A method for preventing leakage based on modified asphalt

By constructing a multi-layer stress dissipation system and adjusting dynamic parameters during roof construction, the problem of waterproofing layer damage caused by stress accumulation in each structural layer was solved, thus improving the seepage prevention effect of ultra-long and large-span projects.

CN123109394APending Publication Date: 2026-11-17BEIJING SECOND URBAN CONSTR ENG CO
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611161192.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-03
Publication Date
2026-11-17

Smart Images

  • Figure CN123109394A_ABST
    Figure CN123109394A_ABST
Patent Text Reader

Abstract

This invention relates to the field of waterproofing construction technology, and more particularly to a waterproofing construction method based on modified asphalt. The method includes: dividing the roof substrate into several construction areas and grinding them; then applying a non-curing coating and laying non-woven fabric to form a first stress dissipation layer and achieve initial stress attenuation; laying insulation boards and covering them with an isolation film to form a temperature difference buffer isolation layer; constructing a first rigid protective layer on this basis, followed by laying modified asphalt roll material to form a second stress dissipation layer to achieve secondary stress attenuation; constructing the second rigid protective layer, which, together with the first rigid protective layer, forms a synergistic constraint on the intermediate flexible layers; and simultaneously obtaining environmental temperature difference and wind speed values ​​to determine the spacing of the dividing joints and the depth of sealant application. This invention, by constructing a stress dissipation layer and coordinating with the upper and lower synergistic constraint protective layers, allows the stress generated in the substrate to be transmitted and attenuated step by step along each layer, effectively improving the waterproofing effect of large-area construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of anti-seepage construction technology, and in particular to an anti-seepage construction method based on modified asphalt. Background Technology

[0002] In the field of building roof waterproofing, traditional construction methods typically design and construct functional layers such as waterproofing layers, insulation layers, and protective layers independently. This lack of systematic coordination between layers leads to stress accumulation and transfer between layers under multiple stress sources, including temperature stress, wind loads, and substrate deformation. This results in potential leaks such as cracking of the waterproofing layer, delamination between the waterproofing membrane and the substrate, and cracking of the protective layer. Existing construction methods often rely on fixed design parameters and uniform construction standards, making it difficult to dynamically adjust to the actual working conditions of the construction area. Furthermore, they lack a collaborative working system between the various structural layers, failing to meet the stringent requirements of zero-leakage roofs for important projects such as ultra-long and large-span structures.

[0003] Chinese Patent Application Publication No. CN109648947A discloses an SBS modified bitumen composite non-curing waterproof membrane and its preparation method. The waterproof membrane body is composed of, from top to bottom along the thickness direction, a PET film layer, a first SBS modified bitumen impregnated material layer, a polyester base layer, a second SBS modified bitumen impregnated material layer, a non-curing coating, and an anti-stick release film layer. This invention, by combining the PET film layer, the first SBS modified bitumen impregnated material layer, the polyester base layer, the second SBS modified bitumen impregnated material layer, the non-curing coating, and the anti-stick release film layer into a single unit in a factory workshop, can precisely control the thickness of the non-curing coating, avoiding the problem of uneven thickness during on-site scraping or spraying. Furthermore, because secondary heating is not required, it also avoids safety issues such as burns to workers and environmental pollution caused by fumes.

[0004] However, the above-mentioned technical solutions mainly focus on improving the product structure of the waterproof membrane itself. Their quality assurance is still limited to the precise control of the thickness of the non-cured coating in the factory prefabrication process. They do not involve the coordination and cooperation between the various structural layers during on-site construction, thus making it difficult to improve the anti-leakage effect of large-area construction. Summary of the Invention

[0005] Therefore, this invention provides a waterproofing construction method based on modified bitumen to overcome the problem that existing technologies only focus on improving the structure of the waterproof membrane itself, and cannot coordinate the various structural layers during on-site construction, thus making it difficult to improve the waterproofing effect of large-area construction.

[0006] To achieve the above objectives, the present invention provides a seepage prevention construction method based on modified asphalt, comprising: Step S1: Divide the roof base layer into several construction areas and grind each construction area separately to remove laitance and loose particles from the base layer surface. Step S2: Apply non-curing asphalt waterproof coating to the base surface of each construction area, and lay non-woven fabric on the non-curing asphalt waterproof coating layer so that the non-curing asphalt waterproof coating and non-woven fabric work together to form a first stress dissipation layer to achieve stress attenuation. Step S3: Lay an insulation board on the non-woven fabric and cover the insulation board with an isolation film so that the insulation board and the isolation film work together to form a temperature difference buffer isolation layer to avoid the temperature difference stress concentration being transmitted to adjacent layers. Step S4: Obtain the ambient temperature difference and wind force value during construction, and determine the final spacing of the waterproof protective layer joints and the final filling depth of the sealant for each construction area based on the ambient temperature difference and wind force value. Step S5: Construct a first rigid protective layer on the isolation membrane as the first rigid constraint to constrain the position of each flexible layer below, wherein the position includes the horizontal and vertical positions of each flexible layer. Step S6: A modified bitumen waterproof membrane is laid on the first rigid protective layer to form a second stress dissipation layer, thereby achieving secondary stress attenuation. Step S7: Apply a second rigid protective layer as a second rigid constraint on the modified bitumen waterproof membrane, and cooperate with the first rigid protective layer to form a synergistic constraint on the intermediate flexible layers. Step S8: Fill the joints of the second rigid protective layer with sealant according to the final filling depth of the sealant to complete the construction of the waterproof protective layer.

[0007] Further, step S2 includes: The non-woven fabric is laid and compacted while the non-curing asphalt waterproof coating is in an uncured state, so that the gaps between the fibers of the non-woven fabric are fully wetted and penetrated by the non-curing asphalt waterproof coating. Based on the creep characteristics of the non-curing asphalt waterproof coating, the substrate deformation energy is absorbed, so that the non-woven fabric acts as a stress dispersion skeleton and transmits the concentrated stress evenly to the surroundings, so as to form a first stress dissipation layer and achieve stress attenuation.

[0008] Further, step S3 includes: The insulation board is laid on the non-woven fabric; The joints between adjacent insulation boards are laid in a staggered manner and sealed. Cover the insulation board with the insulating film; The insulation board and the first rigid protective layer are separated by the isolation membrane, so that the insulation board can freely expand and contract under the action of environmental temperature difference, and the temperature difference buffer isolation layer is formed.

[0009] Further, step S6 includes: The modified bitumen waterproof membrane is laid on the first rigid protective layer using a hot-melt full-adhesion process. Based on the elongation characteristics of the modified bitumen waterproof membrane, it absorbs the temperature stress and structural deformation energy transmitted from the first rigid protective layer, so as to achieve secondary stress attenuation. The modified bitumen waterproof membrane and the first rigid protective layer are bonded together in an integral manner through the hot-melt full-bonding process, so that stress is transferred between the layers and absorbed by the membrane.

[0010] Further, step S7 includes: The first rigid protective layer and the second rigid protective layer are made of fine stone concrete of the same thickness and type, and are reinforced with steel mesh of the same diameter. The first rigid protective layer serves as the lower constraint layer, used to constrain the horizontal and vertical displacements of the underlying flexible layers; The second rigid protective layer serves as an upper constraint layer, which cooperates with the first rigid protective layer to form a clamping constraint on the modified bitumen waterproof membrane.

[0011] Furthermore, the process of step S4 includes: The temperature difference spacing adjustment coefficient and temperature difference depth adjustment coefficient are determined based on the comparison results between the ambient temperature difference during construction and the first and second temperature difference set values. The wind force adjustment coefficient is determined based on the comparison between the wind force value during construction and the first and second wind force settings. The final spacing is determined based on the product of the temperature difference spacing adjustment coefficient and the grid seam reference spacing; The final filling depth is determined based on the product of the temperature difference depth adjustment coefficient, the wind force adjustment coefficient, and the sealant reference filling depth. Wherein, the first temperature difference setting value and the second temperature difference setting value are environmental temperature difference boundary values ​​determined according to the specification for setting the expansion joints of the rigid protective layer of the roof; the first wind force setting value and the second wind force setting value are wind force boundary values ​​determined according to the building structure load specification and the environmental requirements for sealant construction.

[0012] Furthermore, conductive fillers are added to the non-curing asphalt waterproof coating according to a preset ratio; The conductive filler enables the non-curing asphalt waterproof coating layer to have a piezoresistive effect, and the leakage location is identified based on the resistance change value of the corresponding construction area. The conductive filler forms a three-dimensional conductive network inside the non-curing asphalt waterproof coating. When the waterproof layer experiences local strain due to stress or leakage, the conductive network structure in the corresponding area changes, and the resistance value changes. Based on the fact that the change in resistance value is greater than the upper limit of the change in resistance value, it is determined that there is leakage or abnormal stress in the corresponding construction area.

[0013] Furthermore, the strength grade of the fine aggregate concrete is C20, and the laying thickness is 50mm; The steel bars used in the steel mesh have a diameter of 6mm; The modified bitumen waterproof membrane is an SBS modified bitumen waterproof membrane with a nominal thickness of 3mm and a thickness tolerance of ±0.3mm. The coating thickness of the non-curing asphalt waterproof coating is 1.2mm to 2.0mm; The insulation board is an extruded polystyrene board with a thickness of 50mm to 100mm; The nonwoven fabric is a polyester nonwoven fabric, and the overlap width of any two adjacent nonwoven fabrics is greater than or equal to 50mm. The isolation membrane is a PE membrane, and the overlap width of any two adjacent isolation membranes is greater than or equal to 50 mm.

[0014] Further, step S1 includes: Based on the roof slope, catchment area, waterproofing grade requirements, and joint locations of the roof base layer, the roof base layer is divided into several construction areas.

[0015] Furthermore, step S1 also includes: Obtain the base flatness deviation and base moisture content of each construction area after grinding; Based on the fact that the flatness deviation value is greater than the allowable flatness deviation, the corresponding construction area is determined to be re-grinded. Based on the fact that the moisture content is greater than the upper limit of the moisture content, the corresponding construction area is determined to be dried again.

[0016] Compared with the prior art, the beneficial effects of this invention are as follows: the roof base layer is divided into several construction areas, and each construction area is ground separately; on this basis, a non-curing asphalt waterproof coating is applied to the base surface, and a non-woven fabric is laid on the non-curing asphalt waterproof coating layer, so that the non-curing asphalt waterproof coating and the non-woven fabric synergistically form a first stress dissipation layer and achieve primary stress attenuation; then, an insulation board is laid on the non-woven fabric and covered with an isolation film, so that the insulation board and the isolation film synergistically form a temperature difference buffer isolation layer to avoid the concentrated transmission of temperature difference stress to adjacent layers; a first rigid protective layer is constructed on the isolation film as the first rigid constraint to constrain the position of the flexible layers below; and a modified asphalt waterproof membrane is laid on the first rigid protective layer to form a second stress dissipation layer and achieve secondary stress attenuation, so that the second rigid protective layer and the first rigid protective layer cooperate to form a synergistic constraint on the intermediate flexible layers; at the same time, the final spacing of the waterproof protective layer joints and the final filling depth of the sealant in each construction area are determined based on the ambient temperature difference and wind force during construction, and a waterproof protective layer is constructed on the second rigid protective layer. Thus, by constructing a first stress dissipation layer of non-curing coating + non-woven fabric and a second stress dissipation layer of modified bitumen roll material, and with the upper and lower synergistic constraint of the double-layer rigid protective layer, the stress generated by the base layer is transmitted and attenuated step by step along each layer, thereby effectively solving the problem of functional separation of each layer and stress accumulation between layers leading to damage to the waterproof layer in traditional roof construction, and thus improving the anti-seepage effect of large-area construction.

[0017] Furthermore, this invention lays and compacts a non-woven fabric while the non-curing asphalt waterproof coating is in its uncured state, allowing the fiber gaps of the non-woven fabric to be fully impregnated and penetrated by the non-curing asphalt waterproof coating. After curing, a fiber-reinforced composite stress dissipation layer is formed. In this way, the non-curing coating utilizes its creep characteristics to absorb the deformation energy of the substrate, and the non-woven fabric, as a stress-dispersing skeleton, evenly transmits concentrated stress to the surrounding areas, thereby synergistically achieving a significant stress attenuation.

[0018] Furthermore, this invention uses an isolation film to block the bonding channel between the insulation board and the first rigid protective layer, allowing the insulation board to freely expand and contract under environmental temperature differences, thus preventing temperature stress from being transmitted to the insulation board and the underlying flexible layers through the bonding channel. In this way, the temperature buffer isolation layer releases temperature stress while utilizing the thermal inertia of the insulation board's low thermal conductivity to mitigate the downward transmission of temperature shocks, preventing stress concentration and accumulation between layers.

[0019] Furthermore, this invention employs a hot-melt full-adhesion process to lay the modified bitumen waterproof membrane onto the first rigid protective layer. The membrane's elongation characteristics absorb the temperature stress and structural deformation energy transmitted from the first rigid protective layer, achieving secondary stress attenuation. Thus, the second stress dissipation layer further absorbs and dissipates the residual stress after the first attenuation.

[0020] Furthermore, this invention employs fine aggregate concrete of the same thickness and type for both the first and second rigid protective layers, and incorporates steel mesh of the same diameter within them, allowing the two rigid protective layers to work together to constrain each other. This effectively prevents interlayer slippage, warping, or cumulative deformation of the intermediate flexible layers under stress, ensuring a smooth transition of stress between layers.

[0021] Furthermore, this invention determines the temperature difference spacing adjustment coefficient, temperature difference depth adjustment coefficient, and wind force adjustment coefficient based on the ambient temperature difference and wind force during construction, and accordingly determines the final spacing of the expansion joints and the final sealing depth. In this way, the expansion joint spacing and sealing depth can be dynamically adjusted according to the actual on-site environmental conditions, avoiding the potential for cracking and leakage caused by fixed design parameters that cannot adapt to different construction conditions.

[0022] Furthermore, this invention incorporates carbon nanotubes or graphene conductive fillers into the non-curing asphalt waterproof coating, giving the coating layer a piezoresistive effect. Thus, when the waterproof layer experiences localized strain due to stress or leakage, the resistance value of the corresponding area changes, thereby identifying the leakage location and achieving early identification and precise location of leaks. Attached Figure Description

[0023] Figure 1 This is a flowchart illustrating the anti-seepage construction method based on modified asphalt according to an embodiment of the present invention; Figure 2 This is a logic decision diagram based on flatness deviation value and moisture content in an embodiment of the present invention; Figure 3 This is a logic diagram of an embodiment of the present invention based on the comparison between the resistance value change range and the upper limit of the resistance value change range; Figure 4 This is a schematic diagram of the stress transfer path according to an embodiment of the present invention. Detailed Implementation

[0024] To make the objectives and advantages of the present invention clearer, the present invention will be further described below with reference to embodiments; it should be understood that the specific embodiments described herein are merely for explaining the present invention and are not intended to limit the present invention.

[0025] Preferred embodiments of the present invention will now be described with reference to the accompanying drawings. Those skilled in the art should understand that these embodiments are merely illustrative of the technical principles of the present invention and are not intended to limit the scope of protection of the present invention.

[0026] In data center projects, roof leaks can directly infiltrate core functional areas such as server rooms, power distribution rooms, and battery rooms. All equipment within a data center is extremely sensitive to water; leaks can cause short circuits, equipment damage, data loss, and even service interruptions. Unlike traditional building roof leaks, which primarily cause damage to interior finishes, data center roof leaks can trigger a chain reaction of consequences, including business interruptions, permanent data loss, customer claims, and damage to the company's reputation. Furthermore, if leaked water spreads along cable trays and pipelines, it can cause secondary disasters such as electrical fires. Therefore, data center roof waterproofing is not simply about preventing leaks in the conventional sense; it is the last line of defense for ensuring the physical security and business continuity of the data center. For ultra-long, large-span data center projects, the large roof area, complex structural deformation, and significant temperature stress place far more stringent requirements on waterproofing construction than on ordinary buildings.

[0027] Specifically, during its service life after construction, the roof waterproofing layer mainly bears the following three types of stress: First, temperature stress: Modified bitumen waterproof membranes are primarily bitumen-based, making them heat-absorbing materials. Under direct sunlight, the surface temperature of the black membrane can rise significantly. At night, as the temperature drops, the membrane itself experiences drastic temperature changes, leading to repeated thermal expansion and contraction, resulting in significant temperature stress. The expansion and contraction of ultra-long, large-span roof structures are far greater than those of ordinary roofs, resulting in more concentrated and greater amplitude of temperature stress. The horizontal thermal expansion and contraction displacement of roof components caused by temperature changes is one of the main reasons for cracking and leakage in the waterproof layer.

[0028] Second, structural deformation stress: The roof substrate will undergo structural deformation under load, concrete shrinkage and creep, and uneven settlement. The flexural deformation and end displacement of ultra-long, large-span roofs are significantly greater than those of conventional roofs. When the substrate deforms, if the waterproofing layer is not fully bonded to the substrate and cannot adapt to this deformation, the waterproofing layer will crack or detach from the substrate. Furthermore, the deformation rates and amplitudes of the different structural layers of the roof vary under temperature changes, resulting in differential deformation stress between the layers.

[0029] Third, wind load stress: The roof waterproofing protective layer directly bears the wind load during use. Under strong wind conditions, the roof vibrates and deforms, and the sealant at the expansion joints is prone to fatigue cracking or adhesion failure under repeated vibration. The impact of wind load is more significant on ultra-long and large-span roofs.

[0030] It should be noted that the three types of stress mentioned above do not act independently, but rather are multiple factors coupled and superimposed on the various structural layers of the waterproof layer. Stress first originates from the base layer and is transmitted upwards through each structural layer. If a certain layer cannot effectively absorb or dissipate the stress, the stress will accumulate within that layer, ultimately leading to cracking, delamination, or leakage in the waterproof layer. This embodiment provides a waterproofing construction method based on modified asphalt. By constructing a multi-layered, collaborative stress dissipation system and a dynamic environmental parameter adjustment mechanism, the roof structure is upgraded from a single protection to a multi-level stress attenuation system. This allows the stress generated by the base layer to be transmitted and attenuated step-by-step along each structural layer, effectively solving the problem of stress accumulation between layers leading to waterproof layer damage.

[0031] Please see Figure 1 The diagram shows a flowchart of a waterproofing construction method based on modified asphalt according to an embodiment of the present invention. The construction method in this embodiment includes at least the following steps: Step S1: Divide the roof base layer into several construction areas and grind each construction area separately to remove laitance and loose particles from the base layer surface. Step S2: Apply non-curing asphalt waterproof coating to the base surface of each construction area, and lay non-woven fabric on the non-curing asphalt waterproof coating layer so that the non-curing asphalt waterproof coating and non-woven fabric work together to form the first stress dissipation layer to achieve stress attenuation. Step S3: Lay an insulation board on the non-woven fabric and cover the insulation board with an isolation film so that the insulation board and the isolation film work together to form a temperature difference buffer isolation layer to avoid the temperature difference stress concentration being transmitted to adjacent layers. Step S4: Obtain the ambient temperature difference and wind force value during construction, and determine the final spacing of the waterproof protective layer joints and the final filling depth of the sealant for each construction area based on the ambient temperature difference and wind force value. Step S5: Construct a first rigid protective layer on the isolation membrane as the first rigid constraint to constrain the position of each flexible layer below, wherein the position includes the horizontal and vertical positions of each flexible layer. Step S6: Lay a modified bitumen waterproof membrane on the first rigid protective layer to form a second stress dissipation layer to achieve secondary stress attenuation. Step S7: Apply a second rigid protective layer as the second rigid constraint on the modified bitumen waterproof membrane, and coordinate with the first rigid protective layer to form a synergistic constraint on the intermediate flexible layers. Step S8: Fill the joints of the second rigid protective layer with sealant according to the final filling depth of the sealant to complete the construction of the waterproof protective layer.

[0032] In this embodiment, the process of dividing the roof base layer into several construction areas in step S1 includes: Obtain the design drawings and on-site survey data for the roof base layer. Divide the roof base layer into several construction areas based on the roof slope, catchment area, waterproofing grade requirements, and key locations. The roof waterproofing grade is determined according to the building's type, importance, and functional requirements. Higher building types, importance, and functional requirements necessitate higher waterproofing grades, longer service life of the waterproofing layer, and more stringent protection requirements.

[0033] Based on the fact that the drainage capacity of the roof is significantly reduced and water accumulation is likely to occur when the roof slope is less than the minimum slope required by the specification, this area is designated as a key monitoring area for drainage performance; based on the fact that the scouring and water pressure on the waterproof layer are significantly enhanced when the catchment area exceeds the standard catchment area of ​​a single downpipe, this area is designated as a large catchment area; based on the fact that the highest waterproofing level requires the strictest construction quality standards and testing requirements, this area is designated as a high waterproofing level area; and for nodes with complex geometry, significant stress concentration, and a much higher risk of leakage than large catchment areas, such as downpipes, equipment and pipe roots, corners, and expansion joints, this area is designated as a node reinforcement area.

[0034] Based on the following conditions: the roof slope meets the specifications, the catchment area is within a reasonable range, the waterproofing level is not the highest level, and there are no aforementioned key points, the area is designated as a general construction area; other areas are designated as key construction areas. The area of ​​each construction area is controlled within a reasonable range to facilitate quality inspection and parameter control during subsequent construction.

[0035] After the division is completed, each construction area is numbered and marked, and the basis for the division and the degree of importance of each area are recorded as the basis for subsequent differentiated construction.

[0036] Furthermore, the process of grinding each construction area separately includes: Professional grinding machinery is used to grind the entire roof base structure. Handheld or ride-on concrete grinders are selected, and appropriate grinding heads or grinding wheels are chosen according to the strength of the base. The grinding depth is controlled between 1mm and 3mm to remove laitance, cement residue, oil stains, and slope defects from the base surface, so as to form a rough, clean, and solid bonding interface.

[0037] During the grinding process, the base surface is thoroughly and evenly ground, with a focus on repeatedly grinding raised areas, residual mortar, and sloping areas until the surface flatness meets the requirements. After grinding, an industrial vacuum cleaner or high-pressure blower is used to remove dust and loose particles from the base surface, ensuring that the surface is free of standing water, oil, and dust.

[0038] Furthermore, the process of obtaining the flatness deviation and moisture content of the base layer in each construction area after grinding, and comparing them with the allowable flatness deviation and the upper limit of moisture content, to determine whether the corresponding construction area needs to be re-grinded or re-dried, includes: The flatness deviation value of the base layer is used to determine whether the unevenness of the roof base layer surface after grinding meets the requirements for subsequent waterproofing layer construction. Specifically, the flatness deviation value of the base layer is determined based on measurements using a 2m straightedge and feeler gauge, with the maximum gap between the 2m straightedge and the base layer surface being used as the flatness deviation value.

[0039] The moisture content of the substrate is used to determine whether the dryness of the roof substrate meets the construction requirements of coating-based waterproofing materials. Specifically, a moisture meter is used to measure the moisture content of the substrate, and the arithmetic mean of the moisture content at each measuring point is taken as the substrate moisture content value for the corresponding construction area.

[0040] Using the allowable deviation of flatness as the criterion, the actual flatness deviation of the substrate is compared to determine whether the substrate, after grinding, meets the application conditions for the first stress dissipation layer. The allowable deviation of flatness is determined to be 5mm, based on the conventional standard in this field for the flatness of the leveling layer surface in roof waterproofing projects.

[0041] Specifically, the upper limit of moisture content is used as the criterion to determine whether the dryness of the substrate meets the construction requirements of non-curing asphalt waterproof coatings. The upper limit of moisture content is determined according to the industry-standard construction requirements for substrate dryness of non-curing asphalt waterproof coatings, and should not exceed 9%.

[0042] Please see Figure 2 As shown, this is a logic judgment diagram based on the flatness deviation value and moisture content in an embodiment of the present invention. The comparison process based on the flatness deviation value and the allowable flatness deviation, and the moisture content and the upper limit of the moisture content is as follows: In this embodiment, the deviation value of the base layer flatness exceeds the allowable flatness deviation, indicating that the unevenness of the base surface in the corresponding construction area exceeds the basic requirements for base layer flatness in subsequent waterproofing layer construction. If re-grinding is not performed, the coating thickness cannot be guaranteed to be uniformly distributed when applying the non-curing asphalt waterproof coating. Excessive coating accumulation in depressions and insufficient coating or even missed coating in protrusions will weaken the stress absorption and dispersion effect of the first stress dissipation layer, and at the same time cause the potential for local water accumulation on the roof. Therefore, the corresponding construction area is identified and re-grinding is performed.

[0043] Based on the fact that the flatness deviation of the substrate is less than or equal to the allowable flatness deviation, it indicates that the flatness of the substrate surface in the corresponding construction area meets the basic requirements for substrate flatness in subsequent waterproofing layer construction. Under this flatness condition, the application of non-curing asphalt waterproof coating can ensure uniform distribution of the coating thickness. The stress absorption and dispersion effect of the first stress dissipation layer will not be weakened due to unevenness of the substrate, and the roof drainage slope will not cause local water accumulation risks due to uneven substrate. The current flatness of the substrate is sufficient to ensure the construction quality and service life of the subsequent waterproofing layer. Therefore, it is determined that the corresponding construction area will not be re-grinded.

[0044] The fact that the substrate moisture content exceeds the upper limit indicates that the moisture content of the substrate in the corresponding construction area has exceeded the basic requirements for the dryness of the substrate for non-curing asphalt waterproof coatings. If the non-curing asphalt waterproof coating is applied directly under these moisture conditions, the moisture will be trapped between the substrate and the coating. When heated and expanded, it will create water vapor pressure, which will lead to blistering, delamination, or decreased adhesion of the coating, thus causing the waterproof layer to fail. Therefore, it is determined that the corresponding construction area should be dried again.

[0045] Based on the fact that the substrate moisture content is less than or equal to the upper limit, it indicates that the substrate moisture content in the corresponding construction area meets the basic requirements for the dryness of the substrate for non-curing asphalt waterproof coatings. Under these dryness conditions, the non-curing asphalt waterproof coating can form a reliable bond with the substrate. Moisture will not create water vapor pressure at the interface between the coating and the substrate, and the coating will not blister, delaminate, or experience a decrease in adhesion due to excessive substrate moisture content. The interfacial adhesion performance between the non-curing asphalt waterproof coating and the substrate is fully guaranteed. Therefore, it is determined that the corresponding construction area does not require re-drying treatment.

[0046] In step S2, a non-curing asphalt waterproof coating is applied to the base surface of each construction area, and a non-woven fabric is laid on the non-curing asphalt waterproof coating layer so that the non-curing asphalt waterproof coating and the non-woven fabric work together to form a first stress dissipation layer, thereby achieving a stress attenuation process. This process includes: After the base treatment in step S1 is qualified, apply non-curing asphalt waterproof coating to the base surface of each construction area.

[0047] Among them, non-curing asphalt waterproof coating is a commonly used non-curing rubber asphalt waterproof coating in this field. It is a waterproof coating with creep characteristics, prepared with modified asphalt as the main component and special additives. After construction, it maintains a certain creep performance and self-healing ability, does not cure or form a film, and can maintain a viscous paste state for a long time. The application method can be selected by scraping or spraying according to the area of ​​the construction area and site conditions: for small key construction areas or nodes, scraping is used to accurately control the coating thickness; for large general construction areas, spraying is used to improve construction efficiency. The coating thickness is determined according to the waterproofing level of the roof project. The waterproofing level is divided according to the roof engineering technical specifications. Among them, the coating thickness is not less than 2.0mm when the waterproofing is level one, and not less than 1.2mm when the waterproofing is level two; for detailed nodes such as drain outlets, equipment and pipe roots, and internal and external corners, the additional layer thickness is not less than 1.5mm.

[0048] Furthermore, before applying the non-curing asphalt waterproof coating, conductive fillers are added to the non-curing asphalt waterproof coating according to a preset ratio. The conductive fillers are selected from carbon nanotubes or graphene. The conductive fillers are uniformly dispersed in the non-curing asphalt waterproof coating through high-speed shear dispersion or ultrasonic dispersion processes, giving the non-curing asphalt waterproof coating layer a piezoresistive effect.

[0049] In this process, multiple groups of coating samples with different amounts of conductive filler were prepared, and the volume resistivity of each group of samples was measured to determine the dosage range corresponding to the step decrease in resistivity. This dosage range was then used as a preset ratio.

[0050] The study utilizes the piezoresistive effect to investigate the resistance changes of non-curing asphalt waterproof coatings under stress or leakage conditions. Carbon nanotubes or graphene are uniformly dispersed as conductive fillers within the non-curing asphalt waterproof coating, forming a three-dimensional conductive network within the coating. When the waterproof layer experiences localized strain due to stress or when leakage causes changes in the localized medium environment, the conductive network structure in that area alters, resulting in a change in resistance.

[0051] Furthermore, the method of identifying leakage locations through changes in resistance values ​​involves placing detection terminals at the edges of each construction area, with these terminals connected to a resistance measuring instrument via wires. During construction or use, the resistance values ​​of each construction area are periodically measured, and the results are compared with initial resistance reference values. When the resistance value change in a construction area exceeds the upper limit of the resistance value change range, it is determined that the corresponding construction area has leakage or abnormal stress. For the implementation with an embedded sensor grid, the sensor grid is arranged in an orthogonal matrix. By scanning the resistance or capacitance values ​​at each intersection point using an edge controller, the coordinates of the leakage point can be accurately located.

[0052] The initial resistance benchmark value serves as the standard resistance value of the waterproofing layer in each construction area under intact conditions, providing a benchmark for comparing subsequent resistance changes. The initial resistance benchmark value is set to eliminate the influence of factors such as differences in construction areas, variations in the uniformity of conductive filler dispersion, and changes in environmental temperature and humidity on the resistance value, ensuring consistency and comparability in determining resistance changes. Specifically, the initial resistance benchmark value is the initial resistance measurement value of each construction area after the waterproofing layer is completed but before it is put into use. After the waterproofing layer is completed and cured, the resistance value of each construction area is measured through detection terminals, and this measurement value is used as the initial resistance benchmark value for the corresponding construction area.

[0053] The upper limit of the resistance value change is used as the standard for determining whether there is leakage or abnormal stress in the construction area. This upper limit is a pre-set threshold for the amount of resistance value change. This upper limit distinguishes between resistance fluctuations caused by conventional environmental factors and resistance changes caused by leakage or stress strain. The upper limit is determined based on the piezoresistive sensitivity of the conductive filler, prevailing construction standards in the field, and the actual testing requirements of the project.

[0054] Specifically, under normal environmental conditions where there is no leakage and no significant stress or strain in the construction area, the resistance value of the coating layer is continuously monitored, and the maximum value fluctuation of the resistance value caused by conventional factors such as ambient temperature and humidity is recorded. At the same time, leakage or stress and strain conditions are simulated in the construction area, and the amount of resistance value change caused by leakage or significant stress and strain is recorded. The upper limit of the resistance value change range is set within the range between the maximum value of conventional fluctuation and the amount of resistance value change caused by leakage or stress and strain.

[0055] Please see Figure 3 As shown, this is a logic diagram of the present invention based on the comparison between the resistance value change range and the upper limit of the resistance value change range. The comparison process based on the resistance value change range and the upper limit of the resistance value change range is as follows: In this embodiment, the fact that the change in resistance value exceeds the upper limit of the resistance value change range indicates that the waterproof layer in the corresponding construction area has experienced local strain due to stress or that leakage has caused changes in the local medium environment, altering the conductive network structure and causing the resistance value to deviate from the initial reference value. Therefore, it is determined that the corresponding construction area requires leakage repair or stress relief treatment.

[0056] Since the change in resistance value is less than or equal to the upper limit of the resistance value change range, it indicates that the conductive network structure of the waterproof layer in the corresponding construction area remains stable, the resistance value is within the normal fluctuation range of the initial reference value, and the waterproof layer has not experienced stress concentration or localized changes in the medium environment caused by leakage. Therefore, it is determined that no leakage repair or stress relief treatment is required for the corresponding construction area.

[0057] Furthermore, while the non-curing asphalt waterproof coating is still in an uncured state, that is, during the period after application when it has not yet fully impregnated and stabilized with the substrate, non-woven fabric should be laid immediately and compacted.

[0058] The non-woven fabric is made of polyester, with a unit area mass of not less than 100g / m², and is laid in the same direction as the length of the construction area. Compaction is performed using rubber rollers or flat vibratory compaction tools to ensure the non-woven fabric is smoothly adhered to the surface of the non-curing asphalt waterproof coating, and to ensure that the interstices between the fibers of the non-woven fabric are fully impregnated by the non-curing asphalt waterproof coating. The overlap width between adjacent non-woven fabrics should be greater than or equal to 50mm to ensure the continuity and integrity of the non-woven fabric laying. During compaction, care should be taken to eliminate air bubbles between the non-woven fabric and the coating to ensure there are no voids or detachments between them.

[0059] Furthermore, the mechanism by which the non-curing asphalt waterproof coating and non-woven fabric synergistically form the first stress dissipation layer is as follows: The non-curing asphalt waterproof coating itself has excellent creep characteristics, and its creep deformation is the sum of elastic creep, high-elastic creep, and viscous flow creep. That is, after the material is subjected to stress, it produces both instantaneous elastic deformation and viscous flow deformation that develops over time. When the base layer deforms, it can absorb and dissipate the deformation energy of the base layer through its own viscous flow, preventing the deformation energy from being transferred to the upper part of the waterproof layer. After the non-woven fabric, as a fiber-reinforced skeleton, is fully impregnated and wrapped by the non-curing asphalt waterproof coating, a three-dimensional fiber network structure is formed inside the coating. When concentrated stress is applied to the surface of the coating, the non-woven fabric fiber network will evenly distribute and transfer the concentrated stress to the surrounding area, avoiding local damage caused by stress concentration. After the non-curing asphalt coating penetrates into the gaps between the non-woven fibers, the resulting composite layer possesses both viscous damping and tensile strength. Creep energy absorption and stress dispersion mechanisms work synergistically to form a fiber-reinforced composite stress dissipation layer after curing, achieving primary stress attenuation. That is, the deformation energy and stress generated by the base layer are first absorbed, dispersed, and attenuated within this composite layer, resulting in a significant reduction in stress transmitted to the upper structure, thereby achieving multi-directional stress composite dissipation.

[0060] In step S3, the process of laying an insulation board on the non-woven fabric and covering the insulation board with an isolation film, so that the insulation board and the isolation film work together to form a temperature difference buffer layer to prevent the temperature difference stress concentration from being transmitted to adjacent layers, includes: After the first stress dissipation layer is constructed in step S2, an insulation board is laid on the non-woven fabric of the first stress dissipation layer. The insulation board is made of extruded polystyrene (XPS), which has a closed-cell honeycomb structure, low water absorption, high compressive strength, and low thermal conductivity. The thickness of the insulation board is determined according to the building design energy-saving requirements and commonly used construction specifications in this field. Based on the roof heat transfer coefficient limit, its thickness can be 50mm to 100mm through thermal calculations to meet the requirements of different climate zones and different building energy-saving standards. During installation, the insulation board is laid flat on the surface of the non-woven fabric. No adhesive is required between the insulation board and the non-woven fabric; the insulation board maintains its position stability by its own weight.

[0061] Furthermore, the joints between adjacent insulation boards are treated with a staggered laying method. Staggered laying means that the joints of adjacent rows of insulation boards are staggered to avoid forming continuous straight seams, thus preventing the thermal bridging effect. After the insulation boards are laid, the joints between adjacent insulation boards are sealed using special sealing tape or polyurethane foam to ensure a tight seal and prevent moisture from penetrating to the underlying layers.

[0062] Furthermore, a release liner is placed over the insulation board. The release liner is made of PE film, which is characterized by high strength, good flexibility, and resistance to chemical corrosion. The PE film is laid evenly across the surface of the insulation board, covering the entire insulation layer to ensure complete coverage. The overlap between adjacent PE films is greater than or equal to 50mm to ensure continuity and overall sealing.

[0063] Furthermore, the mechanism by which the insulation board and PE film synergistically form a temperature difference buffer layer is as follows: the PE film, covering the insulation board, severs the bonding channel between the insulation board and the subsequent rigid protective layer, creating a relatively sliding interface between them. When the ambient temperature changes, the insulation board can freely expand and contract at this interface, unconstrained by the bonding of the first rigid protective layer. This prevents temperature stress from being directly transmitted to the insulation board and the underlying flexible layers such as non-woven fabric and non-curing coating through the bonding channel. Simultaneously, the insulation board itself has a low thermal conductivity, effectively slowing down the rate at which temperature changes are transmitted to the underlying layers, protecting the underlying flexible layers from the impact of rapid temperature changes. After the PE film covers the surface of the insulation board, the two together form a buffer layer with temperature stress release function, i.e., a temperature difference buffer layer, preventing the concentrated transmission of temperature stress to adjacent layers and ensuring that the first and second stress dissipation layers can operate normally within their respective design temperature ranges.

[0064] In step S4, the process of obtaining the ambient temperature difference and wind speed during construction includes: The temperature variation in the roof construction area during construction is determined by the ambient temperature difference, which is the difference between the daily maximum and minimum temperatures during construction. The magnitude of the ambient temperature difference directly affects the expansion and contraction deformation of the second rigid protective layer under temperature stress. The larger the temperature difference, the greater the expansion and contraction deformation of the second rigid protective layer, requiring smaller joint spacing and a deeper sealant application depth. Therefore, accurately obtaining the ambient temperature difference is crucial for determining the final joint spacing and sealant application depth. Specifically, by consulting meteorological forecast data or historical meteorological records for the construction area during the construction period, the maximum daily ambient temperature difference during construction is used as the final ambient temperature difference for determining the joint spacing and sealant application depth.

[0065] The wind force value is used to determine the intensity of wind load on the roof construction area during construction. This is determined by the daily average wind force level or the measured wind force level during the construction period. The magnitude of the wind force directly affects the intensity of wind load on the roof waterproofing protective layer during use. The stronger the wind, the more significant the vibration and deformation of the roof waterproofing protective layer under wind load, and the more prone the sealant in the expansion joints is to fatigue cracking or adhesion failure under repeated vibration. Therefore, accurate acquisition of the wind force value is an important supplementary basis for determining the final sealing depth. Specifically, by consulting meteorological forecast data for the construction area during the construction period or through real-time monitoring using an on-site anemometer, the maximum daily wind force level during the construction period is used as the final wind force value for determining the sealing depth.

[0066] It should be noted that the acquisition period for ambient temperature difference and wind speed values ​​covers the entire construction period of the waterproof protective layer, including the entire process of pouring, curing, cutting of expansion joints, and filling with sealant for the second rigid protective layer. When the ambient temperature difference or wind speed changes significantly during construction, the final spacing of the expansion joints and the final filling depth of the sealant are re-determined based on the changed ambient temperature difference and wind speed to ensure that the spacing of the expansion joints and the filling depth of the sealant always match the actual construction conditions.

[0067] Furthermore, the process of determining the temperature difference interval adjustment coefficient and temperature difference depth adjustment coefficient based on the comparison results of the ambient temperature difference with the first temperature difference setpoint and the second temperature difference setpoint, and determining the wind force adjustment coefficient based on the comparison results of the wind force value with the first wind force setpoint and the second wind force setpoint, includes: Specifically, the impact of ambient temperature difference on the spacing of the waterproof protective layer's expansion joints and the depth of sealant application is quantified using temperature difference spacing adjustment coefficients and temperature difference depth adjustment coefficients. The greater the ambient temperature difference, the greater the thermal expansion and contraction deformation of the second rigid protective layer. The expansion joints need to be spaced smaller to release temperature deformation stress, and the sealant needs to be applied deeper to provide greater deformation tolerance.

[0068] Specifically, a first temperature difference setting value and a second temperature difference setting value are used as the basis for determining the range of the ambient temperature difference. The first temperature difference setting value is the upper limit of the ambient temperature difference influence level, and the second temperature difference setting value is the lower limit of the ambient temperature difference influence level. The first temperature difference setting value is greater than the second temperature difference setting value. The first and second temperature difference setting values ​​are determined as follows: the expansion and contraction deformation of the second rigid protective layer is obtained by multiplying the linear expansion coefficient of concrete by the spacing of the expansion joints and then by the ambient temperature difference. This expansion and contraction deformation is compared with the allowable deformation of the sealant. When the expansion and contraction deformation reaches the upper limit of the sealant's allowable deformation, the corresponding ambient temperature difference is the first temperature difference setting value; when the expansion and contraction deformation is within the safety margin of the sealant's allowable deformation, the corresponding ambient temperature difference is the second temperature difference setting value.

[0069] In this embodiment, when the ambient temperature difference exceeds the first set temperature difference value, it indicates a large ambient temperature difference, resulting in a significant increase in the expansion and contraction deformation of the second rigid protective layer. Therefore, the spacing between the expansion joints needs to be reduced proportionally to ensure that the deformation of a single expansion joint does not exceed the allowable deformation of the sealant. Simultaneously, the sealant filling depth needs to be increased proportionally to provide greater deformation tolerance. The temperature difference spacing adjustment coefficient is determined based on the ratio of the design reference temperature difference to the actual ambient temperature difference. The design reference temperature difference is a representative value of the daily temperature difference during the normal construction period from years of meteorological statistics at the construction site. When the actual temperature difference is greater than the design reference temperature difference, this ratio is less than one, and the spacing is reduced accordingly. The temperature difference depth adjustment coefficient is also determined based on the ratio of the actual ambient temperature difference to the design reference temperature difference. When the actual temperature difference is greater than the design reference temperature difference, this ratio is greater than one, and the depth is increased accordingly. The two coefficients have opposite values. Therefore, the temperature difference spacing adjustment coefficient is set to a value less than one, and the temperature difference depth adjustment coefficient is set to a value greater than one. When the ambient temperature difference is greater than the second temperature difference setting value and less than or equal to the first temperature difference setting value, it indicates that the ambient temperature difference is within a moderate range, and the expansion and contraction deformation of the second rigid protective layer is within the conventional design range. The spacing of the dividing joints and the sealing paste filling depth can meet the deformation adaptation requirements by setting the benchmark values, and no adjustment is required. Therefore, the temperature difference spacing adjustment coefficient and the temperature difference depth adjustment coefficient are both set to one.

[0070] When the ambient temperature difference is less than or equal to the second temperature difference setting value, it indicates that the ambient temperature difference is relatively small, and the expansion and contraction deformation of the second rigid protective layer is limited. Therefore, while ensuring the crack resistance of the waterproof protective layer, the spacing between expansion joints can be increased proportionally to reduce the number of expansion joints, and the sealing compound filling depth can be decreased proportionally to reduce the amount of sealing compound used. The temperature difference spacing adjustment coefficient is determined based on the ratio of the design reference temperature difference to the actual ambient temperature difference. When the actual temperature difference is less than the design reference temperature difference, this ratio is greater than one, and the spacing is correspondingly increased. The temperature difference depth adjustment coefficient is determined based on the ratio of the actual ambient temperature difference to the design reference temperature difference. When the actual temperature difference is less than the design reference temperature difference, this ratio is less than one, and the depth is correspondingly decreased. Therefore, the temperature difference spacing adjustment coefficient is set to a value greater than one, and the temperature difference depth adjustment coefficient is set to a value less than one.

[0071] Specifically, the impact of wind force on the sealant application quality during construction is quantified using a wind force adjustment coefficient. The higher the wind force value, the more significant the wind disturbance to the sealant during application, making it more difficult to ensure the compactness of the application. After use, the sealant is more prone to fatigue cracking under the combined effects of wind-induced vibration and temperature stress, thus requiring a corresponding increase in the application depth of the sealant.

[0072] Specifically, a first wind force setting value and a second wind force setting value are used as the basis for determining the wind force value's range. The first wind force setting value is the upper limit of the wind force impact level, and the second wind force setting value is the lower limit of the wind force impact level. The first wind force setting value is greater than the second wind force setting value. The determination of the first and second wind force setting values ​​is based on the building structure load code and roof structure design parameters. Through correlation analysis of wind force level and roof vibration, combined with the adhesion durability test data of sealant under vibration conditions, the degree of influence of different wind force levels on the sealant filling quality is determined, thereby determining the first and second wind force setting values.

[0073] Simultaneously, based on the adhesion durability test data of the sealant under cyclic vibration loading conditions, a correlation between vibration acceleration and the fatigue life of the sealant was established. When the fatigue life of the sealant drops to its design service life, the corresponding wind force level is the first wind force setting value. At this point, the sealant filling depth needs to be increased to compensate for the risk of fatigue cracking. When the sealant fatigue loss caused by vibration acceleration is lower than a negligible threshold, the corresponding wind force level is the second wind force setting value. At this point, the sealant filling depth can be appropriately reduced. Through the above analysis, the values ​​of the first and second wind force setting values ​​have clear structural mechanics and material testing basis.

[0074] In this embodiment, when the wind force value is greater than the first wind force setting value, it indicates that the wind force is relatively strong. The sealant is significantly disturbed by the wind during the application process, and after use, it is prone to fatigue cracking under the combined effects of wind-induced vibration and temperature stress. Therefore, the sealant application depth needs to be increased proportionally to compensate for the adverse effects of strong wind conditions. The wind force adjustment coefficient is determined based on the ratio of the actual wind pressure to the design reference wind pressure. The design reference wind pressure is a representative value determined according to the building structure load code and the basic wind pressure at the construction site. When the actual wind pressure is greater than the design reference wind pressure, this ratio is greater than one, and the application depth increases accordingly. Therefore, the wind force adjustment coefficient is determined to be greater than one.

[0075] When the wind force value is greater than the second wind force setting value and less than or equal to the first wind force setting value, it indicates that the wind force is in a moderate range. The sealant filling quality is less affected by wind disturbance, and the bonding durability requirements can be met by applying the sealant to the reference filling depth. No adjustment is needed due to wind factors. Therefore, the wind force adjustment coefficient is set to one.

[0076] When the wind force value is less than or equal to the second wind force setting value, it indicates that the wind force is relatively low, and the sealant application is minimally affected by wind disturbance. Therefore, the sealant application depth can be reduced proportionally to decrease the amount of sealant used, while ensuring the quality of the sealant application. The wind force adjustment coefficient is determined based on the ratio of the actual wind pressure to the design reference wind pressure. When the actual wind pressure is less than the design reference wind pressure, this ratio is less than one, and the application depth is reduced accordingly. Therefore, the wind force adjustment coefficient is set to a value less than one.

[0077] Furthermore, the process of determining the final spacing of the waterproof protective layer joints and the final sealing depth of each construction area includes: The final spacing of the expansion joints determines the actual distance between each expansion joint on the second rigid protective layer. This distance controls the shrinkage cracks generated in the second rigid protective layer under temperature stress, allowing them to be released in an orderly manner at the expansion joint locations, thus preventing irregular cracking on the surface of the second rigid protective layer. If the final spacing of the expansion joints is too large, the expansion and contraction deformation of the second rigid protective layer under temperature stress will exceed the adjustment capacity of the expansion joints, leading to cracks in irregular locations and compromising the integrity and sealing of the waterproof layer. If the final spacing of the expansion joints is too small, although it can improve the crack resistance of the second rigid protective layer, it will increase the workload of expansion joint construction and the amount of sealant used. The final spacing of the expansion joints is determined by the product of the temperature difference spacing adjustment coefficient and the reference spacing of the expansion joints. The spacing of the expansion joints is mainly determined by the expansion and contraction deformation of the concrete caused by temperature stress. The influence of wind force on the expansion and contraction deformation of the rigid protective layer is negligible compared to temperature stress. The sealant filling depth is directly related to the fatigue life of the sealant under wind-induced vibration; therefore, the wind force adjustment coefficient is only used in the calculation of the final sealant filling depth.

[0078] Among them, the spacing of the second rigid protective layer under normal construction conditions is determined by the reference spacing of the dividing joints. The reference spacing of the dividing joints is calculated based on the linear expansion coefficient of concrete, the design reference temperature difference, and the allowable deformation of the sealant. The maximum allowable spacing of a single dividing joint under normal temperature difference conditions is calculated by dividing the allowable deformation of the sealant by the product of the linear expansion coefficient of concrete and the design reference temperature difference. The quotient obtained is the maximum allowable spacing of the dividing joints.

[0079] At the same time, the limit requirements for the spacing of rigid protective layer joints in the roof engineering technical specifications are checked, and the smaller value between the calculated maximum allowable spacing and the specification limit is taken as the reference spacing of the joints.

[0080] The design reference temperature difference is a representative value of the daily temperature difference during the normal construction period, determined based on years of meteorological statistics of the construction site. The allowable deformation of the sealant is determined based on the material performance parameters and safety factor of the selected sealant. In this way, the value of the reference spacing of the expansion joints simultaneously meets the constraints of material deformation capacity and the requirements of the specification limits, and has clear engineering calculability.

[0081] Specifically, the actual filling depth of the sealant within the expansion joint is determined by the final filling depth of the sealant, ensuring that the sealant provides sufficient deformation adaptability and sealing and waterproofing capabilities. If the final filling depth of the sealant is too shallow, it is easily torn or detached from the joint wall under temperature stress or wind-induced vibration, leading to leakage channels at the expansion joint. If the final filling depth of the sealant is too deep, although it can improve the deformation adaptability of the sealant, it will increase the amount of sealant used and the difficulty of filling. The final filling depth of the sealant is determined by the product of the sealant reference filling depth, the temperature difference depth adjustment coefficient, and the wind force adjustment coefficient.

[0082] Specifically, the sealant filling depth of the expansion joints under conventional construction conditions is determined by using a reference filling depth. This reference filling depth is determined based on the joint width and the ratio of the sealant filling depth to the joint width. The ratio of depth to joint width is determined according to the specifications for sealant material construction, using a ratio of one-half to two-thirds of the joint width as the filling depth. The joint width is determined based on the design dimensions of the expansion joints in the second rigid protective layer.

[0083] At the same time, the reference filling depth of the sealant must also meet the minimum deformation adaptability requirements of the sealant material, that is, the deformation of the sealant at the reference filling depth under normal temperature stress shall not exceed its allowable deformation. Thus, the value of the reference filling depth of the sealant has a clear material performance basis and is calculable according to specifications.

[0084] In step S5, the process of constructing a first rigid protective layer on the release membrane as the first rigid constraint to constrain the position of the underlying flexible layers includes: After the temperature difference buffer layer in step S3 is completed, the first rigid protective layer is constructed on the PE film. The first rigid protective layer is made of C20 fine aggregate concrete, with a thickness of 50mm. Before pouring, a two-way steel mesh is laid on the PE film according to the design requirements to enhance the overall rigidity and crack resistance of the first rigid protective layer. When laying the steel mesh, spacers or stirrups are placed underneath to ensure that the steel mesh maintains the designed protective layer thickness during concrete pouring. During the fine aggregate concrete pouring, a plate vibrator or immersion vibrator is used for compaction to ensure that the concrete and steel mesh form an integral structure, avoiding defects such as honeycomb and voids. After the concrete pouring is completed, the surface is smoothed and polished to make the surface of the first rigid protective layer flat and dense.

[0085] Furthermore, the first rigid protective layer, acting as the first rigid constraint layer, constrains the positions of the underlying flexible layers as follows: The first rigid protective layer is a concrete slab with high rigidity and integrity, covering the PE film. Regarding horizontal position constraint, the first rigid protective layer, through its overall rigidity and self-weight, presses down on the underlying flexible layers and restricts their horizontal movement. When the roof structure undergoes horizontal deformation due to temperature changes or loads, the flexible layers are pressed together by the first rigid protective layer, preventing free sliding in the horizontal direction, thus maintaining the stability of the relative positions between the layers. Regarding vertical position constraint, the first rigid protective layer, through its self-weight and rigidity, suppresses the vertical undulation deformation of the underlying flexible layers, preventing local compression or bulging of the insulation board under construction loads, ensuring that each flexible layer always maintains the designed flatness and structural thickness. The underlying flexible layers include a non-curing asphalt waterproof coating layer, a non-woven fabric layer, and an insulation board layer.

[0086] Furthermore, the first rigid protective layer, while serving a restraining function, also acts as a rigid medium for stress transmission. The residual stress from the underlying flexible layers after initial attenuation is transmitted uniformly through the first rigid protective layer to the modified bitumen waterproof membrane layer above it, providing stress input for the secondary stress attenuation of the second stress dissipation layer.

[0087] Furthermore, after the first rigid protective layer is poured, it shall be cured in accordance with the prevailing construction specifications in this field, and the curing time shall not be less than the prevailing concrete curing period requirements in this field, that is, not less than 7 days.

[0088] In step S6, the process of laying modified bitumen waterproof membrane on the first rigid protective layer to form a second stress dissipation layer and achieve secondary stress attenuation includes: While a single stress attenuation layer can absorb and dissipate most of the deformation energy of the substrate, it cannot achieve complete attenuation. This is because: First, non-curing coatings primarily absorb deformation energy through viscous flow, and their absorption capacity is limited by coating thickness, creep performance, and the duration of stress application. When the substrate deformation exceeds the creep regulation range of the non-curing coating, the excess stress still needs to be transmitted upwards. Second, temperature stress originates not only from the substrate but also from the waterproofing layer itself—the self-expansion stress generated by the membrane absorbing heat during the day and dissipating heat at night. The first stress dissipation layer, located above the substrate, primarily blocks deformation energy from the substrate but cannot completely dissipate the stress generated by temperature changes within the membrane itself. Third, the first rigid protective layer, as a rigid medium, must evenly transmit residual stress from below to the upper membrane layer. Without a second stress dissipation layer to absorb this transmitted stress again, the stress will accumulate within the membrane layer, eventually leading to cracking or detachment from the protective layer. Fourth, data center roofs require zero leakage. If a single stress dissipation layer fails due to material aging, construction defects, or exceeding the design load, it will lose its stress buffering capacity. Two stress dissipation layers form a redundant design, so that the second layer can still function after the first layer fails, ensuring the long-term reliability of the waterproofing system.

[0089] Therefore, primary stress attenuation addresses the absorption of deformation energy in the substrate; secondary stress attenuation addresses the dissipation of residual stress plus the self-generated temperature stress of the membrane. These two processes have different functions, levels, and target objects, together forming a complete stress dissipation chain.

[0090] Specifically, after the first rigid protective layer in step S4 has been cured to a satisfactory condition, a modified bitumen waterproof membrane is laid on top of it. The modified bitumen waterproof membrane used is SBS modified bitumen waterproof membrane, a new type of building waterproofing material. It uses polyester or fiberglass as the base material and styrene-butadiene-styrene block copolymer modified bitumen as the impregnation material, with both sides covered with a release liner. It features high elongation, excellent high and low temperature resistance, and high tensile strength, meeting the mechanical and durability requirements of roof waterproofing projects. The specifications of the membrane are determined according to prevailing construction standards and roof waterproofing grade requirements in this field.

[0091] Furthermore, a hot-melt full-adhesion process is used to lay the modified bitumen waterproof membrane onto the first rigid protective layer. The specific operation of the hot-melt full-adhesion process includes: heating the bottom surface of the membrane and the surface of the first rigid protective layer using a flame torch or hot-melt machine, controlling the heating temperature within the range specified by commonly used construction standards in this field, i.e., to a molten and flowing state, so that the modified bitumen coating on the bottom surface of the membrane is molten and flowing, while the surface of the first rigid protective layer is also heated to an appropriate temperature. The membrane is then laid onto the surface of the first rigid protective layer and rolled with a pressure roller to ensure full contact, wetting, and bonding between the molten modified bitumen and the surface of the first rigid protective layer, forming a full bond between the membrane and the protective layer, without gaps or air bubbles. The overlap joints between adjacent membranes are heated and pressed together using the same hot-melt method to ensure a tight seal.

[0092] Furthermore, the mechanism by which SBS modified bitumen waterproof membrane acts as a second stress dissipation layer to achieve secondary stress attenuation is as follows: SBS modified bitumen waterproof membrane has high elongation characteristics. When temperature stress and structural deformation energy transmitted from the first rigid protective layer act on the membrane layer, the membrane absorbs and dissipates this stress through its own elastic tensile deformation, preventing further upward transmission of stress. Simultaneously, the hot-melt full-bonding process forms an integral bond between the SBS modified bitumen waterproof membrane and the first rigid protective layer, with no relative sliding surface between them. This ensures that the stress from the first rigid protective layer can be effectively transmitted to the membrane layer and absorbed by the membrane, avoiding stress accumulation or concentration at the interface due to weak adhesion. The integral bond between the SBS modified bitumen waterproof membrane and the first rigid protective layer, combined with the membrane's high elongation characteristics, jointly achieves secondary stress attenuation. That is, the residual stress after the first stress attenuation by the first stress dissipation layer is absorbed and dissipated again in the second stress dissipation layer.

[0093] Furthermore, the material mechanism of secondary stress attenuation is as follows: In SBS modified bitumen waterproof membranes, the SBS triblock copolymer forms a two-phase separated structure in the bitumen, and the polystyrene end groups aggregate as physical cross-linking points, endowing the material with elastomeric properties and high elongation. This three-dimensional network structure effectively improves the membrane's low-temperature crack resistance and high-temperature stability, enabling it to absorb and dissipate stress through elastic tensile deformation when subjected to temperature stress and structural deformation energy. Simultaneously, the hot-melt full-bonding process forms an integral bond between the membrane and the first rigid protective layer, ensuring that stress can be effectively transferred to the membrane layer and absorbed. The material's high elongation and integral bonding work synergistically to achieve secondary stress attenuation.

[0094] Furthermore, when laying SBS modified bitumen waterproof membrane, special attention should be paid to strengthening the additional layer treatment at key points such as internal and external corners, expansion joints, drain outlets, and the roots of pipes penetrating the roof. The specific method for additional layer treatment is as follows: First, lay an additional membrane layer at the key points with a width not less than the requirements of commonly accepted construction specifications in this field, i.e., not less than 250mm. This additional layer should be fully adhered to the base layer. Then, lay the main membrane, covering the additional layer and forming an integral bond with it. This reinforcement of the main membrane at the key points by the additional layer ensures that the key points can adapt to structural deformation and temperature stress, preventing cracking or leakage due to stress concentration.

[0095] Furthermore, after the SBS modified bitumen waterproof membrane is laid, the overlap joints of the membrane are sealed in accordance with the common construction specifications in this field, and the surface of the membrane is thoroughly inspected to ensure that there are no defects such as hollow areas, damage, or curling edges.

[0096] In step S7, the process of constructing a second rigid protective layer as a second rigid constraint on the modified bitumen waterproof membrane, and cooperating with the first rigid protective layer to form a synergistic constraint on the intermediate flexible layers, includes: Specifically, after the modified bitumen waterproof membrane in step S5 is laid and inspected and approved, a second rigid protective layer is constructed on top of the modified bitumen waterproof membrane. The second rigid protective layer is made of C20 fine aggregate concrete, with a thickness of 50mm. It contains bidirectional steel mesh with the same diameter and spacing as the first rigid protective layer; that is, its type, thickness, and reinforcement are consistent with the first rigid protective layer. During the pouring of the second rigid protective layer, a plate vibrator or immersion vibrator is used for compaction to ensure that the concrete and steel mesh form an integral structure, avoiding defects such as honeycomb and voids. After the concrete is poured, the surface is smoothed and polished to make the surface of the second rigid protective layer flat, dense, and smooth.

[0097] Furthermore, the second rigid protective layer, as the second rigid constraint layer, works in conjunction with the first rigid protective layer to form a synergistic constraint on the intermediate flexible layers as follows: The first rigid protective layer is located above the lower flexible layers, serving as the lower constraint layer and ensuring the stability of the position of the lower flexible layers, which include a non-curing bitumen waterproof coating layer, a non-woven fabric layer, and an insulation board layer; the second rigid protective layer is located above the modified bitumen waterproof membrane, serving as the upper constraint layer and working in conjunction with the first rigid protective layer; the two rigid protective layers form a vertical clamping force through their own weight and edge construction measures, and restrict the horizontal slippage of the flexible layers through interface friction, thus forming a clamping constraint on the intermediate modified bitumen waterproof membrane layer.

[0098] The two rigid protective layers, with equal thickness and identical reinforcement, achieve a symmetrical design that matches the upper and lower constraint stiffness. Vertically, this creates a clamping effect on the intermediate flexible layers, preventing them from bulging upwards or sinking downwards; their vertical position is jointly defined by the two rigid protective layers. Horizontally, the two rigid protective layers, through their overall stiffness and symmetrical constraint stiffness, jointly restrict the free sliding of the intermediate flexible layers, preventing interlayer displacement under temperature stress or structural deformation. Through the combined action of the upper and lower rigid protective layers, bidirectional synergistic restraint is achieved on the intermediate flexible layers, including the modified bitumen waterproof membrane layer, preventing interlayer slippage, warping, or cumulative deformation under stress.

[0099] Meanwhile, the coordinated constraint mechanism with matching upper and lower constraint stiffness can uniformly transfer and disperse the deformation energy generated by each flexible layer under temperature stress and structural deformation to the two rigid protective layers, so that the stress can be smoothly transferred between layers and prevent the stress from accumulating in a certain flexible layer and causing damage to the waterproof layer.

[0100] It should be noted that conventional single-layer protective layers can only rely on their own weight to unidirectionally press against the waterproof layer from above. Their horizontal constraint relies solely on passive friction, and their vertical constraint can only suppress bulging but cannot prevent denting. Furthermore, there is a lack of stiffness matching between the single-layer protective layer and the flexible layer, making it prone to abrupt stress changes and concentrations at the interface. Once the single-layer protective layer fails, it loses all its constraint function. In contrast, the double-layer rigid protective layer in this embodiment, through a symmetrical design with stiffness matching, forms a composite constraint system with horizontal bidirectional constraint and vertical bidirectional limitation. Moreover, even if the upper layer fails, the lower layer can still maintain its constraint function. Its technical effect is significantly better than the single constraint effect of a single-layer protective layer.

[0101] Furthermore, after the surface of the second rigid protective layer is polished, it shall be cured in accordance with the prevailing construction specifications in this field, and the curing time shall not be less than the prevailing concrete curing period requirements in this field, that is, not less than 7 days.

[0102] In step S8, the process of filling the joints of the second rigid protective layer with sealant according to the final filling depth, thus completing the waterproof protective layer construction, includes: Cut the expansion joints on the second rigid protective layer according to the final spacing of the expansion joints. Before cutting, mark the positions of the expansion joints on the surface of the second rigid protective layer with a chalk line; when cutting, use a cutting tool to cut along the chalk line, the expansion joints should be continuous from top to bottom, and there should be no cement mortar residue in the joints; after cutting, clean the debris and dust in the joints.

[0103] After cleaning, apply a primer that matches the sealant to the joints. After the primer dries, fill the joints with a backing material that does not adhere to the sealant. Finally, fill the joints with sealant to the final depth of the sealant. The sealant should be filled tightly, fully, and continuously, with a smooth surface, free of bubbles and cracks, to complete the waterproof protective layer construction.

[0104] Please see Figure 4 As shown, this is a schematic diagram of the stress transmission path in an embodiment of the present invention. The roof waterproofing system constructed in this embodiment comprises a total of six layers, and the stress transmission path within it is as follows: The first stage is the base layer, namely the concrete roof slab, which is the source of stress. The second stage is the first stress dissipation layer, which is a synergistic layer of non-curing asphalt waterproof coating and non-woven fabric. The non-curing coating absorbs the deformation energy of the base layer through its creep properties, and the non-woven fabric fiber network evenly disperses the concentrated stress in all directions. The third stage is the temperature difference buffer and isolation layer, which is a synergistic layer of insulation board and PE film. The PE film blocks the bonding channel between the insulation board and the first rigid protective layer, releasing the temperature difference stress.

[0105] The fourth station is the first rigid protective layer, which uniformly transfers the residual stress to the upper layer. The fifth station is the second stress dissipation layer, namely the SBS modified bitumen waterproof membrane layer, which utilizes the high elongation characteristics of the membrane to absorb and dissipate stress again through elastic tensile deformation. The sixth station is the second rigid protective layer, which forms a synergistic constraint with the first rigid protective layer, uniformly distributing the final residual trace stress throughout the entire protective layer.

[0106] Through the aforementioned stress transfer path, the roof waterproofing system constructed in this embodiment achieves a synergistic effect of graded stress attenuation, bidirectional synergistic constraint, and temperature difference isolation. Two stress dissipation layers are respectively placed on both sides of the rigid protective layer to progressively reduce stress; the two rigid protective layers symmetrically sandwich the intermediate flexible layer to prevent interlayer slippage; the PE film blocks the bonding channel between the insulation board and the rigid protective layer, allowing temperature difference stress to be released at the interface. Through the aforementioned graded attenuation, synergistic constraint, and temperature difference isolation, the deformation energy transmitted to the top slab of the structure approaches zero, fundamentally avoiding cracking and leakage of the waterproofing layer caused by stress concentration.

[0107] To verify the technical effectiveness of the stress dissipation layer in this embodiment, a comparative experiment was conducted: Under simulated temperature deformation conditions of the roof base layer, strain gauges were embedded on the surface of the base layer, the bottom surface of the first rigid protective layer, and the bottom surface of the second rigid protective layer. The strain values ​​at each measuring point were measured and converted into stress values ​​based on the elastic modulus of concrete. The stress transfer rate was characterized by the ratio of the stress value at each measuring point to the stress value of the base layer.

[0108] Example group 1 includes both a first stress dissipation layer and a second stress dissipation layer; Comparative Example 1 does not include a stress dissipation layer, i.e., a rigid protective layer is directly constructed on the base surface; Comparative Example 2 includes only a first stress dissipation layer and does not include a second stress dissipation layer.

[0109] The results are shown in Table 1. Table 1. Comparison of Stress Transmissibility

[0110] As shown in Table 1, in Comparative Example 1, almost all the stress in the base layer is transferred to the rigid protective layer, with a stress transfer rate of approximately 95%. In Comparative Example 2, after passing through the first stress dissipation layer, the stress transferred to the first rigid protective layer is reduced to approximately 35% of the stress in the base layer, meaning that the first stress dissipation layer reduces the stress by approximately 65%. In the Example Group, the residual stress after being attenuated by the first stress dissipation layer is further absorbed by the second stress dissipation layer, and the stress finally transferred to the second rigid protective layer is reduced to approximately 12% of the stress in the base layer, meaning that the combined effect of the two stress dissipation layers results in a total stress attenuation rate of approximately 88%.

[0111] The above results show that the first stress dissipation layer absorbs most of the deformation energy of the base layer through the creep energy absorption of the non-curing asphalt waterproof coating and the stress dispersion of the non-woven fabric; the second stress dissipation layer absorbs the residual stress again through the high elongation characteristics of the elastomer modified asphalt waterproof membrane. The gradual attenuation of the two layers significantly reduces the stress that is finally transmitted to the second rigid protective layer, effectively reducing the risk of cracking of the rigid protective layer due to stress concentration.

[0112] The technical solution of the present invention has been described above with reference to the preferred embodiments shown in the accompanying drawings. However, it will be readily understood by those skilled in the art that the scope of protection of the present invention is obviously not limited to these specific embodiments. Without departing from the principles of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will all fall within the scope of protection of the present invention.

Claims

1. A method for preventing leakage based on modified asphalt, characterized in that, include: Step S1: Divide the roof base layer into several construction areas and grind each construction area separately to remove laitance and loose particles from the base layer surface. Step S2: Apply non-curing asphalt waterproof coating to the base surface of each construction area, and lay non-woven fabric on the non-curing asphalt waterproof coating layer so that the non-curing asphalt waterproof coating and non-woven fabric work together to form a first stress dissipation layer to achieve stress attenuation. Step S3: Lay an insulation board on the non-woven fabric and cover the insulation board with an isolation film so that the insulation board and the isolation film work together to form a temperature difference buffer isolation layer to avoid the temperature difference stress concentration being transmitted to adjacent layers. Step S4: Obtain the ambient temperature difference and wind force value during construction, and determine the final spacing of the waterproof protective layer joints and the final filling depth of the sealant for each construction area based on the ambient temperature difference and wind force value. Step S5: Construct a first rigid protective layer on the isolation membrane as the first rigid constraint to constrain the position of each flexible layer below, wherein the position includes the horizontal and vertical positions of each flexible layer. Step S6: Lay a modified bitumen waterproof membrane on the first rigid protective layer to form a second stress dissipation layer to achieve secondary stress attenuation. Step S7: Apply a second rigid protective layer as a second rigid constraint on the modified bitumen waterproof membrane, and cooperate with the first rigid protective layer to form a synergistic constraint on the intermediate flexible layers. Step S8: Fill the joints of the second rigid protective layer with sealant according to the final filling depth of the sealant to complete the construction of the waterproof protective layer.

2. The anti-seepage construction method based on modified asphalt according to claim 1, characterized in that, The process in step S2 includes: The non-woven fabric is laid and compacted while the non-curing asphalt waterproof coating is in an uncured state, so that the fiber gaps of the non-woven fabric are fully wetted and penetrated by the non-curing asphalt waterproof coating. Based on the creep characteristics of the non-curing asphalt waterproof coating, the substrate deformation energy is absorbed, so that the non-woven fabric acts as a stress dispersion skeleton and transmits the concentrated stress evenly to the surroundings, so as to form a first stress dissipation layer and achieve stress attenuation.

3. The anti-seepage construction method based on modified asphalt according to claim 2, characterized in that, The process in step S3 includes: The insulation board is laid on the non-woven fabric; The joints between adjacent insulation boards are laid in a staggered manner and sealed. Cover the insulation board with the insulating film; The insulation board and the first rigid protective layer are separated by the isolation membrane, so that the insulation board can freely expand and contract under the action of environmental temperature difference, and the temperature difference buffer isolation layer is formed.

4. The anti-seepage construction method based on modified asphalt according to claim 3, characterized in that, The process in step S6 includes: The modified bitumen waterproof membrane is laid on the first rigid protective layer using a hot-melt full-adhesion process. Based on the elongation characteristics of the modified bitumen waterproof membrane, it absorbs the temperature stress and structural deformation energy transmitted from the first rigid protective layer, so as to achieve secondary stress attenuation. The modified bitumen waterproof membrane and the first rigid protective layer are bonded together in an integral manner through the hot-melt full-bonding process, so that stress is transferred between the layers and absorbed by the membrane.

5. The anti-seepage construction method based on modified asphalt according to claim 4, characterized in that, The process in step S7 includes: The first rigid protective layer and the second rigid protective layer are made of fine stone concrete of the same thickness and type, and are reinforced with steel mesh of the same diameter. The first rigid protective layer serves as the lower constraint layer, used to constrain the horizontal and vertical displacements of the underlying flexible layers; The second rigid protective layer serves as an upper constraint layer, which cooperates with the first rigid protective layer to form a clamping constraint on the modified bitumen waterproof membrane.

6. The anti-seepage construction method based on modified asphalt according to claim 1, characterized in that, The process of step S4 includes: The temperature difference spacing adjustment coefficient and temperature difference depth adjustment coefficient are determined based on the comparison results between the ambient temperature difference during construction and the first and second temperature difference set values. The wind force adjustment coefficient is determined based on the comparison between the wind force value during construction and the first and second wind force settings. The final spacing is determined based on the product of the temperature difference spacing adjustment coefficient and the grid seam reference spacing; The final filling depth is determined based on the product of the temperature difference depth adjustment coefficient, the wind force adjustment coefficient, and the sealant reference filling depth. Wherein, the first temperature difference setting value and the second temperature difference setting value are environmental temperature difference boundary values ​​determined according to the specification for setting the expansion joints of the rigid protective layer of the roof; the first wind force setting value and the second wind force setting value are wind force boundary values ​​determined according to the building structure load specification and the requirements for the sealant construction environment.

7. The anti-seepage construction method based on modified asphalt according to claim 6, characterized in that, Add conductive filler to the non-curing asphalt waterproof coating according to a preset ratio; The conductive filler enables the non-curing asphalt waterproof coating layer to have a piezoresistive effect, and the leakage location is identified based on the resistance change value of the corresponding construction area. The conductive filler forms a three-dimensional conductive network inside the non-curing asphalt waterproof coating. When the waterproof layer experiences local strain due to stress or leakage, the conductive network structure in the corresponding area changes, and the resistance value changes. Based on the fact that the change in resistance value is greater than the upper limit of the change in resistance value, it is determined that there is leakage or abnormal stress in the corresponding construction area.

8. The anti-seepage construction method based on modified asphalt according to claim 7, characterized in that, The fine aggregate concrete has a strength grade of C20 and a laying thickness of 50mm. The steel bars used in the steel mesh have a diameter of 6mm; The modified bitumen waterproof membrane is an SBS modified bitumen waterproof membrane with a nominal thickness of 3mm and a thickness tolerance of ±0.3mm. The coating thickness of the non-curing asphalt waterproof coating is 1.2mm to 2.0mm; The insulation board is an extruded polystyrene board with a thickness of 50mm to 100mm; The nonwoven fabric is a polyester nonwoven fabric, and the overlap width of any two adjacent nonwoven fabrics is greater than or equal to 50mm. The isolation membrane is a PE membrane, and the overlap width of any two adjacent isolation membranes is greater than or equal to 50 mm.

9. The anti-seepage construction method based on modified asphalt according to claim 1, characterized in that, The process in step S1 includes: Based on the roof slope, catchment area, waterproofing grade requirements, and joint locations of the roof base layer, the roof base layer is divided into several construction areas.

10. The anti-seepage construction method based on modified asphalt according to claim 9, characterized in that, The process in step S1 also includes: Obtain the base flatness deviation and base moisture content of each construction area after grinding; Based on the fact that the flatness deviation value is greater than the allowable flatness deviation, the corresponding construction area is determined to be re-grinded. Based on the fact that the moisture content is greater than the upper limit of the moisture content, the corresponding construction area is determined to be dried again.