Supporting system for manufacturing outdoor refuge storey of high-rise building

By using a support system of cantilevered beams, full-floor scaffolding, steel wire ropes and diagonal braces in high-rise buildings, the problem of traditional construction methods limited by ceramic mosaic exterior walls is solved, and fast and safe outdoor refuge layer construction is achieved, reducing costs and time, improving construction efficiency and safety.

CN221823086UActive Publication Date: 2024-10-11SHANGHAI BAOYE GRP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420071013.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-11
Publication Date
2024-10-11
Estimated Expiration
2034-01-11

AI Technical Summary

Technical Problem

In the construction of outdoor refuge floors of high-rise buildings, the traditional attached lifting scaffolding is limited by the ceramic mosaic exterior wall, resulting in the cantilevered refuge floor having to wait for the scaffolding to be lowered before construction, which increases construction costs and safety risks, and the cantilevered structure requires secondary Connecting steel bars affects construction efficiency and safety.

Method used

A support system including cantilevered beams, full-floor scaffolding, steel wire ropes and diagonal braces is adopted. The cantilevered beams are made of I-beams, which are connected to embedded parts through steel wire ropes. The diagonal braces are anchored to the exterior walls. Protective frames and formwork are set up, and concrete is used. Pour to form a refuge layer.

Benefits of technology

It realizes the rapid and safe construction of secondary structures on the cantilevered platform outside high-rise buildings, reduces construction costs and time, improves construction efficiency and safety, and provides a flexible and practical support system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221823086U_ABST
    Figure CN221823086U_ABST
Patent Text Reader

Abstract

The utility model relates to a supporting system for manufacturing an outdoor refuge floor of a high-rise building, which comprises a cantilever beam and an all-round scaffold, one end of the cantilever beam is horizontally arranged on the outer side of a floor slab, a protective outer frame is erected on the upper portion of the other end of the cantilever beam, and the all-round scaffold is erected on the upper portion of the cantilever beam. The top of the all-round scaffold is connected with a jacking support installed below the formwork. The structure is convenient to implement on the premise that an outer wall scaffold cannot be used and outdoor secondary structure construction needs to be carried out.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of super high-rise secondary structure construction, in particular to a support system for making an outdoor refuge layer of a high-rise building. Background Art

[0002] For civil buildings, there are some common characteristics, such as high total building height and decorative exterior walls, which will have a certain impact on the construction process during construction:

[0003] 1. The cantilever platform used as the outdoor refuge layer needs to be constructed later: When the attached lifting scaffolding is used for construction and the exterior wall is made of ceramic mosaic technology, the attached lifting scaffolding selected for construction cost needs to be lowered for the exterior wall mosaic construction. The traditional attached lifting scaffolding can only be raised but not lowered. Due to the fact that the exterior wall of the building is made of ceramic mosaic, the scaffolding needs to be lowered before it can be used for the facade construction; therefore, the cantilever refuge layer must wait until the scaffolding is lowered before construction can be carried out.

[0004] 2. During the construction of ordinary cantilever structures, such as balcony structures, the steel bars and concrete pouring of the cantilevered parts can be formed at one time. However, for the above-mentioned outdoor refuge layer, due to the construction of the exterior wall mosaic decorative surface, the attached scaffolding needs to be lowered, resulting in the cantilever beam steel bars of the refuge layer having to be connected twice.

[0005] 3. For the cantilever structure of the entire refuge floor, safety assurance during the construction process is also the focus, so the design of the cantilever structure must also meet the requirements of construction load and the structure's own load. Summary of the invention

[0006] The utility model aims to overcome the defects of the prior art and provide a support system for making an outdoor refuge layer of a high-rise building, so as to solve the problem of making a refuge layer in situations where an external wall scaffolding cannot be used and outdoor secondary structure construction is required.

[0007] In order to solve the above technical problems, the utility model is achieved as follows:

[0008] A support system for making an outdoor refuge layer of a high-rise building, characterized in that it includes a cantilever beam and a full-height scaffolding, one end of the cantilever beam is horizontally arranged on the outside of the floor slab, a protective external frame is erected on the upper part of the other end of the cantilever beam, the full-height scaffolding is erected on the upper part of the cantilever beam, and the top of the full-height scaffolding is connected to a jacking bracket installed under the formwork.

[0009] The support system for making an outdoor refuge layer of a high-rise building is characterized in that the cantilever beam is made of I-beam.

[0010] The support system for making an outdoor refuge layer of a high-rise building is characterized in that it also includes steel wire ropes, and the outer end of the cantilever beam is connected to the embedded parts embedded in the upper floor slab and extending out of the outer wall of the building through the steel wire ropes.

[0011] The support system for making an outdoor refuge layer of a high-rise building is characterized in that it also includes an oblique brace connected between the lower part of the outer end of the cantilever beam and the outer wall of the building.

[0012] The support system for making an outdoor refuge layer of a high-rise building is characterized in that wooden wedges are arranged in the gap between the cantilever beam and the outer side of the floor slab.

[0013] The support system for making an outdoor refuge layer of a high-rise building is characterized in that the cantilever beam becomes a refuge layer after being poured with concrete.

[0014] The beneficial effects of the present utility model are as follows: It can be seen from the above technical scheme that the present application provides a support system for making an outdoor refuge layer of a high-rise building, which can be constructed through secondary structure construction and used as a support system for an outdoor refuge layer of a high-rise building. It has the characteristics of reliable overall structural bearing capacity, easy implementation and easy control of construction costs.

[0015] This application uses a simple and practical construction principle, conventional materials and a relatively low cost investment, and can specifically solve the construction problem of external cantilever platforms in super-high-rise projects that require secondary construction when attached lifting scaffolding is used as an external protective facility. This is derived from the traditional cantilever structure support system, which has positive significance for guiding construction in similar working conditions, and also provides a new way to solve such problems. This support system is simple and easy to operate, and can make corresponding adjustments and modifications according to changes in the on-site cantilever structure. It has strong practicality and flexibility, and the cost is relatively low. It improves the on-site construction efficiency and speed, and has a certain promotion significance. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The present invention is further described in detail below in conjunction with the accompanying drawings and implementation examples:

[0017] Figure 1 This is a schematic diagram of the structure of this application.

[0018] Figure 2 This is the cable-stayed structure diagram of the cantilevered end of the I-beam.

[0019] Figure 3 This is the structural diagram of the lower diagonal brace of the I-beam cantilever. DETAILED DESCRIPTION

[0020] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the embodiments of the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection requested by the present application.

[0021] like Figure 1-3 As shown: A support system for making an outdoor refuge layer of a high-rise building, comprising:

[0022] 1. A horizontally arranged cantilever beam 4 is in the form of an I-beam vertical pole, and its inner end is placed on the floor slab 2 of the building through a preset hole or connected to the outer wall of the building through a chemical bolt 1 and a connecting corbel;

[0023] 2. Auxiliary steel wire rope 3, both ends of which are respectively connected to the outer end of the cantilever beam and the embedded parts embedded in the upper floor slab and extending out of the outer wall of the building.

[0024] 3. A diagonal brace 5 is arranged below the horizontal cantilever beam. The diagonal brace is also arranged with an I-beam. A post-anchored corbel is arranged between the diagonal brace and the building exterior wall, and a reinforcement plate is arranged between the post-anchored corbel and the diagonal brace.

[0025] Furthermore, when constructing the above support system, protective measures are set up, including

[0026] 1) A construction protection frame 6 is arranged on the outside of the cantilever beam. The construction protection frame is constructed by a steel pipe scaffolding and partially embedded in the floor slab;

[0027] 2) When constructing the cantilever beam, a full-height scaffold 8 is used to connect with the cantilever beam, and the top of the full-height scaffold is also connected with the top support bracket 7 used for concrete formwork;

[0028] 3) A wooden wedge 9 is provided in the gap between the cantilever beam and the outer side of the floor slab.

[0029] Furthermore, the above-mentioned support system is further transformed into a refuge floor through formwork construction, which is specifically achieved by pouring concrete. During this period, the floor slab steel bars are tied. When the floor slab steel bars are connected to the building exterior wall, straight thread reinforcement welding steel is used. The straight thread joints of the steel bars extend out of the wall to ensure that the joints are not in the same section. The straight thread joints are reinforced and welded by additional steel bars to ensure the connection quality of the steel bar joints.

[0030] This application uses an I-beam lower support. The triangular support system is relatively stable, and the possibility of deflection at the end of the cantilevered I-beam is very small. At the same time, the I-beam on the lower support structure can be connected to the end of the cantilevered steel beam by welding, which has better stability. The steel wire rope can be used as a safety rope during the construction process to improve the structural safety of the entire steel platform.

[0031] The above are only embodiments provided for the present application and are not intended to limit the present application. Although the present application is described in detail with reference to the embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A support system for making an outdoor refuge layer of a high-rise building, characterized in that: It includes a cantilever beam and a full-floor scaffolding, one end of the cantilever beam is horizontally arranged on the outside of the floor slab, a protective external frame is set up on the upper part of the other end of the cantilever beam, the full-floor scaffolding is set up on the upper part of the cantilever beam, and the top of the full-floor scaffolding is connected with a top supporting bracket installed under the formwork; the cantilever beam adopts an I-beam; it also includes a steel wire rope, and the outer end of the cantilever beam is connected to an embedded part embedded in the upper floor slab and extending out of the outer wall of the building through the steel wire rope; it also includes an oblique brace, which is connected between the lower part of the outer end of the cantilever beam and the outer wall of the building; a wooden wedge is set in the gap between the cantilever beam and the outer side of the floor slab; the cantilever beam becomes a refuge layer after being poured with concrete.