Split type decarbonization regeneration tower
By dividing the tower body of the decarbonization regeneration tower into multiple sections and adopting a detachable connection design, the problem of the inability to install manholes in the small-diameter tower body is solved, enabling convenient packing cleaning and replacement, and improving the efficiency and safety of the tower body. sex.
Patent Information
- Application Number
- CN202420230116.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2034-01-31
AI Technical Summary
The existing small-diameter decarbonization regeneration tower cannot install a manhole, making it difficult for personnel to enter, which makes it very troublesome to clean and replace the packing.
A split-type decarbonization regeneration tower is designed. The tower body is divided into multiple sections of pipes. Each section is detachably connected. The sprinkler and partition are connected by bolts. The diameter of the tank bottom is larger than the diameter of the tower body to accommodate more absorption liquid. A manhole is provided on the outside of the tower to facilitate personnel entry and cleaning and replacement of fillers.
It achieves unitized processing and convenient packing cleaning and replacement, improves the efficiency and safety of the tower, and ensures effective maintenance and repair even under small diameter conditions.
Smart Images

Figure CN221808466U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of biogas treatment, in particular to a split decarbonization regeneration tower. Background Art
[0002] Biogas is mainly composed of methane and carbon dioxide, and usually contains some other gases, such as nitrogen, oxygen, ammonia, hydrogen sulfide, etc. The main function of the decarbonization tower is to remove carbon dioxide from biogas and increase the concentration of methane in biogas, thereby increasing its calorific value and combustion efficiency, making it more suitable for use as an energy source.
[0003] After the biogas to be treated enters the decarbonization chamber, it passes upward through the packing layer in the tower body. At the same time, the absorbent sprayed by the sprayer, such as water or alkaline solution, is sprayed or flows from the sprayer at the top of the tower and passes downward through the packing layer. On the surface of the packing, the carbon dioxide tower is fully in contact with the liquid. The absorbent rich in carbon dioxide flows downward into the bottom of the tank and is discharged into the flash tower through the drain pipe. In the flash tower, the pressure is suddenly reduced to quickly release the gas dissolved in the absorption liquid. The absorption liquid is then sent to the regeneration tower to react with the packing to reduce the absorption liquid.
[0004] Among them, the packings used in the packed decarbonization regeneration tower include regular packings and random packings. These packings need to be cleaned and replaced regularly, but the diameter of the manhole used to enter the decarbonization regeneration tower is required to be no less than 450㎜. If a decarbonization regeneration tower with a diameter of less than 600㎜ is installed with a 450㎜ manhole, the strength of the tower body will be greatly reduced. Therefore, a small diameter decarbonization regeneration tower is difficult to enter, and it is more troublesome to clean and replace the packing. Utility Model Content
[0005] The utility model aims to provide a split decarbonization regeneration tower, which is used to solve the problem in the prior art that small-diameter decarbonization regeneration towers cannot be installed with manholes, making it difficult for personnel to enter, and it is troublesome to clean and replace the fillers.
[0006] The technical solution adopted by the utility model is as follows: a split decarbonization regeneration tower, comprising a skirt seat, a tank bottom installed above the skirt seat, a tower body connected to the inner cavity of the tank bottom, an exhaust hole connected to the inner cavity of the tank bottom, a sprayer connected to the inner cavity of the tank bottom, a liquid replenishment pipe connected to the inner cavity of the tank bottom, a liquid discharge pipe connected to the inner cavity of the tank bottom, and a sewage discharge pipe connected to the inner cavity of the tank bottom;
[0007] The tower body includes multiple branch pipes, each of which is provided with a first partition, a second partition and a distributor in sequence from bottom to top, a receiving cavity for accommodating fillers is formed between the first partition and the second partition, and feeding pipes connected to the receiving cavity are installed at the upper and lower ends of the receiving cavity on the outside of the branch pipe along its meridian direction.
[0008] Furthermore, the branch pipes are connected via flanges;
[0009] The first baffle, the second baffle and the distributor are detachably connected;
[0010] The sprinkler includes a sprinkler pipe which penetrates the inner wall of the tower body along the longitudinal direction and is then equipped with a sprinkler head, and the sprinkler pipe and the sprinkler head are connected by bolts;
[0011] The first partition and the second partition each include a plurality of unit partitions, the unit partitions are installed by bolt connection, and the distributor includes a plurality of unit dispersers, the unit dispersers are installed by bolt connection;
[0012] The maximum outer dimensions of the unit partition and the unit disperser are smaller than the diameter of the branch pipe.
[0013] Furthermore, the diameter of the tank bottom is greater than the diameter of the tower body.
[0014] Furthermore, a tank bottom manhole is installed on the side of the tank bottom.
[0015] Furthermore, a wire mesh demister is installed on the tower body between the exhaust hole and the sprinkler.
[0016] Furthermore, a thermal insulation layer is provided on the outside of the tower body.
[0017] In summary, due to the adoption of the above technical solution, the beneficial effects of the utility model are:
[0018] 1. The utility model divides the tower body of the decarbonization regeneration tower into multiple sections to realize unitized processing. When it is necessary to put random fillers into the accommodating chamber, the feeding pipe arranged at the upper end of the accommodating chamber is opened, and the feeding pipe arranged at the lower end of the accommodating chamber is closed, and the random fillers are put into the accommodating chamber through the feeding pipe at the upper end of the accommodating chamber;
[0019] When the random filler needs to be cleaned or replaced and needs to be discharged, the feeding pipe at the lower end is opened, and the random filler in the accommodating cavity is discharged through the feeding pipe at the lower end;
[0020] 2. The tower body in the utility model is a split structure, and each section of the branch pipe is connected in a detachable manner. When the structured packing of the accommodating cavity needs to be cleaned or replaced, the branch pipe is first disassembled, and then the inside of each of the branch pipes is entered through the opening of the branch pipe, and the first partition, the second partition, the distributor, the spray pipe and the spray head are removed, and the structured packing can be easily cleaned or replaced;
[0021] 3. The diameter of the tank bottom in the utility model is larger than the diameter of the tower body, so that more absorption liquid can be accommodated. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a structural schematic diagram of the utility model;
[0023] Figure 2 It is a structural schematic diagram of the first partition and the second partition in the utility model;
[0024] Figure 3 It is a structural schematic diagram of the distributor in the utility model.
[0025] Description of reference numerals:
[0026] 1. Skirt; 2. Tank bottom; 3. Drain pipe; 4. Drain pipe; 5. Tower body; 5 1. First baffle; 5 2. Second baffle; 5 3. Distributor; 5 4. Branch pipe; 5 5. Feeding pipe; 6. Wire mesh demister; 7. Pressure gauge; 8. Exhaust hole; 9. Spray pipe; 10. Spray head; 11. Liquid replenishment pipe; 1 2. Manhole at the bottom of the tank. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0028] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] Example 1
[0030] Figure 1 As shown: a split decarbonation regeneration tower, including a skirt 1, a tank bottom 2 is installed above the skirt 1, a tower body 5 connected to the inner cavity of the tank bottom 2 is arranged above the tank bottom 2, an exhaust hole 8 connected to the inner cavity of the tower body 5 is arranged on the top, a sprayer connected to the inner cavity of the tower body 5 is installed on the upper side of the tower body 5, a liquid replenishment pipe 11 connected to the inner cavity of the tank bottom 2 is arranged on one side, a liquid discharge pipe 3 connected to the inner cavity of the tank bottom 2 is arranged on the other side, and a sewage discharge pipe 4 connected to the inner cavity of the tank bottom 2 is arranged at the bottom;
[0031] The liquid to be reduced is sprayed or flows in from the sprinkler at the top of the tower body 5, and passes through the packing layer downward. On the surface of the packing, the absorption liquid fully contacts the packing to achieve reduction. The reduced absorbent flows downward into the tank bottom 2, is discharged through the drain pipe 3, and is sent to the regeneration unit. The gas generated during the reduction process moves upward from the top of the tower body 5 and is discharged from the exhaust hole 8. The pressure gauge 7 installed on the outside of the tower body 5 and connected to its inner cavity can detect the internal pressure of the detector. In order to compensate for the loss of the absorbent and maintain its performance, a liquid replenishment pipe 11 is installed on the tank bottom 2 to replenish the absorption liquid into the tower in time.
[0032] In order to allow personnel to enter, a manhole will be installed on the tower body of the decarbonization regeneration tower, and in order to facilitate the passage of personnel, the diameter of the manhole shall not be less than 450㎜. However, compared with the decarbonization regeneration tower with a diameter greater than 600㎜, if a decarbonization regeneration tower with a diameter less than 600㎜ is installed with a 450㎜ manhole, the strength of the tower body will be greatly reduced.
[0033] Therefore, the tower body 5 includes a plurality of branch pipes 54, each of which is provided with a first partition plate 51, a second partition plate 52 and a distributor 53 from bottom to top. A receiving cavity for receiving fillers is formed between the first partition plate 51 and the second partition plate 52. A feeding pipe 55 communicating with the receiving cavity is installed at the upper and lower ends of the receiving cavity on the outer side of the branch pipe 54 along the meridian direction thereof.
[0034] The tower body 5 of the decarbonization regeneration tower is divided into multiple sections 54 to achieve unitized processing. When it is necessary to put random fillers into the accommodating chamber, the feeding pipe 55 arranged at the upper end of the accommodating chamber is opened, and the feeding pipe 55 arranged at the lower end of the accommodating chamber is closed, and the random fillers are put into the accommodating chamber through the feeding pipe 55 at the upper end of the accommodating chamber;
[0035] When the random filler needs to be cleaned or replaced and needs to be discharged, the feeding pipe 55 at the lower end is opened, and the random filler in the accommodating cavity is discharged through the feeding pipe 55 at the lower end.
[0036] Example 2
[0037] The difference between this embodiment and embodiment 1 is that due to the structured design of the regular packing, the regular packing can usually provide a larger gas-liquid contact area than the random packing, thereby improving the mass transfer efficiency. However, compared with the manhole that is suitable for the entry and exit of personnel, the feeding pipe 55 is difficult to achieve personnel entry and exit, and thus it is difficult to clean or replace the regular packing. Therefore, the branch pipes 54 are connected by flanges, so that it is convenient for personnel to enter the interior from the pipe mouth of the branch pipe 54.
[0038] Furthermore, the first baffle 51, the second baffle 52 and the distributor 53 are connected by bolts, so that they can be easily disassembled.
[0039] The sprinkler comprises a sprinkler pipe 9 and a sprinkler head 10. The sprinkler pipe 9 penetrates the inner wall of the tower body 5 along the longitudinal direction and is then installed with the sprinkler head 10. The sprinkler pipe 9 is connected to the sprinkler head 10 by bolts.
[0040] Through the detachable connection method, when the packing of the accommodating cavity needs to be cleaned or replaced, the flange connection between the branch pipes 54 is disconnected, thereby facilitating entry into each branch pipe 54, and the first partition plate 51, the second partition plate 52, the distributor 53, the spray pipe 9 and the spray head 10 are removed, and the regular packing in the branch pipe 54 can be conveniently cleaned or replaced.
[0041] Due to the use requirements of the first partition 51, the second partition 52, the distributor 53, the spray pipe 9 and the spray head 10, their overall size is consistent with the diameter of the tower body 5. Therefore, after the first partition 51, the second partition 52, the distributor 53, the spray pipe 9 and the spray head 10 are removed and need to be taken out through the pipe mouth of the branch pipe 54, the first partition 51, the second partition 52, the distributor 53, the spray pipe 9 and the spray head 10 cannot pass through the pipe mouth of the branch pipe 54.
[0042] Therefore, the first partition plate 51 and the second partition plate 52 each include a plurality of unit partition plates, and the unit partition plates are installed by bolt connection, and the distributor 53 includes a plurality of unit dispersers, and the unit dispersers are installed by bolt connection;
[0043] Furthermore, the maximum external dimensions of the unit partition and the unit disperser are smaller than the diameter of the branch pipe 54 , so that the first partition 51 , the second partition 52 and the distributor 53 can be separated and passed through the branch pipe 54 .
[0044] Example 3
[0045] The difference between this embodiment and the first embodiment is that the diameter of the tank bottom 2 is larger than the diameter of the tower body 5, so that more absorption liquid can be accommodated.
[0046] Example 4
[0047] The difference between this embodiment and the first embodiment is that a tank bottom manhole 12 is installed on the side of the tank bottom 2, so as to facilitate entering the tank bottom 2 for maintenance.
[0048] Example 5
[0049] The difference between this embodiment and the first embodiment is that a wire mesh demister 6 is installed on the tower body 5 between the exhaust hole 8 and the sprinkler to prevent debris from moving upward and blocking the exhaust hole 8 .
[0050] Example 6
[0051] The difference between this embodiment and embodiment 1 is that a heat-insulating layer is provided on the outer side of the tower body 5 to maintain the temperature inside the tower body 5 and improve the processing efficiency.
[0052] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.
Claims
1. A split decarbonization regeneration tower, characterized in that: The invention comprises a skirt seat (1), a tank bottom (2) mounted above the skirt seat (1), a tower body (5) connected to an inner cavity of the tank bottom (2) arranged above the tank bottom (2), an exhaust hole (8) connected to the inner cavity of the tank bottom (2) arranged at the top of the tower body (5), a sprayer connected to the inner cavity of the tank bottom (5) arranged on the upper side of the tower body (5), a liquid replenishing pipe (11) connected to the inner cavity of the tank bottom (2) arranged on one side, a liquid drain pipe (3) connected to the inner cavity of the tank bottom (2) arranged on the other side, and a sewage drain pipe (4) connected to the inner cavity of the tank bottom (2) arranged at the bottom; The tower body (5) comprises a plurality of branch pipes (54), each of which is provided with a first partition plate (51), a second partition plate (52) and a distributor (53) in sequence from bottom to top, a receiving cavity for receiving fillers is formed between the first partition plate (51) and the second partition plate (52), and a feeding pipe (55) communicating with the receiving cavity is installed at the upper and lower ends of the receiving cavity on the outer side of the branch pipe (54) along the longitudinal direction thereof.
2. A split decarbonization regeneration tower according to claim 1, characterized in that: The branch pipes (54) are connected via flanges; The first baffle (51), the second baffle (52) and the distributor (53) are detachably connected; The sprinkler comprises a sprinkler pipe (9) and a sprinkler head (10). The sprinkler pipe (9) penetrates the inner wall of the tower body (5) along the longitudinal direction and is then provided with the sprinkler head (10). The sprinkler pipe (9) and the sprinkler head (10) are connected by bolts. The first partition plate (51) and the second partition plate (52) each include a plurality of unit partition plates, and the unit partition plates are installed by bolt connection. The distributor (53) includes a plurality of unit dispersers, and the unit dispersers are installed by bolt connection. The maximum outer dimensions of the unit partition and the unit disperser are smaller than the diameter of the branch pipe (54).
3. A split decarbonization regeneration tower according to claim 1, characterized in that: The diameter of the tank bottom (2) is greater than the diameter of the tower body (5).
4. A split decarbonization regeneration tower according to claim 3, characterized in that: A tank bottom manhole (12) is installed on the side of the tank bottom (2).
5. A split decarbonization regeneration tower according to claim 3, characterized in that: A heat-insulating layer is arranged on the outer side of the tower body (5).
6. A split decarbonization regeneration tower according to claim 5, characterized in that: A wire mesh demister (6) is installed on the tower body (5) between the exhaust hole (8) and the sprinkler.