Fabricated bridge deck slab
Through the design of the prefabricated bridge deck, the use of L-shaped steel plates and extended rib structures combined with cast-in-place concrete filling solves the problems of construction complexity and safety hazards of the bridge substructure, and achieves the effect of simplifying the process and improving construction efficiency.
Patent Information
- Application Number
- CN202323410318.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-14
AI Technical Summary
The on-site pouring construction of the bridge substructure has problems such as complex procedures, long construction period, difficulty in ensuring construction quality, and potential safety hazards, especially when crossing rivers, lakes, or in small construction spaces.
The prefabricated bridge deck is adopted, including the piers and the first and second bridge decks that are pressed against the top of the piers. Through the combined structure of L-shaped steel plates, extended ribs and steel bars, the connection grooves are filled with cast-in-place concrete, combined with high-strength bolts and Steel bar connecting sleeves realize the disassembly and connection of the bridge deck and the integrated construction.
The construction process is simplified, the connection reliability and construction efficiency are improved, the construction period is shortened, the waste of raw materials is reduced, and the construction safety is enhanced.
Smart Images

Figure CN221798152U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to an assembled bridge deck. Background Art
[0002] Prefabricated and assembled construction has gradually replaced traditional on-site cast-in-place concrete construction and is widely used in the field of bridge construction. Its characteristics are centralized prefabrication of components in the factory, full use of modern formwork and maintenance technology, and transportation of components to the bridge site for on-site assembly after prefabrication. Node connection technology is used to connect scattered components into a whole to meet the performance requirements under operational and extreme load conditions, thereby realizing the industrialization, automation and assembly construction of bridge component production.
[0003] The bridge pier is the intermediate supporting structure of a bridge with two or more spans, except for the abutments at both ends that connect to the embankment. The bridge pier is mainly composed of a cap and a pier body. The bridge abutment is mainly composed of a cap and a pier body. The bridge piers are divided into solid piers, column piers and frame piers. According to the plane shape, they can be divided into rectangular piers, pointed piers, circular piers, etc. The materials used to build bridge piers can be wood, stone, concrete, reinforced concrete, steel, etc. The location of the bridge pier is closely related to the span arrangement of the bridge superstructure and should be determined through technical and economic comparisons. At present, for the construction of bridges in expressways, local roads and urban roads, the upper structure of the bridge (i.e., the driving part) has been prefabricated and assembled, while the lower structure of the bridge (i.e., the pier part) is still cast on site using traditional technology. During the construction of bridges, when encountering narrow construction space, short construction period and high construction quality requirements such as crossing rivers, lakes or roads, the conventional on-site cast concrete construction plan requires more templates and scaffolding, a long construction period, and it is difficult to ensure the quality and accuracy of on-site casting. In addition, the personal safety of on-site construction workers cannot be guaranteed, and there are certain safety hazards. In the existing housing construction technology, the floor slab of the light house structure mainly adopts the form of cast-in-place reinforced concrete floor slab. The cast-in-place reinforced concrete floor slab requires multiple construction processes such as formwork, steel bar binding, concrete pouring, maintenance, and demolding at the construction site, and the upper structure can only be installed after the floor slab concrete maintenance reaches the design strength. Therefore, it has the defect of complex construction process. Summary of the invention
[0004] The utility model aims to provide an assembled bridge deck in view of the problem of complicated construction process in the background technology.
[0005] The technical solution of the utility model is as follows: an assembled bridge deck, comprising a bridge pier and a first bridge deck and a second bridge deck pressed against two ends of the top of the bridge pier, the first bridge deck and the second bridge deck are prefabricated with an L-shaped steel plate on one side opposite to the other, the L-shaped steel plate is detachably connected to the bridge pier, a first protruding rib is fixed to the bottom of the first bridge deck near the second bridge deck, a first protruding steel bar fixed to the first bridge deck is fixed on the first protruding rib, and a first groove is provided on the top of the first protruding rib;
[0006] A second protruding rib is fixed to the bottom of the second bridge deck on one side close to the first bridge deck, a second protruding steel bar is prefabricated above the second protruding rib, a second groove for inserting the first protruding rib is opened at the bottom of the second protruding rib, and the second protruding rib overlaps with the first groove.
[0007] Optionally, a connecting groove is formed on one side of the first bridge deck and the second bridge deck that are opposite to each other, and the first and second extending steel bars are located in the connecting groove.
[0008] Optionally, the connection groove is filled with cast-in-place concrete to connect the entire structure into a whole.
[0009] Optionally, the positions of the first protruding steel bar and the second protruding steel bar correspond to each other, and a steel bar connecting sleeve is provided between the first protruding steel bar and the second protruding steel bar.
[0010] Optionally, steel plate grooves for inserting L-shaped steel plates are respectively opened inwardly on both sides of the pier, and reserved bolt holes connected to the steel plate grooves are opened on both sides of the pier, and a first high-strength bolt is threadedly installed on the reserved bolt hole, and one end of the first high-strength bolt is threadedly connected to the L-shaped steel plate.
[0011] Optionally, both the first and second protruding ribs are provided with threaded holes, the threaded hole of the first and second protruding ribs are connected, the threaded hole of the first and second protruding ribs are located directly below the threaded hole of the second protruding rib, and a second high-strength bolt is threadedly installed between the threaded hole of the first and second protruding ribs.
[0012] Compared with the prior art, the utility model has the following beneficial technical effects:
[0013] The utility model increases the contact area and friction between the first bridge deck and the second bridge deck, further strengthens the connection reliability between the first bridge deck and the second bridge deck, connects and locks the first bridge deck and the second bridge deck, is easy to operate, has a simple structure and good integrity, greatly shortens the construction period, reduces raw material waste, and greatly improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1Schematic diagram of prefabricated bridge deck.
[0015] Figure 2 This is a diagram of the bridge deck splicing.
[0016] Figure 3 Top view of the bridge deck.
[0017] In the figure: 1. first bridge deck; 1-1. first protruding rib; 1-2. first protruding steel bar; 1-3. first groove; 2. second bridge deck; 2-1. second protruding rib; 2-2. second protruding steel bar; 2-3. second groove; 3. bridge pier; 4. steel plate groove; 5. L-shaped steel plate; 6. connecting groove; 7. cast-in-place concrete; 8. steel bar connecting sleeve; 9. reserved bolt hole; 10. first high-strength bolt. DETAILED DESCRIPTION
[0018] The technical solution of the present utility model will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present utility model, rather than all of the embodiments.
[0019] The components of the embodiments of the present invention generally described and shown in the drawings herein can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention.
[0020] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.
[0021] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0022] It should be noted that the terms "include", "comprises" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0023] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0024] Example
[0025] like Figure 1 As shown, the utility model proposes an assembled bridge deck, including a bridge pier 3 and a first bridge deck 1 and a second bridge deck 2 pressed against the two ends of the top of the bridge pier 3, and the first bridge deck 1 and the second bridge deck 2 are pressed against the bridge pier 3.
[0026] like Figure 1-3 As shown, an L-shaped steel plate 5 is prefabricated on the opposite side of the first bridge panel 1 and the second bridge panel 2. The L-shaped steel plate 5 is cast together with the first bridge panel 1 and the second bridge panel 2, and the L-shaped steel plate 5 is detachably connected to the pier 3; steel plate grooves 4 for inserting the L-shaped steel plate 5 are respectively opened inward on both sides of the pier 3, and reserved bolt holes 9 connected to the steel plate grooves 4 are opened on both sides of the pier 3. The reserved bolt holes 9 are threadedly installed with first high-strength bolts 10, and one end of the first high-strength bolt 10 is threadedly connected to the L-shaped steel plate 5. The first high-strength bolt 10 is used to fix the connection between the first bridge panel 1 and the second bridge panel 2 and the pier 3 through the provision of the first high-strength bolt 10.
[0027] Among them, a first protruding rib 1-1 is fixed to the bottom of one side of the first bridge deck 1 close to the second bridge deck 2, a first protruding steel bar 1-2 fixed to the first bridge deck 1 is fixed on the first protruding rib 1-1, and a first groove 1-3 is opened on the top of the first protruding rib 1-1; through the arrangement of the first protruding rib 1-1, the first protruding steel bar 1-2 and the first groove 1-3, the contact area and friction force between the first bridge deck 1 and the second bridge deck 2 are increased, so that during casting, the connection between the first bridge deck 1 and the second bridge deck 2 is made more secure and stable.
[0028] In addition, a second protruding rib 2-1 is fixed to the bottom of the second bridge deck 2 near the first bridge deck 1, a second protruding steel bar 2-2 is prefabricated above the second protruding rib 2-1, a second groove 2-3 for the first protruding rib 1-1 to be inserted is provided at the bottom of the second protruding rib 2-1, and the second protruding rib 2-1 overlaps with the first groove 1-3. By providing a combination of the second protruding rib 2-1, the second protruding steel bar 2-2, and the second groove 2-3, the contact area and friction force between the first bridge deck 1 and the second bridge deck 2 are increased, and the connection reliability between the first bridge deck 1 and the second bridge deck 2 is further strengthened.
[0029] like Figure 1 As shown, a connecting groove 6 is opened on the opposite side of the first bridge deck 1 and the second bridge deck 2, the first protruding steel bar 1-2 and the second protruding steel bar 2-2 are located in the connecting groove 6, and the connecting groove 6 is filled with cast-in-place concrete 7 to connect the entire structure into a whole.
[0030] Further, such as Figure 1-2 As shown, the positions of the first protruding steel bar 1-2 and the second protruding steel bar 2-2 correspond, and a steel bar connection sleeve 8 is sleeved between the first protruding steel bar 1-2 and the second protruding steel bar 2-2. After the concrete is poured later, the steel bar connection sleeve 8 is connected to the first protruding steel bar 1-2 and the second protruding steel bar 2-2 as a whole, so that the first protruding steel bar 1-2 and the second protruding steel bar 2-2 are firmly connected.
[0031] It is worth noting that if Figure 2-3 As shown, the first cantilever rib 1-1 and the second cantilever rib 2-1 are both provided with threaded holes, the threaded hole of the first cantilever rib 1-1 and the threaded hole of the second cantilever rib 2-1 are connected, the threaded hole of the first cantilever rib 1-1 is located directly below the threaded hole of the second cantilever rib 2-1, and a second high-strength bolt is threadedly installed between the threaded hole of the first cantilever rib 1-1 and the threaded hole of the second cantilever rib 2-1. By adding the second high-strength bolt in the vertical direction and screwing it into the threaded hole of the first cantilever rib 1-1 and the threaded hole of the second cantilever rib 2-1, the first bridge deck 1 and the second bridge deck 2 are connected and locked, which is convenient to operate, simple in structure and good in integrity.
[0032] The above-mentioned specific embodiments are only several optional embodiments of the present invention. Based on the technical solution of the present invention and the relevant inspiration of the above-mentioned embodiments, those skilled in the art can make various alternative improvements and combinations to the above-mentioned specific embodiments.
Claims
1. An assembled bridge deck, comprising a bridge pier (3) and a first bridge deck (1) and a second bridge deck (2) pressed against the top ends of the bridge pier (3), an L-shaped steel plate (5) is prefabricated on the opposite side of the first bridge deck (1) and the second bridge deck (2), and the L-shaped steel plate (5) is detachably connected to the bridge pier (3), characterized in that: A first protruding rib (1-1) is fixed to the bottom of one side of the first bridge deck (1) close to the second bridge deck (2), a first protruding steel bar (1-2) fixed to the first bridge deck (1) is fixed to the first protruding rib (1-1), and a first groove (1-3) is provided at the top of the first protruding rib (1-1); A second protruding rib (2-1) is fixed to the bottom of one side of the second bridge deck (2) close to the first bridge deck (1); a second protruding steel bar (2-2) is prefabricated above the second protruding rib (2-1); a second groove (2-3) for the first protruding rib (1-1) to be inserted is provided at the bottom of the second protruding rib (2-1); the second protruding rib (2-1) and the first groove (1-3) are overlapped in cooperation.
2. The assembled bridge deck according to claim 1, characterized in that: A connecting groove (6) is provided on one side of the first bridge deck (1) and the second bridge deck (2) that is opposite to each other, and the first protruding steel bar (1-2) and the second protruding steel bar (2-2) are located in the connecting groove (6).
3. The assembled bridge deck according to claim 2, characterized in that: The connection groove (6) is filled with cast-in-place concrete (7).
4. The assembled bridge deck according to claim 1, characterized in that: The positions of the first protruding steel bar (1-2) and the second protruding steel bar (2-2) correspond to each other, and a steel bar connection sleeve (8) is sleeved between the first protruding steel bar (1-2) and the second protruding steel bar (2-2).
5. The assembled bridge deck according to claim 1, characterized in that: The two sides of the bridge pier (3) are respectively provided with steel plate grooves (4) for inserting the L-shaped steel plate (5), and the two sides of the bridge pier (3) are provided with reserved bolt holes (9) connected with the steel plate grooves (4), and the reserved bolt holes (9) are threadedly installed with first high-strength bolts (10), and one end of the first high-strength bolt (10) is threadedly connected to the L-shaped steel plate (5).
6. The assembled bridge deck according to claim 1, characterized in that: The first protruding rib (1-1) and the second protruding rib (2-1) are both provided with threaded holes, the threaded hole of the first protruding rib (1-1) is connected to the threaded hole of the second protruding rib (2-1), the threaded hole of the first protruding rib (1-1) is located directly below the threaded hole of the second protruding rib (2-1), and a second high-strength bolt is threadedly installed between the threaded hole of the first protruding rib (1-1) and the threaded hole of the second protruding rib (2-1).