15 m; simultaneously, when the water level in the two rivers rises to an elevation of 14.86 m, the first and second pumping stations are activated to discharge floodwater into the outer river to control the river water level to not exceed the elevation of 14.86 m.
[0109] Condition 5: During the flood discharge phase after the flood peak, the supporting flood discharge gate with a design flow of 800 m³ / s, two existing old gates, the first control gate with a design flow of 615 m³ / s, and the second control gate with a design flow of 240 m³ / s will be opened on the outer river side. Flood discharge will be carried out as appropriate according to the water level of the outer river, and the floodwater in the flood storage area will be discharged to the outer river.
[0110] Condition 6: If rainfall continues after the water level in the flood storage area reaches the 17.35m flood storage level, and the water level in the outer river is still higher than the river channel level and the flood storage level, partially open the first and second control gates. Under the condition that the river channel water level is controlled to not exceed the 14.86m elevation level, start the first and second pumping stations to discharge floodwater into the outer river. After the water level in the outer river is lower than the river channel level, switch to the flood discharge mode of Condition 5 until the end of the flood season.
[0111] 2. Drought-resistant water diversion model during the dry season
[0112] When the flood storage and detention area lacks water supply during the dry season, the existing old sluice gates at the confluence of the two rivers with the first and second control gates will be used for joint operation. When the water level of the outer river can meet the water replenishment needs, the existing old gate and the first and second control gates will be opened to transfer water from the outer river to the flood storage and detention area and the river channel to ensure the water supply for production and daily life in the basin. When the water level of the outer river is too low to be continuously replenished, the existing old sluice gate and the first and second control gates are closed to impound and store water in the flood storage area and river channel to maintain the water supply of the basin.
[0113] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.
Claims
1. A method for sequential construction of a sluice gate system under complex riverside conditions, characterized in that, The gate and pumping station system is deployed on two waterways connecting the flood storage area and the outer river. The two waterways are the first waterway on the upstream side and the second waterway on the downstream side. The first waterway is equipped with a first control gate and a first pumping station, and the second waterway is equipped with a second control gate and a second pumping station. The system includes the following steps: Construction has begun, and at least one river channel must be maintained to connect the flood storage and detention area with the outer river throughout the entire construction process to maintain the flood control and drainage functions of the basin. The upstream and downstream cofferdams were filled to block the first channel of the river, and the second channel took over the function of flood control and drainage of the basin. The construction of the first control gate and the first pumping station was completed in sequence, and the construction of the dikes and structures penetrating the dikes of the first channel was carried out in sections simultaneously. After the first control gate and the first pumping station were ready for water supply, the cofferdams of the first channel were removed to restore the flood control function of the river. The upstream and downstream cofferdams were filled to block the second channel, and the first channel took over the function of flood control and drainage of the basin. The construction of the second pumping station and the second control gate was completed in sequence, and the construction of the dikes and structures penetrating the dikes of the second channel was carried out simultaneously. After the completion of the construction of all control gates, pumping stations, dikes and structures penetrating the dikes, commissioning and acceptance will be carried out to form a watershed water regulation system for daily water supply and flood control and storage during the flood season.
2. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 1, characterized in that, The first control gate adopts a construction method that combines multi-sequence parallel installation with reverse-sequence installation, as detailed below: After the upstream and downstream cofferdams of the first control gate corresponding to the building section are filled, the upstream and downstream cofferdams cross the entire cross section of the river channel to achieve the first river channel closure. Then, the deep foundation pit of the first control gate is excavated, and the underwater soft soil treatment, main gate chamber structure, upstream and downstream auxiliary structures of the gate chamber, left and right bank wing walls and embankment reinforcement are carried out in sequence and in parallel. After the main structure of the underwater gate pier is completed, the construction of the upper structure of the gate chamber will be temporarily suspended. The gate slots will be buried and the gates will be installed first, so that the gates can be opened and closed to block water and perform temporary flood control duty in advance. After the gate was put into temporary flood control duty, construction continued on the upper structure of the gate chamber, the hoisting equipment, the electromechanical system and the external power supply line.
3. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 1, characterized in that, The first pumping station adopts a construction method that combines multi-sequence construction with process re-reset, as detailed below: The upstream cofferdam of the first pumping station was filled in, and the downstream section relied on the existing dike to block water, forming a dry construction area for the first pumping station. Within this dry construction area, the construction of the inlet gate and inlet culvert was carried out in parallel in sections and sequence. At the same time, the main foundation pit support system of the pumping station was constructed, dewatering wells were laid, and the layered excavation of the foundation pit was started. The construction of the upstream and downstream auxiliary structures of the pumping station was also carried out in parallel. When the water level of the outer river rises during the flood season to the point where the difference between the water levels inside and outside the foundation pit exceeds the safety threshold, and there is a risk of piping and slope instability, the process reset procedure shall be initiated: First, the excavation of the foundation pit was stopped, the existing support and enclosure system was preserved, all dewatering wells were sealed, and the original appearance of the dike and its toe was restored. Next, the excavated foundation pit was backfilled in layers to the original landform elevation, and the geological stability was restored by soil weight load. At the same time, a 24-hour inspection and safety monitoring mechanism was launched. Finally, construction resumed after the flood season when the water level of the outer river receded to a safe range. The existing support and enclosure system was used to redeploy dewatering wells to restore drainage. The foundation pit was excavated to the designed foundation surface, and the main structure of the pumping station was completed.
4. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 3, characterized in that, The inlet gate and downstream flood control gate of the first pumping station were both constructed using a reverse-sequence method. After the substructure is completed, the gates will be installed first and used to seal off the water to ensure the safety of the pumping station pit. After the flood peak passes and the water level returns to normal, the construction of the superstructure, hoist and electromechanical installation will continue.
5. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 1, characterized in that, The second pumping station adopts a phased, multi-track, and efficient construction method, employing corresponding construction techniques and local cofferdam forms for different construction sections of the pumping station: Riverbed cofferdam section: A partial construction cofferdam is constructed using a double-row steel sheet pile cofferdam structure, which is suitable for the complex geology of the riverbed silt layer and encloses the dry construction area. In the old dike seepage interception section: a construction method combining riprap grouting foundation reinforcement with plastic concrete cutoff wall is adopted to construct a permanent cutoff wall, reinforce the foundation and improve the stability of the dike. Downstream outlet section: A combination of rock dumping and silt removal, crushed stone cushion layer and gravity concrete buttress retaining wall is used to treat the deep silty soft foundation; the silt generated during construction is environmentally solidified and recycled for shoreline restoration.
6. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 5, characterized in that, The second pumping station's flood control gate on the riverside was constructed using a combination of underwater forward-sequence and upper-level reverse-sequence methods. After the underwater section is completed in the correct order, the gate slots and gates will be installed first, so that the gates can be put into flood control duty status in advance, and then the above-water structure, equipment installation and electromechanical engineering construction will continue.
7. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 1, characterized in that, The second control gate was constructed using a sequential construction method. First, the upstream and downstream cofferdams corresponding to the construction section of the second control gate are filled to form the water-retaining area for the construction of the second control gate. Then, the foundation pit excavation and dewatering construction are carried out. After excavation to the foundation surface, foundation treatment and structural construction are carried out. For the unfavorable geological conditions of the landfill layer and silt layer in the construction area, a combination of replacement and pile foundation treatment is adopted.
8. The method for sequential construction of a sluice gate system under complex riverside conditions as described in claim 1, characterized in that, After construction is completed, the first control gate, the first pumping station, the second control gate, and the second pumping station will operate in conjunction with the existing old gates at the confluence of the two river channels and the supporting flood control gates and flood discharge gates on the outer river side. Flood control and storage will be implemented in stages based on the water level relationship between the flood storage and detention area and the outer river. The specific operating mode is as follows: Operating Condition 1: When the water level in the flood storage and detention area is higher than that in the outer river, the two existing old gates are opened to discharge water into the outer river. The first and second control gates are kept open, and the water level regulation and normal flow between the flood storage and detention area and the outer river are achieved through the natural water level difference. Condition 2: When the water level of the outer river is higher than that of the flood storage area during the flood season and flood storage is not required, the two existing old gates are closed to prevent backflow of the outer river, while the first and second control gates remain open to maintain the flow and drainage of the river. Condition 3: During the flood season, when the water level of the outer river is higher than that of the flood storage area, the two existing old sluice gates are closed to block water. When the water level of the flood storage area rises to the elevation level but does not meet the flood storage conditions, both the first and second control gates are closed to block water, and local regulation and storage of floodwater are carried out within the flood storage area. When the water level in the two rivers rises to the elevation level, the first and second pumping stations are activated to discharge floodwater into the outer river to control the river water level from exceeding the elevation level and ensure the safety of villages and towns along the riverbanks on the safe side during the flood season. Operating Condition 4: When implementing basin-wide flood storage and dispatching, operate according to Operating Condition 3 mode; when the water level of the outer river continues to rise to above the warning level, open the supporting flood gate on the outer river side to divert the floodwater from the outer river to the flood storage and detention area for flood storage and peak regulation; simultaneously, when the water levels in the two rivers rise to the elevation level, start the first and second pumping stations to discharge floodwater into the outer river to control the river water level from not exceeding the elevation level; Condition 5: During the flood receding phase after the flood peak, the supporting flood discharge gates on the outer river side, the two existing old gates, as well as the first and second control gates will be opened. Flood discharge will be carried out as appropriate according to the water level of the outer river, and the floodwater in the flood storage and detention area will be discharged to the outer river. Condition 6: If rainfall continues after the water level in the flood storage area reaches the flood storage level, and the water level in the outer river is still higher than the river channel level and the flood storage level, partially open the first and second control gates. Under the condition that the river channel water level does not exceed the elevation level, start the first and second pumping stations to discharge floodwater into the outer river. After the water level in the outer river is lower than the river channel level, switch to the flood discharge mode of Condition 5 until the end of the flood season.
9. The method for sequential construction of a sluice gate system under complex riverside conditions according to claim 1, characterized in that, After construction is completed, a combined sluice gate and pumping station system will be used for drought relief and water diversion during the dry season: When the flood storage and detention area lacks water supply during the dry season, the existing old sluice gates at the confluence of the two rivers with the first and second control gates will be jointly operated; when the water level of the outer river can meet the water replenishment needs, the existing old sluice gates and the first and second control gates will be opened to divert water from the outer river to the flood storage and detention area and the river channel to ensure the water supply for production and daily life in the basin; when the water level of the outer river is too low to continuously replenish water, the existing old sluice gates on the Yangtze River side will be closed to impound and store water in the flood storage and detention area and the river channel to maintain the water supply of the basin.
10. A dual-channel cascade gate system under complex riverside conditions, characterized in that, The system includes a first and a second river channel connecting the flood storage area and the outer river. A first control gate and a first pumping station are installed on the first river channel, and a second control gate and a second pumping station are installed on the second river channel. Embankments and structures penetrating the embankments are installed along the banks of the two river channels. The gate and pumping station system is constructed using the sequential construction method for gate and pumping station systems under complex conditions near the river as described in any one of claims 1-9. Throughout the construction process, at least one river channel is kept connected to the flood storage area and the outer river, ultimately forming a watershed water regulation system for daily water supply, flood control and storage during the flood season, and drought relief and water regulation during the dry season.
Citation Information
Patent Citations
Construction method of plastic concrete seepage interception wall for embankment grouting solid foundation in riprap rescue section
CN120925519A
High-stability double-row steel sheet pile cofferdam mechanism for river mud layer
CN120945925A