A method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders

By combining interlocking pile wall protection and reverse circulation drilling rig, the construction problem of large-diameter cast-in-place piles in loose overburden layers was solved, achieving safe and economical construction results and improving the strength and service life of the pile foundation.

CN123109140APending Publication Date: 2026-11-17KUNMING JIECHENG PILING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611571879.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-12
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In loose overburden containing large boulders, existing technologies struggle to effectively address the safety and economic challenges of constructing large-diameter cast-in-place piles, particularly in ensuring borehole stability and the high cost and difficulty in recycling large-diameter steel casings.

Method used

The interlocking pile retaining wall construction method is adopted. A ring-shaped closed retaining wall is formed by alternating construction of A-sequence piles and B-sequence piles. The overburden layer is cut with a full casing drilling rig and alloy cutter head. When encountering boulders, they are broken and removed. The hole is drilled to the design depth using a reverse circulation drilling rig. Finally, concrete is poured to form the pile.

Benefits of technology

It enables safe and reliable construction of large-diameter cast-in-place piles under complex geological conditions, reduces construction costs, improves the continuity of construction and the strength of pile foundations, simplifies procedures and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109140A_ABST
    Figure CN123109140A_ABST
Patent Text Reader

Abstract

This invention discloses a method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders, belonging to the field of large-diameter pile foundation construction technology. The construction steps are as follows: First, level the site and construct interlocking pile guide walls. Then, construct an interlocking pile retaining wall outside the designed large-diameter pile foundation, formed by alternating interlocking of A-sequence piles and B-sequence piles. Next, use a grab bucket to extract soil within the interlocking pile retaining wall area to drill holes down to the rock surface. Subsequently, use a reverse circulation drilling rig to drill holes to the designed depth, forming a large-diameter pile hole. Finally, hoist a reinforcing cage into the pile hole and pour concrete to complete the construction of the large-diameter pile foundation. This construction method has strong applicability. When encountering large boulders, the interlocking drilling and cutting method is first used to divide the obstacle into multiple pieces before removing them one by one, effectively solving the problem of difficult drilling in loose strata containing large boulders.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of large-scale pile foundation construction technology, specifically relating to a method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders. Background Technology

[0002] In many large-scale infrastructure projects, large-diameter cast-in-place piles are often required for foundation treatment. Taking a hydropower station as an example, the cofferdam foundation treatment is planned to use large pile foundations with a single pile diameter of about 6.3m and a pile length of about 70m. The engineering geological conditions are complex: within about 45m below the ground surface, the main covering layer is loose overburden such as fine sand, gravel, boulders, and boulders; below about 45m, the main layer is moderately to slightly weathered limestone with a rock compressive strength of 25~70MPa.

[0003] Under the above conditions, traditional construction methods have the following prominent problems:

[0004] (1) If the loose overburden layer 0~45m below the ground is directly drilled with mud wall protection, the stability of the hole wall is difficult to guarantee, and the hole is prone to collapse, making it impossible to form a hole smoothly. Rigid wall protection should be used to follow the drilling.

[0005] (2) If the steel casing is sunk to the rock surface (about 45m deep) as a protective wall using the rolling pipe method or the vibratory pipe sinking method, the cost of the φ6.3m large-diameter steel casing and the matching sinking equipment is high; there is also a great risk that the large-diameter steel casing can be successfully pulled out and recovered; when the vibratory pipe sinking method is used in the rock and boulders strata, it is easy to cause problems such as pipe edge curling and casing deformation, which will make it impossible to sink the pipe into place; when encountering large boulders with a diameter exceeding a certain amount, they must be removed in advance before construction can continue, which further increases the difficulty and cost of construction.

[0006] In summary, existing technologies lack a construction method that can effectively address complex geological conditions while ensuring construction safety and economy for the construction of large-diameter cast-in-place piles in loose overburden containing large boulders, and such method urgently needs improvement. Summary of the Invention

[0007] The purpose of this invention is to provide a method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders, which is easy to operate and can effectively solve the above-mentioned problems.

[0008] The embodiments of the present invention are implemented as follows:

[0009] The present invention provides a method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders, comprising the following steps:

[0010] S1: First, level the site in the construction area, then measure and lay out the lines, and construct the interlocking pile guide wall;

[0011] S2: The interlocking pile construction equipment is in place, and an interlocking pile retaining wall is constructed on the outside of the designed pile foundation, which is formed by the alternating interlocking of A-sequence piles and B-sequence piles. The lower end of each A-sequence pile and B-sequence pile is embedded at least 0.5 meters below the rock surface.

[0012] S3: Drill holes to the rock surface in the internal area of ​​the interlocking pile retaining wall;

[0013] S31: First, use a grab bucket to remove the soil covering the inner area of ​​the interlocking pile retaining wall;

[0014] S32: When encountering large boulders during soil extraction, first break the boulders with impact and remove them;

[0015] S33: Then continue to remove the overlying soil downwards using the grab bucket until the soil reaches the rock surface;

[0016] S4: In the inner area of ​​the interlocking pile retaining wall, use a reverse circulation drilling rig to drill from the rock surface downwards, embedding the hole to the designed depth;

[0017] S5: Clean the hole and pass the acceptance test to form a large-diameter pile hole;

[0018] S6: Hoist the pile foundation reinforcement cage into the pile hole;

[0019] S7: Pour concrete into the pile hole to complete the construction of the large-diameter cast-in-place pile.

[0020] Furthermore, in step S1, the guide wall is formed by cast-in-place reinforced concrete or by prefabricated steel structure assembly.

[0021] Furthermore, in step S2, the construction of the interlocking pile retaining wall is as follows:

[0022] S21: Using interlocking pile construction equipment, steel casing is hoisted and driven into the designed interlocking pile hole location. The first A-sequence pile hole is constructed first, with a hole depth of at least 0.5 meters below the rock surface. The hole is cleaned and inspected, and concrete is poured into the first A-sequence pile hole to form a pile, thus completing the construction of the first A-sequence pile.

[0023] S22: At a position one interlocking pile hole away from the first A-sequence pile, construct the second A-sequence pile according to the method in step S21;

[0024] S23: Conduct tunnel boring between the first A-sequence pile and the second A-sequence pile. During the tunnel boring process, cut off part of the first A-sequence pile and the second A-sequence pile to form the first B-sequence pile hole. The hole depth should reach at least 0.5 meters below the rock surface. Clean the hole and pass the inspection. Pour concrete into the first B-sequence pile hole to form a pile. Alternatively, first hoist the interlocking pile reinforcement cage into the first B-sequence pile hole, and then pour concrete to form a pile, thereby completing the construction of the first B-sequence pile.

[0025] S24: At a position one interlocking pile hole away from the second A-sequence pile, construct the third A-sequence pile according to the method in step S21. Between the second A-sequence pile and the third A-sequence pile, construct the second B-sequence pile according to the method in step S23.

[0026] S25: By analogy, the construction of the remaining A-sequence piles and B-sequence piles is completed alternately in sequence, eventually forming a closed ring-shaped interlocking pile retaining wall.

[0027] Furthermore, a full-casing drilling rig is used to drive the steel casing to the rock surface. During the construction of each A-sequence pile hole and B-sequence pile hole, multiple sections of steel casing are required. During the casing driving process, multiple sections of steel casing are lowered one by one and then spliced ​​together as a whole. The verticality of the steel casing is monitored in real time. A grab bucket and a rotary drilling rig are used to remove the slag from the steel casing. After reaching the rock surface, the rock layer below the rock surface is drilled to a depth of at least 0.5 meters to ensure that after the piles are completed, the lower ends of the A-sequence piles and B-sequence piles are embedded in the rock layer by at least 0.5 meters.

[0028] Furthermore, during the tunnel immersion process, the verticality deviation of the steel casing is less than or equal to three per thousand.

[0029] Furthermore, during the tunnel immersion process, if an isolated rock is encountered, it can be directly drilled through using an alloy cutter head at the lower end of the steel casing.

[0030] Furthermore, after the A-sequence pile is cut, a recess is formed on the outer wall of the A-sequence pile. A portion of the outer wall of the adjacent B-sequence pile is embedded in the recess of the A-sequence pile to form an interlocking structure. The center of the recess of the A-sequence pile coincides with the center of the B-sequence pile.

[0031] Furthermore, in step S3, the diameter of the pile hole below the rock surface is less than or equal to the diameter of the pile hole above the rock surface.

[0032] Furthermore, in step S32, when encountering large boulders, a rotary drilling rig or down-the-hole hammer is used to drill multiple holes in the boulders to divide them into multiple pieces.

[0033] The beneficial effects of this invention are as follows:

[0034] (1) The present invention uses pre-constructed interlocking piles as rigid protective walls for the drilling of large-diameter pile foundations. The interlocking pile protection technology is mature, the construction equipment is flexible, and no personnel are required to go down into the hole for operation, which is safe and reliable. At the same time, there is no need to use large steel casings and related sinking and pulling pipe equipment to protect the drilling walls of large-diameter pile foundations, which avoids the risk that large-diameter steel casings are difficult to pull out and recover, and the overall economic efficiency is better.

[0035] (2) Alloy cutting teeth are installed at the lower end of the steel casing during the construction of interlocking piles. During the pile formation process, the full casing drilling rig drives the steel casing to rotate and press down with high torque, which powerfully cuts sand, gravel and boulders, and can effectively penetrate the loose overburden layer. If large boulders are encountered, they can also be effectively cut and drilled through by the alloy cutting head without prior separate removal, and the construction continuity is good.

[0036] (3) The interlocking pile wall structure has strong self-stability and does not require internal support during excavation, which simplifies the construction process and reduces costs.

[0037] (4) In addition to serving as a retaining wall structure for drilling large-diameter pile foundations, interlocking pile retaining walls can also serve as an additional reinforcing and protective structure for pile foundations, further enhancing the strength and service life of the pile foundations.

[0038] (5) For loose overburden layers, soil is extracted and holes are formed using a grab bucket. For rock-embedded sections, reverse circulation drilling is used. This method is mature, reliable, and economical. If large boulders are encountered, the interlocking drilling and cutting method can be used to divide the obstacles into multiple pieces before removing them one by one. This method is convenient and effectively solves the problem of difficult hole formation in strata containing large boulders. Attached Figure Description

[0039] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained from these drawings without creative effort.

[0040] Figure 1 A flowchart of the construction method provided for an embodiment of the present invention;

[0041] Figure 2 This is a structural schematic diagram of the guide wall in the construction area;

[0042] Figure 3 A construction diagram for hoisting and placing the steel sleeve;

[0043] Figure 4 This is a schematic diagram of drilling operations inside a steel casing.

[0044] Figure 5 A construction diagram showing the pouring of concrete for the first A-sequence pile;

[0045] Figure 6 A schematic diagram of the forming process of the interlocking pile retaining wall;

[0046] Figure 7 Schematic diagram of soil extraction and hole formation for the internal area of ​​the interlocking pile retaining wall;

[0047] Figure 8A schematic diagram of reverse circulation drilling rig rock-embedded hole formation;

[0048] Figure 9 A construction diagram showing the hoisting and placement of the pile foundation reinforcement cage;

[0049] Figure 10 This is a construction diagram showing the pouring of concrete into the pile hole.

[0050] In the diagram: 1-External guide wall; 2-Central guide wall; 3-Steel casing; 4-Crawler crane; 5-Rotary drilling rig; 6-Interlocking pile retaining wall; 7-Grab bucket; 8-Reverse circulation drilling rig; 9-Pile foundation reinforcement cage; 10-Conduit pipe; 11-Full casing drilling rig. Detailed Implementation

[0051] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.

[0052] It should be noted that, where there is no conflict, the features in the embodiments of this invention can be combined with each other.

[0053] In the description of this invention, it should be noted that the terms "first," "second," etc., are used only for distinguishing descriptions and should not be construed as indicating or implying relative importance.

[0054] refer to Figure 1 As shown, this invention provides a method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders, comprising the following steps:

[0055] S1: First, level the site in the construction area, then measure and lay out the lines, and construct the interlocking pile guide wall.

[0056] Before construction, relevant personnel are organized to conduct on-site briefings and verifications. The ground in the construction area is then cleaned, removing weeds, garbage, stones, and other debris. After cleaning, the construction area is leveled and compacted, and then the lines are measured and laid out according to the design drawings.

[0057] After the layout is completed, guide walls are constructed. The guide walls primarily serve as a load-bearing platform for the various construction equipment, ensuring stability during construction. Simultaneously, they act as a coordinate control structure for the interlocking piles, constraining the horizontal position of the pile heads and providing guidance during pile formation. (Reference) Figure 2 As shown, the guide wall includes an outer guide wall 1 and a central guide wall 2. The outer guide wall 1 refers to the area located outside the designed interlocking pile retaining wall 6, and the central guide wall 2 refers to the area located inside the designed interlocking pile retaining wall 6.

[0058] In some cases, the guide wall is made of reinforced concrete cast on site, with a surface flatness error of no more than 5mm and a thickness of no less than 300mm. The bottom of the reinforced concrete guide wall is tightly bonded to the soil layer, has good stability, and can be constructed under various complex environmental conditions.

[0059] In other cases, guide walls can be assembled from steel structural components. All components of the steel guide wall are prefabricated, resulting in high construction efficiency, recyclability, and environmental friendliness.

[0060] S2: The interlocking pile construction equipment is in place, and an interlocking pile retaining wall 6 is constructed on the outside of the designed pile foundation, which is formed by the alternating interlocking of A-sequence piles and B-sequence piles. The lower end of each A-sequence pile and B-sequence pile is embedded at least 0.5 meters below the rock surface.

[0061] It should be noted that the rock surface refers to the geological boundary between the overburden layer and the rock layer. Below the rock surface is a weathered and hard rock layer, and above the rock surface is a soft overburden layer. The thickness of each layer varies depending on the geological environment. During construction, survey data should be referenced and real-time monitoring should be carried out.

[0062] In this step, the construction method of the interlocking pile retaining wall 6 is as follows:

[0063] S21: Lowering steel casing 3 using interlocking pile construction equipment (reference) Figure 3 As shown), the casing is driven at the designed interlocking pile hole location. First, the first A-sequence pile hole is constructed, with a depth of at least 0.5 meters below the rock surface. After cleaning and acceptance, concrete is poured into the first A-sequence pile hole to form the pile, thus completing the construction of the first A-sequence pile (see reference). Figure 5 (As shown).

[0064] S22: At a position one interlocking pile hole away from the first A-sequence pile, construct the second A-sequence pile according to the method in step S21.

[0065] S23: Conduct tunnel boring between the first A-sequence pile and the second A-sequence pile. During the tunnel boring process, cut off part of the first A-sequence pile and the second A-sequence pile to form the first B-sequence pile hole. The hole depth should reach at least 0.5 meters below the rock surface. Clean the hole and pass the acceptance test. First, hoist the interlocking pile reinforcement cage into the first B-sequence pile hole, and then pour concrete to form the pile, thereby completing the construction of the first B-sequence pile.

[0066] Of course, in another alternative embodiment, when constructing the B-sequence pile, the interlocking pile reinforcement cage can be omitted, and concrete can be directly poured into the first B-sequence pile hole to form the pile.

[0067] S24: At a position one interlocking pile hole away from the second A-sequence pile, construct the third A-sequence pile according to the method in step S21. Between the second and third A-sequence piles, construct the second B-sequence pile according to the method in step S23.

[0068] S25: Following this pattern, the remaining A-sequence piles and B-sequence piles are constructed alternately, ultimately forming a closed ring-shaped interlocking pile retaining wall 6 (reference). Figure 6 (As shown).

[0069] In this embodiment, reference Figure 4 As shown, the construction equipment for interlocking piles includes a crawler crane 4 and a full-casing drilling rig 11. The crawler crane 4 is used to lift the steel casing 3, and the full-casing drilling rig 11 is used to drive the steel casing 3 into the ground. During the construction of each A-sequence pile hole and B-sequence pile hole, multiple sections of steel casing 3 are required. During the driving process, multiple sections of steel casing 3 are lowered one by one and then spliced ​​together as a whole. After each section of steel casing 3 is driven, the excavated soil inside the steel casing 3 can be removed using a grab bucket 7 and a rotary drilling rig 5. When the bottom end of the steel casing 3 reaches the rock surface, all the excavated soil inside the steel casing 3 is removed, and then the rock layer is drilled downwards to ensure that after the piles are completed, the lower ends of the A-sequence piles and B-sequence piles are embedded in the rock layer by at least 0.5 meters, thus ensuring the stability of the A-sequence piles and B-sequence piles.

[0070] During the tunnel immersion process, the verticality of the steel casing 3 needs to be monitored in real time. The verticality deviation of the steel casing 3 must be less than or equal to three per thousand. If it exceeds the maximum allowable deviation, it needs to be corrected in time.

[0071] During the tunnel immersion process, if a large boulder is encountered, it can be directly drilled through using the alloy cutter head at the lower end of the steel casing 3.

[0072] In step S23, the cutting of sequence A piles needs to be carried out before the concrete hardens, which facilitates the cutting. After sequence A piles are cut, a recess is formed on the outer wall of sequence A piles. Part of the outer wall of the adjacent sequence B piles is embedded into the recess of sequence A piles to form an interlocking structure. The center of the recess of sequence A piles and the center of sequence B piles are basically coincident.

[0073] It should be noted that when pouring concrete into the A-sequence pile holes and the B-sequence pile holes, the steel sleeve 3 is pulled out simultaneously.

[0074] When immersing the tunnel, it is necessary to estimate the thickness of the overburden layer and the location of large boulders in advance based on the geological survey report. When approaching the estimated location, the drilling speed needs to be slowed down. At the same time, the operator's feel, equipment data and the drill cuttings removed are used to determine whether boulders are encountered or the rock surface is reached.

[0075] S3: Drill holes to the rock surface in the internal area of ​​the interlocking pile retaining wall 6.

[0076] In this step, before excavation and hole drilling, the central guide wall 2 inside the interlocking pile retaining wall 6 needs to be broken. The hole drilling operation above the rock surface is as follows:

[0077] S31: First, use the grab bucket 7 to remove the soil covering the inner area of ​​the interlocking pile retaining wall 6.

[0078] refer to Figure 7 As shown, the grab bucket 7 starts grabbing the soil from the ground and transfers the excavated soil to a designated location using transport equipment.

[0079] S32: When encountering large boulders during soil extraction, first break the boulders with impact and remove them.

[0080] The procedure for breaking up a boulder is as follows: first, use a jack drill or impact drill to drill multiple holes in the boulder, then use an impact hammer to break it up, and finally use a grab bucket 7 to remove the fragments.

[0081] S33: After the boulder is removed, continue to remove the overlying soil by using the grab bucket 7 downwards until the soil reaches the rock surface.

[0082] S4: In the internal area of ​​the interlocking pile retaining wall 6, use a reverse circulation drilling rig 8 to drill a hole from the rock surface downwards, embedding the hole to the designed depth (reference). Figure 8 (As shown).

[0083] When drilling into rock, the diameter of the pile hole below the rock surface is less than or equal to the diameter of the pile hole above the rock surface. This ensures the stability of the interlocking pile retaining wall 6 and prevents it from sinking.

[0084] S4: Clean the hole and pass the inspection to form a large-diameter pile hole.

[0085] When cleaning the hole, the drill cuttings inside the hole should be removed as thoroughly as possible. During inspection, it is also necessary to check whether the bottom of the hole is flat. Otherwise, continue to use the reverse circulation drilling machine 8 to level the bottom of the hole.

[0086] S6: Hoisting a large-diameter pile foundation reinforcement cage 9 into the pile hole (reference) Figure 9 (As shown).

[0087] The pile foundation reinforcement cage is prefabricated in 9 sections, and then lifted and connected into the pile hole using a crawler crane 4.

[0088] S7: Pour concrete into the pile hole to complete the construction of the large-diameter cast-in-place pile.

[0089] refer to Figure 10 As shown, concrete can be transported by concrete mixer truck. When pouring concrete, multiple sets of guide pipes 10 are used to uniformly deliver concrete into the pile hole. Initially, the guide pipes 10 need to be extended to the bottom of the pile hole, with the bottom of the guide pipe 10 about 0.5m from the bottom of the hole. Then, when pouring concrete, the guide pipes 10 are lifted upward at a uniform speed, ensuring that the bottom of the guide pipe 10 is buried in the concrete to a depth of 2~6m. Special underwater micro-expansion self-compacting concrete is used to ensure the quality of large-diameter piles.

[0090] This invention is not limited to the above-described optional embodiments. Anyone can derive other various operating methods under the guidance of this invention. All technical solutions that fall within the scope of the claims of this invention are within the protection scope of this invention.

Claims

1. A method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders, characterized in that, Includes the following steps: S1: First, level the site in the construction area, then measure and lay out the lines, and construct the interlocking pile guide wall; S2: The interlocking pile construction equipment is in place, and an interlocking pile retaining wall is constructed on the outside of the designed pile foundation, which is formed by the alternating interlocking of A-sequence piles and B-sequence piles. The lower end of each A-sequence pile and B-sequence pile is embedded at least 0.5 meters below the rock surface. S3: Drill holes to the rock surface in the internal area of ​​the interlocking pile retaining wall; S31: First, use a grab bucket to remove the soil covering the inner area of ​​the interlocking pile retaining wall; S32: When encountering large boulders during soil extraction, first break the boulders with impact and remove them; S33: Then continue to remove the overlying soil downwards using the grab bucket until the soil reaches the rock surface; S4: In the inner area of ​​the interlocking pile retaining wall, use a reverse circulation drilling rig to drill from the rock surface downwards, embedding the hole to the designed depth; S5: Clean the hole and pass the acceptance test to form a large-diameter pile hole; S6: Hoist the pile foundation reinforcement cage into the pile hole; S7: Pour concrete into the pile hole to complete the construction of the large-diameter cast-in-place pile.

2. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 1, characterized in that, In step S1, the guide wall is formed by cast-in-place reinforced concrete or by prefabricated steel structure assembly.

3. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 1, characterized in that, In step S2, the construction of the interlocking pile retaining wall is as follows: S21: Using interlocking pile construction equipment, steel casing is hoisted and driven into the designed interlocking pile hole location. The first A-sequence pile hole is constructed first, with a hole depth of at least 0.5 meters below the rock surface. The hole is cleaned and inspected, and concrete is poured into the first A-sequence pile hole to form a pile, thus completing the construction of the first A-sequence pile. S22: At a position one interlocking pile hole away from the first A-sequence pile, construct the second A-sequence pile according to the construction method in step S21; S23: Conduct tunnel boring between the first A-sequence pile and the second A-sequence pile. During the tunnel boring process, cut off part of the first A-sequence pile and the second A-sequence pile to form the first B-sequence pile hole. The hole depth should reach at least 0.5 meters below the rock surface. Clean the hole and pass the inspection. Pour concrete into the first B-sequence pile hole to form a pile. Alternatively, first hoist the interlocking pile reinforcement cage into the first B-sequence pile hole, and then pour concrete to form a pile, thereby completing the construction of the first B-sequence pile. S24: At a position one interlocking pile hole away from the second A-sequence pile, construct the third A-sequence pile according to the construction method of step S21. Between the second A-sequence pile and the third A-sequence pile, construct the second B-sequence pile according to the method of step S23. S25: By analogy, the construction of the remaining A-sequence piles and B-sequence piles is completed alternately in sequence, eventually forming a closed ring-shaped interlocking pile retaining wall.

4. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 3, characterized in that, Using a full-casing drilling rig, steel casing is driven to the rock surface. During the construction of each A-sequence pile hole and B-sequence pile hole, multiple sections of steel casing are required. These sections are lowered one by one and then spliced ​​together. The verticality of the steel casing is monitored in real time. A grab bucket and a rotary drilling rig are used to remove the soil from the steel casing. After reaching the rock surface, the rock layer below the rock surface is drilled to a depth of at least 0.5 meters to ensure that after the piles are completed, the lower ends of the A-sequence piles and B-sequence piles are embedded in the rock layer by at least 0.5 meters.

5. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 4, characterized in that, During the tunnel immersion process, the verticality deviation of the steel casing is less than or equal to three per thousand.

6. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 4, characterized in that, If a boulder is encountered during the tunnel immersion process, it can be directly drilled through using an alloy cutter head at the lower end of the steel casing.

7. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 4, characterized in that, After the A-sequence pile is cut, a recess is formed on the outer wall of the A-sequence pile. The outer wall of the adjacent B-sequence pile is embedded in the recess of the A-sequence pile to form an interlocking structure. The center of the recess of the A-sequence pile coincides with the center of the B-sequence pile.

8. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 1, characterized in that, In step S3, the diameter of the pile hole below the rock surface is less than or equal to the diameter of the pile hole above the rock surface.

9. The method for constructing large-diameter cast-in-place piles in loose overburden containing large boulders according to claim 1, characterized in that, In step S32, when encountering a large boulder, use a core drill or impact drill to drill multiple holes in the boulder to divide it into multiple pieces.