Asphalt mixing station
Through the design of the quick-installation mechanism and the detachable climbing frame, the problem of poor positioning accuracy and stability during the installation and disassembly of the semi-fixed asphalt mixing plant is solved, and the stability of the tank is improved during transportation, achieving a more efficient construction and transportation process.
Patent Information
- Application Number
- CN202323552994.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-25
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-12-25
Smart Images

Figure CN221822671U_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of asphalt processing equipment, and in particular relates to an asphalt mixing station. Background Art
[0002] Asphalt mixing plant, also known as asphalt concrete mixing plant or asphalt concrete mixing plant, refers to a complete set of equipment used for batch production of asphalt concrete. According to the mixing method, it can be divided into forced intermittent type and continuous production type; according to the transportation method, it can be divided into fixed type, semi-fixed type and mobile type.
[0003] The semi-stationary asphalt mixing plant is a type of asphalt production equipment that combines the characteristics of fixed and mobile mixing plants. It has a certain degree of flexibility, unlike completely fixed equipment, but it is not completely mobile like a mobile mixing plant. Overall, the semi-stationary asphalt mixing plant combines the advantages of fixed and mobile equipment, providing a certain degree of flexibility and stability, making it suitable for a range of road and construction projects of different sizes and types.
[0004] When installing a semi-fixed asphalt mixing plant, the following problems may occur:
[0005] It often takes a certain amount of time to install and fix the main structure. For example, when installing the base plate, column and main body, the traditional square slot needs high precision when positioning the four corners using a crane. It also needs manual assistance and positioning while the crane is adjusted, and then fixed between the column and the base plate.
[0006] The connection between the built main structure and the movable overall equipment is poor, such as the lack of connectivity between the main structure and the external hoist, so the overall stability needs to be enhanced.
[0007] When disassembling and transporting a semi-fixed asphalt mixing plant, the following problems may occur:
[0008] Cylindrical tanks, such as dust tanks, need to be transported by tank trucks. However, the tanks are fixed to the frame by straps, and the overall stability is poor, which can easily cause bumps during transportation. Summary of the invention
[0009] In view of the above defects, the present invention provides an asphalt mixing plant, including a main engine platform for fixing a mixing main engine, a fuel lifting system, an asphalt lifting system and a dust removal system, wherein the main engine platform includes a plurality of fixed base plates, and the four end corners of each of the fixed base plates are connected by a quick-install mechanism;
[0010] The fuel lifting system and the powder lifting system are both connected to each quick-install mechanism via a connecting rod;
[0011] The dust removal system and the powder lifting system respectively include a dust tank and a powder tank, and the outsides of the dust tank and the powder tank are both installed with detachable climbing frames.
[0012] Furthermore, the quick-loading mechanism includes a load-bearing column and a column angle groove opened at the end corner of the fixed base plate, the openings at the upper and lower ends of the column angle groove are square and circular respectively, the bottom end of the load-bearing column is snugly matched with the square opening, the interior of the load-bearing column is snugly matched with the circular opening through an inlaid inner support tube, the inner wall of the column angle groove is installed with an inner plate layer for the inner support tube to pass through, two fixing grooves are opened at the square opening, fixing blocks matching the fixing grooves are fixed on both sides of the load-bearing column, and bolt holes matching the fixing grooves are opened inside, and the height value of the fixing block is greater than the depth value of the fixing groove.
[0013] Furthermore, the outer edge of the inner plate layer is fixed to the inner wall of the column corner groove, and an annular groove for the support tube to pass through is opened in the middle of the inner plate layer, and two reinforcement grooves facing the adjacent end corners of the fixed base plate are also opened inside the inner plate layer. The reinforcement groove is L-shaped, and a matching external connecting piece is arranged inside the reinforcement groove.
[0014] Furthermore, the external connecting member includes a lower pressure plate and a linkage plate located inside the reinforcement groove, the working ends of the lower pressure plate and the linkage plate respectively penetrate the two open ends of the reinforcement groove, the two open ends are respectively located on the upper surface and the side of the inner plate layer, and the opening of the side is connected to the extension groove set at the end corner of the fixed base plate, the working end of the linkage plate sequentially penetrates the opening and the extension groove of the side, and the working end of the linkage plate is provided with a fixing member for connecting with the fuel lifting system, the asphalt lifting system and the dust removal system;
[0015] The lower pressing plate includes an arc-shaped top plate and an arc-shaped bottom plate, the arc-shaped top plate is located inside the opening at the top of the reinforcement groove, the width of the arc-shaped bottom plate is greater than the width of the arc-shaped top plate, and is limited by the opening at the top of the reinforcement groove, and the thickness of the arc-shaped bottom plate is less than the height of the reinforcement groove;
[0016] The side where the lower pressing plate and the linkage plate are close to and fitted with each other is a mutually parallel inclined surface, and the end of the arc-shaped top plate and the opening at the top of the reinforcement groove close to the annular groove is an arc surface.
[0017] Furthermore, sliders are fixed on one end of both sides of the linkage plate close to the lower pressure plate, and the two sliders are respectively clamped in the inside of the slide groove I opened on the inner wall of the reinforcement groove, and the inner wall of the extension groove connected to the reinforcement groove is provided with a slide groove II connected to the slide groove box I, and the slide groove I is connected to the clamped slider through a spring, and a magnet layer I is fixed on the bottom surface of the lower pressure plate, and a magnet layer II is fixed on the inner bottom wall of the reinforcement groove, and the magnet layer I and the magnet layer II have the same magnetic poles.
[0018] Furthermore, a central insert pipe is fixed at the bottom end of the inner support tube for penetrating the annular groove and being inserted and fixed into the through groove of the inner support tube.
[0019] Furthermore, the detachable climbing frame includes a plurality of movably connected climbing frame bodies, and two adjacent climbing frame bodies are threadedly connected to threaded holes opened at upper and lower ends via threaded rods.
[0020] Furthermore, the climbing frame body includes an arc-shaped inner rod and an outer rod, the inner rod is used to fit with the outer surface of the dust tank or the powder tank, and the outer rod is used to form a climbing passage between the inner rod, and the inner rod and the outer rod are connected by two groups of reinforcement beams, and the two groups of reinforcement beams are respectively located on both sides of the climbing passage, and a rubber sleeve for climbing and grasping is provided in the middle of the inner rod, and the inner rod is connected to the dust tank or the powder tank through two movable connecting parts located at the far end.
[0021] Furthermore, the number of the threaded rods is not less than five, which are respectively located at both ends of the inner rod and both ends and the middle of the outer rod.
[0022] Furthermore, a guide channel is provided inside the inner support tube, and inner support rods equidistant and cross-distributed are fixed to the inner wall of the guide channel, an inner hole for connecting with the guide channel is provided inside the central insert tube, and a dust suction hole connected with the inner hole is provided on the outer surface of the load-bearing column.
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] 1. When constructing and installing the mixing plant at the construction site, the upper and lower round openings set at the fixed base plate make it easier for the crane and manual labor to position and install the four-end load-bearing columns. That is, when the crane lifts the fixed base plate and positions the four load-bearing columns fixed to the foundation, the round interface is easier to adjust than the square one, and there will be no end corner jamming that causes the plate to tilt. When the load-bearing columns are installed on the top of the fixed base plate, the square positioning has better stability, that is, it increases the contact area at the bottom;
[0025] 2. The telescopic quick-install mechanism increases the connection force between the host platform and other movable devices, thereby increasing stability. It can be retracted when not installed, and will not cause damage to the quick-install mechanism during transportation, affecting subsequent use. That is, the internal lower pressure plate pushes the linkage plate through the top pressure effect, thereby achieving external connection;
[0026] 3. Compared with traditional ladders, detachable ladders are more convenient to install. While taking into account the climbing effect of workers, they also have the effect of protecting the outside of the tank during transportation and facilitating fixation to the vehicle. That is, the connection to the tank is achieved through movable connectors, and the detachable ladder is symmetrically fixed to the outside of the tank to achieve a surround wrapping effect. At the same time, compared with the smooth surface of the tank, it can be fixed on the outer rod, inner rod, reinforcement beam, etc., which increases stability during transportation. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is an overall schematic diagram of the present invention.
[0028] Figure 2 It is a schematic diagram of the structure between the fixed base plate and the upper and lower load-bearing columns in the present invention.
[0029] Figure 3 It is a schematic diagram of the top view of the annular groove in the present invention.
[0030] Figure 4 It is a structural schematic diagram of the lower pressing plate and the linkage plate in the present invention.
[0031] Figure 5 It is a schematic diagram of the structure between the two climbing frame bodies in the present invention.
[0032] Figure 6 This is a schematic diagram of the detachable ladder of the present invention in a state of wrapping and transporting a dust can.
[0033] Figure 7 It is a schematic diagram of the inner support tube in the present invention when viewed from above.
[0034] In the figure: 1. mixing host; 2. host platform; 20. fixed base plate; 201. column angle groove; 202. load-bearing column; 203. inner support tube; 204. diversion channel; 2041. inner support rod; 205. central insert; 206. inner plate layer; 207. fixed groove; 208. fixed block; 209. bolt hole; 210. annular groove; 211. reinforcement groove; 212. extension groove; 31. lower pressure plate; 32. linkage plate; 33. inclined plane; 34. slider; 35. magnet layer I; 4. detachable climbing frame; 41. outer rod; 42. inner rod; 43. reinforcement beam; 44. climbing channel; 45. threaded rod; 46. movable connector; 47. threaded hole; 48. rubber sleeve; 5. powder tank; 6. dust tank. DETAILED DESCRIPTION
[0035] In order to facilitate the understanding of the present invention, the device of the present invention will be described more fully below with reference to the relevant drawings. Embodiments of the device are given in the drawings. However, the device can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.
[0036] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "set" should be understood in a broad sense, for example, they can be fixedly connected or set, or detachably connected or set, or integrally connected or set. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0037] Example 1
[0038] like Figure 1-4 As shown, this embodiment provides an asphalt mixing plant, including a main engine platform 2 for fixing a mixing main engine 1, a fuel lifting system, an asphalt lifting system and a dust removal system, the main engine platform includes a plurality of fixed base plates 20, and the four end corners of each fixed base plate 20 are connected by a quick-install mechanism;
[0039] The fuel lifting system and the powder lifting system are connected to each quick-install mechanism through a connecting rod. It should be noted that other dust removal systems, power distribution rooms, etc. can also be connected to the quick-install mechanism (that is, connected to the fast-install mechanism that is pressed and extended by the fixing parts, the fixing parts can be bolt holes and other structures that are fixedly connected to the external connecting rods, and do not affect the retraction and reset function, so no further elaboration is made here);
[0040] The quick-installation mechanism includes a load-bearing column 202 and a column angle groove 201 opened at the end corner of the fixed base plate 20. The openings at the upper and lower ends of the column angle groove 201 are square and circular respectively. The bottom end of the load-bearing column 202 fits snugly with the square opening. When the crane lifts the fixed base plate 20 and positions the four load-bearing columns 202 fixed to the foundation, the circular interface is easier to adjust than the square interface, and there will be no situation where the square surface corners are stuck and the fixed base plate 20 is tilted. When the load-bearing column 202 is installed on the top of the fixed base plate 20, since the area of the square is larger than the circle, the contact area of the bottom is increased, thereby increasing the stability of the support. The load-bearing column 202 is not adjusted by a crane, and the manual installation method will not cause the corners to get stuck.
[0041] The interior of the load-bearing column 202 is fitted with the circular opening through the embedded inner support tube 203, and the inner wall of the column corner groove 201 is installed with an inner plate layer 206 for the inner support tube 203 to pass through, that is, during installation, the two top and bottom load-bearing columns 202 clamp the inner plate layer 206 in between, so that the connection state between the two load-bearing columns 202 is integrated into the whole of the fixed base plate 20 through the inner plate layer 206, thereby achieving an increased connection stability effect; the outer edge of the inner plate layer 206 is fixed to the inner wall of the column corner groove 201 (it can also be achieved by embedding or one-piece molding), and the middle of the inner plate layer 206 is provided with an annular groove 210 for the support tube to pass through, and the interior of the inner plate layer 206 is also provided with two reinforcement grooves 211 facing the adjacent end corners of the fixed base plate 20, the reinforcement groove 211 is L-shaped, and the interior of the reinforcement groove 211 is provided with a matching external connection piece.
[0042] A central insert pipe 205 is fixed at the bottom end of the inner support pipe 203 for penetrating the annular groove 210 and being inserted and fixed into the through groove of the inner support pipe 203 . The central insert pipe 205 enables the two vertical load-bearing columns 202 to be internally connected.
[0043] The external connecting member includes a lower pressing plate 31 and a linkage plate 32 located inside the reinforcement groove 211. The working ends of the lower pressing plate 31 and the linkage plate 32 respectively penetrate the two opening ends of the reinforcement groove 211. The two opening ends are respectively located on the upper surface and the side of the inner plate layer 206, and the opening of the side is connected to the extension groove 212 set at the end corner of the fixed base plate 20. The working end of the linkage plate 32 sequentially penetrates the opening of the side and the extension groove 212 to limit it without affecting the extension and retraction, thereby ensuring the stability of the fixed end in the later stage.
[0044] Slide blocks 34 are fixed to one end of the two sides of the linkage plate 32 close to the lower pressure plate 31. The two slide blocks 34 are respectively engaged with the inner side of the slide groove I (i.e., the inner side wall of the transverse groove of the slide groove I) provided on the inner wall of the reinforcement groove 211. Figure 4The state can achieve the effect of sliding left and right), and the inner wall of the extension groove 212 connected to the reinforcement groove 211 is provided with a slide II connected to the slide box I, which is used for the slider 34 to transition from the slide I to the slide II. It should be noted that the maximum movement range of the slide II should ensure that the linkage plate 32 is extended and exposed. Excessive extension will lead to poor stability. The slide I is connected to the clamped slider 34 through a spring, and the rebound effect of the linkage plate 32 is increased by the spring. The bottom surface of the lower pressure plate 31 is fixed with a magnet layer I35, and the inner bottom wall of the reinforcement groove 211 is fixed with a magnet layer II. The magnet layer I35 and the magnet layer II are mutually like poles. The principle of like poles repel each other is used to make the lower pressure plate 31 and the reinforcement groove 211 have a reverse thrust. Since the top is used to install equipment such as the mixing host 1, the pressure is relatively large, so compared with the spring, it is better to use magnetic force. The working end of the linkage plate 32 is provided with fixings for connecting with the fuel lifting system, asphalt lifting system and dust removal system. The fixings may be structures such as bolt holes and slots, which are used to fix with the connecting rods to achieve connection between the host platform 2 and other external equipment, thereby increasing the overall stability.
[0045] The lower pressing plate 31 includes an arc-shaped top plate and an arc-shaped bottom plate. The arc-shaped top plate is located inside the opening at the top of the reinforcement groove 211. The width of the arc-shaped bottom plate is greater than the width of the arc-shaped top plate. The arc-shaped bottom plate is limited by the opening at the top of the reinforcement groove 211 to prevent it from falling off. The thickness of the arc-shaped bottom plate is less than the height of the reinforcement groove 211, ensuring that it has a certain downward movement space to realize the subsequent push of the linkage plate 32.
[0046] The side where the lower pressure plate 31 and the linkage plate 32 are close to and fit together is a parallel inclined surface 33. The lower pressure plate 31 is pressed by the top pressure to realize its downward movement. During the downward movement, the inclined surface 33 can push the fitting linkage plate 32 to extend outward, and the end of the arc-shaped top plate and the opening at the top of the reinforcement groove 211 close to the annular groove 210 is an arc surface, which is convenient for fitting with the outside of the inner support tube 203 to ensure stability.
[0047] Two fixing grooves 207 are provided at the square opening, and fixing blocks 208 adapted to the fixing grooves 207 are fixed on both sides of the load-bearing column 202, and bolt holes 209 adapted to the fixing grooves 207 are provided inside. The height of the fixing block 208 is greater than the depth of the fixing groove 207, and after being inserted, the fixing base plate 20 and the load-bearing column 202 are reinforced by bolts.
[0048] It should be noted that the four load-bearing columns 202 located at the bottom and fixed to the foundation are not provided with a central insert 205, which is convenient for fixing to the foundation. The overall installation sequence should be installed from bottom to top, that is, the four load-bearing columns 202 are installed first, and then the fixed base plate 20 is hoisted for installation, and the lower hopper, crushing, mixing equipment, etc. are installed in the reserved groove of the fixed base plate 20, and then the layering operation is carried out, that is, the four load-bearing columns 202 are installed again, and then the fixed base plate 20 is installed until the top is capped; during disassembly, on the contrary, the fixed base plate 20 is disassembled first, and then the four load-bearing columns 202 are disassembled, until the disassembly is completed.
[0049] like Figure 5-6 As shown, the dust removal system and the powder lifting system include a dust tank 6 and a powder tank 5 respectively. The outside of the dust tank 6 and the powder tank 5 are both installed with a detachable climbing frame 4. The detachable climbing frame 4 includes a plurality of movably connected climbing frame bodies. Two adjacent climbing frame bodies are threadedly connected to threaded holes 47 opened at the upper and lower ends through threaded rods 45. The number of threaded rods 45 is not less than five, which are respectively located at the two ends of the inner rod 42 and the two ends and the middle of the outer rod 41, so as to ensure the detachable climbing frame 4.
[0050] The climbing frame body includes an arc-shaped inner rod 42 and an outer rod 41. The inner rod 42 is used to fit with the outer surface of the dust tank 6 or the powder tank 5, and the outer rod 41 is used to form a climbing passage 44 for people to shuttle between the inner rod 42. The inner rod 42 and the outer rod 41 are connected by two groups of reinforcement beams 43. The two groups of reinforcement beams 43 are respectively located on both sides of the climbing passage 44 to ensure the stability between the inner rod 42 and the outer rod 41, and a rubber sleeve 48 for climbing and grasping is provided in the middle of the inner rod 42. The inner rod 42 is connected to the dust tank 6 or the powder tank 5 through two movable connecting parts 46 located at the far end.
[0051] It should be noted that the movable connecting member 46 can be a T-shaped plug plate (the insertion end of which should be an arc surface that matches the dust tank 6 or the powder tank 5), and the outer walls of the dust tank 6 and the powder tank 5 are provided with two sets of slots for the plug plates to be inserted (the dust tank 6 or the powder tank 5 is generally a solid structure such as carbon steel, stainless steel, etc., and a slot can be provided on its inner wall). When in use, the detachable climbing frame 4 is inserted into the slot, and the slot is sealed by a sealing plate to achieve the installation of the climbing frame; for and subsequent transportation, the spare detachable climbing frame 4 is inserted into the slot on the other side to form a shape as shown in the attached Figure 6 The wrapped state shown can be fixed to the vehicle by ropes or support beams (either winding or adapter connection).
[0052] It should be noted that, in order to ensure that the two detachable climbing frames 4 have good packaging properties during transportation, the proximal ends of the inner rod 42 and the outer rod 41 should be in contact.
[0053] Example 2
[0054] As attached Figure 7 As shown, the difference from the above-mentioned embodiment 1 lies in that a guide channel 204 is provided inside the inner support tube 203, and the inner wall of the guide channel 204 is fixed with inner support rods 2041 which are equidistant and cross-distributed, and an inner hole for communicating with the guide channel 204 is provided inside the central insert 205, and a dust suction hole connected with the inner hole is provided on the outer surface of the load-bearing column 202 (the dust removal equipment can be connected with the load-bearing column 202 through a pipeline), so that dust removal can be carried out in the personnel operation warehouse or the unloading place; and for multi-layer dust removal, each central insert 205 is in a connected state, and the dust suction connection can be carried out at the bottom load-bearing column 202.
[0055] It should be noted that the structure described in the present invention can be implemented in a variety of different forms and is not limited to the described embodiments. Any equivalent transformations made by ordinary technicians in this field using the contents of the present invention description and drawings, or directly or indirectly applied to other related technical fields, such as the loading and unloading of other items, are included in the protection scope of the present invention.
Claims
1. An asphalt mixing plant, comprising a mainframe platform for fixing a mixing mainframe, a fuel lifting system, an asphalt lifting system and a dust removal system, Features: The host platform includes a plurality of fixed base plates, and the four end corners of each of the fixed base plates are connected by a quick-install mechanism; The fuel lifting system and the powder lifting system are both connected to each quick-install mechanism via a connecting rod; The dust removal system and the powder lifting system respectively include a dust tank and a powder tank, and the outsides of the dust tank and the powder tank are both installed with detachable climbing frames.
2. An asphalt mixing plant as claimed in claim 1, Features: The quick-install mechanism includes a load-bearing column and a column angle groove opened at the end corner of the fixed base plate, the openings at the upper and lower ends of the column angle groove are square and circular respectively, the bottom end of the load-bearing column is snugly matched with the square opening, the interior of the load-bearing column is snugly matched with the circular opening through an inlaid inner support tube, the inner wall of the column angle groove is installed with an inner plate layer for the inner support tube to pass through, two fixing grooves are opened at the square opening, fixing blocks matched with the fixing grooves are fixed on both sides of the load-bearing column, and bolt holes matched with the fixing grooves are opened inside, and the height value of the fixing block is greater than the depth value of the fixing groove.
3. An asphalt mixing plant as claimed in claim 2, Features: The outer edge of the inner plate layer is fixed to the inner wall of the column angle groove, and an annular groove for the support tube to pass through is opened in the middle of the inner plate layer. Two reinforcement grooves facing the adjacent end corners of the fixed base plate are also opened inside the inner plate layer. The reinforcement groove is L-shaped, and a matching external connecting piece is arranged inside the reinforcement groove.
4. An asphalt mixing plant as claimed in claim 3, Features: The external connecting member includes a lower pressure plate and a linkage plate located inside the reinforcement groove, the working ends of the lower pressure plate and the linkage plate respectively penetrate the two open ends of the reinforcement groove, the two open ends are respectively located on the upper surface and the side of the inner plate layer, and the opening of the side is connected to the extension groove set at the end corner of the fixed base plate, the working end of the linkage plate sequentially penetrates the opening of the side and the extension groove, and the working end of the linkage plate is provided with a fixing member for connecting with the fuel lifting system, the asphalt lifting system and the dust removal system; The lower pressing plate includes an arc-shaped top plate and an arc-shaped bottom plate, the arc-shaped top plate is located inside the opening at the top of the reinforcement groove, the width of the arc-shaped bottom plate is greater than the width of the arc-shaped top plate, and is limited by the opening at the top of the reinforcement groove, and the thickness of the arc-shaped bottom plate is less than the height of the reinforcement groove; The side where the lower pressing plate and the linkage plate are close to and fitted with each other is a mutually parallel inclined surface, and the end of the arc-shaped top plate and the opening at the top of the reinforcement groove close to the annular groove is an arc surface.
5. An asphalt mixing plant as claimed in claim 4, Features: Slide blocks are fixed on one end of both sides of the linkage plate close to the lower pressure plate, and the two slide blocks are respectively clamped in the inside of the slide groove I opened on the inner wall of the reinforcement groove, and the inner wall of the extension groove connected to the reinforcement groove is provided with a slide groove II connected to the slide groove box I, and the slide groove I is connected to the clamped slide block through a spring, and a magnet layer I is fixed to the bottom surface of the lower pressure plate, and a magnet layer II is fixed to the inner bottom wall of the reinforcement groove, and the magnet layer I and the magnet layer II have the same magnetic poles.
6. An asphalt mixing plant as claimed in claim 3, Features: The bottom end of the inner support tube is fixed with a central insert tube which is used to penetrate the annular groove and be inserted and fixed into the through groove of the inner support tube.
7. An asphalt mixing plant as claimed in claim 1, Features: The detachable climbing frame comprises a plurality of movably connected climbing frame bodies, and two adjacent climbing frame bodies are threadedly connected to threaded holes opened at upper and lower ends via threaded rods.
8. An asphalt mixing plant as claimed in claim 7, Features: The climbing frame body includes an arc-shaped inner rod and an outer rod. The inner rod is used to fit the outer surface of the dust tank or the powder tank, and the outer rod is used to form a climbing passage between the inner rod. The inner rod and the outer rod are connected by two groups of reinforcement beams, and the two groups of reinforcement beams are respectively located on both sides of the climbing passage. A rubber sleeve for climbing and grasping is provided in the middle of the inner rod, and the inner rod is connected to the dust tank or the powder tank through two movable connecting parts located at the far end.
9. An asphalt mixing plant as claimed in claim 8, Features: The number of the threaded rods is not less than five, which are respectively located at both ends of the inner rod and both ends and the middle of the outer rod.
10. An asphalt mixing plant as claimed in claim 6, Features: The inner support tube is provided with a guide channel inside, and the inner wall of the guide channel is fixed with inner support rods that are equidistant and cross-distributed. The center insert is provided with an inner hole connected to the guide channel, and the outer surface of the load-bearing column is provided with a dust suction hole connected to the inner hole.