Hinge drilling machining equipment
Through automated hinge drilling processing equipment, the use of belt conveyors and PLC control systems solves the problems of low hinge drilling processing efficiency and safety hazards in the existing technology, and achieves efficient and safe hinge drilling processing.
Patent Information
- Application Number
- CN202323511312.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-21
AI Technical Summary
The existing hinge drilling processing device has low processing efficiency, low product qualification rate, and has safety hazards caused by manual operation.
Design an automated hinge drilling processing equipment including a belt conveyor, transition channel, clamp and drilling power head. Automatic drilling of the hinge is realized through the PLC control system, and the belt conveyor is used to transfer the hinge to the transition channel. , the clamp clamps the hinge and then the drilling power head drills.
It improves processing efficiency and product qualification rate, eliminates safety hazards caused by manual operations, realizes automated drilling, and significantly improves production efficiency and safety.
Smart Images

Figure CN221791891U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a hinge processing device, in particular to hinge drilling processing equipment. Background Art
[0002] A hinge is a piece of hardware that connects two objects and enables them to move. It is a commonly used connector for doors, windows, cabinet doors, etc. The hinge includes a first hinge piece, a second hinge piece, and an axis core. The first hinge piece and the second hinge piece are provided with sleeves that are staggered with each other. The sleeves on the first hinge piece and the second hinge piece are connected through the axis core after being engaged, and the first hinge piece and the second hinge piece can rotate around the axis core. During processing, the hinge piece is stamped from a metal sheet, and the sleeve on the hinge piece is formed by curling. In order to achieve assembly accuracy, the inner hole of the sleeve of the hinge piece needs to be drilled to ensure the roundness and surface roughness of the inner hole of the sleeve, so that the designed accuracy level can be achieved when it cooperates with the axis core. The existing hinge drilling processing device mainly adopts the traditional bench drill, and the fixture adopts the ordinary flat-nose pliers. The drilling is done manually. Due to the special structure of the sleeve on the hinge, it is difficult to clamp and drill. The manual drilling processing efficiency is low, the drilling is easy to be off-center, and the product qualification rate is low. In addition, when manually operated, the drill bit is close to the hand, and the drill bit is easy to scratch the hand, causing harm to the human body, and there are safety hazards. Therefore, it is imperative to develop an automatic hinge drilling device specifically for drilling the inner hole of the hinge sleeve. Utility Model Content
[0003] In order to solve the problems of low processing efficiency, low product qualification rate and potential safety hazards in existing hinge drilling processing devices, the utility model provides a hinge drilling processing equipment, which can realize automatic drilling of hinges through a belt conveyor, a transition flow channel, a clamp, a drilling power head and other components combined with a PLC control system, and has the characteristics of high processing efficiency, high product qualification rate and safety and reliability.
[0004] The technical solution of the utility model is: a hinge drilling processing equipment, including a bracket, a belt conveyor and a drilling power head, the belt conveyor and the drilling power head are respectively installed at the left and right ends above the bracket, the output end of the belt conveyor is provided with a transition flow channel, the transition flow channel is provided with a through groove for accommodating the hinge, the transition flow channel can reciprocate in a direction perpendicular to the hinge conveying, a clamp capable of clamping the hinge is provided between the transition flow channel and the drilling power head, the transition flow channel has two working positions corresponding to the output end of the belt conveyor and the clamp, when the transition flow channel corresponds to the output end of the belt conveyor, the belt conveyor can convey the hinge into the through groove on the transition flow channel, the bracket is provided with a hinge pushing device, when the transition flow channel corresponds to the clamp, the hinge is clamped by the clamp and then drilled by the drilling power head.
[0005] The drilling power head, transition flow channel, clamp and hinge pushing device are all in two sets and are symmetrically arranged on both sides of the belt conveyor. An isolation plate is arranged above the belt conveyor to separate the belt on the belt conveyor into two conveying channels.
[0006] The transition flow channel is connected to the piston rod of the transition cylinder, and the transition flow channel is installed on the transition guide rail.
[0007] A material sensing block is provided on one side of the transition guide rail, and when the transition flow channel corresponds to the output end of the belt conveyor device, the material sensing block corresponds to the through groove on the transition flow channel.
[0008] The clamp is installed on a clamp seat, the clamp seat is connected to the piston rod of the clamp moving cylinder, the clamp seat is installed on the clamp seat track, and the clamp seat has two working positions corresponding to the hinge pushing device and the drilling power head.
[0009] The clamp is clamped and released by a clamping cylinder.
[0010] The frame is provided with a PLC control system.
[0011] The utility model has the following beneficial effects: due to the adoption of the above technical scheme, the hinge is conveyed to the through groove on the transition channel by the belt conveyor, and the transition channel then conveys the hinge to the fixture, and the hinge pushing device pushes the hinge into the fixture. After the fixture clamps the hinge, drilling can be performed by the drilling power head; the hinge loading method is convenient and fast, without unnecessary actions, and when the next hinge pushes the fixture, the last processed hinge is pushed out of the fixture, and there is no need to take out the processed hinge separately for a second time, and loading and unloading are carried out simultaneously, with high production efficiency. During the hinge processing, there is no need for manual participation of the operator, and the operator's limbs are away from the high-speed rotating drill bit, eliminating safety hazards. The utility model can realize automatic drilling of hinges through the belt conveyor, transition channel, fixture, drilling power head and other components combined with the PLC control system, and has the characteristics of high processing efficiency, high product qualification rate and safety and reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a stereogram of the utility model.
[0013] Figure 2 It is a structural schematic diagram of the transition flow channel 4 in the utility model.
[0014] Figure 3 It is a structural schematic diagram of the hinge pushing device 8 in the utility model.
[0015] Figure 4It is a schematic diagram of the structure of the clamp 7 in the present utility model.
[0016] In the figure: 1- bracket, 2- belt conveyor, 3- drilling power head, 4- transition flow channel, 5- hinge, 6- through groove, 7- fixture, 8- hinge pushing device, 9- isolation plate, 10- transition cylinder, 11- transition guide rail, 12- material sensing block, 13- fixture seat, 14- fixture moving cylinder, 15- fixture seat track, 16- clamping cylinder, 17-PLC control system, 18- connection channel. Implementation
[0017] The technical solution of the utility model is clearly and completely described below in conjunction with the accompanying drawings.
[0018] like Figures 1 to 4 As shown, a hinge drilling processing equipment includes a bracket 1, a belt conveyor 2 and a drilling power head 3 The belt conveyor 2 and the drilling power head 3 are respectively installed at the left and right ends above the bracket 1. The output end of the belt conveyor 2 is provided with a transition channel 4, and the transition channel 4 is provided with a through groove 6 for accommodating the hinge 5. The transition channel 4 can reciprocate in the direction perpendicular to the conveying direction of the hinge 5. A clamp 7 capable of clamping the hinge 5 is provided between the transition channel 4 and the drilling power head 3. The transition channel 4 has two working positions corresponding to the output end of the belt conveyor 2 and the clamp 7. When the transition channel 4 corresponds to the output end of the belt conveyor 2, the belt conveyor 2 can convey the hinge 5 to the through groove 6 on the transition channel 4. A hinge pushing device 8 is provided on the bracket 1. The hinge pushing device 8 is composed of a pushing cylinder and a pushing rod. When the transition channel 4 corresponds to the clamp 7, the hinge pushing device 8 can push the hinge 5 into the clamp 7, and the clamp 7 clamps the hinge 5 and then drills a hole through the drilling power head 3. Due to the adoption of the above technical solution, the hinge 5 is transmitted to the through groove 6 on the transition channel 4 by the belt conveyor 2, and the transition channel 4 then transports the hinge 5 to the fixture 7, and the hinge pushing device 8 pushes the hinge 5 into the fixture 7. After the fixture 7 clamps the hinge 5, drilling can be performed by the drilling power head 3; the hinge 5 loading method is convenient and fast, without redundant actions, and when the next hinge 5 pushes the fixture 7, the last processed hinge 5 is pushed out of the fixture 7 by the way, and there is no need to take out the processed hinge 5 separately for a second time, and loading and unloading are carried out simultaneously, with high production efficiency. During the processing of the hinge 5, there is no need for the operator to manually participate, and the operator's limbs are away from the high-speed rotating drill bit, eliminating safety hazards. The utility model can realize automatic drilling of the hinge 5 by combining the belt conveyor 2, the transition channel 4, the fixture 7 and the drilling power head 3 and other components with the PLC control system 17, and has the characteristics of high processing efficiency, high product qualification rate and safety and reliability.
[0019] The drilling power head 3, transition channel 4, fixture 7 and hinge push device 8 are all in two sets and are symmetrically arranged on both sides of the belt conveyor 2. A partition plate 9 is provided above the belt conveyor 2, and the partition plate 9 separates the belt on the belt conveyor 2 into two conveying channels. The drilling power head 3, transition channel 4, fixture 7 and hinge push device 8 adopt a double-set structure, and can complete the drilling processing of two hinges 5 in one cycle. Compared with the traditional bench drill that only processes one hinge 5 at a time, the production efficiency is greatly improved.
[0020] The transition channel 4 is connected to the piston rod of the transition cylinder 10, and the transition channel 4 is installed on the transition guide rail 11. The transition channel 4 can reciprocate along the transition guide rail 11 under the action of the transition cylinder 10.
[0021] A material sensing block 12 is provided on one side of the transition guide rail 11. When the transition channel 4 corresponds to the output end of the belt conveyor 2, the material sensing block 12 corresponds to the through slot 6 on the transition channel 4. After the material sensing block 12 detects the hinge 5, the belt conveyor 2 stops, and the transition cylinder 10 driving the transition channel 4 moves the transition channel 4 to the position of the fixture 7. The material sensing block 12 is used to detect whether there is a hinge 5 in the through slot 6. If there is a hinge 5, the transition cylinder 10 performs the transfer action. If there is no hinge 5, the transition cylinder 10 does not move.
[0022] The fixture 7 is mounted on a fixture seat 13, which is connected to the piston rod of a fixture moving cylinder 14, and the fixture seat 13 is mounted on a fixture seat track 15. The fixture seat 13 has two working positions corresponding to the hinge pushing device 8 and the drilling power head 3. When the hinge pushing device 8 pushes the hinge 5 into the fixture 7, the hinge pushing device 8 is reset, and the transition cylinder 10 is reset at the same time, and the next hinge 5 is prepared for processing. After the drilling power head 3 completes the drilling process, the drilling power head 3 is reset, and the fixture moving cylinder 14 and the clamping cylinder 16 are reset.
[0023] The clamp 7 is clamped and released by a clamping cylinder 16. The clamping cylinder 16 positions and locks the hinge 5 to prevent the hinge 5 from shaking.
[0024] The frame 1 is provided with a PLC control system 17. The PLC control system 17 uses a touch screen, which is convenient for operators to input and modify processing parameters, and can monitor the equipment operation status and fault prompts in real time, with a simple structure and convenient maintenance.
[0025] A connecting channel 18 is provided between the output end of the belt conveyor 2 and the transition channel 4. The connecting channel 18 plays a connecting and guiding role, and the distance between the connecting channel 18 and the transition channel 4 can be designed to be small, so that the hinge 5 can smoothly enter the through groove 6 of the transition channel 4. In addition, the connecting channel 18 can also temporarily store the hinge 5 to prevent the hinge 5 at the output end of the belt conveyor 2 from falling off when the belt conveyor 2 stops.
Claims
1. A hinge drilling processing device, comprising a support (1), a belt conveyor (2) and a drilling power head (3), wherein the belt conveyor (2) and the drilling power head (3) are respectively installed at the left and right ends above the support (1). Features: The output end of the belt conveyor (2) is provided with a transition channel (4), the transition channel (4) is provided with a through groove (6) for accommodating a hinge (5), the transition channel (4) is capable of reciprocating in a direction perpendicular to the conveying direction of the hinge (5), a clamp (7) capable of clamping the hinge (5) is provided between the transition channel (4) and the drilling power head (3), the transition channel (4) has two corresponding to the output end of the belt conveyor (2) and the clamp (7). In the working position, when the transition channel (4) corresponds to the output end of the belt conveyor (2), the belt conveyor (2) can convey the hinge (5) into the through groove (6) on the transition channel (4), and the bracket (1) is provided with a hinge pushing device (8). When the transition channel (4) corresponds to the clamp (7), the hinge pushing device (8) can push the hinge (5) into the clamp (7), and the clamp (7) clamps the hinge (5) and then drills a hole through the drilling power head (3).
2. A hinge drilling equipment according to claim 1, Features: The drilling power head (3), transition flow channel (4), clamp (7) and hinge pushing device (8) are all in two sets and are symmetrically arranged on both sides of the belt conveyor (2). An isolation plate (9) is provided above the belt conveyor (2), and the isolation plate (9) separates the belt on the belt conveyor (2) into two conveying channels.
3. A hinge drilling equipment according to claim 1 or 2, Features: The transition flow channel (4) is connected to the piston rod of the transition cylinder (10), and the transition flow channel (4) is installed on the transition guide rail (11).
4. A hinge drilling equipment according to claim 3, Features: A material sensing block (12) is provided on one side of the transition guide rail (11), and when the transition flow channel (4) corresponds to the output end of the belt conveyor (2), the material sensing block (12) corresponds to the through groove (6) on the transition flow channel (4).
5. A hinge drilling equipment according to claim 1 or 2, Features: The clamp (7) is mounted on a clamp seat (13), the clamp seat (13) is connected to the piston rod of a clamp moving cylinder (14), the clamp seat (13) is mounted on a clamp seat track (15), and the clamp seat (13) has two working positions corresponding to the hinge pushing device (8) and the drilling power head (3).
6. A hinge drilling equipment according to claim 1 or 2, Features: The clamp (7) is clamped and released by a clamping cylinder (16).
7. A hinge drilling equipment according to claim 1 or 2, Features: The frame (1) is provided with a PLC control system (17).
8. A hinge drilling equipment according to claim 1 or 2, Features: A storage channel (18) is provided between the output end of the belt conveyor device (2) and the transition flow channel (4).