Wheel hub bore diameter measuring equipment and methods

By designing an automated wheel hub hole diameter measuring device, employing automated horizontal conveying and rotating measuring components, and combining it with sample ring calibration, the problems of low measurement accuracy and low efficiency in existing technologies have been solved, achieving high-precision and high-efficiency wheel hub hole measurement.

CN123111162APending Publication Date: 2026-11-17LUOYANG JIURUI TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611513313.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-28
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In existing technologies, the measurement accuracy and efficiency of wheel hub hole diameter are low, and the measurement is mainly carried out manually by hand using a micrometer, which is difficult to meet the requirements of vehicle assembly quality and operational safety.

Method used

Design a wheel hub bore diameter measuring device, including a main frame, a hub alignment device and a diameter measuring device. It adopts automated horizontal transmission, a height-adjustable and rotatable measuring component, and combines sample ring calibration and calibration deviation compensation measurement logic to achieve automated and non-contact measurement.

Benefits of technology

It improves the accuracy and efficiency of hub hole measurement, reduces the need for manual operation, ensures the accuracy and consistency of measurement results, and adapts to the continuous operation requirements of wheel production lines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123111162A_ABST
    Figure CN123111162A_ABST
Patent Text Reader

Abstract

This application relates to a wheel hub bore diameter measuring device and method. The wheel hub bore diameter measuring device includes a main frame, a hub alignment device, and a diameter measuring device. The main frame includes a horizontal conveying assembly with an clearance opening. The hub alignment device includes a first lifting assembly, an annular seat with a first central hole, and multiple positioning elements. The annular seat is correspondingly arranged with the clearance opening, and the multiple positioning elements are spaced apart circumferentially on the annular seat to fix the wheel hub and achieve hub alignment. The first lifting assembly drives the annular seat to rise and fall, and the clearance opening allows the annular seat to pass through. The diameter measuring device includes a second lifting assembly, a rotating assembly, and a measuring element. The measuring element is correspondingly arranged with the clearance opening. The second lifting assembly drives the measuring element to rise and fall, and the first central hole and clearance opening allow the measuring element to pass through. The rotating assembly drives the measuring element to rotate around a vertical axis to measure the diameter of the wheel hub bore. This application effectively improves measurement accuracy and efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of wheel manufacturing and testing technology, and in particular to a wheel hub bore diameter measuring device and measuring method. Background Technology

[0002] The wheel hub is the core assembly structure of a train wheel. The wheel is press-fitted to the axle through the hub hole, which is a key mating part of the vehicle's running gear. Before pressing the wheel to the axle, the diameter of the hub hole needs to be accurately measured to ensure that the press-fit interference meets the process requirements and to ensure the assembly quality and operational safety of the vehicle.

[0003] Currently, in wheel pressing production lines, the diameter of the wheel hub hole is mostly measured manually with a handheld micrometer, which has technical problems of low measurement accuracy and low work efficiency. Summary of the Invention

[0004] This application provides a wheel hub hole diameter measuring device and method, which is beneficial to improving the measurement accuracy and efficiency of wheel hub holes.

[0005] This application provides a wheel hub bore diameter measuring device, which includes a main frame, a hub alignment device, and a diameter measuring device.

[0006] The main frame includes a horizontal conveyor assembly with an clearance opening. The horizontal conveyor assembly is used to carry the wheel hub to be measured and to transport the measured wheel hub away from the wheel hub bore diameter measuring device.

[0007] The wheel hub alignment device includes a first lifting component, an annular seat with a first central hole, and multiple positioning components. In the vertical direction, the annular seat is correspondingly arranged with the clearance opening. The annular seat is connected to the first lifting component. The multiple positioning components are spaced apart on the annular seat along the circumference. The multiple positioning components are used to fix the wheel hub and realize wheel hub alignment. The first lifting component drives the annular seat to rise and fall, and the clearance opening allows the annular seat to pass through.

[0008] The diameter measuring device includes a second lifting assembly, a rotating assembly, and a measuring element. The measuring element is arranged vertically and corresponding to the clearance opening. The rotating assembly is connected to the second lifting assembly, and the measuring element is connected to the rotating assembly. The second lifting assembly drives the measuring element to rise and fall. The first central hole and the clearance opening allow the measuring element to pass through. The rotating assembly drives the measuring element to rotate around the vertical axis to measure the diameter of the hub hole. The vertical axis is coaxial with the axis of the annular seat.

[0009] The wheel hub bore diameter measuring device of this application integrates a horizontal conveying assembly with a clearance opening, a liftable hub alignment device, and a liftable and rotatable diameter measuring device into the main frame. Furthermore, the vertical axis of the measuring component's rotation is coaxial with the axis of the annular seat, achieving automated measurement of the hub bore without the need for manual handheld operation, effectively improving measurement accuracy and efficiency. Simultaneously, the hub alignment device and diameter measuring device are positioned below the clearance opening, and both can extend through the opening for operation, resulting in a more compact overall structure that meets the continuous operation requirements of wheel production lines. Moreover, the coaxial alignment of the measuring component's vertical axis with the annular seat axis ensures a consistent measurement reference, enhancing the accuracy of the measurement results.

[0010] In some feasible embodiments, the horizontal conveying assembly includes a first conveying roller group and a second conveying roller group. Along a first horizontal direction, the second conveying roller group is disposed on both sides of the first conveying roller group. The first conveying roller group includes a first sub-conveying roller and a second sub-conveying roller. The first sub-conveying roller and the second sub-conveying roller are spaced apart along a second horizontal direction, and an avoidance opening is provided between the first sub-conveying roller and the second conveying roller.

[0011] By splitting the horizontal conveying assembly into a first conveying roller group and a second conveying roller group, and forming an avoidance opening between the first and second sub-conveying rollers spaced apart along the second horizontal direction, the wheel can be smoothly carried and transported through the structure of the first and second sub-conveying rollers. At the same time, a lifting operation channel for the wheel hub centering device and the diameter measuring device is reserved, eliminating the need to open additional holes on the main frame, thus making the structure of the wheel hub hole diameter measuring device simpler.

[0012] In some feasible methods, the measuring element includes a contour scanner.

[0013] By using a contour scanner as the measuring element, data on the inner wall of the wheel hub hole can be obtained in a non-contact scanning manner, which effectively reduces the possibility of scratching the inner wall of the wheel hub hole caused by contact measurement. At the same time, it effectively improves the sampling accuracy and acquisition efficiency of the measuring element.

[0014] In some feasible implementations, the locating element is radially movably connected to the annular seat.

[0015] By setting the positioning component to be radially movable along the annular seat, the hub alignment device can perform hub alignment operations for hubs with different outer diameter specifications, effectively improving the versatility of the hub alignment device; at the same time, the radially movable positioning component can accurately fit the hub contour, ensuring that the axis of the hub hole after alignment is coaxial with the vertical axis of rotation of the measuring component, providing a benchmark guarantee for subsequent high-precision measurements.

[0016] In some feasible implementations, the hub alignment device further includes a first drive assembly that passes through an annular seat and is connected to a positioning member. The first drive assembly is used to drive the positioning member to move radially along the annular seat so that the positioning member pushes the hub and achieves hub alignment.

[0017] By adding a first drive component to automatically drive the positioning component to move synchronously along the radial direction, the wheel hub is aligned by pushing, thus realizing the automated execution of the wheel hub alignment action. This eliminates the need for manual alignment and effectively improves the alignment efficiency and accuracy of the wheel hub.

[0018] In some feasible embodiments, the main frame also includes a wheel outlet, and the wheel hub bore diameter measuring device further includes a pusher assembly, which includes a pusher assembly and a second drive assembly. The pusher assembly is positioned on the side of the horizontal conveying assembly away from the wheel outlet. Vertically, the pusher assembly is positioned above the horizontal conveying assembly, and the second drive assembly drives the pusher assembly to move along a first horizontal direction to push the measured wheel hub out of the wheel outlet along the horizontal conveying assembly.

[0019] By adding a pusher device inside the equipment, the second drive component drives the pusher component to move along the first horizontal direction. After the wheel hub measurement is completed, the wheel hub can be automatically pushed from the wheel outlet to the next production line station. This realizes the automated connection between measurement and unloading, eliminating the need for manual intervention in unloading and transfer, and effectively improving the overall operation efficiency of the production line.

[0020] In some possible implementations, the pusher assembly includes a pusher beam and a protective pusher block, the pusher beam being connected to a second drive assembly, and the protective pusher block being connected to the pusher beam and positioned on the side of the pusher beam facing the wheel outlet.

[0021] By setting the pusher assembly as a pusher beam and a protective pusher block, the pusher beam can ensure the structural rigidity and motion stability during the pushing process, and the protective pusher block directly contacts the wheel hub for pushing, which can effectively reduce the possibility of bumps and scratches caused by hard contact to the wheel hub surface, thus achieving wheel hub protection while ensuring pushing reliability.

[0022] In some feasible embodiments, the pusher device further includes a first limiting assembly connected to the main frame. The first limiting assembly includes a first limiting member and a second limiting member. The first limiting member is disposed on both sides of the horizontal conveying assembly away from the clearance opening, and the second limiting member is disposed on the side of the first limiting member away from the clearance opening. The first limiting member and the second limiting member are used to monitor the position of the pusher beam.

[0023] By setting up a two-stage first limit assembly including a first limiter and a second limiter, the normal working position detection and abnormal overtravel protection of the pusher beam can be realized respectively. This ensures that the pusher beam stops after the pusher action is completed, and can also trigger safety protection when the pusher device malfunctions or the pusher beam exceeds the normal travel, reducing the possibility of the pusher beam being damaged by impact and effectively improving the safety and service life of the pusher device.

[0024] This application provides a method for measuring the diameter of a wheel hub bore, specifically including the following steps: Provide wheel hub bore diameter measuring equipment; A sample ring assembly is provided, which includes a sample ring support and a sample ring with an inner hole. The sample ring support carries the sample ring, and the axis of the sample ring is coaxial with the axis of the sample ring support. Place the sample ring assembly on the hub alignment device; The hub alignment device is fixed and the alignment ring bracket is used; The diameter measuring device measures the inner diameter of the sample ring to obtain the measured diameter of the sample ring; The calibration deviation is calculated based on the measured diameter of the sample ring and the inner diameter of the hole. Remove the sample ring assembly from the hub alignment device; Provide the wheel hub to be measured; The hub alignment device is fixed and aligned with the hub to be measured; A diameter measuring device measures the hub bore to obtain the measured diameter of the hub bore. The true diameter of the wheel hub hole is obtained by compensation calculation based on the measured diameter of the hub hole and the calibration deviation.

[0025] The wheel hub hole diameter measurement method of this application adopts a measurement logic of sample ring calibration and calibration deviation compensation. First, the system calibration deviation is measured by a standard sample ring with known parameters. Then, the actual wheel hub hole measurement result is compensated and corrected. This can effectively reduce the measurement deviation caused by the system error of the wheel hub hole diameter measuring equipment itself and factors such as ambient temperature fluctuations, improve the accuracy of the wheel hub hole diameter measurement result, and enhance the measurement precision and data reliability.

[0026] In some feasible embodiments, the diameter measuring device includes a measuring element that measures the diameter of the hub bore of the wheel hub to be measured, thereby obtaining the measured hub bore diameter, and further includes the following steps: The measuring component is kept at an interval from the hub hole, and the inner wall of the hub hole to be measured is scanned through the measuring component to obtain point cloud data; Two opposite circular arc segments along the first direction are extracted from the point cloud data and fitted to a circle to obtain the first diameter; Two opposite circular arc segments along the second direction are cut and circle fitting is performed to obtain the second diameter, with the first direction perpendicular to the second direction; The average of the first diameter and the second diameter is used to obtain the measured diameter of the hub hole.

[0027] By scanning to obtain point cloud data of the inner wall of the hub hole, and then fitting the diameters of two sets of mutually perpendicular arc segments and taking the average value, the influence of the hub hole's own roundness error and local surface defects on the measurement results can be effectively reduced, making the final hub hole diameter value more representative and further improving the accuracy of the hub hole diameter measurement results. Attached Figure Description

[0028] The features, advantages, and technical effects of exemplary embodiments of this application will now be described with reference to the accompanying drawings.

[0029] Figure 1 This is a schematic diagram of the structure of the wheel hub bore diameter measuring device provided in some embodiments of this application when measuring the wheel hub; Figure 2 This is a schematic diagram of the assembly structure of the main frame and the sample ring assembly provided in some embodiments of this application; Figure 3 A first-view structural schematic diagram of a wheel hub bore diameter measuring device provided in some embodiments of this application; Figure 4 for Figure 3 Enlarged diagram of A in the middle; Figure 5 A second-view structural schematic diagram of a wheel hub bore diameter measuring device provided in some embodiments of this application; Figure 6 for Figure 5 Enlarged diagram of B in the middle; Figure 7 A third-view structural schematic diagram of a wheel hub bore diameter measuring device provided in some embodiments of this application; Figure 8 for Figure 7 Enlarged diagram of C in the middle; Figure 9 This is a schematic diagram of the structure of a hub alignment device provided in some embodiments of this application; Figure 10 for Figure 9 Enlarged diagram of D in the middle; Figure 11 A first-view structural schematic diagram of a diameter measuring device provided in some embodiments of this application; Figure 12 This is a second-view structural schematic diagram of a diameter measuring device provided in some embodiments of this application; Figure 13 This is a schematic diagram of the structure of the sample ring assembly provided in some embodiments of this application; Figure 14This is a flowchart illustrating a method for measuring the diameter of a wheel hub hole provided in some embodiments of this application.

[0030] The accompanying drawings are not necessarily drawn to scale.

[0031] Explanation of reference numerals in the attached figures: 1. Main frame; 100. Wheel outlet; 10. Main storage space; 11. Horizontal conveyor assembly; 110. Clearance opening; 111, First conveyor roller group; 1111, First sub-conveyor roller; 1112, Second sub-conveyor roller; 112. Second conveyor roller group; 1121. Third sub-conveyor roller; 1122. Fourth sub-conveyor roller; 12. Shock-absorbing support feet; 2. Hub alignment device; 21. First lifting assembly; 211. Second driving component; 22. Annular seat; 220. First central hole; 23. Positioning component; 231. First positioning surface; 232. Second positioning surface; 233. First sensing element; 241. First sub-rack; 242. First mounting base; 25. First drive assembly; 251. First drive element; 252. Transmission assembly; 2521. First transmission gear; 2522. Second transmission gear; 26. Second limiting component; 261. First position detection component; 262. Second position detection component; 263. Third position detection component; 3. Diameter measuring device; 31. Second lifting assembly; 311. Third driving component; 312. Synchronous pulley; 313. Synchronous belt; 314. Lead screw; 315. Second linear guide rail; 32. Rotating assembly; 321. Rotating platform; 322. Fifth driving component; 33. Measuring component; 34. Measuring component mounting base; 35. Second fixed base; 36. Second subframe; 37. Second cable chain; 4. Push wheel device; 41. Push wheel assembly; 411. Push wheel crossbeam; 4111. Bushing; 4112. Second sensing element; 412. Protective push block; 42. Second drive assembly; 421. Fourth drive component; 422. Drive shaft; 423. Rack; 424. Third transmission gear; 425. First cable chain; 43. First limiting component; 431. First limiting member; 432. Second limiting member; 5. Temperature sensor; 6. Sample ring assembly; 61. Sample ring bracket; 610. Second center hole; 611. First support ring; 612. Second support ring; 613. Support rod; 62. Sample ring; 7. Control device; 8. Wheel hub; X, first horizontal direction; Y, second horizontal direction; Z, vertical direction. Detailed Implementation

[0032] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.

[0033] Unless otherwise defined, all technical and scientific terms used in this application have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains; the terminology used in the description of this application is for the purpose of describing particular embodiments only and is not intended to limit the application; the terms "comprising" and "having," and any variations thereof, in the description, claims, and accompanying drawings of this application are intended to cover non-exclusive inclusion. The terms "first," "second," etc., in the description, claims, or accompanying drawings of this application are used to distinguish different objects, not to describe a specific order or hierarchy.

[0034] In this application, the reference to "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment that is mutually exclusive with other embodiments.

[0035] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," "linking," and "attachment" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal communication between two components. Those skilled in the art can understand the specific meaning of the above terms in this application according to the specific circumstances.

[0036] In the embodiments of this application, the same reference numerals denote the same components, and for the sake of brevity, detailed descriptions of the same components are omitted in different embodiments. It should be understood that the thickness, length, width, and other dimensions of various components in the embodiments of this application shown in the accompanying drawings, as well as the overall thickness, length, width, and other dimensions of the integrated device, are merely illustrative and should not constitute any limitation on this application.

[0037] In this application, "multiple" means two or more (including two).

[0038] like Figures 1 to 12 As shown in the figure, this application provides a wheel hub bore diameter measuring device, which includes a main frame 1, a hub alignment device 2, and a diameter measuring device 3.

[0039] The main frame 1 includes a horizontal conveying assembly 11, which is provided with an clearance opening 110. The horizontal conveying assembly 11 is used to carry the wheel hub 8 to be measured and to transport the wheel hub 8 after measurement away from the measuring equipment.

[0040] The wheel hub centering device 2 includes a first lifting assembly 21, an annular seat 22 with a first central hole 220, and a plurality of positioning elements 23. Along the vertical direction Z, the annular seat 22 is correspondingly arranged with the clearance opening 110. The annular seat 22 is connected to the first lifting assembly 21. The plurality of positioning elements 23 are arranged at intervals along the circumference of the annular seat 22. The plurality of positioning elements 23 are used to fix the wheel hub 8 and realize the centering of the wheel hub 8. The first lifting assembly 21 drives the annular seat 22 to rise and fall, and the clearance opening 110 allows the annular seat 22 to pass through.

[0041] The diameter measuring device 3 includes a second lifting assembly 31, a rotating assembly 32, and a measuring element 33. The measuring element 33 is positioned in the vertical direction Z and is correspondingly arranged with the clearance opening 110. The rotating assembly 32 is connected to the second lifting assembly 31, and the measuring element 33 is connected to the rotating assembly 32. The second lifting assembly 31 drives the measuring element 33 to rise and fall. The first central hole 220 and the clearance opening 110 allow the measuring element 33 to pass through. The rotating assembly 32 drives the measuring element 33 to rotate around the vertical axis to measure the diameter of the hub hole. The vertical axis is coaxial with the axis of the annular seat 22.

[0042] The wheel hub bore diameter measuring device of this application integrates a horizontal conveying assembly 11 with a clearance opening 110, a liftable hub alignment device 2, and a liftable and rotatable diameter measuring device 3 into the main frame 1. The vertical axis of rotation of the measuring element 33 is coaxial with the axis of the annular seat 22, thus achieving automated measurement of the wheel hub bore diameter without the need for manual handheld operation, effectively improving measurement accuracy and efficiency. The hub alignment device 2 and diameter measuring device 3 are correspondingly positioned within the clearance opening 110, and both can extend through the clearance opening 110 for operation, making the overall structure of the wheel hub bore diameter measuring device more compact and suitable for continuous operation in wheel processing production lines. Simultaneously, the coaxial alignment of the vertical axis of rotation of the measuring element 33 with the axis of the annular seat 22 ensures a unified measurement reference, improving the accuracy of the measurement results.

[0043] In some feasible ways, equipment in the previous process of the wheel processing line transports the wheel hub 8 to be measured above the clearance opening 110. For example, a robotic arm in the wheel processing line places the wheel hub 8 to be measured onto the horizontal conveyor assembly 11 and positions it above the clearance opening 110.

[0044] In some feasible methods, an external robotic arm places the wheel hub 8 to be measured above the clearance opening 110. The first lifting assembly 21 drives the annular seat 22 to rise and pass through the clearance opening 110 to reach the working position. Multiple positioning elements 23 fix the wheel hub 8 to be measured and center it. Subsequently, the second lifting assembly 31 drives the measuring element 33 to rise, passing through the clearance opening 110 and the first center hole 220 in sequence and extending into the wheel hole of the wheel hub 8 to be measured. The rotating assembly 32 drives the measuring element 33 to rotate around the vertical axis to complete the measurement of the wheel hole diameter. After the measurement is completed, the second lifting assembly 31 drives the measuring element 33 to descend and reset, the positioning elements 23 release the measured wheel hub 8, and the first lifting assembly 21 drives the annular seat 22 to descend and reset.

[0045] After the wheel hub hole diameter measurement process is completed, the wheel hub 8 is conveyed and removed from the wheel hub hole diameter measuring device by the horizontal conveyor assembly 11, and the wheel hub 8 is transferred to the next process.

[0046] In some feasible ways, such as Figure 9 As shown, the hub alignment device 2 also includes a first sub-frame 241 and a first fixed base 242. The first sub-frame 241 is fixedly connected to the main frame 1. The annular seat 22 is fixedly connected to the top of the first fixed base 242. The first lifting assembly 21 includes a second drive member 211 and a first linear guide rail (not shown in the figure).

[0047] Along the vertical direction Z, the first linear guide rail is fixedly mounted on the first sub-frame 241. The first fixed seat 242 is slidably connected to the first linear guide rail. The second drive unit 211 is connected to the first sub-frame 241. The output end of the second drive unit 211 is connected to the first fixed seat 242. The output end of the second drive unit 211 drives the first fixed seat 242 to perform vertical reciprocating lifting and lowering motion along the first linear guide rail, thereby driving the first fixed seat 242 and the ring seat 22 to lift and lower as a whole, so that the ring seat 22 passes through the clearance opening 110 of the horizontal conveying assembly 11 to complete the wheel alignment operation, or descends below the clearance opening 110 to avoid the wheel conveying action.

[0048] In some examples, the second drive element 211 may be, but is not limited to, a cylinder or an electric cylinder.

[0049] In some feasible ways, such as Figure 9 As shown, the wheel hub bore diameter measuring device also includes a temperature sensor 5, which is connected to the first sub-frame 241. The temperature sensor 5 is used to collect the ambient temperature of the measuring component 33 to monitor the temperature drift of the measuring component 33 and reduce the possibility of temperature factors interfering with the measurement results.

[0050] In some feasible ways, such as Figure 11 and Figure 12 As shown, the diameter measuring device 3 also includes a measuring element mounting base 34 and a second fixed base 35. The rotating assembly 32 includes a connected rotating platform 321 and a fifth driving member 322. Along the vertical direction Z, the measuring element 33 is connected to the top of the measuring element mounting base 34, and the rotating platform 321 is connected to the bottom of the measuring element mounting base 34. The fifth driving member 322 drives the rotating platform 321 to rotate, and the rotating platform 321 drives the measuring element mounting base 34 and the measuring element 33 to rotate. The fifth driving member 322 is connected to the second fixed base 35, and the second fixed base 35 is connected to the second lifting assembly 31. The second lifting assembly 31 drives the second fixed base 35 to rise and fall along the vertical direction, so as to drive the measuring element 33, the measuring element mounting base 34, the rotating platform 321, and the fifth driving member 322 to rise and fall along the vertical direction Z.

[0051] In some feasible embodiments, the diameter measuring device 3 further includes a second sub-frame 36, which is fixedly connected to the main frame 1. The second lifting assembly 31 includes a third drive element 311, two synchronous pulleys 312, a synchronous belt 313, a lead screw 314, and a second linear guide rail 315.

[0052] Two synchronous pulleys 312 are respectively mounted on the output shaft of the third drive component 311 and the end of the lead screw 314. A synchronous belt 313 is wound around the two synchronous pulleys 312. The second sub-frame 36 is equipped with a nut seat, and the lead screw 314 is threadedly connected to the nut seat to achieve threaded transmission. The lead screw 314 and the second linear guide rail 315 are both arranged in the vertical direction Z. The lead screw 314 is rotatably mounted on the second fixed seat 35 through a bearing assembly, and the bearing assembly is connected and fixed to the second fixed seat 35. The second linear guide rail 315 is fixedly connected to the second fixed seat 35. The second sub-frame 36 is equipped with a slider, and the second linear guide rail 315 and the slider slide and guide each other in the vertical direction Z.

[0053] When the third drive unit 311 outputs power, it drives the lead screw 314 to rotate via the synchronous pulley 312 and the synchronous belt 313. Since the nut seat is fixed to the second sub-frame 36 and remains stationary, the rotating lead screw 314 generates an axial displacement in the vertical direction Z under the action of the threaded pair. The lead screw 314 drives the second fixed seat 35 to rise and fall together. The second fixed seat 35 drives the second linear guide rail 315 to slide relative to the slider in the vertical direction Z, thereby driving the rotating platform 321, the measuring component mounting seat 34 and the measuring component 33 to rise and fall synchronously in the vertical direction Z.

[0054] In some feasible implementations, the diameter measuring device 3 also includes a second cable chain 37. One end of the second cable chain 37 is fixedly connected to the second subframe 36, and the other end is connected to the second fixed base 35. The second cable chain 37 moves up and down in the vertical direction Z with the second fixed base 35. It internally houses the power supply cables and signal transmission cables of components such as the third drive component 311 and the measuring component 33, and provides constraint, guidance and protection for the cables, reducing the possibility of the cables being pulled, bent, entangled and worn during the lifting and lowering process, and ensuring the stability and reliability of the equipment's power supply and signal transmission.

[0055] In some examples, the third drive unit 311 and the fifth drive unit 322 may be, but are not limited to, servo motors.

[0056] In some feasible ways, such as Figure 2 and Figure 13 As shown, the wheel hub bore diameter measuring device also includes a sample ring assembly 6, which is used to calibrate the measurement accuracy of the diameter measuring device 3. The sample ring assembly 6 includes a sample ring 62 and a sample ring support 61. The sample ring support 61 has a second central hole 610, and the sample ring 62 is disposed above the sample ring support 61 and is detachably connected to the sample ring support 61. The axis of the sample ring 62 is coaxial with the axis of the second central hole 610.

[0057] By setting up the sample ring assembly 6 to calibrate the measurement accuracy of the diameter measuring device 3, the possibility of measurement deviation caused by the system error of the wheel hub hole diameter measuring device itself and the fluctuation of environmental factors can be effectively reduced, thereby improving the accuracy of the measurement results of the wheel hub hole diameter measuring device. The sample ring 62 and the sample ring bracket 61 are detachably connected, which makes it easy to replace the sample ring 62 of different specifications according to different calibration requirements, effectively improving the adaptability of the wheel hub hole diameter measuring device.

[0058] In some feasible methods, when calibrating the measurement accuracy, the sample ring assembly 6 is placed above the clearance opening 110 of the horizontal conveying assembly 11. The first lifting assembly 21 drives the annular seat 22 to rise and pass through the clearance opening 110 to reach the working position. Multiple positioning elements 23 move radially along the annular seat 22 to center and position the sample ring support 61. Subsequently, the second lifting assembly 31 drives the measuring element 33 to rise and pass through the clearance opening 110, the first center hole 220, and the second center hole 610 in sequence to extend into the sample ring 62. The rotating assembly 32 drives the measuring element 33 to rotate around the vertical axis to complete the measurement of the inner diameter of the sample ring 62. After the measurement is completed, the second lifting assembly 31 drives the measuring element 33 to descend and reset, the first lifting assembly 21 drives the annular seat 22 to descend and reset, the positioning elements 23 release the sample ring assembly 6, and remove the sample ring assembly 6 from above the clearance opening 110.

[0059] In some feasible ways, such as Figure 2 and Figure 13 As shown, the sample ring support 61 includes a support rod 613, a first support ring 611, and a second support ring 612. A second central hole 610 passes through the first support ring 611 and the second support ring 612. The two ends of the support rod 613 are respectively connected to the first support ring 611 and the second support ring 612. Along the vertical direction Z, the first support ring 611 is positioned above the second support ring 612. The sample ring 62 is detachably connected to the first support ring 611. The axes of the first support ring 611, the second support ring 612, the second central hole 610, and the sample ring 62 are coaxially arranged.

[0060] In some feasible methods, when calibrating the measurement accuracy, the sample ring 62 is first installed above the first support ring 611, so that the sample ring 62 and the first support ring 611 are coaxially set. Then, the entire sample ring assembly 6 is placed above the clearance opening 110 of the horizontal conveying assembly 11. The first lifting assembly 21 drives the annular seat 22 to rise and pass through the clearance opening 110 to reach the working position. Multiple positioning elements 23 move radially along the annular seat 22 and push the outer contour of the second support ring 612 to complete the centering and positioning. Subsequently, the second lifting assembly 31 drives the measuring element 33 to rise and pass through the clearance opening 110, the first center hole 220 and the second center hole 610 in sequence to extend into the sample ring 62. The rotating assembly 32 drives the measuring element 33 to rotate around the vertical axis to complete the measurement of the inner diameter of the sample ring 62.

[0061] In some feasible ways, such as Figure 10 As shown, the positioning component 23 includes a first positioning surface 231 and a second positioning surface 232 connected to each other. The first positioning surface 231 and the second positioning surface 232 are both located on the side of the positioning component 23 facing the first central hole 220. Along the vertical direction Z, the first positioning surface 231 is disposed above the second positioning surface 232. The first positioning surface 231 is used to push and fix the hub 8, and the second positioning surface 232 is used to push and fix the second support ring 612.

[0062] In some feasible ways, such as Figure 2 As shown, the main frame 1 includes a main receiving space 10, which is located below the horizontal conveying assembly 11 along the vertical direction Z. The sample ring assembly 6 is disposed within the main receiving space 10.

[0063] In some feasible ways, such as Figure 1 As shown, the main frame 1 also includes shock-absorbing support feet 12, which are located at the bottom of the main frame 1.

[0064] In some feasible ways, such as Figure 2 As shown, the horizontal conveying assembly 11 includes a first conveying roller group 111 and a second conveying roller group 112. Along the first horizontal direction X, the second conveying roller group 112 is disposed on both sides of the first conveying roller group 111. The first conveying roller group 111 includes a first sub-conveying roller 1111 and a second sub-conveying roller 1112. The first sub-conveying roller 1111 and the second sub-conveying roller 1112 are spaced apart along the second horizontal direction Y. An avoidance opening 110 is provided between the first sub-conveying roller 1111 and the second sub-conveying roller 1112.

[0065] By splitting the horizontal conveying assembly 11 into a first conveying roller group 111 and a second conveying roller group 112, and forming an avoidance opening 110 between the first sub-conveying rollers 1111 and the second sub-conveying rollers 1112 spaced apart along the second horizontal direction Y, the structure of the first sub-conveying rollers 1111 and the second sub-conveying rollers 1112 achieves both stable bearing and conveying of the wheel, and also reserves a lifting operation channel for the wheel hub centering device 2 and the diameter measuring device 3. There is no need to open additional holes on the main frame 1, making the structure of the wheel hub hole diameter measuring device simpler.

[0066] In some feasible implementations, the hub 8 to be measured is supported by a first conveyor roller group 111 and a second conveyor roller group 112 and conveyed along a first horizontal direction X. The second conveyor roller group 112 is arranged on both sides of the first conveyor roller group 111 to help ensure the smooth conveying of the hub 8 to be measured. The first sub-conveyor roller 1111 and the second sub-conveyor roller 1112 in the first conveyor roller group 111 are spaced apart along a second horizontal direction Y, and together carry the hub 8 to be measured forward. When the hub 8 to be measured is conveyed to the clearance opening 110 between the first sub-conveyor roller 1111 and the second sub-conveyor roller 1112, the conveying action stops, and the hub 8 to be measured is in place to await subsequent measurement operations.

[0067] In some feasible ways, such as Figure 2 As shown, the second conveyor roller group 112 includes a third sub-conveyor roller 1121 and a fourth sub-conveyor roller 1122. The third sub-conveyor roller 1121 and the fourth sub-conveyor roller 1122 are arranged at intervals along the second horizontal direction Y.

[0068] In some examples, the interval between the third sub-transfer roller 1121 and the fourth sub-transfer roller 1122 along the second horizontal direction Y is smaller than the interval between the first sub-transfer roller 1111 and the second sub-transfer roller 1112 along the second horizontal direction Y.

[0069] For example, the first sub-transfer roller 1111, the second sub-transfer roller 1112, the third sub-transfer roller 1121 and the fourth sub-transfer roller 1122 may be, but are not limited to, unpowered rollers.

[0070] In some feasible ways, such as Figure 11 and Figure 12 As shown, the measuring component 33 includes a contour scanner.

[0071] By using a contour scanner as the measuring element 33, data on the inner wall of the hub hole is obtained in a non-contact scanning manner, which effectively reduces the possibility of scratching the inner wall of the hub hole caused by contact measurement. At the same time, it effectively improves the sampling accuracy and acquisition efficiency of the measuring element 33.

[0072] In some feasible methods, the contour scanner extends into the wheel hub hole and rotates circumferentially around the vertical axis. During the rotation, it continuously emits detection signals to the inner wall of the wheel hub hole and receives feedback, collecting the contour coordinate information of the inner wall of the wheel hub hole point by point, and obtaining complete inner wall point cloud data, which provides data support for the subsequent fitting calculation of the wheel hub hole diameter.

[0073] In some feasible ways, such as Figure 9 As shown, the positioning member 23 is movably connected to the annular seat 22 along the radial direction of the annular seat 22.

[0074] By setting the positioning element 23 to be radially movable along the annular seat 22, the hub centering device 2 can perform centering operations on hubs 8 with different outer diameter specifications, effectively improving the versatility of the hub centering device 2; at the same time, the radially movable positioning element 23 can relatively easily fit the contour of the hub 8, ensuring that the axis of the hub hole after centering is coaxial with the vertical axis of rotation of the measuring element 33, providing a benchmark guarantee for subsequent high-precision measurements.

[0075] In some feasible ways, after the annular seat 22 rises to the working position, multiple positioning elements 23, which are spaced apart around the annular seat 22, move radially along the annular seat 22. By adjusting the position of the positioning elements 23 in the radial direction of the annular seat 22, they can be adapted to the wheel hubs 8 with different outer diameters, providing a basis for subsequent wheel hub 8 centering operations.

[0076] In some feasible ways, such as Figure 9 and Figure 10 As shown, the hub alignment device 2 also includes a first drive assembly 25. The first drive assembly 25 partially passes through the annular seat 22 and is connected to the positioning member 23. The first drive assembly 25 is used to drive the positioning member 23 to move radially along the annular seat 22 so that the positioning member 23 pushes the hub 8 and achieves hub alignment.

[0077] By adding a first drive component 25 to automatically drive the positioning component 23 to move synchronously along the radial direction, the wheel hub 8 is aligned by pushing, thus realizing the automated execution of the wheel hub 8 alignment action. No manual alignment is required, which effectively improves the alignment efficiency and alignment accuracy of the wheel hub 8.

[0078] In some feasible ways, the first drive assembly 25 outputs power to drive multiple positioning elements 23 to move synchronously along the radial direction of the annular seat 22, so that each positioning element 23 gradually pushes the wheel hub 8 to be measured, and adjusts the position of the wheel hub 8 to be measured by the circumferentially uniformly applied pushing force, and finally achieves the centering and positioning of the wheel hub 8 to be measured.

[0079] In some feasible ways, such as Figure 9 and Figure 10As shown, the first drive assembly 25 includes a first drive member 251 and a transmission assembly 252. Part of the transmission assembly 252 is disposed within the annular seat 22. The first drive member 251 is connected to the input end of the transmission assembly 252. The bottom of the positioning member 23 passes through the top wall of the annular seat 22 and is connected to the output end of the transmission assembly 252. The first drive member 251 is used to drive the transmission assembly 252 to move. The transmission assembly 252 is used to drive the positioning member 23 to move radially along the annular seat 22, so that the positioning member 23 pushes the wheel hub 8 and realizes the centering of the wheel hub 8.

[0080] By partially housing the transmission assembly 252 within the annular seat 22, the overall structure of the hub alignment device 2 becomes more compact, and the transmission assembly 252 is protected, reducing the possibility of dust or oil contamination affecting transmission accuracy and service life. The transmission assembly 252 synchronously drives multiple positioning elements 23 to move radially, effectively improving the synchronicity of their radial movement and thus enhancing the positioning accuracy of the hub alignment device 2. This ensures that the axis of the hub 8 is coaxial with the measuring axis of the diameter measuring device 3 after alignment.

[0081] In some feasible ways, the first drive member 251 outputs power to drive the transmission assembly 252 to operate. The transmission assembly 252 transmits the power synchronously to the bottom of multiple positioning members 23, causing each positioning member 23 to move synchronously along the radial direction of the annular seat 22, gradually pushing the wheel hub 8 to be measured. The position of the wheel hub 8 is adjusted by the circumferentially uniformly applied pushing force, and finally the centering and positioning of the wheel hub 8 is completed.

[0082] In some possible implementations, the annular seat 22 includes an annular receiving space (not shown) and an annular opening (not shown) communicating with the annular receiving space, wherein the annular opening opens downward in the vertical direction Z. The top of the annular seat 22 has a limiting sliding hole (not shown) that penetrates the top wall along its radial direction, and the positioning element is slidably engaged with the limiting sliding hole in the radial direction.

[0083] The transmission assembly 252 includes a first transmission gear 2521 and a second transmission gear 2522. The first transmission gear 2521 is connected to the output end of the first drive member 251. The second transmission gear 2522 meshes with the first transmission gear 2521 along the vertical direction Z. Part of the second transmission gear 2522 is housed in an annular receiving space. The top of the second transmission gear 2522 faces the top wall of the annular seat 22. The part of the second transmission gear 2522 outside the annular receiving space meshes with the first transmission gear 2521. The top of the second transmission gear 2522 is provided with a spiral protrusion. The bottom of the positioning member 23 is provided with a sliding groove that matches the spiral protrusion. The sliding groove at the bottom of the positioning member 23 is slidably connected to the spiral protrusion.

[0084] The first driving member 251 outputs power to drive the first transmission gear 2521 to rotate, and the first transmission gear 2521 drives the second transmission gear 2522 to rotate around the vertical axis. The spiral protrusion at the top of the second transmission gear 2522 rotates synchronously with the second transmission gear 2522. Along the radial direction of the annular seat 22, the side surface of the spiral protrusion and the side surface of the slide groove come into contact with each other to apply a radial thrust to the positioning member 23, causing the positioning member 23 to move radially linearly relative to the annular seat 22. Multiple positioning members 23 can move synchronously along the radial direction of the annular seat 22 towards or away from the first central hole 220 to push the wheel hub 8 to be measured, completing the centering and positioning of the wheel hub 8.

[0085] In some examples, the first drive element 251 may be, but is not limited to, a servo motor.

[0086] In some feasible ways, such as Figure 10 As shown, the wheel hub bore diameter measuring device also includes a control device 7, and the hub alignment device 2 also includes a second limiting component 26. The second limiting component 26 is disposed on one side of the positioning member 23 and connected to the top wall of the annular seat 22. The second limiting component 26 includes a first position detection element 261, a second position detection element 262, and a third position detection element 263 arranged radially and spaced apart along the annular seat 22. The first position detection element 261 is disposed on the side of the second position detection element 262 away from the first central hole 220, and the third position detection element 263 is disposed on the side of the second position detection element 262 close to the first central hole 220. The first sensing plate 233 is disposed on the side of the positioning member 23 close to the second limiting component 26 and connected to the side wall of the positioning member 23. The first position detection element 261, the second position detection element 262, the third position detection element 263, and the first driving element 251 are all electrically connected to the control device 7.

[0087] During the radial reciprocating movement of the positioning member 23 along the annular seat 22, the first sensing plate 233 moves synchronously with the positioning member 23. The second limiting component 26 senses the movement state and position of the positioning member 23 through the position of the first sensing plate 233. Specifically, taking the position of the second position detection component 262 as the origin of movement of the positioning member 23, when the positioning member 23 moves away from the first central hole 220, the first sensing plate 233 moves away from the first central hole 220 along with the positioning member 23. When the first sensing plate 233 moves to the sensing area of ​​the first position detection component 261, the first position detection component 261 outputs an external limit position signal to the control device 7. The control device 7 controls the first driving component 251 to stop driving, thereby stopping the positioning member 23 from continuing to move outward. When the positioning member 23 moves closer to the first central hole 220... When the center hole 220 moves, the first sensing plate 233 moves with the positioning member 23 toward the direction of the first center hole 220. When the first sensing plate 233 moves to the sensing area of ​​the third position detection member 263, the third position detection member 263 outputs an inner limit position signal to the control device 7. The control device 7 controls the first driving member 251 to stop driving, thereby causing the positioning member 23 to stop moving toward the direction of the first center hole 220. The second position detection member 262 is used to output the origin position signal to realize the zeroing calibration and initial position positioning of the positioning member 23.

[0088] In some examples, the first position detector 261, the second position detector 262, and the third position detector 263 may be, but are not limited to, proximity switches.

[0089] In some feasible ways, such as Figure 1 As shown, the main frame 1 also includes a wheel outlet 100, and the wheel hub bore diameter measuring device also includes a pusher device 4. The pusher device 4 includes a pusher assembly 41 and a second drive assembly 42. The pusher assembly 41 is disposed on the side of the horizontal conveying assembly 11 away from the wheel outlet 100. Along the vertical direction Z, the pusher assembly 41 is disposed above the horizontal conveying assembly 11. The second drive assembly 42 drives the pusher assembly 41 to move along the first horizontal direction X, so as to push the measured wheel hub 8 out of the wheel outlet 100 along the horizontal conveying assembly 11.

[0090] By setting a pusher device 4 inside the equipment, the second drive component 42 drives the pusher component 41 to move along the first horizontal direction X. After the wheel hub 8 is measured, it can automatically push the wheel hub 8 from the wheel outlet 100 to the next production line station, realizing the automated connection between measurement and unloading. No manual intervention is required for unloading and transfer, which effectively improves the overall operation efficiency of the production line.

[0091] In some feasible methods, after the measured wheel hub 8 completes the measurement, the second drive assembly 42 outputs power to drive the push wheel assembly 41 to move along the first horizontal direction X. The push wheel assembly 41 starts from the side of the horizontal transmission assembly 11 away from the wheel outlet 100, moves above the horizontal transmission assembly 11 along the first horizontal direction X, acts on the measured wheel hub 8, and pushes the measured wheel hub 8 on the horizontal transmission assembly 11 along the first horizontal direction X towards the wheel outlet 100 side, and finally pushes the measured wheel hub 8 out of the wheel outlet 100.

[0092] In some feasible ways, such as Figure 1 As shown, the pusher assembly 41 includes a pusher beam 411 and a protective pusher block 412. The pusher beam 411 is connected to the second drive assembly 42, and the protective pusher block 412 is connected to the pusher beam 411 and is disposed on the side of the pusher beam 411 facing the wheel outlet 100.

[0093] By setting the pusher assembly 41 as a pusher beam 411 and a protective pusher block 412, the pusher beam 411 can ensure the structural rigidity and motion stability during the pushing process. The protective pusher block 412 directly contacts the wheel hub 8 for pushing, which can effectively reduce the possibility of impacts and scratches caused by rigid contact to the surface of the wheel hub 8. While ensuring the reliability of pushing, the wheel hub 8 is protected.

[0094] In some possible implementations, the second drive assembly 42 drives the pusher beam 411 to move along the first horizontal direction X, causing the protective push block 412 mounted on the side of the pusher beam 411 facing the wheel outlet 100 to move synchronously; the protective push block 412 directly contacts the wheel hub 8 that has completed the measurement and applies a thrust, pushing the wheel hub 8 to move along the first horizontal direction X on the horizontal transmission assembly 11.

[0095] In some feasible ways, such as Figure 3 and Figure 4 As shown, the second drive assembly 42 includes a fourth drive member 421, a drive shaft 422, a rack 423, a third drive gear 424, and a third linear guide (not shown in the figure). Along the second horizontal direction Y, the rack 423 and the third linear guide are respectively disposed on both sides of the main frame 1 and fixedly connected to the main frame 1. The rack 423 and the third linear guide are arranged parallel to each other. A bushing 4111 is provided on the side of the pusher beam 411 facing away from the wheel outlet 100. The drive shaft 422 passes through the bushing 4111 and can rotate relative to the bushing 4111. The drive shaft 422 can drive the pusher beam 411 to move linearly along the third linear guide through the bushing 4111. The third drive gear 424 is respectively mounted on both ends of the drive shaft 422, and the third drive gear 424 meshes with the rack 423 on the corresponding side.

[0096] The fourth driving component 421 drives the transmission shaft 422 to rotate, and the transmission shaft 422 drives the third transmission gear 424 to rotate. The third transmission gear 424 meshes with the fixed rack 423 to drive the transmission shaft 422 to move linearly along the third linear guide. The transmission shaft 422 can rotate relative to the bushing 4111. The rotational motion is not transmitted to the push wheel assembly 41. The transmission shaft 422 drives the push wheel assembly 41 to move linearly along the third linear guide synchronously through the bushing 4111. The push wheel assembly 41 completes the wheel pushing.

[0097] In some feasible embodiments, the second drive assembly 42 also includes a first drag chain 425. One end of the first drag chain 425 is fixedly connected to the main frame 1, and the other end is connected to the pusher beam 411. The first drag chain 425 moves in a reciprocating linear motion along the extension direction of the third linear guide rail with the pusher beam 411. It internally houses the power supply cables and signal transmission cables of the fourth drive component 421 and the matching detection elements of the pusher assembly 41, which play a role in traction constraint and protection of the cables, reducing the possibility of the cables being pulled, tangled, scratched and damaged during the reciprocating motion of the pusher device 4, and ensuring the stability of the electrical operation of the equipment.

[0098] In some examples, the fourth drive 421 may be, but is not limited to, a servo motor.

[0099] In some feasible ways, such as Figures 5 to 8 As shown, the pusher device 4 also includes a first limiting component 43, which is connected to the main frame 1. The first limiting component 43 includes a first limiting member 431 and a second limiting member 432. The first limiting member 431 is disposed on both sides of the horizontal conveying component 11 away from the clearance opening 110, and the second limiting member 432 is disposed on the side of the first limiting member 431 away from the clearance opening 110. The first limiting member 431 and the second limiting member 432 are used to monitor the position of the pusher beam 411.

[0100] By setting up a two-stage first limit assembly 43 including a first limit member 431 and a second limit member 432, the normal working position detection and abnormal overtravel protection of the pusher beam 411 can be realized respectively. This allows the pusher beam 411 to stop after the pusher action is completed, and to trigger safety protection when the pusher device 4 malfunctions or the pusher beam 411 exceeds the normal travel, reducing the possibility of the pusher beam 411 being damaged by impact and effectively improving the safety and service life of the pusher device 4.

[0101] In some feasible implementations, during the movement of the pusher beam 411 along the first horizontal direction X, the first limiting component 43 connected to the main frame 1 monitors the position of the pusher beam 411 in real time; when the pusher beam 411 moves to the detection position of the first limiting component 431, the first limiting component 431 outputs a positioning signal to the wheel hub hole diameter measuring device; if the pusher beam 411 crosses the first limiting component 431 due to equipment malfunction and continues to move to the detection position of the second limiting component 432, the second limiting component 432 outputs a protection signal to the wheel hub hole diameter measuring device.

[0102] In some feasible embodiments, the wheel hub bore diameter measuring device further includes a control device 7, which is electrically connected to the first limiting member 431, the second limiting member 432, and the fourth driving member 421. The pusher beam 411 includes a second sensing plate 4112. Along the second horizontal direction Y, the second sensing plate 4112 is disposed on the side of the pusher beam 411 near the first limiting member 43. Along the first horizontal direction X, the second sensing plate 4112 reciprocates with the pusher beam 411. The second sensing plate 4112 is located on the same side as the first limiting member 431 and the second limiting member 432, and when the second sensing plate 4112 moves, it can block the sensing areas of the first limiting member 431 and the second limiting member 432.

[0103] The pusher beam 411 drives the second sensing element 4112 to move along the first horizontal direction X. When the second sensing element 4112 moves to the sensing area of ​​the first limiting member 431 and blocks the first limiting member 431, the first limiting member 431 outputs a positioning detection signal to the control device 7. After receiving the signal, the control device 7 controls the fourth driving member 421 to stop working, and the pusher beam 411 stops pushing. If an equipment malfunction occurs and the pusher beam 411 continues to move beyond its travel range, the second sensing element 4112 blocks the sensing area of ​​the second limiting member 432, and the second limiting member 432 outputs an overtravel protection signal to the control device 7. After receiving the overtravel protection signal, the control device 7 controls the fourth driving member 421 to stop urgently, so that the pusher beam 411 immediately stops moving.

[0104] In some examples, the first limiter 431 may be, but is not limited to, a proximity switch, and the second limiter 432 may be, but is not limited to, an over-limit switch.

[0105] like Figure 14 As shown in the figure, this application provides a method for measuring the diameter of a wheel hub bore, which specifically includes the following steps: Provide wheel hub bore diameter measuring equipment; A sample ring assembly 6 is provided, which includes a sample ring support 61 and a sample ring 62 with an inner hole. The sample ring support 61 carries the sample ring 62, and the axis of the sample ring 62 is coaxial with the axis of the sample ring support 61. Place the sample ring assembly 6 on the hub alignment device 2; The hub alignment device 2 is fixed and the alignment ring bracket 61 is used; The diameter measuring device 3 measures the inner diameter of the sample ring 62 to obtain the measured diameter of the sample ring 62; The calibration deviation is calculated based on the measured diameter and inner diameter of sample ring 62. Remove the sample ring assembly 6 from the hub alignment device 2; Provide 8 wheel hubs to be measured; The hub alignment device 2 is fixed and aligned with the hub 8 to be measured; The diameter measuring device 3 measures the hub hole to obtain the measured diameter of the hub hole; The true diameter of the wheel hub hole is obtained by compensation calculation based on the measured diameter of the hub hole and the calibration deviation.

[0106] The wheel hub hole diameter measurement method of this application adopts a measurement logic of calibration and calibration deviation compensation using a standard sample ring 62. First, the system calibration deviation is measured using a standard sample ring 62 with known parameters. Then, the actual wheel hub hole measurement result is compensated and corrected. This can effectively reduce the measurement deviation caused by the system error of the wheel hub hole diameter measuring equipment itself and factors such as environmental temperature fluctuations, improve the accuracy of the wheel hub hole diameter measurement result, and enhance the measurement precision and data reliability.

[0107] In some feasible embodiments, the diameter measuring device 3 includes a measuring element 33, which measures the diameter of the hub bore of the wheel hub 8 to be measured, thereby obtaining the measured hub bore diameter, and further includes the following steps: The measuring element 33 is kept at an interval from the hub hole and the inner wall of the hub hole to be measured is scanned by the measuring element 33 to obtain point cloud data; Two opposite circular arc segments along the first direction are extracted from the point cloud data and fitted to a circle to obtain the first diameter; Two opposite circular arc segments along the second direction are cut and circle fitting is performed to obtain the second diameter, with the first direction perpendicular to the second direction; The average of the first diameter and the second diameter is used to obtain the measured diameter of the hub hole.

[0108] By scanning to obtain point cloud data of the inner wall of the hub hole, and then fitting the diameters of two sets of mutually perpendicular arc segments and taking the average value, the influence of the hub hole's own roundness error and local surface defects on the measurement results can be effectively reduced, making the final hub hole diameter value more representative and further improving the accuracy of the hub hole diameter measurement results.

[0109] Although this application has been described with reference to preferred embodiments, various modifications can be made thereto and components can be replaced with equivalents without departing from the scope of this application. In particular, the technical features mentioned in the various embodiments can be combined in any manner, provided there is no structural conflict. This application is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.

Claims

1. A wheel hub bore diameter measuring device, characterized in that, include: The main frame includes a horizontal conveying assembly with an clearance opening. The horizontal conveying assembly is used to carry the wheel hub to be measured and to transport the measured wheel hub away from the wheel hub hole diameter measuring device. A wheel hub alignment device includes a first lifting assembly, an annular seat with a first central hole, and a plurality of positioning members. In the vertical direction, the annular seat is correspondingly arranged with the clearance opening. The annular seat is connected to the first lifting assembly. The plurality of positioning members are arranged at intervals along the circumference of the annular seat. The plurality of positioning members are used to fix the wheel hub and realize wheel hub alignment. The first lifting assembly drives the annular seat to rise and fall. The clearance opening allows the annular seat to pass through. A diameter measuring device includes a second lifting assembly, a rotating assembly, and a measuring element. Along the vertical direction, the measuring element is correspondingly arranged with the clearance opening. The rotating assembly is connected to the second lifting assembly, and the measuring element is connected to the rotating assembly. The second lifting assembly drives the measuring element to rise and fall. The first central hole and the clearance opening allow the measuring element to pass through. The rotating assembly drives the measuring element to rotate around a vertical axis to measure the diameter of the hub hole. The vertical axis is coaxial with the axis of the annular seat.

2. The wheel hub bore diameter measuring device according to claim 1, characterized in that, The horizontal conveying assembly includes a first conveying roller group and a second conveying roller group. Along a first horizontal direction, the second conveying roller group is disposed on both sides of the first conveying roller group. The first conveyor roller group includes a first sub-conveyor roller and a second sub-conveyor roller, which are spaced apart along a second horizontal direction, and the clearance opening is provided between the first sub-conveyor roller and the second sub-conveyor roller.

3. The wheel hub bore diameter measuring device according to claim 1, characterized in that, The measuring device includes a contour scanner.

4. The wheel hub bore diameter measuring device according to any one of claims 1 to 3, characterized in that, The positioning element is movably connected to the annular seat along the radial direction of the annular seat.

5. The wheel hub bore diameter measuring device according to claim 4, characterized in that, The hub alignment device further includes a first drive assembly, which drives the positioning member to move radially along the annular seat, so that the positioning member pushes the hub and achieves hub alignment.

6. The wheel hub bore diameter measuring device according to any one of claims 1 to 3, characterized in that, The main frame also includes a wheel outlet, and the wheel hub bore diameter measuring device further includes a pusher device. The pusher device includes a pusher assembly and a second drive assembly. The pusher assembly is located on the side of the horizontal conveying assembly away from the wheel outlet. Along the vertical direction, the pusher assembly is positioned above the horizontal conveying assembly, and the second drive assembly drives the pusher assembly to move along the first horizontal direction to push the measured wheel hub out of the wheel outlet along the horizontal conveying assembly.

7. The wheel hub bore diameter measuring device according to claim 6, characterized in that, The pusher assembly includes a pusher beam and a protective pusher block. The pusher beam is connected to the second drive assembly, and the protective pusher block is connected to the pusher beam and disposed on the side of the pusher beam facing the wheel outlet.

8. The wheel hub bore diameter measuring device according to claim 7, characterized in that, The pusher device further includes a first limiting component, which is connected to the main frame. The first limiting component includes a first limiting member and a second limiting member. The first limiting member is disposed on both sides of the horizontal conveying component away from the clearance opening, and the second limiting member is disposed on the side of the first limiting member away from the clearance opening. The first limiting member and the second limiting member are used to monitor the position of the pusher beam.

9. A method for measuring the diameter of a wheel hub bore, characterized in that, Provide a wheel hub bore diameter measuring device as claimed in any one of claims 1 to 8; A sample ring assembly is provided, comprising a sample ring support and a sample ring having an inner hole, wherein the sample ring support carries the sample ring, and the axis of the sample ring is coaxial with the axis of the sample ring support; Place the sample ring assembly on the hub alignment device; The hub alignment device fixes and aligns the sample ring bracket; The diameter measuring device measures the inner diameter of the sample ring to obtain the measured diameter of the sample ring; The calibration deviation is calculated based on the measured diameter of the sample ring and the inner diameter of the hole. Remove the sample ring assembly from the hub alignment device; Provide the wheel hub to be measured; The hub alignment device is fixed and aligns the hub to be measured; The diameter measuring device measures the hub hole to obtain the measured diameter of the hub hole; The true diameter of the wheel hub hole is obtained by compensation calculation based on the measured diameter of the hub hole and the calibration deviation.

10. The method for measuring the diameter of a wheel hub bore according to claim 9, characterized in that, The diameter measuring device includes a measuring element, which measures the diameter of the hub bore of the wheel hub to be measured, and obtains the measured diameter of the hub bore. The device also includes the following steps: The measuring element is kept at an interval from the hub hole and the measuring element scans the inner wall of the hub hole to be measured to obtain point cloud data. Two opposite circular arc segments along a first direction are extracted from the point cloud data and fitted to a circle to obtain a first diameter; Two opposite circular arc segments along the second direction are cut and circle fitting is performed to obtain the second diameter, wherein the first direction is perpendicular to the second direction; The average of the first diameter and the second diameter is used to obtain the measured diameter of the hub hole.