Novel tubular pile joint structure
Through the spiral docking method of the new pipe pile joint structure and the threaded structure of the connecting column and the connecting sleeve, the problems of poor pipe pile splicing quality and low construction efficiency in the existing technology are solved, and efficient and stable pipe pile connection is achieved. Building safety and construction efficiency are ensured.
Patent Information
- Application Number
- CN202323460029.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-19
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-19
AI Technical Summary
The on-site splicing of existing pipe piles has problems of poor quality, low construction efficiency, and poor stability. In particular, welded joints are greatly affected by weather and operators, and traditional mechanical connections take a long time to connect and have large vertical errors, leading to potential construction safety hazards.
A new pipe pile joint structure is adopted, including the lower end pile head and the upper end pile head of the pipe pile. Through the spiral docking of the connecting column and the connecting sleeve, the threaded structure is used to achieve rapid positioning and connection, reduce the welding process, and improve the construction efficiency and joint stability.
It improves the joint bearing capacity and docking verticality of pipe piles, simplifies the construction process, reduces quality problems and thermal deformation risks, ensures construction efficiency and safety, and reduces labor costs and welding quality problems.
Smart Images

Figure CN221798416U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of pipe piles, in particular to a pipe pile joint butt joint structure. Background Art
[0002] With the rapid development of construction projects, special building models have higher and higher requirements for pile foundations. A single pipe pile may not be able to meet the requirements, which requires connecting multiple pipe piles into a whole to improve their overall bearing capacity and stability.
[0003] There are serious defects in the on-site splicing of pipe piles today. Conventional welded joints are greatly affected by weather and the level of operators, and are usually of poor quality. The cooling time of the welds is insufficient. After the piles are pressed into the soil, the welds quickly cool down when they encounter groundwater, causing cracks in the welds and poor quality of the pile connections. If the cooling time of the welds is not guaranteed, the construction efficiency will be affected, and the difficulty of sinking the pipe piles will increase due to soil recovery, which often leads to failure to reach the designed elevation and poses a hidden danger to building safety. With traditional mechanical connections, the centering and positioning of the two-section piles requires manpower and auxiliary facilities at the same time. The time for connecting the piles is long, the coaxiality and verticality errors are large, the connection stability of the two end faces is poor, and gaps are easily generated between the two end plate planes, which brings unimaginable adverse consequences to the building. Utility Model Content
[0004] In order to solve the above technical problems, the utility model provides a new type of pipe pile joint structure, including a pile head at the lower end of the pipe pile and a pile head at the upper end of the pipe pile; the pile head at the lower end of the pipe pile includes a hollow pipe pile body, an end plate, a connecting column and a pile sleeve; the connecting column is externally connected to the end plate; the pile head at the upper end of the pipe pile includes a hollow pipe pile body, an end plate, a connecting sleeve and a pile sleeve; the connecting sleeve is provided with a cavity adapted to the connecting column, and the connecting sleeve is embedded in the end of the hollow pipe pile body; the pile sleeve is externally wrapped around the hollow pipe pile body, and the end plate is located at the end where the hollow pipe pile body is connected; the connecting column and the connecting sleeve are arranged opposite to each other.
[0005] The connecting column can be quickly plugged into the connecting sleeve for easy positioning and connection.
[0006] Preferably, the connecting column is conical and is provided with an external thread; the connecting sleeve is provided with a conical cavity, and the inner wall of the connecting sleeve is provided with an internal thread, which matches the external thread of the connecting column.
[0007] The connecting column is conical in shape. When the first section of the pile body sinks, the pipe pile can be rotated and the connecting column at the lower end of the pipe pile can be used to quickly break the ground.
[0008] Preferably, the connecting column is cylindrical and is provided with an external thread; the connecting sleeve is cylindrical and the inner wall of the connecting sleeve is provided with an internal thread, which matches the external thread of the connecting column.
[0009] Preferably, the connecting column is covered with a steel plate and is welded and fixed to the end plate, and the interior is filled with high-strength concrete.
[0010] Preferably, the connecting sleeve is formed by pressing a steel coil, is filled with high-strength concrete on all sides and is welded and fixed to the end plate.
[0011] Preferably, the end plate is provided with main reinforcement anchor holes which are evenly distributed around the circumference of the end plate.
[0012] Preferably, the hollow pipe pile body is a hollow cylinder, and its diameter can be adjusted according to actual engineering.
[0013] Preferably, the pile sleeve is made of steel plate rolled into a cylindrical shape, the joints are welded and rounded, and the two indentations can be made into other forms, depending on the actual project.
[0014] The utility model discloses a pipe pile joint structure, which rotatably connects a connecting column at one end with a connecting sleeve at the other end, thereby improving the bearing capacity of the joint of the hollow pipe pile, ensuring the verticality of the connection of multi-section pipe piles, and having high construction efficiency.
[0015] Compared with the original pipe pile joint butt joint type, the new pipe pile joint structure adopts a spiral butt joint structure. The spiral butt joint of pipe pile joints can improve work efficiency and save construction time. Since the spiral butt joint method can simplify the construction process, it reduces the butt joint time and labor costs. At the same time, the new butt joint method can reduce the welding process, reduce the risk of thermal deformation and stress concentration generated during the butt joint process, reduce quality problems during the butt joint process, improve the stability and sealing of the joint, and ensure the safety and reliability of the pipe pile. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The present invention is further described below in conjunction with the accompanying drawings and specific implementations.
[0017] Figure 1 This is a structural schematic diagram of a novel pipe pile joint structure of Example 1 of the utility model;
[0018] Figure 2 This is a schematic diagram of the pipe pile joint connection of Example 1 of the utility model;
[0019] Figure 3 yes Figure 2 Bottom view of the middle pipe pile joint;
[0020] Figure 4 yes Figure 3 AA section view.
[0021] Figure 5 This is a structural schematic diagram of a new type of pipe pile joint structure in Example 2 of the utility model;
[0022] Figure 6This is a schematic diagram of the pipe pile joint connection of Example 2 of the utility model;
[0023] Figure 7 yes Figure 6 Bottom view of the middle pipe pile joint;
[0024] Figure 8 yes Figure 7 AA section view. DETAILED DESCRIPTION
[0025] The technical solution of the utility model is further described in detail below in conjunction with the accompanying drawings.
[0026] Example 1
[0027] like Figure 1-4 As shown, the utility model discloses a novel pipe pile joint structure, comprising a pipe pile lower end pile head 1 and a pipe pile upper end pile head 2; the pipe pile lower end pile head 1 comprises a hollow pipe pile body 3, an end plate 4, a connecting column 5 and a pile hoop 8; the connecting column 5 is externally connected to the end plate 4; the pipe pile upper end pile head 2 comprises a hollow pipe pile body 3, an end plate 4, a connecting sleeve 7 and a pile hoop 8; the connecting sleeve 7 is provided with a cavity adapted to the connecting column 5, and the connecting sleeve 7 is embedded in the end of the hollow pipe pile body 3; the pile hoop 8 is externally wrapped around the hollow pipe pile body 3, and the end plate 4 is located at the end where the hollow pipe pile body 3 is connected; the connecting column 5 and the connecting sleeve 7 are arranged opposite to each other.
[0028] The connecting column 5 is conical and is provided with external threads.
[0029] The connecting column 5 is covered with a steel plate and is welded and fixed to the end plate 4, and the interior thereof is filled with high-strength concrete.
[0030] The connecting sleeve 7 is provided with a conical cavity, and the inner wall of the connecting sleeve 7 is provided with an internal thread, which matches the external thread of the connecting column 5 .
[0031] The connecting sleeve 7 is formed by pressing a steel coil, is filled with high-strength concrete on all sides and is welded and fixed to the end plate.
[0032] The end plate 4 is provided with main reinforcement anchor holes 6, which are evenly distributed around the end plate 4;
[0033] The hollow pipe pile body 3 is a hollow cylinder.
[0034] The pile hoop 8 is made of steel plate rolled into a cylindrical shape and welded at the joints.
[0035] When the first section of the pipe pile is buried in the ground, the new type of pipe pile can use the connecting column to quickly break the ground, reducing the time for pile sinking and greatly improving the efficiency of pipe pile construction.
[0036] The technical solution for butt jointing of pipe pile joints in this embodiment includes the following steps:
[0037] (1) Select pipe piles with the appropriate diameter according to the actual project and determine the required number of pipe piles;
[0038] (2) Welding the connecting column 5 to the end plate 4 at the lower end of the pipe pile;
[0039] (3) Determine the pile sinking position, align the pile head 1 at the lower end of the pile with the ground, and rotate the pile sinking;
[0040] (4) Screw the lower end pile head 1 of the second pipe pile and the upper end pile head 2 of the first pipe pile together. After the two piles are tightly connected, continue to rotate to make the pile body sink;
[0041] (5) Repeat the above step (4) until the pile reaches the designed elevation.
[0042] This embodiment improves the existing pipe pile joint and proposes a spiral connection end plate pipe pile joint. One end of the joint is a threaded cone structure, which is welded and reinforced with the end plate. Its exterior is pressed from a steel plate with spiral patterns, and its interior is filled with high-strength concrete. The other end adopts a connecting sleeve structure that matches the thread, which is pressed from a steel coil, is filled with high-strength concrete all around and is welded and fixed to the end plate. It has the following advantages: it uses threaded connection and thread centering positioning, which makes installation convenient and quick, ensures the verticality of multi-pile connections, and improves work efficiency; the pipe pile joint is solid and filled with high-strength concrete, which improves the overall stiffness of the pipe pile and the shear bearing capacity of the joint; when the pipe pile is buried, the threaded connection column can be used to rotate to quickly break the ground, saving construction time.
[0043] It should be noted that the welding quality between the pile tip and the end plate of the pipe pile must meet the specification requirements, and the thread processing accuracy must be high to ensure the tight connection between the two ends during rotational docking.
[0044] Example 2
[0045] This embodiment discloses another type of novel pipe pile joint structure. Different from Embodiment 1, the connecting column 5 is cylindrical and has an external thread; the connecting sleeve 7 is cylindrical and has an internal thread that matches the external thread of the connecting column 5.
[0046] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A new type of pipe pile joint structure, characterized in that: The invention comprises a pile head (1) at the lower end of a pipe pile and a pile head (2) at the upper end of the pipe pile; the pile head (1) at the lower end of the pipe pile comprises a hollow pipe pile body (3), an end plate (4), a connecting column (5) and a pile collar (8); the connecting column (5) is externally connected to the end plate (4); the pile head (2) at the upper end of the pipe pile comprises a hollow pipe pile body (3), an end plate (4), a connecting sleeve (7) and a pile collar (8); the connecting sleeve (7) is provided with a cavity adapted to the connecting column (5), and the connecting sleeve (7) is embedded in the end of the hollow pipe pile body (3); the pile collar (8) is externally wrapped around the hollow pipe pile body (3), and the end plate (4) is located at the end where the hollow pipe pile body (3) is connected; the connecting column (5) and the connecting sleeve (7) are arranged opposite to each other.
2. The novel pipe pile joint structure according to claim 1 is characterized in that: The connecting column (5) is conical and is provided with an external thread; the connecting sleeve (7) is provided with a conical cavity, and the inner wall of the connecting sleeve (7) is provided with an internal thread, which matches the external thread of the connecting column (5).
3. The novel pipe pile joint structure according to claim 1 is characterized in that: The connecting column (5) is cylindrical and is provided with an external thread; the connecting sleeve (7) is cylindrical and is provided with an internal thread, which matches the external thread of the connecting column (5).
4. The novel pipe pile joint structure according to claim 2 or 3, characterized in that: The connecting column (5) is covered with a steel plate and is welded and fixed to the end plate (4), and its interior is filled with high-strength concrete.
5. The novel pipe pile joint structure according to claim 2 or 3, characterized in that: The connecting sleeve (7) is formed by pressing a steel coil, is filled with high-strength concrete on all sides, and is welded and fixed to the end plate (4).
6. The novel pipe pile joint structure according to claim 1 is characterized in that: The end plate (4) is provided with main reinforcement anchor holes (6) which are evenly distributed in the circumferential direction of the end plate (4).
7. The novel pipe pile joint structure according to claim 1 is characterized in that: The hollow pipe pile body (3) is a hollow cylinder.
8. The novel pipe pile joint structure according to claim 1 is characterized in that: The pile hoop (8) is made of steel plates rolled into a cylindrical shape and welded at the joints.