A logically interconnected intelligent monitoring system and method for wastewater treatment
By establishing a logical interconnection between monitoring videos and process flow topology diagrams in the wastewater treatment system, the problem of cognitive flow interruption caused by operators frequently switching interfaces in the existing system is solved. This enables an efficient decision chain for global process control and parameter adjustment, improving monitoring efficiency and decision quality.
Patent Information
- Application Number
- CN202611390888.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-09
- Publication Date
- 2026-11-17
AI Technical Summary
Existing wastewater treatment monitoring systems cannot realize a complete decision-making chain from macro-level process understanding to micro-level on-site confirmation within a single operating interface. This results in frequent interruptions for operators when switching cognitive tasks, affecting monitoring efficiency and decision-making quality.
By establishing a multi-dimensional logical interconnection between monitoring videos and process flow topology demonstration diagrams, the monitoring videos and process flow can be displayed on the same screen. The node linkage module enables users to retrieve monitoring videos with a click, the parameter association display module updates node status and predicts parameter changes in real time, and the alarm management module monitors anomalies in real time.
Operators can simultaneously obtain global process information and local field information within the same field of view, reducing frequent interruptions in cognitive flow, improving monitoring efficiency and decision-making quality, and reducing environmental risks and economic losses from parameter adjustments.
Smart Images

Figure CN123113546A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of intelligent monitoring technology, and more specifically, to a logically interconnected intelligent monitoring system and method for wastewater treatment. Background Technology
[0002] Electroplating wastewater treatment is an important part of industrial wastewater treatment. Electroplating wastewater has a complex composition and typically contains Cr. 6 The wastewater contains various toxic and harmful substances such as ⁺, Ni²⁺, Cu²⁺, and CN⁻. The treatment process is lengthy and includes multiple parallel treatment lines (such as chromium-containing wastewater treatment lines and cyanide-containing wastewater treatment lines). Each stage requires high parameter precision and carries significant adjustment risks. A complete electroplating wastewater treatment process typically includes multiple treatment units such as equalization tanks, reduction reaction tanks, oxidation reaction tanks, neutralization reaction tanks, coagulation reaction tanks, sedimentation tanks, and filtration tanks, with each unit physically distributed throughout the plant area. In the long-process, multi-stage monitoring scenario of electroplating wastewater treatment, operators need to frequently switch between multiple cognitive tasks such as "grasping the overall process", "viewing the local scene", "adjusting operating parameters" and "confirming alarm information". Existing wastewater treatment monitoring systems deploy cameras at each treatment tank and equipment to collect monitoring videos. Operators are faced with dozens or even hundreds of independent video feeds. Due to the physical dispersion of each treatment tank and the large number of cameras, operators need to frequently switch between multiple video feeds to understand the overall process status. It is impossible to obtain global process information and local scene information simultaneously in the same field of view. Although the monitoring video can truly reflect the scene status, the image itself is fragmented and unstructured, lacking the organizational framework of the process flow. Although some existing solutions integrate the status, instrument data, remote control panels, monitoring audio, and video of various decentralized wastewater treatment devices through B / S configuration units for configuration display, "video monitoring," "process display," "parameter adjustment," and "alarm prompts" are designed as independent subsystems. Each subsystem solves its own local problem, but no consideration has been given to how to organically integrate these subsystems at the user interface level to support the operator's complete cognitive process. There is no node-level mapping relationship between the video and the configuration diagram. Operators cannot directly access the live video of a certain link by clicking on a link in the configuration diagram. Every time an operator switches cognitive tasks, they need to go through an interface jump and attention redirection, resulting in frequent interruptions to the cognitive flow and seriously affecting monitoring efficiency and decision-making quality. In summary, there is an urgent need for a wastewater treatment intelligent monitoring system and method that can organically integrate the on-site realism of video surveillance with a structured panoramic view of the process, enabling operators to achieve a complete decision-making chain from macro-process understanding to micro-on-site confirmation and parameter adjustment prediction within the same operating interface, without interrupting the operator's cognitive flow when switching between each link. Summary of the Invention
[0003] The purpose of this invention is to provide a logically interconnected intelligent monitoring system and method for wastewater treatment. The aim is to establish a multi-dimensional logical interconnection between monitoring videos and process flow topology demonstration diagrams at the display, semantic, operational, and decision-making levels, so that operators can maintain the continuity of cognitive flow within the same operating interface, thereby significantly improving the efficiency and decision-making quality of wastewater treatment monitoring.
[0004] To address the aforementioned technical problems, one objective of this invention is to provide a logically interconnected intelligent monitoring system for wastewater treatment, comprising: The monitoring data acquisition module is used to collect monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. The demonstration diagram generation module is used to generate a process flow topology demonstration diagram based on the treatment tanks involved in the wastewater treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between the nodes. The module also establishes the correspondence between each monitoring video and each node. The display module is used to display the monitoring videos on the first display area of the screen and the process flow topology demonstration diagram on the second display area of the screen, with the first display area and the second display area displayed side by side on the same screen. The parameter association display module is used to dynamically update the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, it allows for custom parameters in the second display area to update the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The module also simulates and demonstrates the operating trend and water quality change trend of the wastewater treatment process in a future preset time period on the process flow topology demonstration diagram in an animated manner. The node linkage module is used to respond to the user's click operation on any node in the process flow topology demonstration diagram, query the corresponding relationship, and highlight the monitoring video corresponding to the node in the first display area; The alarm management module is used to monitor the operating status of each node in real time. When any node is abnormal, an alarm icon is generated at the display location of that node, and the alarm count is updated in the designated area of the demonstration diagram.
[0005] Preferably, the monitoring data acquisition module includes a video acquisition subunit, a parameter acquisition subunit, and a data alignment and preprocessing subunit; The video acquisition subunit is used to continuously acquire on-site monitoring videos of each treatment pool in the sewage treatment process at a preset video acquisition frame rate. Each frame of the monitoring video carries a timestamp of the acquisition time and the node identifier of the corresponding treatment pool. The parameter acquisition subunit is used to continuously acquire the operating parameters and water quality parameters of each treatment pool at a preset parameter sampling frequency. Each parameter data carries a timestamp of the acquisition time and the node identifier of the corresponding treatment pool. The data alignment and preprocessing subunit is used to receive the monitoring video data output by the video acquisition subunit and the parameter data output by the parameter acquisition subunit. It classifies and collects the video data and parameter data of each processing pool according to the node identifier, and performs time axis alignment on the video frames and parameter data belonging to the same processing pool according to the timestamp. It binds the video frames and parameter data with timestamp differences less than a preset threshold into data pairs at the same time. The data after spatiotemporal alignment and preprocessing is written into the real-time database.
[0006] Preferably, the treatment tank includes at least one of the following: a chromium-containing wastewater conditioning tank, a cyanide-containing wastewater conditioning tank, a comprehensive wastewater conditioning tank, a reduction reaction tank, an oxidation reaction tank, a neutralization reaction tank, a coagulation reaction tank, a sedimentation tank, and a filtration tank; the water quality parameters include at least one of the following: heavy metal ion concentration, pH value, ORP value, COD value, and suspended solids concentration.
[0007] Preferably, the demonstration diagram generation module includes a topology generation subunit, a node attribute configuration subunit, and a video mapping and binding subunit; The topology generation subunit is used to obtain the process configuration information of the wastewater treatment process. The process configuration information includes a list of treatment tanks and the process connection relationships between each treatment tank. Based on the process configuration information, an initial topology of the process flow topology demonstration diagram is automatically generated using a hierarchical layout algorithm based on graph theory. The initial topology includes several nodes and directed lines between the nodes. Each node corresponds to a treatment tank. The direction of the directed lines represents the process flow direction and the medium flow direction. When the wastewater treatment process includes two or more parallel treatment lines, the nodes of each parallel line are arranged in parallel in the demonstration diagram and converge at the merging node through the directed lines. The node attribute configuration subunit is used to configure a unique list of monitoring parameters for each node. The list of monitoring parameters is determined based on the function of the treatment tank corresponding to the node in the process flow and the reaction process involved. The list of monitoring parameters includes operating parameters and water quality parameters. The video mapping and binding subunit is used to obtain the video channel information of each monitoring video, match each monitoring video with the corresponding node, establish and store the one-to-one correspondence between each monitoring video and each node, and generate a video channel-node mapping table.
[0008] Preferably, when the initial topology of the process flow topology demonstration diagram is automatically generated in the topology generation subunit based on the process configuration information using a hierarchical layout algorithm of graph theory, the following steps are included: Each treatment pool is used as a vertex in the graph model, and the process connection relationships between the treatment pools are used as directed edges in the graph model to construct a directed graph model of the wastewater treatment process. The directed graph model is topologically sorted to determine the hierarchical position of each vertex in the process flow, wherein vertices in parallel lines are assigned to parallel hierarchical tracks, and merging nodes are the intersection points of two or more parallel tracks. Based on the hierarchical position and the directed edge relationships between each vertex, the layout coordinates of each vertex in the demonstration diagram are calculated to generate the initial topology.
[0009] Preferably, the video mapping binding subunit further includes a mapping verification subunit, used to display a video status indicator light in the vicinity of each node in the demonstration diagram after the video channel-node mapping table is established. The color of the video status indicator light indicates the mapping status between the node and the corresponding monitoring video, wherein: The first color indicates that the node has been successfully bound to one monitoring video and the video stream is normal; the second color indicates that the node has not been bound to a video or the video stream is abnormal.
[0010] Preferably, the parameter association display module includes a color dynamic update subunit, a parameter display and adjustment subunit, and a simulation pre-play subunit; The color dynamic update subunit is used to obtain the real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module, and dynamically update the display color of the corresponding node in the process flow topology demonstration diagram according to the operating parameters and water quality parameters of each node. The display color simultaneously encodes two dimensions of information of the node: equipment operating status and water quality treatment status. The equipment operating status is determined according to the operating parameters, and the water quality treatment status is determined according to the water quality parameters. Different color codes correspond to different combinations of equipment operating status and water quality treatment status. The parameter display and adjustment subunit is used to display the operating parameters and water quality parameters of each node in real time at the corresponding position of each node in the process flow topology demonstration diagram, so that the operating parameters and water quality parameters are visually associated with the node status, and to update the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The simulation pre-run subunit is used to respond to parameter adjustment operations. Based on the adjusted parameters and the preset wastewater treatment process simulation model, it calculates the predicted parameter values of each node in the future preset time period. Based on the predicted parameter values, it displays the medium flow state between each node in a flow animation on the process flow topology demonstration diagram and shows the water quality change trend of each node in a gradient transition of node color. At the same time, it synchronously drives the color dynamic update subunit to update the display color of the node, so that the operator can evaluate.
[0011] Preferably, the node linkage module includes an event capture subunit, a mapping query subunit, and a video positioning subunit; The event capture subunit is used to listen for and capture the user's click operation on the node on the process flow topology demonstration diagram, and identify the node identifier of the clicked node. The mapping query subunit is used to query the video channel-node mapping table with the node identifier as the index to obtain the video stream address of the monitoring video corresponding to the node. The video channel-node mapping table stores a one-to-one correspondence between each node identifier and the video stream address of each monitoring video in advance. The video positioning subunit is used to locate the target video sub-window corresponding to the video stream address in multiple video sub-windows in the first display area according to the video stream address, and send a highlighting instruction to the display module to perform a highlighting operation on the target video sub-window in the first display area, so that the monitoring video corresponding to the node is highlighted in the first display area. The highlighting shall be achieved by at least one of the following methods: enlarging the image of the target video sub-window, adding a highlight border around the image of the target video sub-window, or placing the image of the target video sub-window on top of other video sub-windows.
[0012] Preferably, the alarm management module includes a data acquisition and judgment subunit, an alarm identifier generation subunit, an alarm counting and statistics subunit, and an alarm linkage triggering subunit; The data acquisition and judgment subunit is used to acquire the real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module at a preset detection cycle, compare the real-time value of each parameter with the preset threshold range, and determine that the node is abnormal when any parameter exceeds the corresponding threshold range, and generate an abnormal record containing node identifier, abnormal parameter, real-time value, threshold range and alarm level. The alarm identifier generation subunit is used to generate an alarm identifier at the display position of the corresponding node in the process flow topology demonstration diagram based on the abnormal record. The alarm identifier is superimposed on the node, and the display method of the alarm identifier corresponds to the alarm level. Different alarm levels correspond to different colors and dynamic features. The alarm counting and statistics subunit is used to update the number of alarms in real time in a designated area of the demonstration diagram. The number of alarms includes at least the total number of alarms and the detailed statistics classified by alarm level. The alarm linkage triggering subunit is used to send an automatic push instruction to the node linkage module according to the abnormal record. The automatic push instruction includes the node identifier and triggers the node linkage module to highlight the monitoring video corresponding to the node in the first display area.
[0013] The second objective of this invention is to provide a logically interconnected intelligent monitoring method for wastewater treatment, applicable to any of the logically interconnected intelligent monitoring systems for wastewater treatment described above, comprising the following steps: S1. The monitoring data acquisition module collects monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. S2. The demonstration diagram generation module generates a process flow topology demonstration diagram based on the treatment tanks involved in the wastewater treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between nodes. The correspondence between each monitoring video and each node is established. S3. The monitoring videos are displayed on the first display area of the screen through the display module, and the process flow topology demonstration diagram is displayed on the second display area of the screen. The first display area and the second display area are displayed side by side on the same screen. S4. The parameter association display module dynamically updates the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, the module displays custom parameters in the second display area and updates the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The module also simulates the operating trend and water quality change trend of the wastewater treatment process in the future preset time period on the process flow topology demonstration diagram in an animated manner. S5. The node linkage module responds to the user's click operation on any node in the process flow topology demonstration diagram, queries the corresponding relationship, and highlights the monitoring video corresponding to the node in the first display area. S6. The alarm management module monitors the operating status of each node in real time. When any node is abnormal, an alarm sign is generated at the display position of that node, and the alarm count is updated in the designated area of the demonstration diagram.
[0014] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention utilizes the collaborative work of a monitoring data acquisition module and a demonstration diagram generation module. The demonstration diagram generation module abstracts the processing pools scattered throughout the plant area into nodes of a process flow topology demonstration diagram. The display module displays the monitoring video and the process flow topology demonstration diagram side-by-side on the same screen in the first and second display areas. This allows operators to see the actual scene and grasp the entire process operation logic within the same line of sight. At the same time, the node linkage module establishes an interactive channel between the demonstration diagram nodes and the monitoring video, enabling the target video to be identified at a glance in the multi-grid layout. Operators can see the scene and understand the process and location. Meanwhile, the parameter adjustment function is directly integrated into the demonstration diagram interface. The parameter association display module displays the key parameter values of each node in the vicinity of the node in the form of numerical labels. Based on the adjusted parameters and the preset wastewater treatment process simulation model, the parameter value change curve is predicted. Based on the predicted parameter values, the medium flow state between each node is displayed on the demonstration diagram in a flowing animation. The color dynamic update sub-unit is driven synchronously to display the water quality change trend of each node with the node color gradient. A time progress bar is displayed at the top of the demonstration diagram to show the current position on the simulation timeline. By observing the flowing animation and node color changes on the demonstration diagram, operators can intuitively see the predicted water quality change trend of each node using the adjusted parameters. This allows operators to verify the effect of parameter adjustment in the virtual environment first, and then implement it in the actual system after confirming its feasibility. This avoids environmental risks and economic losses caused by improper parameter adjustment from the source. Attached Figure Description
[0015] Figure 1 This is a block diagram illustrating the overall structural principle of the present invention; Figure 2 This is a schematic diagram illustrating the overall functionality of the present invention. Detailed Implementation
[0016] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0017] Example 1
[0018] like Figures 1-2 As shown, one of the objectives of this invention is to provide a logically interconnected intelligent monitoring system for wastewater treatment, including a monitoring data acquisition module, a demonstration diagram generation module, a display module, a parameter association display module, a node linkage module, and an alarm management module, specifically as follows: Figure 1 As shown: Firstly, the monitoring data acquisition module is used to collect monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. Furthermore, the monitoring data acquisition module includes a video acquisition subunit, a parameter acquisition subunit, and a data alignment and preprocessing subunit; The video acquisition subunit is used to continuously acquire on-site monitoring videos of each treatment pool in the sewage treatment process at a preset video acquisition frame rate (such as once every 1-2 seconds). Each frame of each monitoring video carries a timestamp of the acquisition time and the node identifier of the corresponding treatment pool. Specifically, network cameras are deployed at each treatment pool and key equipment, and the cameras continuously acquire real-time monitoring videos of the site. The parameter acquisition subunit is used to continuously collect the operating parameters and water quality parameters of each treatment pool at a preset parameter sampling frequency (such as once every 1-2 seconds). Each parameter data carries a timestamp of the collection time and the node identifier of the corresponding treatment pool. That is, each video and each set of parameters is assigned a node identifier. This establishes a hard node-level mapping relationship that exists from the data source, rather than a soft integration achieved by manual association at the display layer. This provides a fundamental guarantee of data structure for the subsequent implementation of clicking on nodes to watch videos. The data alignment and preprocessing subunit receives monitoring video data output from the video acquisition subunit and parameter data output from the parameter acquisition subunit. It categorizes and aggregates the video and parameter data from each processing pool according to node identifiers, and performs timeline alignment on video frames and parameter data belonging to the same processing pool according to timestamps. Video frames and parameter data with timestamp differences less than a preset threshold are bound as data pairs at the same time. The data after spatiotemporal alignment and preprocessing is written to the real-time database, achieving millisecond-level alignment between video frames and parameter data. This ensures data consistency for subsequent logical interconnection and display. On the other hand, any downstream module can quickly retrieve the complete information of a node at a given time from the database using the node identifier and timestamp.
[0019] Specifically, the electroplating production process generates various types of wastewater, mainly including three categories: chromium-containing wastewater, cyanide-containing wastewater, and mixed wastewater. These three types of wastewater differ in composition, treatment mechanisms, corresponding treatment tanks, and water quality monitoring parameters. The chromium-containing wastewater treatment line sequentially passes through: chromium-containing wastewater equalization tank → reduction reaction tank → neutralization reaction tank → coagulation reaction tank → sedimentation tank; the cyanide-containing wastewater treatment line sequentially passes through: cyanide-containing wastewater equalization tank → primary oxidation tank → secondary oxidation reaction tank → neutralization reaction tank → coagulation reaction tank → sedimentation tank. The two lines converge at the neutralization reaction tank and then pass through subsequent treatment units, finally passing through a filtration tank before being discharged in compliance with standards. Therefore, if... Figure 2The partial demonstration shows that the treatment tanks include at least one of the following: a chromium-containing wastewater equalization tank, a cyanide-containing wastewater equalization tank, a combined wastewater equalization tank, a reduction reaction tank, an oxidation reaction tank, a neutralization reaction tank, a coagulation reaction tank, a sedimentation tank, and a filtration tank; the water quality parameters include at least one of the following: heavy metal ion concentration, pH value, ORP value, COD value, and suspended solids concentration. Among these, pH value directly affects the efficiency of subsequent reduction reactions and the dosage of reducing agent. Monitoring the pH value can determine whether the influent is within the preset range, providing feedforward information for pH adjustment in subsequent reduction reaction tanks. The characteristic pollutants of heavy metal ion concentration wastewater can be used to calculate the accurate dosage of reducing agent, avoiding waste or insufficient dosage. The ORP value is the most critical parameter reflecting the progress of the reduction reaction. During the reduction reaction, as the chromium ion concentration increases... 6 When ⁺ is reduced to Cr³⁺, the redox potential of the system will change from a high potential (Cr⁺). 6 When the potential of the ⁺ / Cr³⁺ redox couple drops from approximately +1.33V to a low potential, the completeness of the reduction reaction can be determined by real-time monitoring of the ORP value. When the ORP value drops to a set threshold (e.g., below 300mV), it indicates that Cr... 6 The ORP value has been fully restored, and the dynamic changes in the ORP value provide real-time feedback for the precise control of the reducing agent dosage. The influent suspended solids concentration in the coagulation reaction tank reflects the effect of the previous treatment, while the effluent suspended solids concentration reflects the coagulation reaction effect. The difference between the influent and effluent suspended solids concentrations (removal rate) is a direct basis for judging whether the coagulant dosage is appropriate and whether the coagulation effect is good. The COD value reflects the content of organic pollutants in the water body. The COD value of the effluent from the filter tank (especially the effluent from the activated carbon filter tank) can reflect the effect of organic matter adsorption and removal. The matching relationship between the above treatment tanks and water quality parameters is not set arbitrarily, but is determined based on the inherent logic of the chemical and physical principles of electroplating wastewater treatment. This is known to those skilled in the art and will not be elaborated here.
[0020] Secondly, the demonstration diagram generation module is used to generate a process flow topology demonstration diagram based on the treatment tanks involved in the sewage treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between nodes. It also establishes the correspondence between each monitoring video and each node. Furthermore, the demonstration diagram generation module includes a topology generation subunit, a node attribute configuration subunit, and a video mapping binding subunit; The topology generation sub-unit is used to obtain the process configuration information of the wastewater treatment process. This information can be entered by operators during system initialization or imported from external design files (such as digital descriptions of process design drawings). The process configuration information includes a list of treatment tanks and the process connections between them. Based on this information, a hierarchical layout algorithm based on graph theory is used to automatically generate the initial topology of the process flow topology demonstration diagram. The initial topology contains several nodes and directed connections between them. Each node corresponds to a treatment tank, and the direction of the directed connections indicates the process flow direction and the direction of media flow. When the wastewater treatment process includes two or more parallel treatment lines, the nodes of each parallel line are arranged in parallel in the demonstration diagram and converge at the meeting point via directed connections. This transforms the demonstration diagram from manual drawing to data-driven generation, facilitating the automatic construction, layout, and rendering of the diagram based on structured process configuration information. When the process changes, only the process configuration information needs to be modified to automatically regenerate the demonstration diagram, significantly reducing the system's deployment and maintenance costs. When automatically generating the initial topology of the process flow topology demonstration diagram using a hierarchical layout algorithm based on graph theory according to the process configuration information in the topology generation sub-unit, the following steps are included: Each treatment tank is treated as a vertex in the graph model, and the process connections between the treatment tanks are treated as directed edges in the graph model to construct a directed graph model of the wastewater treatment process. The directed graph model is topologically sorted to determine the hierarchical position of each vertex in the process flow. Vertices in parallel lines are assigned to parallel hierarchical tracks, and merging nodes are the intersection points of two or more parallel tracks. Based on the hierarchical position and the directed edge relationships between vertices, the layout coordinates of each vertex in the demonstration graph are calculated to generate the initial topology.
[0021] The node attribute configuration subunit is used to configure a unique list of monitoring parameters for each node. This list is determined based on the function of the treatment tank corresponding to the node in the process flow and the reaction processes involved. The monitoring parameter list includes operating parameters and water quality parameters. Preferably, when the treatment tank corresponding to the node is an equalization tank, the monitoring parameter list includes at least pH value, characteristic pollutant concentration, and flow rate; when the treatment tank corresponding to the node is a reaction tank, the monitoring parameter list includes at least pH value, oxidation-reduction potential value, and target pollutant concentration; when the treatment tank corresponding to the node is a sedimentation tank, the monitoring parameter list includes at least suspended solids concentration, heavy metal ion concentration, and pH value ... When the treatment tank is a filtration tank, the monitoring parameter list should at least include suspended solids concentration, chemical oxygen demand (COD), and pH value. Furthermore, when the node attribute configuration subunit configures its own monitoring parameter list for each node, the parameters in the monitoring parameter list of the same node form a complete monitoring chain of "reaction condition parameter - reaction process parameter - treatment effect parameter." pH value is a reaction condition parameter, used to indicate whether the chemical reaction corresponding to that node has suitable acidity or alkalinity conditions; redox potential value is a reaction process parameter, used to reflect the progress of the chemical reaction corresponding to that node in real time; and target pollutant concentration is a treatment effect parameter, used to determine whether the treatment corresponding to that node has achieved the predetermined target. In summary, the node attribute configuration subunit configures unique parameters for each node, making each node in the demonstration diagram not only a "graphic symbol" but also a "data container carrying rich process semantics." This configuration provides a precise data foundation for subsequent dynamic color updates (determining colors based on node-specific parameters), parameter display and adjustment (displaying unique parameters next to nodes), simulation and pre-running (performing chemometric calculations based on unique parameters), and alarm management (judging anomalies based on thresholds of unique parameters).
[0022] The video mapping and binding sub-unit is used to obtain the video channel information of each monitoring video, match each monitoring video with the corresponding node, establish and store the one-to-one correspondence between each monitoring video and each node, and generate a video channel-node mapping table. Each record in the video channel-node mapping table includes: node identifier, node name, camera identifier and video stream address. The mapping table is stored in persistent storage medium for real-time querying by the node linkage module, alarm management module and display module. This makes the video no longer an unstructured image stream, but structured information with process flow semantics. Each video knows which processing pool it belongs to, thus providing a fundamental data-level guarantee for subsequent click-to-view video interaction. Furthermore, the video mapping binding subunit also includes a mapping verification subunit, used to display video status indicator lights in the vicinity of each node in the demonstration diagram after the video channel-node mapping table is established. The color of the video status indicator light indicates the mapping status between the node and the corresponding monitoring video, wherein: The first color indicates that the node has been successfully bound to a monitoring video and the video stream is normal. The second color indicates that the node has not been bound to a video or the video stream is abnormal. When an operator clicks on a node expecting to see the corresponding video but there is no response or an error is displayed, the operator cannot determine whether "the node is not configured with a video" or "there is a video but the video stream has a problem". The mapping verification subunit presents the two status information of whether the node has a video bound and whether the video is normal directly on the node in the form of indicator lights, making the mapping relationship explicit. The operator can grasp the overall status of the video mapping of the entire system at a glance at the demonstration diagram.
[0023] Thirdly, the display module displays each monitoring video in the first display area of the screen, allowing operators to view the real-time images of all treatment pools simultaneously. The dynamic layout automatically adapts to different video channels without manual arrangement. The process flow topology demonstration diagram is displayed in the second display area of the screen, presenting the sewage treatment process to the operators in an intuitive way. The color of the nodes reflects the operating status in real time (driven by the color dynamic update module), allowing operators to grasp the overall status of the entire process at a glance. The first and second display areas are displayed side by side on the same screen. Fourth, the parameter association display module is used to dynamically update the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, it allows users to customize parameters in the second display area, update the set values of operating parameters and water quality parameters in response to user parameter adjustment operations, and simulate the operation trend and water quality change trend of the sewage treatment process in a future preset time period on the process flow topology demonstration diagram in an animated manner. Furthermore, the parameter association display module includes a color dynamic update subunit, a parameter display and adjustment subunit, and a simulation pre-play subunit; The color dynamic update subunit is used to obtain real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module. Based on these parameters, it dynamically updates the display color of the corresponding node in the process flow topology demonstration diagram. The display color simultaneously encodes two dimensions of information for that node: equipment operating status and water quality treatment status. Equipment operating status is determined by operating parameters, and water quality treatment status is determined by water quality parameters. Different color codes correspond to different combinations of equipment operating status and water quality treatment status, upgrading the demonstration diagram from a static graphic to a real-time status mapping diagram. Operators can grasp the entire process operation status simply by viewing the demonstration diagram. The specific principle of the color dynamic update subunit is as follows: The latest operating parameters and water quality parameters of each node are obtained from the real-time database of the monitoring data acquisition module at a preset refresh frequency (e.g., once every 1 second). First, the operating status of the node is determined based on the operating parameters (e.g., equipment current, voltage, operating signals, etc.). If the equipment operating current is within the rated range and the operating signal is "ON", it is determined to be "normal operation". If the equipment operating current is zero and the operating signal is "OFF", it is determined to be "shutdown". If the equipment is in maintenance mode or the operating signal is "MAINTENANCE", it is determined to be "under maintenance". Then, the water quality treatment status of the node is determined based on the water quality parameters. The determination logic varies depending on the node type. For equalization tank nodes, it is based on the concentration of characteristic pollutants (Cr). 6 Water quality status is determined by whether the concentration of Cr⁻, CN⁻, etc., is within a preset threshold range. Below the warning value, it is considered "compliant"; reaching the warning value but not exceeding the standard is considered "warning"; exceeding the standard value is considered "exceeding the standard". For reaction tank nodes, the water quality status is determined based on the target pollutant concentration (Cr⁻). 6 The treatment effect is determined by the concentration of pollutants (such as ⁺ and CN⁻). A concentration below the emission standard is considered "compliant," close to but not exceeding the standard is considered "warning," and exceeding the standard is considered "exceeding the standard." Simultaneously, pH and ORP values are used to determine if the reaction conditions are normal. For sedimentation tanks, a comprehensive judgment is made based on whether the concentrations of heavy metal ions and suspended solids are within the acceptable range. For filtration tanks, a comprehensive judgment is made based on whether the concentrations of suspended solids, COD, and pH are within the acceptable range. The display color of each node is determined according to a preset color coding scheme. This scheme uses a single color to convey information on both the equipment's operating status and the water treatment status, creating a gradient color spectrum from "normal" to "abnormal" using green, yellow, orange, and red. Green represents the optimal state, yellow "needs attention," orange "exceeds the standard," and red "severely abnormal." Operators can obtain information on both dimensions at a glance from the demonstration diagram, without needing to check two separate "equipment status indicators" and "water quality status indicators." The parameter display and adjustment subunit is used to display the operating parameters and water quality parameters of each node in real time at the corresponding position in the process flow topology demonstration diagram. This creates a visual association between the operating parameters and water quality parameters and the node status. It also updates the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation, migrating the parameter adjustment operation from a separate parameter setting interface to the demonstration diagram interface. This eliminates the cognitive interruption caused by interface switching. Specifically, a semi-transparent numerical label is generated in the vicinity of each node (usually to the right or below the node). The label displays the name of the node's key parameters and their current values in text form. The background color of the numerical label is consistent with or gradually transitions to the display color of the node, creating a visual association between the parameter values and the node status. Operators can intuitively associate the parameter values with the overall status of the node while viewing them. When adjusting parameters, users can trigger the parameter setting panel by clicking the parameter value label next to the node. The parameter setting panel is displayed overlaid on the demonstration diagram interface in the form of a modal dialog box or side panel, without covering the main area of the demonstration diagram. The parameter setting panel lists all adjustable parameters of the node (such as pH setting value, dosage setting value, flow rate setting value, etc.). Each parameter displays the current value and adjustable range. Users can adjust the parameter setting value through the slider, numeric input box or increase / decrease buttons (+ / -). During the adjustment process, the panel will display the adjusted value in real time, so that the operator can see the visual feedback of parameter adjustment without leaving the demonstration diagram interface. The simulation pre-run subunit is used to respond to parameter adjustment operations. Based on the adjusted parameters and the preset wastewater treatment process simulation model, it calculates the predicted parameter values of each node within a preset time period. Based on these predicted parameter values, it displays the media flow state between nodes in a flow animation on the process flow topology demonstration diagram, and uses a gradient color transition of the nodes to show the water quality change trend. Simultaneously, it drives the color dynamic update subunit to update the display color of the nodes, allowing operators to evaluate and virtually verify the effect of parameter adjustments before actual execution, significantly reducing trial-and-error costs. The specific principle is as follows: When the parameter display and adjustment subunit detects a user's parameter adjustment operation, it sends a trigger signal to the simulation pre-run subunit and transmits the adjusted parameter values (including the adjusted parameter name, new setting value, adjustment time, etc.). It obtains the real-time parameter values of each node from the real-time database of the monitoring data acquisition module as the initial state of the simulation pre-run. It obtains the directed connection relationship between each node (predecessor / successor node list) from the demonstration diagram generation module to determine the propagation path of the parameter adjustment effect in the process flow. Based on the type of adjusted parameter and the node it is located in, it determines the key focus area of the simulation pre-run. If the adjustment is the dosage of the reduction reaction tank, the key focus area of the simulation is all downstream nodes from the reduction reaction tank to the final discharge outlet. Based on the adjusted parameters and the preset wastewater treatment process simulation model, it calculates the predicted parameter values of each node in the future preset time period. Among them, the wastewater treatment process simulation model is a machine learning model (such as neural networks, random forests, or support vector regression) trained on historical operating data. This type of model can predict the effect of parameter adjustment by learning the mapping relationship between input parameter adjustment and output water quality change in historical data. The data-driven model and the mechanism model can work together. The mechanism model provides prior constraints on the physicochemical process, and the data-driven model learns empirical rules from the data. The two are integrated to form a gray box model, which has both physical interpretability and data fitting accuracy. This is a mapping relationship training model known to those in the technical field, and will not be described in detail here. The real-time operating parameters and water quality parameters of each node are used as initial conditions. The operating parameters and water quality parameters adjusted by the user are input into the wastewater treatment process simulation model. According to the process flow direction (along the directed connection from the upstream node to the downstream node), the predicted parameter values of each node in a preset time period (preferably 2 hours) are output sequentially, and the change curve is calculated. The calculation time step is set to 1 minute, that is, to simulate the predicted parameter values of each node every minute in the next 120 minutes. For parallel lines (including chromium lines and cyanide lines) in electroplating wastewater treatment. The simulation calculates the predicted parameter changes for the two lines separately, and mixes the two treated wastewater streams at the merging node. Based on the predicted calculation results, the simulation demonstrates the operating trend and water quality change trend within a preset time period using animation on the process flow topology demonstration diagram. After the simulation (or at any time during the simulation), the operator evaluates the simulation effect. If the simulation results show an improving water quality trend (node colors gradually return to green, pollutant concentrations gradually decrease, and various indicators approach compliance), the operator can click the "Confirm and Send" button. The simulation subunit will then send the adjusted parameters to the corresponding field equipment (such as dosing pumps, valves, mixers, etc.) through the system's control execution layer, completing a full closed loop from "parameter adjustment" to "effect prediction" to "actual execution." If the simulation results show a deteriorating water quality trend (node colors further deepen to orange or red, pollutant concentrations increase, and indicators continue to exceed standards), the operator can cancel the current adjustment or continue adjusting the parameters and re-perform the simulation until the optimal parameter setting scheme is found, avoiding improper parameter adjustment that could lead to the entire batch of wastewater exceeding standards, causing serious environmental risks and economic losses.
[0024] Fifth, the node linkage module is used to respond to the user's click operation on any node in the process flow topology demonstration diagram, query the corresponding relationship, and highlight the monitoring video corresponding to the node in the first display area; Furthermore, the node linkage module includes an event capture subunit, a mapping query subunit, and a video positioning subunit; The event capturing subunit is used to listen for and capture user clicks on nodes in the process flow topology demonstration diagram, and identify the node identifier of the clicked node. When the user performs mouse operations on the demonstration diagram, the browser or graphics rendering engine will generate corresponding DOM events or graphics events. The event capturing subunit captures these events through registered listeners. If the user clicks on a blank area, directed line, or background element of the demonstration diagram, the event is ignored and node linkage is not triggered. After confirming that the target of the click event is a valid node, the node identifier, node name, and node type are extracted, realizing an instant response that is triggered upon click. The mapping query subunit is used to query the video channel-node mapping table using the node identifier as an index to obtain the video stream address of the monitoring video corresponding to the node. The video channel-node mapping table pre-stores a one-to-one correspondence between each node identifier and the video stream address of each monitoring video. Each record in the video channel-node mapping table contains the node identifier, node name, camera identifier, and video stream address. The unit accesses the mapping table through a standardized data access interface (such as SQL query or key-value pair query). The query time complexity is O(1) (using hash index), ensuring that millisecond-level query response can still be achieved in scenarios with large-scale nodes (tens to hundreds of processing pools), realizing efficient data retrieval from node click to video location. The video positioning subunit is used to locate the target video sub-window corresponding to the video stream address in multiple video sub-windows in the first display area according to the video stream address, and send a highlighting instruction to the display module to perform a highlighting operation on the target video sub-window in the first display area, so that the monitoring video corresponding to the node is highlighted in the first display area. By accurately matching the video stream address in multiple video sub-windows, it ensures that the correct video image is highlighted after clicking the node, rather than a video from another processing pool with a similar image. The highlighting method should employ at least one of the following approaches: magnifying the target video sub-window, adding a highlighted border around the target video sub-window, or placing the target video sub-window on top of other video sub-windows. Alternatively, a combination of these three methods can be used to maximize the highlighting effect, eliminating the need for operators to painstakingly search through numerous video screens. The target video will automatically appear before the operator's eyes, allowing them to clearly track their viewing path.
[0025] Sixth, the alarm management module is used to monitor the operating status of each node in real time. When any node is abnormal, an alarm icon is generated at the display position of that node, and the number of alarms is updated in the designated area of the demonstration diagram.
[0026] Furthermore, the alarm management module includes a data acquisition and judgment subunit, an alarm identifier generation subunit, an alarm counting and statistics subunit, and an alarm linkage triggering subunit; The data acquisition and judgment subunit is used to acquire real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module at a preset detection cycle. It compares the real-time values of each parameter with preset threshold ranges. When any parameter exceeds the corresponding threshold range, it determines that the node has an anomaly and generates an anomaly record containing the node identifier, the anomaly parameter, the real-time value, the threshold range, and the alarm level. The preset threshold range is an absolute threshold set based on national or local emission standards, such as the Cr standard in the electroplating industry. 6 The emission standard is 0.5 mg / L, when the real-time Cr... 6 An alarm is triggered when the concentration of ⁺ exceeds 0.5 mg / L. Based on the operating threshold set according to process control requirements, for example, the endpoint threshold of the ORP value of the reduction reaction tank is 300 mV. When the ORP value does not drop below 300 mV, it indicates that the reduction reaction is insufficient. Based on the emission standard threshold or process control threshold, a certain percentage of warning value (such as 80% of the standard value) is set to trigger the warning in advance. Through continuous and automated threshold comparison, real-time monitoring of the operating status of each node in the entire process is realized without the need for manual checking of parameter values one by one. The alarm identifier generation subunit generates alarm identifiers at the corresponding node display positions in the process flow topology demonstration diagram based on anomaly records. The alarm identifiers are overlaid on the nodes, and their display method corresponds to the alarm level. Different alarm levels correspond to different colors and dynamic features. Specifically, the alarm identifier generation subunit determines the alarm identifier display type based on the alarm level in the anomaly data transmitted by the data acquisition and judgment subunit, including: Emergency Alarm: Use a flashing red exclamation mark (!) or a red bouncing dot, flashing rapidly (e.g., flashing twice per second), in conjunction with a red halo effect; Important alarm: Use an orange exclamation mark or orange dot, flashing at a medium frequency (e.g., once per second). General alarms: use a yellow exclamation mark or yellow dot, flashing slowly (e.g., once every 2 seconds) or display statically; Different types of alarm signs have significant visual differences, enabling operators to quickly determine the severity of the alarm by the color and dynamic characteristics of the signs; The alarm counting and statistics subunit is used to update the alarm count in real time in a designated area of the demonstration diagram. The alarm count includes at least the total number of alarms and the detailed statistics classified by alarm level. The alarm counting and statistics subunit maintains a global alarm counter to record the total number of all unresolved alarms in the current system. The counter is incremented by 1 whenever the data acquisition and judgment subunit generates a new anomaly record; the counter is decremented by 1 whenever the alarm tag generation subunit removes an alarm tag. The alarm counter is further subdivided by alarm level to count the number of emergency alarms, important alarms, and general alarms, so that operators can understand the distribution of alarms of different severity levels. The display location is the upper right corner or top status bar of the demonstration diagram, which displays "Total Alarms: X" in the form of a numerical label. The alarm linkage trigger subunit is used to send automatic push instructions to the node linkage module based on the abnormal records. The automatic push instructions include the node identifier. The trigger node linkage module highlights the monitoring video corresponding to the node in the first display area. When an alarm occurs, the operator does not need to "discover the alarm → locate the node on the flowchart → switch to the video interface to find the corresponding screen". The positioning and switching steps can be completed automatically. The operator only needs to move his eyes to the already highlighted video screen to confirm the situation on site, which shortens the alarm response and improves the degree of automation.
[0027] The second objective of this invention is to provide a logically interconnected intelligent monitoring method for wastewater treatment, applicable to any of the logically interconnected intelligent monitoring systems for wastewater treatment described above, comprising the following steps: S1. The monitoring data acquisition module collects monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. S2. The demonstration diagram generation module generates a process flow topology demonstration diagram based on the treatment tanks involved in the wastewater treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between nodes. The correspondence between each monitoring video and each node is established. S3. The monitoring videos are displayed on the first display area of the screen through the display module, and the process flow topology demonstration diagram is displayed on the second display area of the screen. The first display area and the second display area are displayed side by side on the same screen. S4. The parameter association display module dynamically updates the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, the module displays custom parameters in the second display area and updates the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The module also simulates the operating trend and water quality change trend of the wastewater treatment process in the future preset time period on the process flow topology demonstration diagram in an animated manner. S5. The node linkage module responds to the user's click operation on any node in the process flow topology demonstration diagram, queries the corresponding relationship, and highlights the monitoring video corresponding to the node in the first display area. S6. The alarm management module monitors the operating status of each node in real time. When any node is abnormal, an alarm sign is generated at the display position of that node, and the alarm count is updated in the designated area of the demonstration diagram.
[0028] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely preferred examples and are not intended to limit the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of protection of the present invention is defined by the appended claims and their equivalents.
Claims
1. A logically interconnected intelligent monitoring system for wastewater treatment, characterized in that, include: The monitoring data acquisition module is used to collect monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. The demonstration diagram generation module is used to generate a process flow topology demonstration diagram based on the treatment tanks involved in the wastewater treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between the nodes. The module also establishes the correspondence between each monitoring video and each node. The display module is used to display the monitoring videos on the first display area of the screen and the process flow topology demonstration diagram on the second display area of the screen, with the first display area and the second display area displayed side by side on the same screen. The parameter association display module is used to dynamically update the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, it allows for custom parameters in the second display area to update the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The module also simulates and demonstrates the operating trend and water quality change trend of the wastewater treatment process in a future preset time period on the process flow topology demonstration diagram in an animated manner. The node linkage module is used to respond to the user's click operation on any node in the process flow topology demonstration diagram, query the corresponding relationship, and highlight the monitoring video corresponding to the node in the first display area; The alarm management module is used to monitor the operating status of each node in real time. When any node malfunctions, an alarm flag is generated at the display location of that node, and the alarm count is updated in the designated area of the demonstration diagram.
2. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 1, characterized in that: The monitoring data acquisition module includes a video acquisition subunit, a parameter acquisition subunit, and a data alignment and preprocessing subunit. The video acquisition subunit is used to continuously acquire on-site monitoring videos of each treatment pool in the sewage treatment process at a preset video acquisition frame rate. Each frame of each monitoring video carries a timestamp of the acquisition time and the node identifier of the corresponding treatment pool. The parameter acquisition subunit is used to continuously acquire the operating parameters and water quality parameters of each treatment pool at a preset parameter sampling frequency. Each parameter data carries a timestamp of the acquisition time and the node identifier of the corresponding treatment pool. The data alignment and preprocessing subunit is used to receive the monitoring video data output by the video acquisition subunit and the parameter data output by the parameter acquisition subunit, classify and collect the video data and parameter data of each processing pool according to the node identifier, and perform time axis alignment on the video frames and parameter data belonging to the same processing pool according to the timestamp, and bind the video frames and parameter data with timestamp differences less than a preset threshold into data pairs at the same time. Data that has undergone spatiotemporal alignment and preprocessing is written into a real-time database.
3. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 2, characterized in that: The treatment tank includes at least one of the following: a chromium-containing wastewater conditioning tank, a cyanide-containing wastewater conditioning tank, a comprehensive wastewater conditioning tank, a reduction reaction tank, an oxidation reaction tank, a neutralization reaction tank, a coagulation reaction tank, a sedimentation tank, and a filtration tank; the water quality parameters include at least one of the following: heavy metal ion concentration, pH value, ORP value, COD value, and suspended solids concentration.
4. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 2, characterized in that: The demonstration diagram generation module includes a topology generation subunit, a node attribute configuration subunit, and a video mapping and binding subunit. The topology generation subunit is used to obtain the process configuration information of the wastewater treatment process. The process configuration information includes a list of treatment tanks and the process connection relationships between each treatment tank. Based on the process configuration information, an initial topology of the process flow topology demonstration diagram is automatically generated using a hierarchical layout algorithm based on graph theory. The initial topology includes several nodes and directed lines between the nodes. Each node corresponds to a treatment tank. The direction of the directed lines represents the process flow direction and the medium flow direction. When the wastewater treatment process includes two or more parallel treatment lines, the nodes of each parallel line are arranged in parallel in the demonstration diagram and converge at the merging node through the directed lines. The node attribute configuration subunit is used to configure a unique list of monitoring parameters for each node. The list of monitoring parameters is determined based on the function of the treatment tank corresponding to the node in the process flow and the reaction process involved. The list of monitoring parameters includes operating parameters and water quality parameters. The video mapping and binding subunit is used to obtain the video channel information of each monitoring video, match each monitoring video with the corresponding node, establish and store the one-to-one correspondence between each monitoring video and each node, and generate a video channel-node mapping table.
5. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 4, characterized in that: When the topology generation subunit automatically generates the initial topology of the process flow topology demonstration diagram using a hierarchical layout algorithm based on the process configuration information, it includes the following steps: Each treatment pool is used as a vertex in the graph model, and the process connection relationships between the treatment pools are used as directed edges in the graph model to construct a directed graph model of the wastewater treatment process. The directed graph model is topologically sorted to determine the hierarchical position of each vertex in the process flow, wherein vertices in parallel lines are assigned to parallel hierarchical tracks, and merging nodes are the intersection points of two or more parallel tracks. Based on the hierarchical position and the directed edge relationships between each vertex, the layout coordinates of each vertex in the demonstration diagram are calculated to generate the initial topology.
6. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 4, characterized in that: The video mapping binding subunit further includes a mapping verification subunit, used to display a video status indicator light in the vicinity of each node in the demonstration diagram after the video channel-node mapping table is established. The color of the video status indicator light indicates the mapping status between the node and the corresponding monitoring video, wherein: The first color indicates that the node has been successfully bound to one monitoring video and the video stream is normal; the second color indicates that the node has not been bound to a video or the video stream is abnormal.
7. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 4, characterized in that: The parameter association display module includes a color dynamic update subunit, a parameter display and adjustment subunit, and a simulation pre-play subunit; The color dynamic update subunit is used to obtain the real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module, and dynamically update the display color of the corresponding node in the process flow topology demonstration diagram according to the operating parameters and water quality parameters of each node. The display color simultaneously encodes two dimensions of information of the node: equipment operating status and water quality treatment status. The equipment operating status is determined according to the operating parameters, and the water quality treatment status is determined according to the water quality parameters. Different color codes correspond to different combinations of equipment operating status and water quality treatment status. The parameter display and adjustment subunit is used to display the operating parameters and water quality parameters of each node in real time at the corresponding position of each node in the process flow topology demonstration diagram, so that the operating parameters and water quality parameters are visually associated with the node status, and to update the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The simulation pre-run subunit is used to respond to parameter adjustment operations. Based on the adjusted parameters and the preset wastewater treatment process simulation model, it calculates the predicted parameter values of each node in the future preset time period. Based on the predicted parameter values, it displays the medium flow state between each node in a flow animation on the process flow topology demonstration diagram and shows the water quality change trend of each node in a gradient transition of node color. At the same time, it synchronously drives the color dynamic update subunit to update the display color of the node, so that the operator can evaluate.
8. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 7, characterized in that: The node linkage module includes an event capture subunit, a mapping query subunit, and a video positioning subunit; The event capture subunit is used to listen for and capture the user's click operation on the node on the process flow topology demonstration diagram, and identify the node identifier of the clicked node. The mapping query subunit is used to query the video channel-node mapping table with the node identifier as the index to obtain the video stream address of the monitoring video corresponding to the node. The video channel-node mapping table stores a one-to-one correspondence between each node identifier and the video stream address of each monitoring video in advance. The video positioning subunit is used to locate the target video sub-window corresponding to the video stream address in multiple video sub-windows in the first display area according to the video stream address, and send a highlighting instruction to the display module to perform a highlighting operation on the target video sub-window in the first display area, so that the monitoring video corresponding to the node is highlighted in the first display area. The highlighting shall be achieved by at least one of the following methods: enlarging the image of the target video sub-window, adding a highlight border around the image of the target video sub-window, or placing the image of the target video sub-window on top of other video sub-windows.
9. The logically interconnected intelligent monitoring system for wastewater treatment according to claim 8, characterized in that: The alarm management module includes a data acquisition and judgment subunit, an alarm identifier generation subunit, an alarm counting and statistics subunit, and an alarm linkage triggering subunit. The data acquisition and judgment subunit is used to acquire the real-time operating parameters and water quality parameters of each node from the monitoring data acquisition module at a preset detection cycle, compare the real-time value of each parameter with the preset threshold range, and determine that the node is abnormal when any parameter exceeds the corresponding threshold range, and generate an abnormal record containing node identifier, abnormal parameter, real-time value, threshold range and alarm level. The alarm identifier generation subunit is used to generate an alarm identifier at the display position of the corresponding node in the process flow topology demonstration diagram based on the abnormal record. The alarm identifier is superimposed on the node, and the display method of the alarm identifier corresponds to the alarm level. Different alarm levels correspond to different colors and dynamic features. The alarm counting and statistics subunit is used to update the number of alarms in real time in a designated area of the demonstration diagram. The number of alarms includes at least the total number of alarms and the detailed statistics classified by alarm level. The alarm linkage triggering subunit is used to send an automatic push instruction to the node linkage module according to the abnormal record. The automatic push instruction includes the node identifier and triggers the node linkage module to highlight the monitoring video corresponding to the node in the first display area.
10. A logically interconnected intelligent monitoring method for wastewater treatment, applied to the logically interconnected intelligent monitoring system for wastewater treatment as described in any one of claims 1-9, characterized in that, Includes the following steps: S1. The monitoring data acquisition module collects monitoring videos of each treatment tank in the sewage treatment process, as well as the operating parameters and water quality parameters of each treatment tank. S2. The demonstration diagram generation module generates a process flow topology demonstration diagram based on the treatment tanks involved in the wastewater treatment process. The demonstration diagram contains several nodes, each node corresponds to a treatment tank, and the process flow direction is represented by directed lines between nodes. The correspondence between each monitoring video and each node is established. S3. The monitoring videos are displayed on the first display area of the screen through the display module, and the process flow topology demonstration diagram is displayed on the second display area of the screen. The first display area and the second display area are displayed side by side on the same screen. S4. The parameter association display module dynamically updates the display color of the corresponding node in the process flow topology demonstration diagram based on the collected operating parameters and water quality parameters of each node. The display color simultaneously encodes information on two dimensions: the equipment operating status and the water quality treatment status of the node. In addition, the module displays custom parameters in the second display area and updates the set values of the operating parameters and water quality parameters in response to the user's parameter adjustment operation. The module also simulates the operating trend and water quality change trend of the wastewater treatment process in the future preset time period on the process flow topology demonstration diagram in an animated manner. S5. The node linkage module responds to the user's click operation on any node in the process flow topology demonstration diagram, queries the corresponding relationship, and highlights the monitoring video corresponding to the node in the first display area. S6. The alarm management module monitors the operating status of each node in real time. When any node is abnormal, an alarm sign is generated at the display position of that node, and the alarm count is updated in the designated area of the demonstration diagram.