Connecting structure of valve well and regulating reservoir

By installing water gates, drum grilles and filter components at the connection between the valve well and the regulating tank, the problem of equipment damage caused by domestic waste entering the sewage treatment equipment directly has been solved, and the stability and efficiency of sewage treatment have been improved.

CN221788503UActive Publication Date: 2024-10-01BEIJING GUANGCHENG ENVIRONMENTAL TECH CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420344231.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2024-10-01
Estimated Expiration
2034-02-23

AI Technical Summary

Technical Problem

Domestic waste directly enters the sewage treatment equipment in the sewage, causing equipment damage.

Method used

A connection structure between the valve well and the regulating pool is designed, using a water gate, a drum grille machine and a filter assembly. The flow is controlled through the water gate, and the drum grille machine removes large garbage. The filter assembly includes an interception net and a load-bearing plate to intercept and intercept Small garbage can reduce the amount of garbage entering the sewage treatment equipment.

Benefits of technology

It effectively reduces the amount of garbage entering the sewage treatment equipment, ensures the stability and normal operation of the equipment, and improves the efficiency of sewage treatment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221788503U_ABST
    Figure CN221788503U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of sewage treatment.The valve well and adjusting pool connecting structure comprises a valve well and an adjusting pool, a water gate is arranged in the valve well and divides the valve well into a first cavity and a second cavity, a rotary drum grillage machine is obliquely installed in the second cavity, and a water inlet pipe is connected between the second cavity and the adjusting pool; and a filtering assembly for filtering impurities is arranged in the water inlet pipe. The sewage treatment equipment has the effects that garbage can be conveniently cleaned, and the damage to the sewage treatment equipment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of sewage treatment, and in particular to a valve well and a regulating tank connection structure. Background Art

[0002] At present, sewage treatment technology is widely used in various fields such as construction, agriculture, transportation, energy, and medical care. After purification, sewage can meet the water quality requirements for discharge into a certain water body or reuse, thereby effectively improving resource utilization and being very environmentally friendly.

[0003] Sewage treatment mainly includes domestic sewage treatment and industrial sewage treatment. Domestic sewage treatment mainly transports domestic sewage from various places to sewage treatment plants through sewage pipes, and uses various sewage treatment equipment installed in the sewage treatment plants to purify domestic sewage. However, in order to enable sewage pipes and various structures of sewage treatment plants to work normally and not be affected by peak flow or concentration changes of wastewater, a regulating tank is required before the sewage treatment equipment. In order to clarify the amount of sewage transported from various places, a separate valve well is set at the front end of the regulating tank. The valve well is a civil structure, and is equipped with pipelines, gates and flow meters.

[0004] Regarding the above-mentioned related technologies, there are the following defects: domestic sewage from various places carries a large amount of domestic garbage. If this part of domestic garbage is directly discharged into the regulating tank with the sewage, and further enters the sewage treatment equipment, it is easy to cause damage to the sewage treatment equipment, which needs further improvement. Utility Model Content

[0005] In order to improve the problem that domestic garbage is easily brought into sewage treatment equipment and thus causes damage to sewage treatment equipment, the present application provides a valve well and a regulating tank connection structure.

[0006] The present application provides a valve well and a regulating tank connection structure, which adopts the following technical solution:

[0007] A valve well and regulating tank connection structure includes a valve well and a regulating tank, wherein a sluice is provided in the valve well, the sluice separates the valve well into a first chamber and a second chamber, a rotary drum screen machine is obliquely installed in the second chamber, a water inlet pipe is connected between the second chamber and the regulating tank, and a filter assembly for filtering debris is provided in the water inlet pipe.

[0008] By adopting the above technical solution, after the sewage enters the valve well, it first flows into the first chamber, and the flow of the sewage is regulated by the sluice gate so that an appropriate amount of sewage enters the second chamber, and the large garbage suspended in the sewage is removed by the rotary drum screen machine in the second chamber, and then the sewage in the second chamber is discharged into the regulating tank through the water inlet pipe, and the remaining small garbage is intercepted by the filtering component in the water inlet pipe, thereby further reducing the situation where garbage enters the sewage treatment equipment and ensuring the stability of sewage treatment.

[0009] Optionally, the filter assembly includes an intercepting net and a supporting plate, the intercepting net is vertically arranged in the water inlet pipe, and a leakage port is opened on the bottom wall of the water inlet pipe on the side of the intercepting net close to the valve well, the supporting plate is rotatably connected to the leakage port, and the supporting plate rotates toward the bottom of the leakage port, and a fixing part is also provided on the supporting plate, and the fixing part is used to lock the rotation of the supporting plate.

[0010] By adopting the above technical solution, the fixing part fixes the supporting plate at the leakage port, so that the supporting plate effectively seals the leakage port. When sewage passes through the water inlet pipe, the garbage filtered by the interception net accumulates on the supporting plate. When cleaning is needed later, the supporting plate can be rotated open from the leakage port to quickly discharge the garbage, which is easy to use.

[0011] Optionally, a limiting groove is arranged on the inner wall of the bottom of the leakage port, the top of the supporting plate abuts against the top wall of the limiting groove, and the rotating end of the supporting plate is rotatably connected to any side wall of the limiting groove, the movable end of the supporting plate abuts against the other side wall of the limiting groove, and the fixing part is arranged close to the movable end of the supporting plate.

[0012] By adopting the above technical solution, the rotating end of the carrying plate is rotatably connected to any side wall of the limiting groove, and the movable end of the carrying plate abuts against the other side wall of the limiting groove, so that the carrying plate is firmly embedded in the leakage port, making the rotating connection of the carrying plate stable and the structure reliable.

[0013] Optionally, the fixing device includes a pull rope, a hook and a hanging ring, the pull rope is fixedly mounted on the movable end of the supporting plate, a through hole is provided on the top wall of the water inlet pipe, the pull rope passes through the through hole and is fixedly connected to the hook, the hanging ring is arranged on the outer wall of the water inlet pipe near the through hole, and the hook is hung on the hanging ring.

[0014] By adopting the above technical solution, the pull rope is pulled to drive the load-bearing plate upward to abut against the top wall of the limit groove, so that the load-bearing plate effectively closes the leakage port, and after the hanging ring is hung by the hook, the pull rope is effectively fixed, so that the load-bearing plate is stable to use. When it is necessary to clean up the garbage, the connection between the hook and the hanging ring is released. Under the action of the gravity of the load-bearing plate, the load-bearing plate is conveniently opened to clean up the garbage, which is easy to use.

[0015] Optionally, a tightening spring is also sleeved on the pull rope, one end of the tightening spring is fixedly connected to the top wall of the water inlet pipe, and the other end is fixedly connected to the bearing plate, and the tightening spring causes the bearing plate to abut against the top wall of the limiting groove.

[0016] By adopting the above technical solution, the elastic force of the tightening spring is utilized to make the contact between the load-bearing plate and the limit groove more stable. If the pull rope breaks suddenly, the load-bearing plate can be effectively buffered by the tightening spring, and the operator can be provided with maintenance preparation in time. The leakage port will not be fully opened at once, and the structure is simple and stable to use.

[0017] Optionally, a first sealing ring is disposed on the outer wall of the bearing plate, and a second sealing ring matched with the first sealing ring is disposed on the inner wall of the limiting groove.

[0018] By adopting the above technical solution, when the load-bearing plate closes the leakage opening, the first sealing ring and the second sealing ring are tightly connected, so that the connection between the load-bearing plate and the limiting groove is tightened, leakage is effectively reduced, and the structure is reliable.

[0019] Optionally, a transparent observation portion is provided at the top of the water inlet pipe near the perforation.

[0020] By adopting the above technical solution, the transparent observation part is provided to facilitate the operator to observe the garbage accumulation on the carrying plate, so that the garbage can be cleaned up quickly, and the structure is simple.

[0021] Optionally, a material guiding channel is provided at the bottom of the water inlet pipe around the material leakage port.

[0022] By adopting the above technical solution, the material guide channel is set so that the garbage falls from the same place when discharged from the leakage port, reducing the possibility of garbage being scattered everywhere and affecting the surrounding environment, and the structure is reliable.

[0023] In summary, the present application includes at least one of the following beneficial technical effects of the valve well and regulating tank connection structure:

[0024] 1. Through the installation of the drum screen machine and filter assembly, when the sewage enters the valve well, it first flows into the first chamber, and the flow of sewage is regulated by the sluice gate, so that an appropriate amount of sewage is discharged into the second chamber. At this time, the drum screen machine in the second chamber removes the large garbage suspended in the sewage, and then discharges the sewage in the second chamber into the regulating tank through the water inlet pipe, and uses the filter assembly in the water inlet pipe to intercept the remaining small garbage, further reducing the situation of garbage entering the sewage treatment equipment and ensuring the stability of sewage treatment;

[0025] 2. Through the interception net, leakage port and supporting plate, the small garbage carried by the sewage in the water inlet pipe is effectively filtered out by the interception net, and then the filtered garbage is accumulated on the supporting plate. The supporting plate is subsequently opened by rotation, and the garbage is conveniently dropped from the leakage port and cleaned up, reducing the blockage of the water inlet pipe and the structure is reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;

[0027] Figure 2 is a schematic cross-sectional structural diagram of an embodiment of the present application;

[0028] Figure 3 yes Figure 2 A magnified schematic diagram of part A;

[0029] Figure 4 yes Figure 1 Schematic diagram of the enlarged portion B.

[0030] Figure numerals: 1. valve well; 10. sluice gate; 11. first chamber; 12. second chamber; 2. regulating tank; 20. maintenance manhole; 21. water outlet; 3. cover body; 30. guardrail; 4. rotary drum screen machine; 5. water inlet pipe; 6. filter assembly; 60. interception net; 61. bearing plate; 610. first sealing ring; 611. second sealing ring; 7. leakage port; 70. material guide channel; 71. limiting groove; 8. fixing piece; 80. pull rope; 800. tightening spring; 81. hook; 82. hanging ring; 9. perforation; 90. transparent observation part. DETAILED DESCRIPTION

[0031] The present application is further described in detail below in conjunction with the accompanying drawings.

[0032] The present application embodiment discloses a valve well and a regulating tank connection structure, referring to Figure 1 and Figure 2, including a valve well 1 and a regulating tank 2. In this embodiment, the valve well 1 and the regulating tank 2 are built with concrete. The top of the valve well 1 is provided with a cover 3 and a guardrail 30 to effectively ensure safety. The top of the regulating tank 2 is provided with a maintenance manhole 20. Afterwards, a sluice gate 10 is also provided in the valve well 1, and the valve well 1 is divided into a first chamber 11 and a second chamber 12 by the sluice gate 10. The sewage first flows into the first chamber 11, and then the flow of the sewage is controlled by the sluice gate 10, so that the sewage further enters the second chamber 12. At this time, since there is a large amount of domestic garbage in the sewage, in order to reduce the domestic garbage from entering the regulating tank 2 and further being brought into the sewage treatment equipment, causing damage to the sewage treatment equipment, a rotary drum screen machine 4 is obliquely installed in the second chamber 12, and the rotary drum screen machine 4 can remove the large garbage suspended in the sewage from the valve well 1. At this time, in order to further discharge the sewage in the second chamber 12 into the regulating tank 2, an inlet pipe 5 is connected between the second chamber 12 and the regulating tank 2, and a water outlet 21 is provided on a side wall of the regulating tank 2 away from the inlet pipe 5, and the height of the water outlet 21 is lower than the inlet pipe 5. In addition, a filter assembly 6 for filtering debris is also provided in the inlet pipe 5, and the filter assembly 6 further intercepts some small garbage in the sewage that is not taken away by the rotary drum screen machine 4, thereby reducing the situation where garbage enters the sewage treatment equipment, effectively ensuring the normal operation of the sewage treatment equipment, and improving the sewage treatment efficiency.

[0033] Reference Figure 2 and Figure 3 In this embodiment, the filter assembly 6 includes an interception net 60 and a bearing plate 61. The cross-sectional size of the interception net 60 is adapted to the inner diameter of the water inlet pipe 5. Then the interception net 60 is vertically arranged in the water inlet pipe 5, so that the small garbage carried from the second chamber 12 is effectively intercepted in the water inlet pipe 5, reducing the situation where garbage enters the regulating tank 2. In order to clean up the intercepted garbage and avoid clogging the water inlet pipe 5, a leakage port 7 is opened on the side of the interception net 60 close to the valve well 1 and on the bottom wall of the water inlet pipe 5, and then the bearing plate 61 is rotatably connected to the leakage port 7 and rotated toward the bottom of the leakage port 7. Finally, a fixing member 8 is also provided on the bearing plate 61, and the fixing member 8 can lock the rotation of the bearing plate 61. Thereby, the leakage port 7 is effectively closed by the supporting plate 61, and after the garbage is effectively intercepted in the water inlet pipe 5, the garbage is accumulated on the supporting plate 61. After the supporting plate 61 is rotated and opened, the accumulated garbage is quickly discharged from the leakage port 7. Thereafter, the supporting plate 61 is repositioned at the leakage port 7 through the fixing member 8 to ensure the normal use of the water inlet pipe 5. The structure is simple, and the garbage can be effectively filtered and intercepted, thereby reducing the damage to the sewage treatment equipment.

[0034] Reference Figure 3In this embodiment, when garbage is discharged from the material leakage port 7, in order to reduce the situation where the garbage falls directly everywhere and affects the surrounding environment, a material guide channel 70 is provided around the material leakage port 7 at the bottom of the water inlet pipe 5. The material guide can effectively make the garbage fall in a concentrated manner, and the garbage can be uniformly recovered to the garbage storage area through the material guide channel 70, which is very convenient and environmentally friendly.

[0035] Reference Figure 3 In this embodiment, in order to conveniently realize the rotational connection of the carrying plate 61, a limiting groove 71 is arranged on the inner wall of the leakage port 7 at the bottom, so that the cross-section of the leakage port 7 is arranged in a stepped shape. At this time, the top of the carrying plate 61 is abutted against the top wall of the limiting groove 71, and the rotating end of the carrying plate 61 is rotatably connected to any side wall of the limiting groove 71 through a rotating shaft, and the movable end of the carrying plate 61 is abutted against the other side wall of the limiting groove 71, so that the carrying plate 61 is firmly embedded in the limiting groove 71, and the carrying plate 61 and the leakage port 7 are in a closed state, and the structure is very stable.

[0036] Reference Figure 3 and Figure 4 In this embodiment, after the carrying plate 61 is firmly connected to the limiting groove 71, the fixing member 8 is arranged at the movable end near the carrying plate 61, including a pull rope 80, a hook 81 and a hanging ring 82. The pull rope 80 is made of anti-corrosion material and then fixed to the movable end of the carrying plate 61 by welding. Then, a through hole 9 is opened on the top wall of the water inlet pipe 5, and the pull rope 80 passes through the through hole 9 and is fixedly connected to the hook 81. Finally, the hanging ring 82 is welded to the outer wall of the water inlet pipe 5 near the through hole 9. The operator pulls the pull rope 80 until the carrying plate 61 abuts against the limiting groove 71, and then hangs the hook 81 on the hanging ring 82, thereby effectively fixing the carrying plate 61, so that the carrying plate 61 effectively receives garbage. When the garbage needs to be removed, the connection between the hook 81 and the hanging ring 82 is released. Under the gravity of the garbage and the carrying plate 61, the carrying plate 61 automatically opens, which is easy to operate. In order to facilitate the operator to observe the garbage accumulated on the carrying plate 61, a transparent observation part 90 is provided at the top of the water inlet pipe 5 near the perforation 9. The transparent observation part 90 is arranged around the perforation 9, with a large observation area and convenient use.

[0037] Reference Figure 3When the draw plate 61 is in contact with the limit groove 71, the fastening spring 800 uses the elastic force to further make the draw plate 61 contact with the top wall of the limit groove 71, thereby effectively strengthening the connection of the draw plate 61. When the draw plate 61 is opened, the bearing capacity of the draw plate 61 is greater than the elastic force of the fastening spring 800, and the fastening spring 800 will not interfere with the opening of the draw plate 61. If the draw rope 80 is accidentally disconnected during use, the draw plate 61 will not be directly opened completely under the action of the fastening spring 800, which effectively provides reaction time for the operator to shut down the equipment in time and perform maintenance on the draw plate 61 to avoid large-scale sewage leakage. The structure is reliable.

[0038] Reference Figure 3 In this embodiment, in order to strengthen the connection between the bearing plate 61 and the limiting groove 71 and reduce leakage, a first sealing ring 610 is provided on the outer wall of the bearing plate 61, and a second sealing ring 611 adapted to the first sealing ring 610 is provided on the inner wall of the limiting groove 71. When the bearing plate 61 is fixed in the limiting groove 71, the first sealing ring 610 and the second sealing ring 611 fit tightly, so that the bearing plate 61 is tightly connected, reducing water leakage and having a reliable structure.

[0039] The implementation principle of a valve well and a regulating tank connection structure in an embodiment of the present application is as follows: during the sewage treatment process, the sewage first enters the first chamber 11, and then the flow rate of the sewage is regulated by the sluice gate 10, so that after the sewage enters the second chamber 12, the large suspended garbage in the sewage is effectively removed by the rotary drum screen machine 4, and then the sewage is transported to the regulating tank 2 through the water inlet pipe 5. At this time, in the process of transporting sewage through the water inlet pipe 5, small garbage is effectively intercepted by the interception net 60, reducing the situation of garbage entering the sewage treatment equipment, and the garbage intercepted in the water inlet pipe 5 can be discharged from the leakage port 7 by regularly opening the supporting plate 61, which is very convenient and reliable to use.

[0040] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, all equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A valve well and a regulating tank connection structure, comprising a valve well (1) and a regulating tank (2), characterized in that: A water gate (10) is provided in the valve well (1), and the water gate (10) divides the valve well (1) into a first chamber (11) and a second chamber (12); a rotary drum screen machine (4) is obliquely installed in the second chamber (12); a water inlet pipe (5) is connected between the second chamber (12) and the regulating tank (2); a filter assembly (6) for filtering debris is provided in the water inlet pipe (5).

2. A valve well and regulating tank connection structure according to claim 1, characterized in that: The filter assembly (6) comprises an interception net (60) and a bearing plate (61); the interception net (60) is vertically arranged in the water inlet pipe (5); a leakage port (7) is provided on the bottom wall of the water inlet pipe (5) on the side of the interception net (60) close to the valve well (1); the bearing plate (61) is rotatably connected to the leakage port (7), and the bearing plate (61) rotates toward the bottom of the leakage port (7); and a fixing member (8) is further provided on the bearing plate (61), and the fixing member (8) is used to lock the rotation of the bearing plate (61).

3. A valve well and regulating tank connection structure according to claim 2, characterized in that: A limiting groove (71) is provided on the inner wall of the leakage port (7) at the bottom, the top of the bearing plate (61) abuts against the top wall of the limiting groove (71), and the rotating end of the bearing plate (61) is rotatably connected to any one side wall of the limiting groove (71), the movable end of the bearing plate (61) abuts against the other side wall of the limiting groove (71), and the fixing member (8) is arranged close to the movable end of the bearing plate (61).

4. A valve well and regulating tank connection structure according to claim 3, characterized in that: The fixing member (8) comprises a pull rope (80), a hook (81) and a hanging ring (82); the pull rope (80) is fixedly arranged at the movable end of the bearing plate (61); a through hole (9) is provided on the top wall of the water inlet pipe (5); the pull rope (80) passes through the through hole (9) and is fixedly connected to the hook (81); the hanging ring (82) is arranged on the outer wall of the water inlet pipe (5) near the through hole (9); the hook (81) is hung on the hanging ring (82).

5. A valve well and regulating tank connection structure according to claim 4, characterized in that: A fastening spring (800) is also sleeved on the pull rope (80), one end of the fastening spring (800) being fixedly connected to the top wall of the water inlet pipe (5), and the other end of the fastening spring (800) being fixedly connected to the bearing plate (61), the fastening spring (800) causing the bearing plate (61) to abut against the top wall of the limiting groove (71).

6. The valve well and regulating tank connection structure according to claim 3, characterized in that: A first sealing ring (610) is provided on the outer wall of the bearing plate (61), and a second sealing ring (611) adapted to the first sealing ring (610) is provided on the inner wall of the limiting groove (71).

7. The valve well and regulating tank connection structure according to claim 4, characterized in that: A transparent observation portion (90) is provided at the top of the water inlet pipe (5) near the perforation (9).

8. The valve well and regulating tank connection structure according to claim 3, characterized in that: A material guiding channel (70) is provided at the bottom of the water inlet pipe (5) around the material leakage opening (7).