Operating platform system of cantilever bridge girder erection machine

By designing the operating platform system of the cantilever bridge erecting machine, including the support and anchoring and horizontal anchor systems of the upper and lower operating platforms, the problem of stability and heavy weight of the operating platform of the cantilever bridge erecting machine is solved, and more efficient hoisting and Safer construction process.

CN221822760UActive Publication Date: 2024-10-11NINGBO MUNICIPAL ENG CONSTR GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323141533.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-21
Publication Date
2024-10-11
Estimated Expiration
2033-11-21

AI Technical Summary

Technical Problem

The operating platform of the existing cantilever bridge erecting machine has problems such as poor stability, excessive weight, complex structure and inconvenient hoisting during the construction process, which affects construction efficiency and safety.

Method used

An operating platform system including an upper operating platform, a lower operating platform, a supporting anchor system and a horizontal anchor system is designed. The upper operating platform is suspended from the upper chord of the supporting truss of the cantilever bridge erecting machine through the upper anchor system. The lower operating platform is cross-supported by longitudinal and transverse beams. System and diamond-shaped support structure, reduce the cantilever length of the support beam, and set horizontal constraints to improve overall stability.

Benefits of technology

It reduces the weight of the lower operating platform, simplifies the hoisting process, reduces risk time, improves the stability and safety of the aerial operation of the cantilever bridge erecting machine, and at the same time reduces the reserved space and load effect of the support beam.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221822760U_ABST
    Figure CN221822760U_ABST
Patent Text Reader

Abstract

The utility model discloses an operating platform system of a cantilever bridge girder erection machine. The operating platform system comprises an upper operating platform, a lower operating platform, a supporting anchoring system and a horizontal anchoring system, the supporting and anchoring system comprises an upper anchoring system, an anchor rod and a lower anchoring system suspended below the upper anchoring system through the anchor rod; the upper operation platform is anchored on a cantilever upper chord of a supporting truss system of the cantilever bridge girder erection machine through an upper anchoring system, the lower operation platform is anchored and supported through a lower anchoring system, and the lower operation platform comprises a lower platform supporting structure and a lower platform working panel; the lower platform supporting structure is characterized in that the lower platform supporting structure adopts a longitudinal and transverse beam-crossed supporting system and comprises two main supporting beams, a plurality of secondary supporting beams and a rhombic supporting system; wherein the main supporting beams are arranged in the transverse bridge direction, the secondary supporting beams are arranged in the longitudinal bridge direction, and the rhombic supporting system is arranged in an area defined by the main supporting beams and the secondary supporting beams; and a working panel is paved between the secondary supporting beams. Therefore, the stability and the safety of the cantilever bridge girder erection machine during aerial operation are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to an operating platform system of a cantilever bridge erecting machine, belonging to auxiliary equipment for bridge construction. Background Art

[0002] Chinese patent CN202211543500.0 discloses a piece-by-piece cantilever assembly aerial work platform for all-welded steel truss bridges and its construction method. The aerial work platform is a bridge construction equipment that implements the "front cantilever, rear beam feeding" construction method and is suitable for truss bridges that "cannot arrange temporary support or auxiliary ships and cross valleys and waterways". It combines the "hanging basket" used for cantilever construction and the "bridge erection machine" system used for simple support and continuous construction.

[0003] As a large-scale bridge construction equipment, its design stage needs to focus not only on the safety and functional efficiency of the equipment, but also on the convenience of equipment installation and removal. Domestic large-scale bridge erection machines that cross rivers and valleys either have large components and are installed using large-tonnage floating cranes, large-tonnage truck cranes or crawler cranes; or have small components and are installed using tower cranes or small-tonnage truck cranes.

[0004] In Chinese patent CN202211543500.0, the operating platform for construction workers is not considered. The operating platform includes walkway plates and their supporting beams, railings, etc., all of which need to be assembled from loose parts at high altitudes. On the one hand, this is because the supporting beams of the upper operating platform in this scheme adopt a truss system, the specifications of a single rod are small and the total height of the truss beam is large, and the stability during the lifting operation is not good; on the other hand, the upper operating platform disclosed therein adopts a three-way supporting beam system, and the spacing between the supporting beams is not large, so that the operating platform is set in the plane of the upper chord of the cantilever bridge erection machine. The operating platform is large in size and is not easy to merge with the supporting beam as a whole. In addition, the lower operating platform in this scheme has a complex structure and a heavy overall weight, so it is necessary to reduce its weight. Utility Model Content

[0005] The utility model aims to provide an operating platform system of a cantilever bridge erecting machine to improve the stability and safety of the cantilever bridge erecting machine in aerial operation.

[0006] In order to achieve the above technical objectives, the utility model will adopt the following technical solutions:

[0007] An operating platform system for a cantilever bridge erection machine comprises an upper operating platform, a lower operating platform, a supporting anchoring system and a horizontal anchoring system; the supporting anchoring system comprises an upper anchoring system, anchor rods and a lower anchoring system suspended below the upper anchoring system by the anchor rods; the upper operating platform is anchored to a cantilever upper chord of a supporting truss system of the cantilever bridge erection machine by the upper anchoring system, the lower operating platform is suspended and anchored by the lower anchoring system, and the lower operating platform comprises a lower platform supporting structure and a lower platform working panel; the lower platform supporting structure adopts a longitudinal and transverse beam-cross supporting system, comprising two main supporting beams, a plurality of secondary supporting beams and a diamond supporting system; wherein: the main supporting beams are arranged along the transverse direction of the bridge, the secondary supporting beams are arranged along the longitudinal direction of the bridge, and the diamond supporting system is arranged in the area surrounded by the main supporting beams and the secondary supporting beams; and the working panel is paved between the secondary supporting beams.

[0008] Preferably, there are a total of 7 secondary supporting beams; 2 secondary supporting beams are arranged in the projection area of ​​the two cantilever lower chords of the supporting truss system, 1 secondary supporting beam is arranged in the central area of ​​the main bridge deck, and 1 secondary supporting beam is arranged in the projection area of ​​the cantilever arms on both sides of the supporting truss system.

[0009] Preferably, the lower operating platform is equipped with a horizontal anchoring system; the horizontal anchoring system includes longitudinal constraints and transverse constraints; the transverse constraints are arranged on the main supporting beam of the lower operating platform, and are located on both sides of the lower chord segment of the previous main bridge that has been completed; the longitudinal constraints are located in the projection area of ​​the two cantilever lower chord rods of the supporting truss system and are connected between the secondary supporting beam and the lower chord segment of the previous main bridge that has been completed.

[0010] Preferably, the transverse bridge constraint includes two transverse constraint brackets and a transverse constraint connecting steel plate connecting the two transverse constraint brackets; the transverse constraint bracket includes a transverse constraint vertical rod and a transverse constraint diagonal rod; the transverse constraint vertical rods of the two transverse constraint brackets are connected by the transverse constraint connecting steel plate, and one end of the transverse constraint vertical rod is connected to the main supporting beam, and the other end is located on one side of the lower chord segment of the previous main bridge that has been completed and extends vertically along the lower chord segment of the previous main bridge that has been completed, and one end of the transverse constraint diagonal rod is connected to the transverse constraint vertical rod, and the other end is connected to the main supporting beam.

[0011] Preferably, the constraint along the bridge direction is a connecting steel plate along the bridge direction.

[0012] Preferably, the lower anchoring system is located near the joint of the two outermost secondary supporting beams and the main supporting beam of the lower operating platform, including the anchoring beam of the lower hanging point, the upper lifting ear, the lower lifting ear and the pin; the anchoring beam of the lower hanging point is hoisted under the upper anchoring system by an anchor rod, the upper end of the upper lifting ear is installed on the anchoring beam of the lower hanging point, and the lower end is positioned and connected to the lower lifting ear by a pin, and the lower lifting ear is installed on the secondary supporting beam.

[0013] Preferably, the upper anchoring system includes an upper anchor beam of the upper hanging point, a lower anchor beam of the upper hanging point and a jack; the upper anchor beam of the upper hanging point and the lower anchor beam of the upper hanging point are anchored to the anchor rod by bolts, the lower anchor beam of the upper hanging point is located above the main supporting beam of the upper operating platform, the upper anchor beam of the upper hanging point is located above the lower anchor beam of the upper hanging point, and a jack is installed on the top plate of the lower anchor beam of the upper hanging point.

[0014] Preferably, the upper operating platform comprises an upper platform supporting structure, an upper platform working panel arranged on the upper platform supporting structure, and an upper platform railing system arranged around the upper platform supporting structure.

[0015] Based on the above technical objectives, compared with the prior art, the utility model has the following advantages:

[0016] 1. The operating platform system described in the utility model greatly reduces the weight of the lower operating platform, making the cumulative weight of the lower operating platform less than 14 tons. It is possible to lift the entire platform at one time on site, which greatly reduces the time required for on-site assembly of scattered parts. While the construction machinery is lowered, the load effect of the upper operating platform is reduced, thereby reducing the duration of the risk.

[0017] 2. Reduce the reserved space between the cantilever bridge crane boom and the main structure, and reduce the original 2.0m gap to 0.5m to reduce the cantilever length of the supporting beam.

[0018] 3. Weld steel plates on both sides of the flange of the upper operating platform support beam to increase its bearing capacity.

[0019] 4. In the lower operating platform, diamond supports are set between the distribution beam along the bridge and the transverse main supporting beam to ensure the lateral stability of the lower operating platform. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a three-dimensional structural schematic diagram of the cantilever bridge erecting machine described in the utility model;

[0021] Figure 2 It is the overall layout of the operating platform system in the transverse direction of the bridge;

[0022] Figure 3 It is a plan view of the upper operating platform;

[0023] Figure 4 It is the plan structure diagram of the lower operating platform;

[0024] Figure 5 It is a plan view of the lower platform support structure;

[0025] Figure 6 is a schematic diagram of the structure of the upper anchorage system, in which: (a) is a plan view of the upper anchorage system in the transverse direction of the bridge; (b) is a layout view of the upper anchorage system in the longitudinal direction of the bridge;

[0026] Figure 7 It is the transverse arrangement diagram of the lower anchorage system;

[0027] Figure 8 It is the structural diagram of the lower anchoring system;

[0028] Fig. 9 It is the layout diagram of the horizontal anchorage system;

[0029] In the figure: 1. Support truss system; 2. Multi-directional transport system; 3. Advance-anchor system; 4. Operating platform system; 5. Main bridge deck;

[0030] 411, upper platform working panel; 411-1, first upper platform steel springboard; 411-2, second upper platform steel springboard; 412, upper platform main support beam; 413, upper platform pedestrian passage; 414, upper platform railing system;

[0031] 421, lower anchor beam of upper hanging point; 422, upper anchor beam of upper hanging point; 423, anchor rod; 424, upper anchoring piece of upper hanging point; 425, lower anchoring piece of upper hanging point; 426, jack; 427, anchor beam of lower hanging point; 428-1, connecting pin; 428-2, upper lifting lug 428-2; 428-3, lower lifting lug;

[0032] 431, working panel of lower platform; 432, main supporting beam of lower platform; 433, secondary supporting beam of lower platform; 434-1, railing of lower platform in cross direction of bridge; 434-2, railing of lower platform in along direction of bridge; 435, pressure beam; 436, platform connecting rod;

[0033] 51. The lower chord of the main bridge that has been spliced; 52. The lower chord of the main bridge to be spliced;

[0034] 441. Lateral restraining bracket; 442. Connecting steel plate along the bridge direction. DETAILED DESCRIPTION

[0035] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means any restriction on the utility model and its application or use. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Unless otherwise specified, the relative arrangement, expressions and numerical values ​​of the components and steps described in these embodiments do not limit the scope of the utility model. The techniques, methods and equipment known to ordinary technicians in the relevant fields may not be discussed in detail, but in appropriate cases, the techniques, methods and equipment should be regarded as part of the specification. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, not as a limitation. Therefore, other examples of the exemplary embodiments may have different values.

[0036] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below other devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations).

[0037] like Figure 1 As shown, a cantilever bridge erection machine is disclosed, including a machine body, the machine body includes a supporting truss system 1, an advancing-anchoring system 3, a beam transporting system, a multi-directional transporting system 2 and an operating platform system 4, the advancing-anchoring system 3 includes a machine body travel driving device and a machine body anchoring device, the machine body travel driving device is arranged at the bottom of the anchoring section of the supporting truss system 1, and the machine body anchoring device is installed between the anchoring section of the supporting truss system 1 and the upper bridge deck by a detachable connection method; the beam transporting system is arranged on the upper bridge deck and is in the area surrounded by the bottom trusses of the supporting truss system 1; the multi-directional transporting system 2 is arranged on the middle truss of the supporting truss system 1, and the operating platform system 4 is suspended and installed at the cantilever end of the supporting truss system 1. Among them:

[0038] 1) The supporting truss system 1 is the core force-bearing structural system of the machine body of the utility model; the advancing-anchoring system 3, the beam transport system, the multi-directional transport system 2 and the operating platform system 4 are all constructed through the supporting truss system 1.

[0039] 2) Advance-anchoring system 3, providing the supporting truss system 1 with the functions of "support (anchoring)" and "advance". Specifically, at the preset position of the main bridge steel structure segment assembly, the supporting truss system 1 is anchored on the main bridge deck 5 through the machine anchoring device; after the current main bridge steel structure segment assembly is completed, the machine anchoring device installed between the main bridge deck 5 and the supporting truss system 1 is released, and then the machine is driven by the machine travel drive device to move to the next main bridge steel structure segment assembly preset position, and then the supporting truss system 1 is anchored on the main bridge deck 5 again through the machine anchoring device. This process is repeated until all the main bridge steel structure segments are assembled.

[0040] 3) Multi-directional transport system 2, mainly responsible for the lifting operation of the components of the main bridge steel structure segment from the beam transport system to the operating platform system 4, including lifting equipment, longitudinal track beams, transverse track system and transverse mobile system. Multi-directional transport system 2 is set on the supporting truss system 1.

[0041] 4) Operation platform system 4 is mainly responsible for assembling the components of the steel structure segments of the current main bridge hoisted by the multi-directional transportation system 2, and provides operating space for construction machinery and operators;

[0042] 5) The beam transport system is responsible for transporting the various components of the steel structure segments of the current main bridge, so as to transport the various components of the steel structure segments of the current main bridge lifted by crawler cranes or gantry cranes in the side span area to the loading area of ​​the multi-directional transport system 2, including beam transport trolleys, beam transport tracks, etc.

[0043] The following will be combined with the attached Figure 2-9 The operating platform system 4 described in the utility model is described in detail.

[0044] Considering that the operating platform system 4 is in a suspended state, the functions of the operating platform system 4 must meet the following three requirements:

[0045] 1) The operating platform system 4 must have sufficient vertical stiffness and vertical bearing capacity;

[0046] 2) The operating platform system 4 must have sufficient horizontal bearing capacity, especially under extreme wind load conditions, the operating platform system 4 must have sufficient overall stability;

[0047] 3) A reliable enclosure system must be arranged around the operating platform system 4 to ensure the safety of operators.

[0048] like Figure 2 As shown, the operating platform system 4 described in the utility model is composed of 4 parts, including an upper operating platform, a lower operating platform, a supporting anchoring system and a horizontal anchoring system. Among them, the transverse spacing of the anchor rods 423 involved in the supporting anchoring system is 14m to cover the full width of the main span section (13m).

[0049] The conventional section of the upper operating platform is arranged on one side along the main supporting beam of the working platform, and the ends are arranged symmetrically on both sides due to the need for mechanical jack operation.

[0050] like Figure 3 As shown, the upper operating platform includes an upper platform support structure, an upper platform working panel 411 arranged on the upper platform support structure, and an upper platform railing system 414 arranged around the upper platform support structure; the upper platform support structure includes a full-length [20 channel steel longitudinal beam and a plurality of [20 channel steel transverse beams; the upper platform working panel 411 includes two types of upper platform steel springboards, corresponding to the first and second upper platform steel springboards 411-2. Among them, the channel steel longitudinal beam is arranged facing the main supporting beam side of the working platform, and the distance between the back of the limb and the axis of the main supporting beam of the working platform is 1.0m; the horizontal spacing of the channel steel cross beam matches the stiffening rib of the main supporting beam of the working platform, which is 1.8m, and one end is welded to the stiffening rib of the main supporting beam, and the other end is welded to the channel steel longitudinal beam (the flange of the cross beam is cut off at the intersection); the steel springboard is arranged along the transverse bridge direction, one is 50cm wide and the other is 25cm wide. The conventional section single upper platform steel springboard (the first upper platform steel springboard 411-1) is 1.8m long, and the end area is partially cantilevered. The single upper platform steel springboard (the second upper platform steel springboard 411-2) is 2.4m long. The railing system is arranged along the outer contour of the upper platform working panel 411 to form the upper platform railing system 414, and an entrance and exit are opened at the upper platform pedestrian passage 413.

[0051] The projection range of the upper operating platform (conventional section) should avoid the second section of the cantilever section of the supporting truss (i.e. the area of ​​the middle chord working platform) to facilitate walking on the pedestrian passage 413 of the upper platform.

[0052] like Figure 4-5As shown, the lower operating platform includes the lower platform support structure and the lower platform working panel 431. The lower platform support structure adopts the "longitudinal and transverse beams + cross support" system. Two 15m HN700 steel beams are used as the main support beams 432 of the lower platform in the transverse direction of the bridge, with a spacing of 9.39m (corresponding to the upper working platform, and considering the adjustment of the anchor point structure). Seven 12m HN400 steel beams are used as the secondary support beams of the lower platform in the longitudinal direction of the bridge. Two beams are set in the projection area of ​​the lower chord with a spacing of 1.0m, one beam is set on the cantilever side with a spacing of 2.8m, and one beam is set in the center area of ​​the bridge deck. The spacing from the secondary support beams on both sides is the same, which is 3.1m. Double-jointed [20a channel steel is used to set up a diamond support system between the support beams to ensure the overall stability of the platform plane. The main and secondary support beams and the diamond support are connected by M24 bolts, and the connection surface is located at the upper flange of the main support beam 432 of the lower platform or the lower flange of the secondary support beam. The diamond support system is formed by arranging platform tie rods between the primary and secondary support beams.

[0053] A steel springboard for the lower platform is set between the secondary supporting beams of the lower platform as the working surface for the construction workers. There are two types of steel springboards for the lower platform, corresponding to the first and second steel springboards for the lower platform. Among them, the specifications of the first steel springboard for the lower platform (steel springboard in the cantilever area) are 2.8m (length) × 0.5m (width), and the specifications of the second steel springboard for the lower platform (steel springboard in the bridge deck area) are 3.0m (length) × 0.5m (width). No steel springboard is set in the lower chord area. At the same time, in order to meet the needs of the use of mechanical jacks involved in the construction of the lower chord elevation adjustment, 2 double-piece I14a I-beams are arranged in the bridge deck area (the position is determined according to the actual needs of the project, so it needs to be adjustable) as pressure beams used by mechanical jacks.

[0054] In addition, the lower operating platform is provided with a railing system along the outer periphery of the primary and secondary supporting beams, wherein the railing along the bridge (at the secondary supporting beam of the lower platform) is 1.5m high, and the railing across the bridge (at the main supporting beam 432 of the lower platform) is 2.0m high. It can be seen that the lower platform railing system described in the utility model includes two types, corresponding to the lower platform cross bridge railing 434-1 and the lower platform along bridge railing 434-2.

[0055] The supporting anchoring system consists of three parts: "upper anchoring system", "lower anchoring system" and "anchor rod 423".

[0056] (1) Anchor rod:

[0057] Two anchor rods 423 are set at a single supporting anchor point, with a spacing of 50 cm between the anchor rods 423. Ф32 precision-rolled threaded steel bars are used. The length of a single anchor rod 423 is not less than 25 m. A rubber protective sleeve needs to be provided on the outside of the anchor rod 423 to prevent the influence of flame on its safety performance.

[0058] (2) Upper anchoring system

[0059] like Figure 6 As shown, the upper anchoring system is arranged at the end of the upper platform main support beam 412 of the upper operating platform, including an upper anchor beam 422 of an upper hanging point, a lower anchor beam 421 of an upper hanging point, a 25T mechanical jack 426 and a fine-rolled threaded steel anchoring system. The upper and lower anchor beams of the upper hanging point are both made of double-jointed I45a I-beams, with a lateral spacing of 50mm to accommodate the passage of Ф32 fine-rolled threaded steel, and a height spacing of 30cm (not less than the height of a single mechanical jack) to 45cm (not less than the height of a single mechanical jack and its maximum stroke height).

[0060] The lower anchor beam 421 of the upper hanging point is located above the main support beam of the upper operating platform, the upper anchor beam 422 of the upper hanging point is located above the lower anchor beam 421 of the upper hanging point, and a jack is installed on the top plate of the lower anchor beam 421 of the upper hanging point.

[0061] Two precision-rolled bolt anchor bolts are respectively arranged on the upper flanges of the upper and lower anchor beams of the upper hanging point. When the elevation is adjusted, the upper anchor beam 422 of the upper hanging point is connected and fixed by the upper anchor piece (anchor bolt) of the upper hanging point. When the elevation is fixed, the lower anchor beam 421 of the upper hanging point is connected and fixed by the lower anchor piece (anchor bolt) of the upper hanging point.

[0062] (3) Lower anchoring system

[0063] like Figure 7-8 As shown, the lower anchoring system is located near the joint between the two outermost lower platform secondary support beams and the lower platform main support beam 432 of the lower operating platform.

[0064] The single lower anchoring system adopts a pin drive mode to reduce the bending effect of the anchor rod 423. The lower anchoring system includes an anchoring beam 427 of the lower hanging point, an upper hanging ear 428-2, a lower hanging ear 428-3 and its stiffening system, a Ф50 pin and a precision rolled threaded steel anchoring system.

[0065] The anchor beam 427 of the lower hanging point is made of double-jointed [20a channel steel, with the channel steel limbs arranged oppositely and a spacing of 60mm. Finished rolled threaded steel bars are arranged at both ends, and anchor bolts are arranged on both the upper and lower sides. An upper hanging ear 428-2 is set in the middle. The upper hanging ear 428-2 is 540mm long, 180mm wide, and 40mm thick. A Ф50 pin hole is opened at the bottom, and reinforcing steel plates with an outer diameter of 160mm and a thickness of 20mm are added on both sides. The upper part is connected to the upper anchor beam through a weld. In order to meet the 60mm seam width requirement, a 10mm filler plate is set on each side of the hanging ear.

[0066] The lower hanging ears 428-3 are arranged on both sides of the lower end of the upper hanging ears 428-2, with a center spacing of 140mm. A single lower hanging ear 428-3 is 200mm wide, 200mm high, and 20mm thick. A 10mm steel plate with a diameter of 160mm is applied to each side of the hanging ear. A 12mm thick, 100mm wide, and 200mm long stiffening rib is set at each end of the lower hanging ear 428-3, and a stiffening system corresponding to the position of the lower hanging ear 428-3 and its stiffening rib is arranged on the anchoring secondary support beam.

[0067] Horizontal anchoring system:

[0068] The lower operating platform is supported vertically by 8 finely rolled rebars at 4 supporting points. To ensure its overall stability, horizontal constraints need to be set, including longitudinal and transverse constraints. The specific structure is as follows: Fig. 9 shown.

[0069] The transverse bridge constraint is set on the main supporting beam 432 of the lower platform, located on both sides of a single lower chord segment. The single transverse bridge constraint includes two transverse constraint brackets 441 and a transverse constraint connecting steel plate connecting the two transverse constraint brackets 441; the transverse constraint bracket 441 includes a transverse constraint vertical rod and a transverse constraint diagonal rod; the transverse constraint vertical rods of the two transverse constraint brackets 441 are connected by a transverse constraint connecting steel plate, and one end of the transverse constraint vertical rod is connected to the main supporting beam of the lower platform, and the other end is located on one side of the lower chord segment of the previous main bridge that has been spliced ​​and extends vertically along the lower chord segment 51 of the previous main bridge that has been spliced, and one end of the transverse constraint diagonal rod is connected to the transverse constraint vertical rod, and the other end is connected to the main supporting beam. The transverse constraint vertical rod and the transverse constraint diagonal rod are both made of double-joined [10 channel steel.

[0070] The longitudinal constraint is located in the projection area of ​​the two cantilever lower chords of the supporting truss system and is connected between the secondary supporting beam and the lower chord segment 51 of the previous main bridge that has been spliced, and is 50mm away from the joint of the lower chord segment. It consists of 4 longitudinal connecting steel plates 442 with a length of 500mm and a thickness of 20mm. The width of the longitudinal connecting steel plates 442 is determined according to the different states of each segment. The lower end is aligned with the web of the secondary supporting beam, and the upper end is directly welded to the bottom plate of the lower chord.

Claims

1. An operating platform system of a cantilever bridge erecting machine, comprising an upper operating platform, a lower operating platform, a supporting anchoring system and a horizontal anchoring system; the supporting anchoring system comprises an upper anchoring system, anchor rods and a lower anchoring system suspended below the upper anchoring system by the anchor rods; the upper operating platform is anchored to the cantilever upper chord of the supporting truss system of the cantilever bridge erecting machine by the upper anchoring system, the lower operating platform is suspended and anchored by the lower anchoring system, and the lower operating platform comprises a lower platform supporting structure and a lower platform working panel; it is characterized in that The lower platform support structure adopts a longitudinal and transverse beam-cross support system, including two main supporting beams, several secondary supporting beams and a diamond support system; among which: the main supporting beams are arranged along the transverse direction of the bridge, the secondary supporting beams are arranged along the longitudinal direction of the bridge, and the diamond support system is arranged in the area surrounded by the main supporting beams and the secondary supporting beams; the working panels are paved between the secondary supporting beams.

2. The operating platform system of the cantilever bridge erecting machine according to claim 1 is characterized in that: There are a total of 7 secondary supporting beams; 2 secondary supporting beams are arranged in the projection area of ​​the two cantilever lower chords of the supporting truss system, 1 secondary supporting beam is arranged in the central area of ​​the main bridge deck, and 1 secondary supporting beam is arranged in the projection area of ​​the cantilever arms on both sides of the supporting truss system.

3. The operating platform system of the cantilever bridge erecting machine according to claim 2 is characterized in that: The lower operating platform is equipped with a horizontal anchoring system; the horizontal anchoring system includes longitudinal constraints and transverse constraints; the transverse constraints are arranged on the main supporting beam of the lower operating platform, and are located on both sides of the lower chord segment of the previous main bridge that has been completed; the longitudinal constraints are located in the projection area of ​​the two cantilever lower chord rods of the supporting truss system and are connected between the secondary supporting beam and the lower chord segment of the previous main bridge that has been completed.

4. The operating platform system of the cantilever bridge erecting machine according to claim 3 is characterized in that: The transverse bridge constraint includes two transverse constraint brackets and a transverse constraint connecting steel plate connecting the two transverse constraint brackets; the transverse constraint bracket includes a transverse constraint vertical rod and a transverse constraint diagonal rod; the transverse constraint vertical rods of the two transverse constraint brackets are connected by the transverse constraint connecting steel plate, and one end of the transverse constraint vertical rod is connected to the main supporting beam, and the other end is located on one side of the lower chord segment of the previous main bridge that has been completed and extends vertically along the lower chord segment of the previous main bridge that has been completed, one end of the transverse constraint diagonal rod is connected to the transverse constraint vertical rod, and the other end is connected to the main supporting beam.

5. The operating platform system of the cantilever bridge erecting machine according to claim 3 is characterized in that: The constraint along the bridge direction is the connecting steel plate along the bridge direction.

6. The operating platform system of the cantilever bridge erecting machine according to claim 2 is characterized in that: The lower anchoring system is located near the joint of the two outermost secondary supporting beams and the main supporting beam of the lower operating platform, including the anchoring beam of the lower hanging point, the upper lifting ear, the lower lifting ear and the pin; the anchoring beam of the lower hanging point is hoisted under the upper anchoring system through anchor rods, the upper end of the upper lifting ear is installed on the anchoring beam of the lower hanging point, and the lower end is positioned and connected with the lower lifting ear through a pin, and the lower lifting ear is installed on the secondary supporting beam.

7. The operating platform system of the cantilever bridge erecting machine according to claim 2 is characterized in that: The upper anchoring system includes an upper anchor beam of the upper hanging point, a lower anchor beam of the upper hanging point and a jack; the upper anchor beam of the upper hanging point and the lower anchor beam of the upper hanging point are anchored to the anchor rod by bolts, the lower anchor beam of the upper hanging point is located above the main supporting beam of the upper operating platform, the upper anchor beam of the upper hanging point is located above the lower anchor beam of the upper hanging point, and a jack is installed on the top plate of the lower anchor beam of the upper hanging point.

8. The operating platform system of the cantilever bridge erecting machine according to claim 2 is characterized in that: The upper operating platform comprises an upper platform supporting structure, an upper platform working panel arranged on the upper platform supporting structure, and an upper platform railing system arranged around the upper platform supporting structure.