Drainage structure at junction of metal roof and concrete roof in steel structure building

By designing a multi-layer drainage structure and sealing measures in the steel structure building, the leakage and rainwater drainage problems at the junction of the metal roof and the concrete roof were solved, and the effective drainage of rainwater and the sealing of the junction were improved.

CN221823243UActive Publication Date: 2024-10-11SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420176207.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-10-11
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

In steel structure buildings, there are hidden dangers of leakage at the junction of metal roofs and concrete roofs and the problem of rainwater not being discharged in time, especially the risk of rainwater pouring back into the metal roof when the siphon rainwater bucket is clogged.

Method used

A drainage structure is designed, including drainage gutter one and drainage gutter two on the concrete roof. Drainage gutter one is equipped with a siphon drainage assembly, drainage gutter two is equipped with drainage floor drains and drainage pipes, and the end of the metal roof extends into the drainage Gutter 1, and the sealing performance of the junction is enhanced through sealing measures such as drip sheets, waterproof membranes and water-stop steel plates.

Benefits of technology

It effectively solves the hidden danger of rainwater pouring back into the metal roof, enhances the sealing performance at the junction of the metal roof and the concrete roof, avoids water leakage, and ensures the timely discharge of rainwater.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221823243U_ABST
    Figure CN221823243U_ABST
Patent Text Reader

Abstract

The utility model provides a drainage structure at the junction of a metal roof and a concrete roof in a steel structure building, which belongs to the technical field of steel structure buildings and comprises a first drainage gutter and a second drainage gutter which are arranged on the concrete roof. The first drainage gutter is arranged on the outer side of the junction of the metal roof and the concrete roof, and the second drainage gutter is arranged on the inner side of the junction of the metal roof and the concrete roof. The first drainage gutter is provided with a siphon drainage assembly, the second drainage gutter is provided with a drainage floor drain, and the drainage floor drain is communicated with a drainage pipe. The end of the metal roof extends into the first drainage gutter. The hidden danger problem that rainwater flows back into the metal roof is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of steel structure buildings, in particular to a drainage structure at the junction of a metal roof and a concrete roof in a steel structure building. Background Art

[0002] Steel structure buildings are buildings that use construction steel to form a load-bearing structure. Usually, the load-bearing structure is composed of beams, columns, trusses and other components made of steel and steel plates. Together with the surrounding structures such as roofs, floors and walls, they form a building.

[0003] For some steel structures with large spans, deep heights and heavy loads, metal roof structures are generally used for public building roofs. In order to improve the utilization rate of building space, metal roofs and concrete roofs are used for public building roofs. In this combination, the metal roof is located above the concrete roof, and the concrete roof is provided with a gutter for drainage. After the rainwater from the metal roof is discharged to the gutter, it is discharged through a siphon rainwater system. When the siphon rainwater bucket is blocked and the rain flow is large, the rainwater in the gutter cannot be discharged in time, and the hidden danger of rainwater in the gutter backflowing into the metal roof is easy to occur. Utility Model Content

[0004] The utility model aims to provide a drainage structure at the junction of a metal roof and a concrete roof in a steel structure building, aiming to solve the problem of leakage at the junction of the metal roof and the concrete roof in the prior art, and the problem that rainwater in the gutter cannot be discharged in time.

[0005] The utility model is achieved in this way:

[0006] The technical solution of the present application provides a drainage structure at the junction of a metal roof and a concrete roof in a steel structure building, comprising a drainage gutter 1 and a drainage gutter 2 arranged on the concrete roof, wherein the drainage gutter 1 is arranged on the outer side of the junction of the metal roof and the concrete roof, and the drainage gutter 2 is arranged on the inner side of the junction of the metal roof and the concrete roof;

[0007] The drainage gutter 1 is provided with a siphon drainage component, the drainage gutter 2 is provided with a drainage floor drain, and the drainage floor drain is connected with a drainage pipe;

[0008] The end of the metal roof extends into the drainage gutter.

[0009] In some embodiments of the utility model, the siphon drainage assembly includes a siphon drainage pipe, one end of which is connected to the drainage gutter one, and the other end of which is connected to the outside of the drainage gutter one, and the end cover of the siphon drainage pipe in the drainage gutter one is provided with a siphon rainwater protective cover.

[0010] In some embodiments of the present utility model, the concrete roof is provided with embedded parts, and the embedded parts are provided with steel folding parts connected to the metal roof.

[0011] In some embodiments of the utility model, the steel folding part is provided with a flashing plate and a drip sheet, the drip sheet is located above the flashing plate, and the drip sheet and the metal roof are sealed by a steel plate strip, sealing putty and a sealing plug.

[0012] In some embodiments of the utility model, the metal roof includes purlins, purlin drag plates and metal plates, and the purlin drag plates in the first drainage gutter and the second drainage gutter are coated with anti-rust paint.

[0013] In some embodiments of the present invention, a water-stopping steel plate is provided at the junction of the drainage gutter 1 and the drainage gutter 2.

[0014] In some embodiments of the present utility model, the drainage gutter 1 and the drainage gutter 2 are respectively paved with a first concrete guide wall and a second concrete guide wall.

[0015] In some embodiments of the present invention, waterproof coiled materials are provided at the junctions of the first concrete guide wall, the second concrete guide wall and the concrete roof, and the waterproof coiled materials are coated with waterproof coating.

[0016] In some embodiments of the present invention, the opposite ends of the two waterproof membranes are connected, and the connection between the two waterproof membranes is wrapped over the steel folding member.

[0017] Compared with the prior art, the technical solution of the present invention has at least the following advantages or beneficial effects:

[0018] (1) In the present application, drainage is carried out through the siphon drainage component in the drainage gutter 1. When the siphon drainage component in the drainage gutter 1 is blocked and the rain flow is large, the rainwater in the drainage gutter 1 cannot be discharged in time. At this time, the rainwater in the drainage gutter 1 flows back into the drainage gutter 2 in the metal roof, thereby collecting the backflow water and draining the backflow water through the drainage floor drain and the drainage pipe, thereby solving the hidden danger of rainwater flowing back into the metal roof.

[0019] (2) The drip sheet is connected to the metal roof through steel plate strips, sealing putty and sealing plugs, which enhances the sealing performance of the joint between the metal roof and the concrete roof and solves the hidden danger of leakage at the junction of the metal roof and the concrete roof.

[0020] (3) The waterproof membrane is wrapped over the steel folding parts, which further improves the sealing performance at the junction of the metal roof and the concrete roof, and greatly avoids the occurrence of water leakage. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solution of the implementation mode of the utility model, the drawings required for use in the implementation mode will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 It is a schematic diagram of a drainage structure at the junction of a metal roof and a concrete roof in a steel structure building provided by an embodiment of the utility model;

[0023] Figure 2 yes Figure 1 A partial enlarged view of middle A.

[0024] Icons: 1-concrete roof, 2-siphon rainwater protection cover, 3-siphon drain pipe, 4-drainage gutter one, 5-drainage gutter two, 6-first concrete guide wall, 7-second concrete guide wall, 8-flash board, 9-metal roof, 10-waterstop steel plate, 11-drainage pipe, 12-drip sheet, 13-steel folding parts, 14-embedded parts, 15-waterproof membrane. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the implementation mode of the present invention clearer, the technical solution in the implementation mode of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the implementation mode of the present invention.

[0026] Example:

[0027] like Figure 1 and Figure 2 The present embodiment provides a drainage structure at the junction of a metal roof 9 and a concrete roof 1 in a steel structure building, comprising a drainage gutter 1 4 and a drainage gutter 2 5 arranged on the above-mentioned concrete roof 1, wherein three concrete sills are arranged at intervals in the same direction on the top side of the concrete roof 1, and the junction of the metal roof 9 and the concrete roof 1 is located at the middle concrete sill, the outside of the junction of the two is the above-mentioned drainage gutter 1 4, and the inside of the junction is the drainage gutter 2 5; the above-mentioned drainage gutter 1 4 is provided with a siphon drainage component, and the siphon drainage component can drain the water in the drainage gutter 1 4, the above-mentioned drainage gutter 2 5 is provided with a drainage floor drain, and the above-mentioned drainage floor drain is connected with a drainage pipe 11, and the drainage floor drain and the drainage pipe 11 constitute the drainage structure of the drainage gutter 2 5, which can realize the drainage of water in the drainage gutter 2 5; the end of the above-mentioned metal roof 9 extends into the above-mentioned drainage gutter 1 4.

[0028] In the present application, drainage is carried out through the siphon drainage component in the drainage gutter 1 4. When the siphon drainage component in the drainage gutter 1 4 is blocked and the rainfall volume is large, the rainwater in the drainage gutter 1 4 cannot be discharged in time. At this time, the rainwater in the drainage gutter 1 4 flows back into the drainage gutter 2 5 in the metal roof 9, thereby collecting the backflow water and draining the backflow water through the drainage floor drain and the drainage pipe 11, thereby solving the hidden danger of rainwater flowing back into the metal roof 9.

[0029] In some embodiments of the utility model, the siphon drainage assembly includes a siphon drainage pipe 3, one end of the siphon drainage pipe 3 is connected to the drainage gutter 4, and the other end of the siphon drainage pipe 3 is connected to the outside of the drainage gutter 4, and the end of the siphon drainage pipe 3 in the drainage gutter 4 is covered with a siphon rainwater protective cover 2.

[0030] In this embodiment, since the end of the metal roof 9 extends into the drainage gutter 1 4, rainwater on the top side of the metal roof 9 is gathered in the drainage gutter 1 4 under the action of gravity and discharged through the siphon effect of the siphon drain pipe 3. The siphon rainwater protective cover 2 is used to prevent debris such as roof garbage from clogging the siphon drain pipe 3, and is practical. The siphon rainwater protective cover 2 is supported by stainless steel, and the cover body made of stainless steel has small round holes for rainwater circulation.

[0031] In some embodiments of the present utility model, the concrete roof 1 is provided with embedded parts 14 , and the embedded parts 14 are provided with steel folded parts 13 connected to the metal roof 9 .

[0032] In this embodiment, the steel folded member 13 and the metal roof 9 are detachably connected via a bolt group, so that the metal roof 9 can be quickly installed or removed.

[0033] In some embodiments of the utility model, the steel folding part 13 is provided with a flashing plate 8 and a drip sheet 12. The drip sheet 12 is located above the flashing plate 8. The drip sheet 12 and the metal roof 9 are sealed by steel plate moldings, sealing putty and sealing plugs.

[0034] In this embodiment, when the ambient humidity is high, the evaporation of water in the air at the roof height is likely to cause condensation on the bottom surface of the metal roof 9, and there will be a hidden danger of leakage at the junction of the metal roof 9 and the concrete roof 1. The drip sheet 12 is connected to the metal roof 9 through a steel plate strip, a sealing putty and a sealing plug, which enhances the sealing performance of the connection between the metal roof 9 and the concrete roof 1 and solves the hidden danger of leakage at the junction of the metal roof 9 and the concrete roof 1.

[0035] Part of the drip sheet 12 and part of the flashing plate 8 are overlapped, and the overlapping part of the drip sheet 12 and the flashing plate 8 is connected to the steel folding member 13 by a bolt group.

[0036] In some embodiments of the present invention, the metal roof 9 includes purlins, purlin drag plates and metal plates, and the purlin drag plates in the drainage gutter 1 4 and the drainage gutter 2 5 are coated with anti-rust paint.

[0037] In this embodiment, the anti-rust paint can reduce the probability of rusting of the purlin drag plates in the drainage gutter 1 4 and the above-mentioned drainage gutter 2 5, and increase the service life of the purlin drag plates. The purlins and the purlin drag plates are fixedly connected by nuts.

[0038] In some embodiments of the present invention, a water-stop steel plate 10 is provided at the junction of the drainage gutter 1 4 and the drainage gutter 2 5 .

[0039] In this embodiment, the water-stop steel plate 10 can improve the waterproof performance of the junction between the drainage gutter 1 4 and the above-mentioned drainage gutter 2 5.

[0040] In some embodiments of the present utility model, the drainage gutter 1 4 and the drainage gutter 2 5 are respectively paved with a first concrete guide wall 6 and a second concrete guide wall 7 .

[0041] In this embodiment, the first concrete guide wall 6 and the second concrete guide are both made of concrete materials (cement mortar layer and fine stone concrete water protection layer), which is beneficial to improving the waterproof performance of the drainage gutter 14 and the drainage gutter.

[0042] In some embodiments of the present invention, waterproof coiled materials 15 are provided at the junctions of the first concrete guide wall 6, the second concrete guide wall 7 and the concrete roof 1, and the waterproof coiled materials 15 are coated with waterproof coating.

[0043] In this embodiment, the waterproof membrane 15 can improve the sealing performance between the first concrete guide wall 6 and the concrete roof 1, and between the second concrete guide wall 7 and the concrete roof 1, thereby reducing the probability of water leakage.

[0044] In some embodiments of the present invention, the opposite ends of the two waterproof membranes 15 are connected, and the connection between the two waterproof membranes 15 is wrapped over the steel folding member 13 .

[0045] In this embodiment, the waterproof coiled material 15 is wrapped over the steel folded member 13, which further improves the sealing performance at the junction of the metal roof 9 and the concrete roof 1, and greatly avoids the occurrence of water leakage.

[0046] The above description is only the preferred implementation of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building is characterized by: It includes a drainage gutter 1 and a drainage gutter 2 arranged on the concrete roof, wherein the drainage gutter 1 is arranged on the outside of the junction of the metal roof and the concrete roof, and the drainage gutter 2 is arranged on the inside of the junction of the metal roof and the concrete roof; The drainage gutter 1 is provided with a siphon drainage component, the drainage gutter 2 is provided with a drainage floor drain, and the drainage floor drain is connected with a drainage pipe; The end of the metal roof extends into the drainage gutter; The siphon drainage assembly includes a siphon drainage pipe, one end of which is connected to the drainage gutter 1, and the other end of which is connected to the outside of the drainage gutter 1. The end cover of the siphon drainage pipe in the drainage gutter 1 is provided with a siphon rainwater protection cover.

2. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 1 is characterized in that: The concrete roof is provided with embedded parts, and the embedded parts are provided with steel folding parts connected with the metal roof.

3. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 2 is characterized in that: The steel folding part is provided with a flashing plate and a drip sheet, the drip sheet is located above the flashing plate, and the drip sheet and the metal roof are sealed by a steel plate strip, sealing putty and a sealing plug.

4. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 3 is characterized in that: The metal roof comprises purlins, purlin drag plates and metal plates, and the purlin drag plates in the first drainage gutter and the second drainage gutter are coated with anti-rust paint.

5. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 2, characterized in that: A water-stop steel plate is arranged at the junction of the first drainage gutter and the second drainage gutter.

6. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 5, characterized in that: The first drainage gutter and the second drainage gutter are respectively paved with a first concrete guide wall and a second concrete guide wall.

7. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 6, characterized in that: Waterproof coiled materials are provided at the junctions of the first concrete guide wall, the second concrete guide wall and the concrete roof, and the waterproof coiled materials are coated with waterproof coating.

8. The drainage structure at the junction of the metal roof and the concrete roof in the steel structure building according to claim 7, characterized in that: The opposite ends of the two waterproof membranes are connected, and the connection between the two waterproof membranes is wrapped over the top of the steel folding member.