High-low side combined heat supply peak shaving system integrated with auxiliary steam turbine

By introducing an auxiliary steam turbine and an electric-thermal conversion device into the high- and low-side combined heating system, and using the auxiliary steam turbine to generate power to drive the electric-heat conversion device and heat the return water from the heating network, the problems of energy waste and insufficient heating capacity in the combined high- and low-side heating system are solved. , achieving more efficient energy utilization and improving heating capacity.

CN221810858UActive Publication Date: 2024-10-08NORTH CHINA UNIV OF WATER RESOURCES & ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420354340.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-08
Estimated Expiration
2034-02-27

AI Technical Summary

Technical Problem

The combined high- and low-side heating system has the problems of energy waste and insufficient heating capacity, which results in the need to balance the axial thrust when increasing the heating capacity, resulting in huge energy losses.

Method used

An auxiliary steam turbine and an electric-heat conversion device are introduced into the high- and low-side combined heating system. The auxiliary steam turbine generates power to drive the electric-heat conversion device, and heats the return water from the heating network to increase the water supply temperature of the heating network and achieve more efficient energy utilization.

Benefits of technology

Without increasing the steam extraction volume, the energy utilization rate and heating capacity of the system are improved, energy loss is reduced, and the overall efficiency and heating capacity of the unit are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221810858U_ABST
    Figure CN221810858U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of coal electricity, and relates to a high-low side combined heat supply peak shaving system integrated with an auxiliary steam turbine, which mainly comprises the auxiliary steam turbine, a coal-fired boiler, a steam turbine, a condenser, a generator and the like. In the high-low bypass combined heat supply system, main steam shunted by the high-pressure bypass is introduced into the auxiliary steam turbine to do work for power generation through expansion, the steam after work doing returns to the reheating cold section, the purpose of reducing temperature and pressure is achieved, meanwhile, the generated electricity heats heat supply network return water through the electricity-heat conversion device, and the heat supply network return water is recycled. And then the air enters the peak heater to meet the temperature requirement required by the heat supply network. According to the utility model, the heat supply capacity of the coal-fired unit is obviously improved while the energy is fully utilized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of coal-fired power generation, in particular to a high-low bypass combined heating peak regulation system with an integrated auxiliary steam turbine. Background Art

[0002] Coal-fired cogeneration units have always been the main energy supply in northern my country. However, with the continuous increase in housing population and the continuous expansion of heating areas, cogeneration units are facing the problem of insufficient heating capacity. On the other hand, in order to ensure the implementation of the dual-carbon strategy, cogeneration also needs to increase heating capacity to replace scattered coal and boiler room heating in the region to achieve the goal of reducing carbon dioxide emissions.

[0003] High-low bypass technology is a solution to improve the heating capacity of cogeneration units. Its main principle is to reduce the steam entering the steam turbine for power generation by diverting a part of the steam from the hot reheating section for heating, thereby reducing the power generation and improving the heating capacity. However, in order to balance the axial thrust, it is necessary to divert the same amount of steam from the main steam pipeline, reduce the temperature through desuperheating water, and return to the cold reheating section after the throttle valve reduces the pressure. This process will generate huge energy losses. Therefore, optimizing the high-low bypass combined heating system can be one of the development directions of its technology. Summary of the invention

[0004] In view of the shortcomings of the existing methods, the utility model provides a high-low bypass combined heating peak-shaving system with an integrated auxiliary steam turbine. By adding an auxiliary steam turbine and an electric heat conversion device to the high-low bypass combined heating system, the problems of energy waste and insufficient heating capacity of the high-low bypass combined heating unit mentioned in the background technology are solved, and the goals of reducing energy loss and increasing the heating capacity of the unit are achieved while the high-low bypass technology is used normally.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A high-low bypass combined heating peak-shaving system integrated with an auxiliary steam turbine, characterized in that the steam outlet of a coal-fired boiler (1) is connected to the inlet of a first diverter valve (2), the outlet of the first diverter valve (2) is connected to the inlet of an auxiliary steam turbine (3) and the inlet of a high-pressure cylinder (4), the inlet of a first mixing valve (5) is respectively connected to the outlet of the auxiliary steam turbine (3) and the outlet of the high-pressure cylinder (4), the outlet of the first mixing valve (5) is connected to the inlet of a boiler reheater, the outlet of the reheater is connected to the inlet of a second diverter valve (6), the outlet of the second diverter valve (6) is respectively connected to the inlet of a second mixing valve (7) and an intermediate-pressure cylinder (8), the outlet of the intermediate-pressure cylinder (8) is connected to the inlet of a third diverter valve (9), and the outlet of the third diverter valve (9) is connected to the outlet of the They are respectively connected to the inlets of the mixer (7) and the low-pressure cylinder (10), the outlet of the low-pressure cylinder (10) is connected to the condenser (11), and the outlet of the second mixing valve (7) is connected to the peak heater (16); the high-pressure cylinder (4), the medium-pressure cylinder (8), the low-pressure cylinder (10) and the generator (12) are coaxially connected; the auxiliary steam turbine (3) is coaxially connected to the auxiliary generator (13); the auxiliary generator (13) is connected to the electric heat conversion device (15) through the transmission line (14); the heat network return water is connected to the heat network water inlet of the electric heat conversion device (15), the heat network water outlet of the electric heat conversion device is connected to the inlet of the peak heater (16), and the heat network water outlet of the peak heater (16) is connected to the heat network as heat network water supply.

[0007] In the integrated auxiliary steam turbine high-low bypass combined heating peak-shaving system, the superheated steam of the outlet steam pipe of the coal-fired boiler (1) is connected to the first diverter valve (2), a part of the steam enters the auxiliary steam turbine (3), and a part enters the high-pressure cylinder (4); the steam entering the auxiliary steam turbine (3) generates power, and the generated electricity acts on the electric heat conversion device (15) through the wire (14); the return water of the heating network enters the electric heat conversion device (15) for heating, and then enters the peak heater (16) for heating, and enters the heating network as the heating network water after reaching the required temperature. The energy utilization rate and the heating capacity of the unit can be improved without increasing the steam extraction amount at the inlet of the second diverter valve (6).

[0008] The drain from the peak heater (16) enters the condenser (11).

[0009] The electric heat conversion device (15) comprises an electric heat pump and an electric boiler.

[0010] The positive and beneficial effects of the utility model:

[0011] The utility model discloses a high-low bypass combined heating peak-shaving system with an integrated auxiliary steam turbine. By integrating an auxiliary steam turbine and an electric heat conversion device in the high-low bypass combined heating system, the heating capacity is improved while ensuring the safe and stable operation of the system. In the utility model, the main steam flows to the auxiliary steam turbine and the high-pressure cylinder respectively through a diverter valve, and the steam entering the auxiliary steam turbine generates electricity by expansion to drive the electric heat conversion device; the return water from the heat network enters the electric heat conversion device for heating, and then enters the peak heater, and enters the heat network after reaching the temperature requirement. At this time, the energy utilization of the system is more sufficient, and the overall efficiency and heating capacity are improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the structure of the high-low combined heating peak-shaving system with integrated auxiliary steam turbine.

[0013] In the figure, 1 is a coal-fired boiler, 2 is a first diverter valve, 3 is an auxiliary steam turbine, 4 is a high-pressure cylinder, 5 is a first mixing valve, 6 is a second diverter valve, 7 is a second mixing valve, 8 is an intermediate-pressure cylinder, 9 is a third diverter valve, 10 is a low-pressure cylinder, 11 is a condenser, 12 is a generator, 13 is an auxiliary generator, 14 is a transmission line, 15 is an electric heat conversion device, and 16 is a peak heater. DETAILED DESCRIPTION

[0014] The present invention is further described below in conjunction with the accompanying drawings and specific examples; it should be emphasized that the following description is merely illustrative and is not intended to limit the scope and application of the present invention.

[0015] A high-low bypass combined heating peak-shaving system integrated with an auxiliary steam turbine, characterized in that a steam outlet of a coal-fired boiler (1) is connected to an inlet of a first diverter valve (2), the outlet of the first diverter valve (2) is connected to an inlet of an auxiliary steam turbine (3) and an inlet of a high-pressure cylinder (4), an inlet of a first mixing valve (5) is respectively connected to an outlet of the auxiliary steam turbine (3) and an outlet of the high-pressure cylinder (4), an outlet of the first mixing valve (5) is respectively connected to an inlet of a boiler reheater, an outlet of the reheater is connected to an inlet of a second diverter valve (6), an outlet of the second diverter valve (6) is respectively connected to an inlet of a second mixing valve (7) and an inlet of an intermediate-pressure cylinder (8), The outlet of the intermediate pressure cylinder (8) is connected to the inlet of the third diverter valve (9), the outlet of the third diverter valve (9) is connected to the inlets of the mixer (7) and the low pressure cylinder (10) respectively, the outlet of the low pressure cylinder (10) is connected to the condenser (11), and the outlet of the second mixing valve (7) is connected to the peak heater (16); the high pressure cylinder (4), the intermediate pressure cylinder (8), the low pressure cylinder (10) and the generator (12) are coaxially connected; the auxiliary steam turbine (3) is coaxially connected to the auxiliary generator (13); the auxiliary generator (13) is connected to the electric heat conversion device (15) through the transmission line (14). The heat network return water is connected to the heat network water inlet of the electric heat conversion device (15), the heat network water outlet of the electric heat conversion device is connected to the inlet of the peak heater (16), and the heat network water outlet of the peak heater (16) is connected to the heat network as the heat network water supply.

[0016] In the integrated auxiliary steam turbine high-low bypass combined heating peak-shaving system, the superheated steam of the outlet steam pipe of the coal-fired boiler (1) is connected to the first diverter valve (2), a part of the steam enters the auxiliary steam turbine (3), and a part enters the high-pressure cylinder (4); the steam entering the auxiliary steam turbine (3) generates power, and the generated electricity acts on the electric heat conversion device (15) through the wire (14); the return water of the heating network enters the electric heat conversion device (15) for heating, and then enters the peak heater (16) for heating, and enters the heating network as the heating network water after reaching the required temperature. The energy utilization rate and the heating capacity of the unit can be improved without increasing the steam extraction amount at the inlet of the second diverter valve (6).

[0017] The drain from the peak heater (16) enters the condenser (11).

[0018] The electric heat conversion device (15) comprises an electric heat pump and an electric boiler.

[0019] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by any technician familiar with the technical field within the technical scope disclosed in the present invention should be included in the protection scope of the present invention; therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A high-low bypass combined heating peak-shaving system with integrated auxiliary steam turbine, characterized in that: The system comprises an auxiliary steam turbine (3), a coal-fired boiler (1), a condenser (11), a generator (12), and a peak heater (16); the steam outlet of the coal-fired boiler (1) is connected to the inlet of a first diverter valve (2), the outlet of the first diverter valve (2) is connected to the inlet of the auxiliary steam turbine (3) and the inlet of a high-pressure cylinder (4), the inlet of a first mixing valve (5) is respectively connected to the outlet of the auxiliary steam turbine (3) and the outlet of the high-pressure cylinder (4), the outlet of the first mixing valve (5) is connected to the inlet of a boiler reheater, the outlet of the reheater is connected to the inlet of a second diverter valve (6), the outlet of the second diverter valve (6) is respectively connected to the inlet of a second mixing valve (7) and an intermediate-pressure cylinder (8), the outlet of the intermediate-pressure cylinder (8) is connected to the inlet of a third diverter valve (9), and the outlet of the third diverter valve (9) is connected to the inlet of a second mixing valve (7) and an intermediate-pressure cylinder (8). The outlet of the diverter valve (9) is connected to the inlet of the second mixing valve (7) and the low-pressure cylinder (10) respectively, the outlet of the low-pressure cylinder (10) is connected to the condenser (11), and the outlet of the second mixing valve (7) is connected to the peak heater (16); the high-pressure cylinder (4), the medium-pressure cylinder (8), the low-pressure cylinder (10) and the generator (12) are coaxially connected; the auxiliary steam turbine (3) is coaxially connected to the auxiliary generator (13); the auxiliary generator (13) is connected to the electric heat conversion device (15) through the transmission line (14); the heat network return water is connected to the heat network water inlet of the electric heat conversion device (15), the heat network water outlet of the electric heat conversion device is connected to the inlet of the peak heater (16), and the heat network water outlet of the peak heater (16) is connected to the heat network as heat network water supply.

2. The high-low bypass combined heating peak-shaving system with integrated auxiliary steam turbine according to claim 1 is characterized in that: The superheated steam of the outlet steam pipe of the coal-fired boiler (1) is connected to the first diverter valve (2), a part of the steam enters the auxiliary steam turbine (3), and a part of the steam enters the high-pressure cylinder (4); the steam entering the auxiliary steam turbine (3) generates power, and then the steam returns to the reheating cold section; the generated electricity acts on the electric heat conversion device (15) through the electric wire (14); the return water of the heating network enters the electric heat conversion device (15) for the first heating, and then enters the peak heater (16) for the second heating, and enters the heating network as the heating network water supply after reaching the required temperature; the energy utilization rate and the heating capacity of the unit can be improved without increasing the steam extraction amount at the inlet of the second diverter valve (6).

3. The high-low bypass combined heating peak-shaving system with integrated auxiliary steam turbine according to claim 1 is characterized in that: The drain from the peak heater (16) enters the condenser (11).

4. The high-low bypass combined heating peak-shaving system with integrated auxiliary steam turbine according to claim 1 is characterized in that: The electric heat conversion device (15) comprises an electric heat pump and an electric boiler.