A power supply reliability switching control method for cross-belt sorting machines
By monitoring and predicting energy storage demand in real time, triggering the pre-charging mode and switching to DC bus power supply, the problem of insufficient energy storage for contactless power supply vehicles in weak sensing areas is solved, and power supply reliability and sorting operation continuity are achieved under high throughput conditions.
Patent Information
- Application Number
- CN202611627140.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-21
- Publication Date
- 2026-11-17
AI Technical Summary
Under high throughput conditions, when a non-contact power supply vehicle enters a weak sensing area, its energy storage charge is insufficient, causing the sorting control signal to be interrupted. Existing technologies cannot effectively solve this problem.
By collecting the real-time output voltage and current of the sorting trolley's power receiving coil, the inductive power extraction efficiency coefficient is calculated. Combined with the current location and load power, the energy storage demand is predicted, triggering the pre-charging mode and switching to DC bus power supply to ensure that the energy storage meets the crossing requirements and achieves a smooth switch.
This improved the success rate of power supply switching, avoided sorting control interruptions due to insufficient energy storage, and ensured the continuity and efficiency of sorting operations.
Smart Images

Figure CN123121978A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of cross-belt sorting machines, specifically relating to a power supply reliability switching control method for cross-belt sorting machines. Background Technology
[0002] Circular cross-belt sorting machines are core equipment for achieving automated high-speed sorting in the express logistics industry. Widely deployed in large transfer centers, these systems are required to sort over 20,000 packages per hour at full capacity, with strictly controlled missorting rates. The sorting trolleys continuously cycle at high speed on a closed circular track; the continuity of their power supply directly determines whether the electric roller drive box can respond to sorting control signals in real time. Any millisecond-level power interruption can lead to the loss of drive control signals, resulting in missorting accidents.
[0003] Patent application CN111845384A discloses a power supply method, device, and logistics equipment for transporting goods. The method is applied to logistics equipment equipped with a rechargeable battery and a supercapacitor, and also has an external power source. The method includes: if the logistics equipment is in operation, powering it through the supercapacitor; during this process, if the supercapacitor's voltage is lower than a first specified voltage value, the rechargeable battery's voltage is higher than a second specified voltage value, and the voltage difference between the supercapacitor and the rechargeable battery is not lower than a preset voltage difference threshold, then powering the supercapacitor through the rechargeable battery; if the logistics equipment is not in operation, powering both the rechargeable battery and the supercapacitor through an external power source. This patent improves the power supply reliability of logistics equipment, effectively ensuring its normal operation.
[0004] Traditional circular cross-belt sorting machines generally use a sliding contact line power supply scheme, continuously powering the trolley with 48V DC or 72V DC. The communication part relies solely on a leaky cable and an onboard PLC to achieve RS485 serial port control. The current improved solution integrates power supply and communication into a single component, replacing the sliding contact line with a medium-frequency induction non-contact cable. At the same time, it uses the same non-contact cable to superimpose a power carrier signal to directly drive the electric roller control box, completely eliminating the onboard PLC and the dedicated leaky communication cable, reducing the number of system components and construction complexity.
[0005] However, the aforementioned contactless power supply scheme has systemic reliability issues under extreme conditions. Contactless inductive power collection relies on electromagnetic induction between the ground power cable and the trolley's receiving coil. When the trolley passes through track joint gaps, curves with varying curvature, or areas with accumulated installation deviations, the inductive energy transfer efficiency between the receiving coil and the power cable temporarily decreases, causing a drop in the trolley's power output. To address this issue, a supercapacitor is typically installed on the trolley as a backup energy storage device. However, under high-throughput operating conditions, the power consumption of the electric roller drive load is already close to the upper limit of the contactless power receiving capacity. The main power supply is almost entirely consumed by the drive load, and the energy storage unit cannot be effectively replenished. Its state of charge is already low before the trolley enters the inductively weak zone. Once entering the inductively weak zone causes a main power interruption, the already depleted energy storage unit cannot continuously maintain the power output required for drive control. The electric roller drive box loses power and loses the current sorting control signal, ultimately leading to mis-sorting. Summary of the Invention
[0006] This invention provides a power supply reliability switching control method for cross-belt sorting machines to solve the technical problem that insufficient energy storage charge of the non-contact power supply trolley before entering the weak sensing area under high throughput conditions leads to failure in switching to backup power supply and interruption of sorting control.
[0007] This invention provides a power supply reliability switching control method for a cross-belt sorting machine, comprising the following steps: S1. Collect the real-time output voltage and output current of the sorting trolley's power receiving coil to calculate the real-time power receiving, and compare the real-time power receiving with the rated power receiving benchmark of the current track section to obtain the inductive power extraction efficiency coefficient. S2, based on the current precise position of the sorting cart, query the track sensing quality distribution map, obtain the typical crossing time of the weak sensing zone ahead, calculate the minimum energy storage guarantee required to cross the weak zone in combination with the current driving load power, and calculate the effective energy storage that the on-board supercapacitor can actually release at present. S3, when the effective energy storage is less than the minimum energy storage guarantee, trigger the pre-charge mode to calculate the dynamic charge threshold, and when the inductive power extraction efficiency coefficient is lower than the reliable working boundary of inductive power extraction, switch the vehicle supercapacitor to the DC bus to take over the non-contact main power supply. S4 executes the main power supply switchback operation when the inductive power extraction efficiency coefficient is stably higher than the reliable working lower limit of inductive power extraction, and performs rolling correction on the typical crossing time in the track induction quality distribution map based on the actual duration of crossing the weak inductive zone.
[0008] Its effect is that, through forward-looking energy demand budgeting and pre-charging control in weak areas, the energy storage unit is proactively replenished to a sufficient state to meet the crossing requirements before the vehicle enters the weak induction zone, effectively eliminating the mismatch blind spot of fixed charge threshold for heavy-load scenarios under high throughput conditions, and significantly improving the power supply switching success rate.
[0009] Furthermore, the real-time output voltage and current of the sorting trolley's power receiving coil are collected to calculate the real-time power receiving capacity. This real-time power receiving capacity is then compared with the rated power receiving capacity of the current track section to obtain the inductive power extraction efficiency coefficient, including: The real-time output voltage and output current of the receiving coil are continuously collected at a fixed sampling period, and the product of the real-time output voltage and output current is calculated as the real-time power received. Obtain the mapping table between the track section number and the corresponding reference power received by the track section established through the full-process no-load reference calibration during the equipment commissioning phase, and extract the rated power received reference corresponding to the current track section; The ratio of real-time power received to the rated power received is calculated to obtain the inductive power extraction efficiency coefficient.
[0010] Its effect is as follows: by collecting the voltage and current of the receiving coil at fixed intervals to calculate the real-time power received, and relying on the track zone reference power mapping table calibrated by the equipment under no-load to calculate the inductive power extraction efficiency coefficient, it can accurately quantify the real-time inductive power transmission status of the vehicle's location online and without human intervention. This provides a standardized and quantifiable real-time judgment basis for subsequent weak zone identification, energy budgeting, and power supply switching triggering, avoiding errors caused by relying on a single voltage to roughly judge the power extraction status.
[0011] Furthermore, the minimum energy storage required to traverse weak zones is calculated based on the current drive load power, and the effective energy storage that the onboard supercapacitor can currently release is also calculated, including: The current drive load power of the electric drum drive box is collected, and the product of the current drive load power and the typical traverse time is calculated to obtain the minimum energy storage guarantee energy. Read the current state of charge and current terminal voltage of the on-board supercapacitor, and obtain the minimum input voltage requirement in the driver box hardware specification as the cutoff voltage; Based on the rated capacity of the vehicle-mounted supercapacitor, the difference between the square of the current voltage and the square of the cutoff voltage is calculated to obtain the effective energy storage.
[0012] Its effect is that by jointly evaluating the forward-looking weak zone location information, the current actual power consumption of the drive, and the effective energy storage that the supercapacitor can release, the system can complete a quantitative energy gap calculation before the vehicle arrives at the weak zone entrance, completely avoiding the risk of switching failure due to the lag in energy storage capacity assessment under high throughput conditions.
[0013] Furthermore, when the effective energy storage is less than the minimum guaranteed energy storage, a pre-charge mode is triggered to calculate the dynamic charge threshold, including: When the effective energy storage is determined to be less than the minimum energy storage guarantee energy, a power limiting signal is sent to the drive box to reduce the electric drum drive power to the minimum maintenance power required to maintain the drive speed. The excess power released is directed to the charging circuit of the on-board supercapacitor, and the product of the minimum sustaining power and the typical travel time is calculated as the minimum energy requirement. By combining the minimum sustaining power, typical ride-through time, rated capacity, and cutoff voltage, the corresponding lower bound of the capacitor terminal voltage is calculated, and the dynamic charging threshold is finally obtained.
[0014] Its effect is that by binding the dynamic charge threshold with the actual load of the current drive and the statistical cross-pass time of the weak zone in real time, it avoids excessive speed limiting or switching failure caused by the static threshold being too high or too low under different load conditions. While ensuring the reliability of power supply, it effectively reduces the interference to the normal sorting cycle.
[0015] Furthermore, by combining the minimum sustaining power, typical ride-through time, rated capacity, and cutoff voltage, the corresponding lower limit of the capacitor terminal voltage is calculated, and finally the dynamic charging threshold is obtained. The process also includes: continuously detecting the current terminal voltage of the on-board supercapacitor; when the current terminal voltage is detected to be greater than or equal to the dynamic charging threshold, it is determined that the pre-charging target has been achieved; and restoring the electric drum drive power to the normal level.
[0016] Furthermore, when the efficiency coefficient of inductive power extraction is lower than the reliable operating lower bound of inductive power extraction, the on-board supercapacitor is switched to the DC bus to replace the contactless main power supply, including: Obtain the absolute minimum input power specified in the driver box hardware specifications, as well as the global average of the calibration reference power for all track zones across the entire line; Calculate the ratio of the absolute minimum input power to the global mean to obtain the lower bound for reliable operation of inductive power supply; When the efficiency coefficient of inductive power extraction is less than the lower limit of reliable operation of inductive power extraction, the energy storage discharge circuit is closed, and the on-board supercapacitor is finally switched to the DC bus to replace the non-contact main power supply.
[0017] Furthermore, when the efficiency coefficient of inductive power extraction is stably higher than the reliable operating lower bound of inductive power extraction, a main power supply switch-back operation is performed, including: When the efficiency coefficient of inductive power extraction is greater than the lower limit of reliable operation of inductive power extraction for multiple consecutive sampling periods, it is determined that the non-contact main power supply has been reliably restored. Control the non-contact power receiving circuit to inject current into the DC bus; Once the bus voltage of the DC bus and the current energy storage discharge voltage of the on-board supercapacitor have reached equilibrium, the energy storage discharge path is disconnected, and the main power supply switching operation is finally completed.
[0018] Its effect is that by using a smooth switching method of equalizing the bus voltage after the main power supply is restored and then disconnecting, the bus voltage step during the alternation of the two power supplies is eliminated, ensuring the complete continuity of the electric drum drive control signal during the entire process of crossing the weak induction zone.
[0019] Furthermore, based on the actual duration of this crossing of the weak sensing zone, the typical crossing duration in the orbital sensing quality distribution map is rolled over and corrected, including: The actual duration of this crossing of the weak sensing zone will be reported to the ground control system. Using the historical crossing time sequence of the corresponding track partition as a sample, the sliding window length corresponding to the first convergence of the variance of the rolling mean in the continuous crossing records to within the preset proportion of the overall variance of the crossing time of each partition of the entire line is statistically analyzed. Calculate the exponentially weighted smoothing coefficient based on the sliding window length; By using the exponentially weighted smoothing coefficient, the actual duration, and the typical crossover duration before correction, the rolling correction of the typical crossover duration is finally completed.
[0020] Furthermore, after using the exponentially weighted smoothing coefficient, the actual duration, and the typical crossover duration before correction, the rolling correction of the typical crossover duration is finally completed, which also includes: Based on accumulated operational data, the historical standard deviation of the duration of stable operation for all partitions across the entire network is statistically analyzed in real time. Determine whether the updated value of the typical travel time continuously exceeds the sum of the historical standard deviations of the initial calibration value and a preset multiple; If the limit is exceeded continuously, the corresponding track partition will be automatically marked as a key inspection area and an alarm will be recorded in the log.
[0021] Furthermore, before obtaining the typical traversal time of the weak sensing area ahead, the following steps are also included: The current precise position of the sorting cart is continuously obtained through pre-set radio frequency identification (RFID) location tags on the track; Use the current precise location as an index to query the orbital sensing mass distribution map issued by the ground control system; Determine whether the current precise location is insufficient in advance from the entrance of the weak sensing zone ahead; If the lead time is insufficient, the step of obtaining the typical travel time of the weak sensing area ahead is triggered.
[0022] The beneficial effects are: the track induction quality distribution map is continuously updated by rolling correction of each actual crossing data, and maintenance alarms are automatically triggered based on statistical deviations, enabling the system to have the proactive early warning capability for degradation of induction power supply performance, and providing traceable data support for on-site operation and maintenance.
[0023] The system can maintain a high and stable switching success rate under different load conditions and different weak zone lengths, effectively avoiding the dual mismatch problem of switching failure caused by a low static threshold in heavy load scenarios and excessive speed limiting caused by a high static threshold in light load scenarios, thus ensuring the efficient operation of sorting operations. Attached Figure Description
[0024] Figure 1 A flowchart of a power supply reliability switching control method for a cross-belt sorter.
[0025] Figure 2 This is a comparison diagram of the distribution of inductive power extraction efficiency coefficients and weak zone identification in each section of the entire track in this invention. Detailed Implementation
[0026] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0027] An embodiment of the power supply reliability switching control method for cross-belt sorting machines provided by this invention: like Figure 1 As shown, the power supply reliability switching control method for a cross-belt sorter includes the following steps: S1, collect the received power to compare and obtain the inductive power extraction efficiency coefficient.
[0028] In an optional embodiment, a voltage sensor and a current sensor are respectively configured on the output side of the power receiving coil of each sorting cart to continuously collect the real-time output voltage of the power receiving coil at a fixed sampling period. With output current And based on this, calculate the real-time power received at the current moment:
[0029] in for The actual power received by the trolley's receiving coil at any given time. and These represent the terminal voltage and output current on the coil output side at the same moment. It should be noted that the specific value of the sampling period can be determined by combining the trolley's running speed and the length of the track section, with the basic constraint being to ensure that at least several effective samples are completed during the trolley's complete traversal of the shortest track section.
[0030] Furthermore, in obtaining Next, it needs to be compared with the rated power reference of the current track section where the trolley is located to evaluate the inductive power extraction efficiency at that moment. During the equipment commissioning phase, the system performs a full-line no-load reference calibration on the entire track: the trolley runs at the rated speed, and the average power of each track section under standard installation conditions is recorded segment by segment, establishing track section numbers. Corresponding reference power The mapping table is stored in the ground control system.
[0031] Next, the inductive power extraction efficiency coefficient is defined based on the calibration data:
[0032] The range of values is , This is the track section number to which the car's current position belongs. This is the calibration reference power for this zone. The lower the value, the worse the induction energy transmission efficiency at the current location, and the closer the area where the vehicle is located is to the weak induction zone. The higher the value, the better the alignment between the receiving coil and the power supply cable, and the more efficient the inductive power extraction. As the basis for subsequent weak sensing zone determination and switching triggering, the input quantity is calculated and continuously maintained in real time by the vehicle's local control unit.
[0033] By directly measuring the electrical quantities at the output side of the energized coil and dynamically comparing them with the track zoning calibration benchmark, the system can quantify the current induction power supply status of each vehicle online without human intervention, providing real-time induction efficiency data for subsequent forward-looking budgeting and switching triggering.
[0034] S2, obtain typical travel time to calculate effective energy storage.
[0035] In an optional embodiment, the local control unit of the sorting vehicle continuously obtains the current precise position of the sorting vehicle through pre-set RFID position tags on the track, and uses this as an index to query the track sensing quality distribution map issued by the ground control system. This distribution map records the track zones from historical operational data by zone. The minimum value and duration are used to mark the start and end zone numbers of the weak sensing zone ahead and its typical crossing time. The unit is seconds. When the trolley's position is less than the predetermined lead time from the entrance of a marked weak zone, the energy demand budgeting process in this step is immediately triggered. It should be noted that the specific value of the predetermined lead time can be determined by comprehensively evaluating the trolley's rated operating speed and the shortest time required for pre-charging, with the basic constraint being to ensure that the pre-charging process has sufficient time to complete before the trolley arrives at the weak zone entrance.
[0036] Furthermore, the budgeting process first collects the actual power consumption of the electric roller drive box at the current moment, i.e., the current drive load power. This value is directly output by the current detection circuit built into the driver box, and then the minimum energy storage required to cross the weak zone is calculated in combination with the current drive load power:
[0037] in The unit is joules. The unit is watts. The unit is seconds. Instead of being fixed parameters set manually, the system automatically adjusts these parameters based on the actual travel time after each vehicle traverses the corresponding zone, ensuring that the system always stays close to the latest actual operating status.
[0038] Next, the vehicle's local control unit reads the current state of charge of the onboard supercapacitor. It is continuously calculated using the Coulomb integral method. This takes into account the cutoff voltage present in the on-board supercapacitor during actual discharge. Below this voltage, the output power is insufficient to maintain the normal operation of the driver box. This value is taken from the minimum input voltage requirement in the driver box hardware specifications. Based on the original physical energy storage formula, and subtracting the unusable energy storage below the cutoff voltage, the effective energy that the on-board supercapacitor can currently release is calculated:
[0039] in The voltage across the current terminal of the capacitor. The values represent the rated capacitance; all variables are derived from direct measurements and fixed physical parameters from the on-board capacitor management module. These values are taken from the hardware specifications and are calibration values. The larger the value, the more abundant the current energy storage capacity, and the longer the drive box can continue to work after switching to backup power. The smaller the value, the tighter the energy storage capacity and the weaker the power supply guarantee capability across the current weak area.
[0040] Will and By comparing the current effective energy storage, we can determine whether it meets the minimum energy storage guarantee requirements for traversing weak zones, and use this as the basis for deciding whether to trigger pre-charging in the next step.
[0041] By jointly evaluating the forward-looking weak zone location information, the current actual power consumption of the drive, and the effective energy storage that can be released from the on-board supercapacitor, the system can complete a quantitative energy gap calculation before the vehicle arrives at the weak zone entrance, completely avoiding the risk of switching failure due to the lag in energy storage capacity assessment under high throughput conditions.
[0042] S3 triggers the pre-charge mode to switch the onboard supercapacitor to the DC bus.
[0043] In an optional embodiment, when effective energy storage When the vehicle's local control unit determines that the current energy storage is insufficient, it immediately triggers the pre-charging mode. In pre-charging mode, the control unit sends a power limiting signal to the drive box, reducing the electric roller drive power from the current value. Appropriately reduce to the minimum holding power required to drive holding speed. The excess power released will be preferentially directed to the charging circuit of the onboard supercapacitor, so as to quickly charge it before entering the weak current range. Upgraded to Above. The lower bound value is determined by the steady-state drive power consumption measured under no-load and uniform speed operation conditions during the equipment commissioning phase.
[0044] Furthermore, during the pre-charging process, The control unit continuously calculates the dynamic charge threshold in real time. This is because the drive power has decreased during the pre-charge phase. The maximum power consumption required by the car during its actual traversal of the weak zone is... The corresponding minimum energy requirement is:
[0045] Transform it into a charge criterion expressed in terms of terminal voltage, and let Based on the aforementioned effective energy storage formula, the corresponding lower bound of the capacitor terminal voltage is derived as follows:
[0046] The above formula is directly derived from the existing physical energy storage formula, and contains a square root, making it a derived form of the original physical formula. The larger the value, the longer the current weak zone crossing time or the higher the minimum maintenance power. Pre-charging requires replenishing the on-board supercapacitor to a higher terminal voltage to meet the crossing protection requirements. The smaller the value, the lighter the crossing load and the more lenient the pre-charge target. When the current terminal voltage is detected... When the pre-charging target is achieved, the control unit restores the electric roller drive power to the normal level, and the trolley enters the weak zone at full load.
[0047] Next, when the car enters the weak zone, the inductive power extraction efficiency coefficient... Continued decline. Define the lower bound for reliable operation of inductive power supply:
[0048] in The absolute minimum input power specified in the driver box hardware specifications is a fixed hardware specification constant. The global average value of the reference power is used to calibrate all track sections of the entire line during the system commissioning phase. It is a fixed constant reflecting the reliable operating boundary of the hardware. Once the efficiency coefficient of inductive power extraction falls below the reliable operating boundary of inductive power extraction, i.e. The control unit immediately closes the energy storage discharge circuit, switching the on-board supercapacitor to the DC bus to replace the non-contact main power supply and continuously power the drive box. The switching action is achieved at the hardware level through closed-loop control of the bus voltage, maintaining the bus voltage within the rated operating voltage range of the drive box to ensure the continuous execution of the electric drum control signal.
[0049] By binding the dynamic charge threshold with the current actual load and weak zone statistical travel time in real time, and achieving seamless switching in a hardware-level bus voltage closed-loop manner after pre-charging, the system can maintain a high degree of stability in switching success rate under different load conditions and different weak zone lengths. This effectively avoids the dual mismatch problem of switching failure caused by a low static threshold in heavy load scenarios and excessive speed limiting caused by a high static threshold in light load scenarios.
[0050] S4 executes the main supply switchback operation and performs rolling correction on the typical travel time.
[0051] In an optional embodiment, after the vehicle traverses the weak zone, It will rebound as conditions for induced power extraction recover. When The value was consistently higher than the average for several consecutive sampling periods. At this point, the control unit determines that the non-contact main power supply has been reliably restored. The number of sampling cycles required for continuous determination is determined based on the maximum discharge current of the on-board supercapacitor and the time constant of the drive bus capacitor. After the determination is successful, the control unit executes the main power supply switchback operation: first, it controls the non-contact power receiving circuit to inject current into the DC bus; after the bus voltage of the DC bus and the current energy storage discharge voltage of the on-board supercapacitor tend to be balanced, it then disconnects the energy storage discharge path, completing a smooth switchback without disturbance, avoiding bus voltage step interference to the drive control signal caused by the alternating switching of the two power supplies.
[0052] Furthermore, after the switchback is completed, the system enters the energy storage priority replenishment phase: the control unit effectively stores energy. With the goal of restoring to full capacity, and without affecting the current sorting cycle, a portion of the remaining main power supply is continuously fed into the onboard supercapacitor charging circuit to ensure that the energy storage unit is fully charged before the next low-capacity period arrives. Since the remaining main power supply is limited under high-throughput conditions, the energy storage replenishment rate is constrained by the difference between the current actual drive load and the rated power of the contactless power receiving system. The control unit prioritizes ensuring that the sorting cycle is not affected, and under this premise, promotes energy storage recovery using the maximum available power difference.
[0053] Next, the control unit will record the actual duration of this crossing of the weak sensing area. The data is reported to the ground control system, which then uses this information to determine the typical travel time for the corresponding zone in the orbital induction mass distribution map. Perform rolling correction:
[0054] Among them, the exponentially weighted smoothing coefficient The determination method is as follows: Using the historical crossing time sequence of the corresponding track section as a sample, the sliding window length corresponding to the first convergence of the variance of the rolling mean in the continuous crossing records to within a preset proportion of the overall variance of the crossing time of all sections of the entire line is calculated. ,make This derivation relies entirely on the convergence characteristics of historical statistical data, requiring no manually given fixed values, and automatically reconverges as track wear evolves. The typical traverse time for a given region... The updated value continuously exceeds its initial calibration value plus a preset multiple. historical standard deviation At that time, the system automatically marks the corresponding track partition as a key inspection area and records an alarm in the log. The specific value is determined based on the on-site maintenance alarm sensitivity requirements. For example, 3 can be chosen; The historical standard deviation of the time taken for all zones along the entire line to reach stable operation is statistically analyzed in real time by the ground control system based on accumulated operational data, and is a completely reproducible statistic.
[0055] In this way, through the coordinated operation of smooth switching back of the main power supply, priority replenishment of energy storage, and rolling correction of the track distribution map, the system can immediately start preparations for the next crossing after completing the current weak zone crossing. At the same time, by automatically triggering maintenance alarms with statistical deviation, the degradation of inductive power extraction performance can be proactively detected before it causes actual power supply failure, providing traceable data support for the on-site operation and maintenance team.
[0056] like Figure 2 As shown, it can be observed that within the distribution range of the weak induction zone, the efficiency coefficient curve of the existing method repeatedly drops below the reliable operating lower limit of induction power supply, while the efficiency coefficient curve of the method of the present invention remains near or above the reliable operating lower limit under the same weak zone distribution. This demonstrates that the present invention effectively addresses the low efficiency of induction through dynamic pre-charging and switching control.
[0057] The above are all preferred embodiments of the present invention and are not intended to limit the scope of protection of the present invention. Therefore, all equivalent changes made in accordance with the structure, shape and principle of the present invention should be covered within the scope of protection of the present invention.
Claims
1. A power supply reliability switching control method for a cross-belt sorting machine, characterized in that, Includes the following steps: S1. Collect the real-time output voltage and output current of the sorting trolley's power receiving coil to calculate the real-time power receiving, and compare the real-time power receiving with the rated power receiving benchmark of the current track section to obtain the inductive power extraction efficiency coefficient. S2, based on the current precise position of the sorting cart, query the track sensing quality distribution map, obtain the typical crossing time of the weak sensing zone ahead, calculate the minimum energy storage guarantee required to cross the weak zone in combination with the current driving load power, and calculate the effective energy storage that the on-board supercapacitor can actually release at present. S3, when the effective energy storage is less than the minimum energy storage guarantee, trigger the pre-charge mode to calculate the dynamic charge threshold, and when the inductive power extraction efficiency coefficient is lower than the reliable working boundary of inductive power extraction, switch the vehicle supercapacitor to the DC bus to take over the non-contact main power supply. S4 executes the main power supply switchback operation when the inductive power extraction efficiency coefficient is stably higher than the reliable working lower limit of inductive power extraction, and performs rolling correction on the typical crossing time in the track induction quality distribution map based on the actual duration of crossing the weak inductive zone.
2. The power supply reliability switching control method for the cross-belt sorter according to claim 1, characterized in that, The real-time output voltage and current of the sorting trolley's power-receiving coil are collected to calculate the real-time power received. This real-time power received is then compared with the rated power received by the current track section to obtain the inductive power extraction efficiency coefficient, including: The real-time output voltage and output current of the receiving coil are continuously collected at a fixed sampling period, and the product of the real-time output voltage and output current is calculated as the real-time power received. Obtain the mapping table between the track section number and the corresponding reference power received by the track section established through the full-process no-load reference calibration during the equipment commissioning phase, and extract the rated power received reference corresponding to the current track section; The ratio of real-time power received to the rated power received is calculated to obtain the inductive power extraction efficiency coefficient.
3. The power supply reliability switching control method for the cross-belt sorter according to claim 1, characterized in that, Calculate the minimum energy storage required to cross weak current zones based on the current drive load power, and calculate the effective energy storage that the onboard supercapacitor can currently release, including: The current drive load power of the electric drum drive box is collected, and the product of the current drive load power and the typical traverse time is calculated to obtain the minimum energy storage guarantee energy. Read the current state of charge and current terminal voltage of the on-board supercapacitor, and obtain the minimum input voltage requirement in the driver box hardware specification as the cutoff voltage; Based on the rated capacity of the vehicle-mounted supercapacitor, the difference between the square of the current voltage and the square of the cutoff voltage is calculated to obtain the effective energy storage.
4. The power supply reliability switching control method for the cross-belt sorter according to claim 1, characterized in that, When the effective energy storage is less than the minimum guaranteed energy storage, a pre-charge mode is triggered to calculate the dynamic charge threshold, including: When the effective energy storage is determined to be less than the minimum energy storage guarantee energy, a power limiting signal is sent to the drive box to reduce the electric drum drive power to the minimum maintenance power required to maintain the drive speed. The excess power released is directed to the charging circuit of the on-board supercapacitor, and the product of the minimum sustaining power and the typical travel time is calculated as the minimum energy requirement. By combining the minimum sustaining power, typical ride-through time, rated capacity, and cutoff voltage, the corresponding lower bound of the capacitor terminal voltage is calculated, and the dynamic charging threshold is finally obtained.
5. The power supply reliability switching control method for a cross-belt sorter according to claim 4, characterized in that, After calculating the lower bound of the capacitor terminal voltage by combining the minimum sustaining power, typical ride-through time, rated capacity, and cutoff voltage, and finally obtaining the dynamic charging threshold, the process also includes: continuously monitoring the current terminal voltage of the on-board supercapacitor; when the current terminal voltage is detected to be greater than or equal to the dynamic charging threshold, it is determined that the pre-charging target has been achieved; and restoring the electric drum drive power to the normal level.
6. The power supply reliability switching control method for a cross-belt sorter according to claim 1, characterized in that, When the efficiency coefficient of inductive power extraction is lower than the reliable operating lower bound of inductive power extraction, the on-board supercapacitor is switched to the DC bus to replace the contactless main power supply, including: Obtain the absolute minimum input power specified in the driver box hardware specifications, as well as the global average of the calibration reference power for all track zones across the entire line; Calculate the ratio of the absolute minimum input power to the global mean to obtain the lower bound for reliable operation of inductive power supply; When the efficiency coefficient of inductive power extraction is less than the lower limit of reliable operation of inductive power extraction, the energy storage discharge circuit is closed, and the vehicle-mounted supercapacitor is finally switched to the DC bus to replace the non-contact main power supply.
7. The power supply reliability switching control method for a cross-belt sorter according to claim 1, characterized in that, When the efficiency coefficient of inductive power extraction is stably higher than the reliable operating lower bound of inductive power extraction, the main power supply is switched back, including: When the efficiency coefficient of inductive power extraction is greater than the lower limit of reliable operation of inductive power extraction for multiple consecutive sampling periods, it is determined that the non-contact main power supply has been reliably restored. Control the non-contact power receiving circuit to inject current into the DC bus; Once the bus voltage of the DC bus and the current energy storage discharge voltage of the on-board supercapacitor have reached equilibrium, the energy storage discharge path is disconnected, and the main power supply switching operation is finally completed.
8. The power supply reliability switching control method for a cross-belt sorter according to claim 1, characterized in that, Based on the actual duration of this crossing of the weak sensing zone, the typical crossing duration in the orbital induction mass distribution map is rolled over and corrected, including: The actual duration of this crossing of the weak sensing zone will be reported to the ground control system. Using the historical crossing time sequence of the corresponding track partition as a sample, the sliding window length corresponding to the first convergence of the variance of the rolling mean in the continuous crossing records to within the preset proportion of the overall variance of the crossing time of each partition of the entire line is statistically analyzed. Calculate the exponentially weighted smoothing coefficient based on the sliding window length; By using the exponentially weighted smoothing coefficient, the actual duration, and the typical crossover duration before correction, the rolling correction of the typical crossover duration is finally completed.
9. The power supply reliability switching control method for a cross-belt sorter according to claim 8, characterized in that, After using the exponentially weighted smoothing coefficient, the actual duration, and the typical crossover duration before correction, the rolling correction of the typical crossover duration is finally completed, which also includes: Based on accumulated operational data, the historical standard deviation of the duration of stable operation for all partitions across the entire network is statistically analyzed in real time. Determine whether the updated value of the typical travel time continuously exceeds the sum of the historical standard deviations of the initial calibration value and a preset multiple; If the limit is exceeded continuously, the corresponding track partition will be automatically marked as a key inspection area and an alarm will be recorded in the log.
10. The power supply reliability switching control method for a cross-belt sorter according to claim 1, characterized in that, Before obtaining the typical traversal time of the weak sensing zone ahead, the following steps are also included: The current precise position of the sorting cart is continuously obtained through pre-set radio frequency identification (RFID) location tags on the track; Use the current precise location as an index to query the orbital sensing mass distribution map issued by the ground control system; Determine whether the current precise location is insufficient in advance from the entrance of the weak sensing zone ahead; If the lead time is insufficient, the step of obtaining the typical travel time of the weak sensing area ahead is triggered.
Citation Information
Patent Citations
Power supply method and device of logistics equipment and logistics equipment
CN111845384A