Novel assembled cement stabilized recycled aggregate pavement base

Through the prefabricated cement-stabilized recycled aggregate pavement base layer, the reinforced recycled aggregate is combined with the cement mortar skeleton structure to solve the problems of long construction period of the traditional cement-stabilized gravel layer and difficult disposal of waste residue, and achieve rapid construction. and stable connection, improving the stability and environmental protection of the road base.

CN221798044UActive Publication Date: 2024-10-01ZHEJIANG PANGU GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202322916978.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-30
Publication Date
2024-10-01
Estimated Expiration
2033-10-30

AI Technical Summary

Technical Problem

The construction period of traditional cement-stabilized gravel layer is long and the waste disposal capacity is insufficient, which affects environmental protection and sustainable development of the project.

Method used

Prefabricated cement-stabilized recycled aggregate pavement base is used. The engineering waste residue is chemically and biologically reinforced to make recycled aggregate, and mixed with cement and sand to form prefabricated blocks, combined with a frame-type cement mortar skeleton structure and stable Connecting structures enable rapid construction and strengthened connections.

Benefits of technology

It has achieved a pavement base layer with fast construction speed, stable quality, green and environmental protection, improved the stability and connection strength of the pavement base layer, and reduced the generation of waste residue.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798044U_ABST
    Figure CN221798044U_ABST
Patent Text Reader

Abstract

The utility model discloses a novel assembled cement-stabilized recycled aggregate pavement base, which belongs to the field of pavement bases and comprises a cement-stabilized recycled aggregate pavement base structure laid at the upper end of a bottom soil road base structure. A top surface layer structure is laid at the upper end of the cement stabilized recycled aggregate pavement base structure, the cement stabilized recycled aggregate pavement base structure is composed of prefabricated cement stabilized recycled aggregate blocks, a cement mortar framework structure and a stable connecting structure, and the cement mortar framework structure is of a frame type structure. Prefabricated cement stabilized recycled aggregate blocks are assembled in a cement mortar skeleton structure, by adopting chemical and biological reinforcement means, recycled aggregate which is made of engineering waste muck and has high water resistance and certain strength is used for replacing gravel in a cement stabilized gravel base, and a prefabricated assembly construction method is adopted. A novel pavement base structure which is high in construction speed, stable in quality and environmentally friendly can be formed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of road base, in particular to a novel assembled cement-stabilized recycled aggregate road base. Background Art

[0002] The pavement base is the load-bearing part of the pavement structure. It mainly bears the vertical force of vehicle loads and diffuses the force transmitted from the surface layer to the roadbed. Therefore, the base should have sufficient strength, water stability and other engineering properties.

[0003] At present, the pavement base of high-grade highways generally adopts cement-stabilized crushed stone layers with high strength and water resistance. The construction of traditional cement-stabilized crushed stone layers requires multiple processes such as mixing, paving, rolling and maintenance, and the construction period is long. At the same time, the amount of waste soil generated during the construction process has increased sharply, and the problem of insufficient disposal capacity has begun to emerge, which has put forward new requirements for environmental protection and sustainable development of projects. Therefore, a new type of assembled cement-stabilized recycled aggregate pavement base is needed to solve the above problems. Utility Model Content

[0004] The main purpose of the utility model is to provide a novel assembled cement-stabilized recycled aggregate pavement base, which can effectively solve the problems in the background technology.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] A novel assembled cement-stabilized recycled aggregate pavement base comprises a cement-stabilized recycled aggregate pavement base structure, wherein the cement-stabilized recycled aggregate pavement base structure is laid on the upper end of a bottom soil road base structure, and a top surface layer structure is laid on the upper end of the cement-stabilized recycled aggregate pavement base structure. The cement-stabilized recycled aggregate pavement base structure is composed of prefabricated cement-stabilized recycled aggregate blocks, a cement mortar skeleton structure and a stable connection structure. The cement mortar skeleton structure is a frame structure, and the prefabricated cement-stabilized recycled aggregate blocks are assembled in the cement mortar skeleton structure. The prefabricated cement-stabilized recycled aggregate blocks are prefabricated structures, and the prefabricated cement-stabilized recycled aggregate blocks are connected to the cement mortar skeleton structure by on-site assembly. The stable connection structure is installed on the cement mortar skeleton structure, and the stable connection structure is composed of an insertion pin rod structure and a top stable connection plate. The top stable connection plate is installed on the upper end of the insertion pin rod structure, and the lower part of the insertion pin rod structure is inserted into the bottom soil road base structure, and the upper part of the insertion pin rod structure and the top stable connection plate are embedded in the top surface layer structure.

[0007] Preferably, the top surface structure is an asphalt layer.

[0008] Preferably, a stabilizing connection groove is provided on the outer wall of the prefabricated cement-stabilized recycled aggregate block on the cement-stabilized recycled aggregate pavement base structure.

[0009] Preferably, the prefabricated cement-stabilized recycled aggregate block is formed by mixing cement, sand, recycled aggregate and water in a certain proportion.

[0010] Preferably, the recycled aggregate is made from engineering waste soil and is reinforced by a curing agent and biological treatment. The curing agent includes cement and magnesium oxide. The particle size of the recycled aggregate is .cm-cm.

[0011] Preferably, a cement mortar stabilizing connecting strip is provided on the side wall of the cement mortar skeleton structure on the cement-stabilized recycled aggregate pavement base structure, the cement mortar skeleton structure and the cement mortar stabilizing connecting strip are an integrally formed structure, and the cement mortar stabilizing connecting strip is located in a stabilizing connecting groove provided on the outer wall of the prefabricated cement-stabilized recycled aggregate block.

[0012] Preferably, the insertion pin rod structure on the stable connection structure and the top stable connection plate are an integrally formed structure, and the insertion pin rod structure passes through the cement mortar skeleton structure from top to bottom.

[0013] Compared with the prior art, the utility model has the following beneficial effects:

[0014] By adopting chemical and biological reinforcement methods, recycled aggregates with high water resistance and certain strength made from engineering waste are used to replace the crushed stone in the cement-stabilized crushed stone base, and a prefabricated assembly construction method is adopted to form a new pavement base structure with fast construction speed, stable quality, and green environmental protection; by setting up a stable connection structure, the connection strength between the cement-stabilized recycled aggregate pavement base structure and the bottom earth road base structure and the top surface structure can be strengthened, making it less likely for the strengthened cement-stabilized recycled aggregate pavement base structure and the bottom earth road base structure and the top surface structure to produce relative displacement, which can ultimately improve the stability of the pavement base. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0016] Figure 2 It is a structural schematic diagram of the cement-stabilized recycled aggregate pavement base structure of the utility model;

[0017] Figure 3 It is a structural schematic diagram of the cement mortar skeleton structure and the stable connection structure of the utility model;

[0018] Figure 4 It is a structural schematic diagram of the prefabricated cement-stabilized recycled aggregate block of the utility model.

[0019] In the figure: 1. Cement stabilized recycled aggregate pavement base structure; 2. Bottom soil road base structure; 3. Top surface structure; 4. Prefabricated cement stabilized recycled aggregate blocks; 5. Cement mortar skeleton structure; 6. Stable connection structure; 7. Stable connection groove; 8. Cement mortar stable connection strip; 9. Insert pin rod structure; 10. Top stable connection plate. DETAILED DESCRIPTION

[0020] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0021] See also Figure 1 , Figure 2 , Figure 3 , Figure 4 As shown, a new type of assembled cement-stabilized recycled aggregate pavement base comprises a cement-stabilized recycled aggregate pavement base structure 1, which is laid on the upper end of a bottom soil road base structure 2, and a top surface layer structure 3 is laid on the upper end of the cement-stabilized recycled aggregate pavement base structure 1, and the top surface layer structure 3 is an asphalt layer.

[0022] See also Figure 1 , Figure 2 , Figure 3 , Figure 4As shown, the cement stabilized recycled aggregate pavement base structure 1 is composed of a prefabricated cement stabilized recycled aggregate block 4, a cement mortar skeleton structure 5 and a stable connection structure 6. The cement mortar skeleton structure 5 is a frame structure. The prefabricated cement stabilized recycled aggregate block 4 is assembled in the cement mortar skeleton structure 5. The prefabricated cement stabilized recycled aggregate block 4 is a prefabricated structure. The prefabricated cement stabilized recycled aggregate block 4 is connected to the cement mortar skeleton structure 5 through on-site assembly. The stable connection structure 6 is installed on the cement mortar skeleton structure 5. The stable connection structure 6 is composed of an inserted pin rod structure 9 and a top stable connection plate 10. The top stable connection The connecting plate 10 is installed at the upper end of the insertion pin rod structure 9, the lower part of the insertion pin rod structure 9 is inserted into the bottom soil road base structure 2, the upper part of the insertion pin rod structure 9 and the top stable connecting plate 10 are embedded in the top surface layer structure 3, and the outer wall of the prefabricated cement stable recycled aggregate block 4 on the cement stable recycled aggregate road base structure 1 is provided with a stable connecting groove 7. The prefabricated cement stable recycled aggregate block 4 is made of cement, sand, recycled aggregate and water mixed in a certain proportion. The recycled aggregate is made of engineering waste slag as raw material and is obtained by curing agent and biological treatment reinforcement. The curing agent includes cement and magnesium oxide. The recycled aggregate The particle size is divided into 0.5cm-3cm, and a cement mortar stable connecting strip 8 is arranged on the side wall of the cement mortar skeleton structure 5 on the cement stabilized recycled aggregate pavement base structure 1. The cement mortar skeleton structure 5 and the cement mortar stable connecting strip 8 are an integrally formed structure, and the cement mortar stable connecting strip 8 is located in a stable connecting groove 7 arranged on the outer wall of the prefabricated cement stabilized recycled aggregate block 4. The insertion pin rod structure 9 on the stable connecting structure 6 is an integrally formed structure with the top stable connecting plate 10, and the insertion pin rod structure 9 passes through the cement mortar skeleton structure 5 from top to bottom. By adopting chemical and biological reinforcement means, the cement mortar skeleton structure 5 is formed by the cement stabilized recycled aggregate pavement base structure 1. Recycled aggregates made from engineering waste soil with high water resistance and certain strength are used to replace the crushed stones in the cement-stabilized crushed stone base, and the prefabricated assembly construction method is adopted to form a new type of pavement base structure with fast construction speed, stable quality and green environmental protection. The existence of the stable connection structure 6 can strengthen the connection strength between the cement-stabilized recycled aggregate pavement base structure 1 and the bottom earth road base structure 2 and the top surface layer structure 3, so that the reinforced cement-stabilized recycled aggregate pavement base structure 1 and the bottom earth road base structure 2 and the top surface layer structure 3 are not easy to produce relative displacement, which can ultimately improve the stability of the pavement base.

[0023] It should be noted that the utility model is a novel assembled cement-stabilized recycled aggregate pavement base. When in use, cement and magnesium oxide are mixed in a certain proportion, and then water is added until the water content reaches the plastic limit of the mixture and then stirred evenly to form a curing agent, and then the curing agent is mixed with engineering waste slag, and then the mixture formed by the curing agent and the engineering waste slag is squeezed into a dense sphere with a particle size of 0.5cm-3cm and a smooth surface through a ball press, and then the dense sphere is subjected to biological enzyme reinforcement treatment and maintenance, at this time, the recycled aggregate is formed, and then the recycled aggregate is mixed with cement, sand and water, and then the mixture is put into a mold for molding, and the product is ready. The prefabricated cement stabilized recycled aggregate block 4 is finally transported to the construction site after reaching the designed strength through maintenance methods such as watering and covering. After the bottom soil road base structure 2 at the site is compacted and leveled, the prefabricated cement stabilized recycled aggregate block 4 is laid on the upper end of the bottom soil road base structure 2, and a gap of 0.5cm-1cm is reserved between two adjacent prefabricated cement stabilized recycled aggregate blocks 4. After the prefabricated cement stabilized recycled aggregate block 4 is laid, the insertion pin rod structure 9 on the stable connection structure 6 is inserted into the bottom soil road base structure 2 from the reserved gap between the two adjacent prefabricated cement stabilized recycled aggregate blocks 4. At this time, the top stable connection plate 10 needs to be in the prefabricated Above the cement-stabilized recycled aggregate block 4, cement mortar with a strength grade not lower than that of the prefabricated cement-stabilized recycled aggregate block 4 is then injected into the gap between two adjacent prefabricated cement-stabilized recycled aggregate blocks 4, thereby forming a cement mortar skeleton structure 5 and a cement mortar stable connecting strip 8. After the cement mortar skeleton structure 5 and the cement mortar stable connecting strip 8 are solidified, the cement mortar skeleton structure 5 and the inserted pin rod structure 9 on the stable connecting structure 6 are fixed together, and finally an asphalt layer is laid on the upper end of the cement-stabilized recycled aggregate pavement base structure 1. At this time, the laid asphalt layer will stabilize the upper part of the inserted pin rod structure 9 on the stable connecting structure 6 and the top of the stable connecting structure 6. The stable connecting plate 10 is wrapped, and by adopting chemical and biological reinforcement means, the recycled aggregate with high water resistance and certain strength made of engineering waste soil is used to replace the crushed stone in the cement-stabilized crushed stone base, and the prefabricated assembly construction method is adopted, which can form a new type of pavement base structure with fast construction speed, stable quality and green environmental protection. By setting the stable connecting structure 6, the connection strength between the cement-stabilized recycled aggregate pavement base structure 1 and the bottom earth road base structure 2 and the top surface layer structure 3 can be strengthened, so that the strengthened cement-stabilized recycled aggregate pavement base structure 1 and the bottom earth road base structure 2 and the top surface layer structure 3 are not easy to produce relative displacement, which can ultimately improve the stability of the pavement base.

[0024] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the aforementioned embodiments, it is still possible for a person skilled in the art to modify the technical solutions described in the aforementioned embodiments or to replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model. The protection scope of the utility model is defined by the attached claims and their equivalents.

Claims

1. A novel assembled cement-stabilized recycled aggregate pavement base layer, comprising a cement-stabilized recycled aggregate pavement base layer structure (1), wherein the cement-stabilized recycled aggregate pavement base layer structure (1) is laid on the upper end of a bottom soil road base layer structure (2), and a top surface layer structure (3) is laid on the upper end of the cement-stabilized recycled aggregate pavement base layer structure (1), characterized in that: The cement stabilized recycled aggregate pavement base structure (1) is composed of a prefabricated cement stabilized recycled aggregate block (4), a cement mortar skeleton structure (5) and a stable connection structure (6). The cement mortar skeleton structure (5) is a frame structure. The prefabricated cement stabilized recycled aggregate block (4) is assembled in the cement mortar skeleton structure (5). The prefabricated cement stabilized recycled aggregate block (4) is a prefabricated structure. The prefabricated cement stabilized recycled aggregate block (4) and the cement mortar skeleton structure (5) are connected by on-site assembly. The stable connection structure (6) is installed on the cement mortar skeleton structure (5). The stable connection structure (6) is composed of an insertion pin rod structure (9) and a top stable connection plate (10). The top stable connection plate (10) is installed on the upper end of the insertion pin rod structure (9). The lower part of the insertion pin rod structure (9) is inserted into the bottom soil road base structure (2). The upper part of the insertion pin rod structure (9) and the top stable connection plate (10) are embedded in the top surface layer structure (3).

2. According to claim 1, a novel assembled cement-stabilized recycled aggregate pavement base layer is characterized by: The top surface layer structure (3) is an asphalt layer.

3. The novel assembled cement-stabilized recycled aggregate pavement base according to claim 2 is characterized by: A stabilizing connection groove (7) is provided on the outer wall of the prefabricated cement-stabilized recycled aggregate block (4) on the cement-stabilized recycled aggregate pavement base structure (1).

4. The novel assembled cement-stabilized recycled aggregate pavement base according to claim 3 is characterized by: The particle size of the recycled aggregate is 0.5cm-3cm.

5. The novel assembled cement-stabilized recycled aggregate pavement base according to claim 4 is characterized by: A cement mortar stabilizing connecting strip (8) is provided on the side wall of the cement mortar skeleton structure (5) on the cement stabilized recycled aggregate pavement base structure (1); the cement mortar skeleton structure (5) and the cement mortar stabilizing connecting strip (8) are an integrally formed structure, and the cement mortar stabilizing connecting strip (8) is located in a stabilizing connecting groove (7) provided on the outer wall of the prefabricated cement stabilized recycled aggregate block (4).

6. The novel assembled cement-stabilized recycled aggregate pavement base according to claim 5 is characterized by: The insertion pin rod structure (9) on the stable connection structure (6) and the top stable connection plate (10) are an integrally formed structure, and the insertion pin rod structure (9) passes through the cement mortar skeleton structure (5) from top to bottom.