Clean air conditioning system suitable for FAB

By using an embedded tube-type enclosure structure and radiation heat exchange method in the FAB, combined with a temperature collector and a pressure sensor, the problems of large return air duct area and high energy consumption are solved, and efficient temperature and humidity control and energy consumption reduction are achieved. .

CN221839810UActive Publication Date: 2024-10-15SHAANXI ELECTRONIC CORE IND TIMES TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420251713.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-01
Publication Date
2024-10-15
Estimated Expiration
2034-02-01

AI Technical Summary

Technical Problem

The clean air conditioning system in the existing FAB has a large return air duct area, resulting in high civil construction costs and high energy consumption. The traditional convection heat exchange method is not energy-saving.

Method used

It adopts an embedded tube-type enclosure structure, embedded in reinforced concrete through cold water pipes, uses radiation heat exchange to replace traditional DCC equipment, and combines temperature collectors and pressure sensors to optimize the control method to reduce the return air duct area and energy consumption.

Benefits of technology

It achieves higher temperature and humidity accuracy, reduces energy consumption, increases the cold storage capacity of the return air duct, optimizes the control method of the air conditioning system, matches the design and actual working conditions, and significantly reduces the energy consumption of the air conditioning system of the semiconductor factory.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221839810U_ABST
    Figure CN221839810U_ABST
Patent Text Reader

Abstract

The utility model provides a clean air-conditioning system suitable for FAB, which comprises an air-conditioning machine room, and an MAU direct-current air-conditioning system is arranged on the inner side surface of the air-conditioning machine room; the air return passageway is arranged on one side of the air conditioner room, and a lower technical interlayer is arranged on the inner side face of the air return passageway. According to the clean air-conditioning system suitable for the FAB, the air-conditioning system can provide a high temperature and humidity precision grade, a traditional air-conditioning DCC device is replaced, the area of an air return passageway is reduced, indoor sensible heat is eliminated in a radiation heat exchange main mode, and due to the structural particularity of an embedded pipe type enclosure structure, the air-conditioning system is suitable for the FAB. The cold storage capacity of the return air passageway is improved, the whole system is more energy-saving, the control mode of the air conditioner is optimized through the arrangement of the temperature collector, the pressure sensor and other parts, the design working condition is perfectly matched with the actual operation working condition, and the air conditioner system solves the problem that the energy consumption of the air conditioner of a semiconductor factory is huge to a certain extent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of air conditioning systems, and in particular to a clean air conditioning system suitable for FAB. Background Art

[0002] FAB has extremely high requirements for the indoor environment, including temperature, humidity, and the number of particles in the air. The HVAC system is particularly important in semiconductor factories. It is linked to process equipment and machines. When the temperature and humidity in the clean room do not reach the designed value, the machine will shut down, which will affect the production of wafers.

[0003] At present, the mainstream practice of clean air conditioning in FAB is: adopting the air conditioning system of MAU+FFU+DCC. The temperature and humidity of the clean production area of ​​this system can be independently controlled. MAU is a direct current air conditioning system, which provides air with a certain temperature, humidity and cleanliness for the clean room to ensure positive pressure in the room. FFU further purifies the air in the clean room to ensure indoor cleanliness. DCC eliminates indoor sensible heat and is responsible for accurately adjusting the indoor temperature of the clean room. Due to the particularity of the industry, the cooling index of semiconductor factories is slightly higher than that of other building factories. Usually, the cooling index of FAB clean air conditioning is about 500W / m2. The total cooling load in the FAB can be estimated according to the building area of ​​the main process area. According to the wind speed through the DCC and the temperature difference on both sides, the cooling capacity borne by the corresponding unit area of ​​DCC can be calculated. DCC is generally set in the TRUSS layer of the lower technical mezzanine and installed in the return air duct, relying on the larger heat exchange area of ​​DCC to achieve the purpose of reducing its air flow temperature.

[0004] However, the area required for DCC affects the setting of the return air duct, and the civil engineering cost is relatively high. In addition, DCC equipment is generally large, the equipment cost is relatively high, and the heat exchange method that relies on convection heat exchange is not energy-efficient. The energy consumption of the air-conditioning system accounts for about 30%-35% of the energy consumption of the entire semiconductor plant.

[0005] Therefore, it is necessary to provide a clean air conditioning system suitable for FAB to solve the above technical problems. Utility Model Content

[0006] The utility model provides a clean air conditioning system suitable for FAB, which solves the problems of large return air duct area, high civil construction cost and low energy-saving effect.

[0007] In order to solve the above technical problems, the utility model provides a clean air conditioning system suitable for FAB, comprising:

[0008] An air-conditioning room, wherein the inner side of the air-conditioning room is provided with a MAU direct current air-conditioning system;

[0009] A return air alley, the return air alley is arranged on one side of the air-conditioning room, a lower technical interlayer is arranged on the inner side of the return air alley, a raised floor is arranged on the top of the lower technical interlayer, a main process area is arranged on the top of the raised floor, and a FFU high-efficiency filter is arranged on the top of the main process area;

[0010] An upper technical interlayer, the upper technical interlayer being arranged on the top of the lower technical interlayer;

[0011] Embedded enclosure, the embedded enclosure is arranged on one side of the lower technical interlayer, the embedded enclosure includes a first cement mortar leveling layer, a first ordinary brick layer, reinforced concrete, a second ordinary brick layer, a second cement mortar leveling layer, a small hole and a pressure sensor, the first ordinary brick layer is arranged on the left side of the reinforced concrete, the second ordinary brick layer is arranged on the right side of the reinforced concrete, the first cement mortar leveling layer is arranged on the left side of the ordinary brick layer, the second cement mortar leveling layer is arranged on the right side of the second ordinary brick layer, one side of the first cement mortar leveling layer and the second cement mortar leveling layer are both fixedly installed with a pressure sensor, and the small holes are respectively opened inside the first cement mortar leveling layer, the first ordinary brick layer, the reinforced concrete, the second ordinary brick layer, the second cement mortar leveling layer, the small hole and the pressure sensor;

[0012] A plurality of cold water pipes are provided inside the reinforced concrete.

[0013] Preferably, the thickness of the first cement mortar leveling layer and the second cement mortar leveling layer are both 20 millimeters.

[0014] Preferably, the thickness of the first ordinary brick layer and the second ordinary brick layer are both 40 millimeters, and the thickness of the reinforced concrete is 200 millimeters.

[0015] Preferably, the spacing between the plurality of cold water pipes is 200 millimeters.

[0016] Preferably, a fixing frame is provided on the other side of the air-conditioning room, and a metal mesh is fixedly installed on the inner side surface of the fixing frame.

[0017] Preferably, side panels are fixedly mounted on the top and bottom of the fixing frame, and mounting bolts are disposed inside both ends of the side panels.

[0018] Preferably, one end of the mounting bolt is threadedly connected to the inside of one side of the air-conditioning room.

[0019] Compared with the related art, the clean air conditioning system suitable for FAB provided by the utility model has the following beneficial effects:

[0020] The utility model provides a clean air-conditioning system suitable for FAB. This air-conditioning system can provide a higher temperature and humidity accuracy level, replaces the traditional air-conditioning DCC equipment, reduces the setting of the return air duct area, eliminates indoor sensible heat mainly in a radiation heat exchange manner, and the embedded tubular enclosure structure increases the cold storage capacity of the return air duct due to its structural particularity. The whole system is more energy-efficient. The setting of components such as temperature collectors and pressure sensors optimizes the control mode of the air-conditioning, so that the design working conditions are perfectly matched with the actual operating conditions. This air-conditioning system solves the problem of huge air-conditioning energy consumption in semiconductor factories to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 A schematic structural diagram of a first embodiment of a clean air conditioning system applicable to FAB provided by the utility model;

[0022] Figure 2 for Figure 1 The schematic diagram of the embedded tubular enclosure structure shown;

[0023] Figure 3 A structural schematic diagram of a second embodiment of a clean air conditioning system suitable for FAB provided by the utility model;

[0024] Figure 4 for Figure 3 The side structure diagram of the fixed frame is shown.

[0025] Numbers in the figure: 1. MAU DC air-conditioning system, 2. FFU high-efficiency filter, 3. Embedded tubular enclosure, 4. Cold water pipe, 5. Raised floor, 6. Main process area, 7. Upper technical mezzanine, 8. Lower technical mezzanine, 9. Return air aisle, 10. Air-conditioning room, 11. First cement mortar leveling layer, 12. First ordinary brick layer, 13. Reinforced concrete, 14. Second ordinary brick layer, 15. Second cement mortar leveling layer, 16. Small holes, 17. Pressure sensor, 18. Fixed frame, 181. Metal mesh, 182. Side panel, 183. Mounting bolts. DETAILED DESCRIPTION

[0026] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.

[0027] First embodiment

[0028] Please refer to Figure 1 , Figure 2 ,in, Figure 1 A schematic structural diagram of a first embodiment of a clean air conditioning system applicable to FAB provided by the utility model; Figure 2 for Figure 1A schematic diagram of an embedded pipe enclosure structure is shown. A clean air conditioning system suitable for FAB comprises: an air conditioning room 10, wherein the inner side of the air conditioning room 10 is provided with a MAU direct current air conditioning system;

[0029] A return air passage 9, the return air passage 9 is arranged on one side of the air conditioning room 10, a lower technical interlayer 8 is arranged on the inner side of the return air passage 9, a raised floor 5 is arranged on the top of the lower technical interlayer 8, a main process area 6 is arranged on the top of the raised floor 5, and a FFU high-efficiency filter 2 is arranged on the top of the main process area 6;

[0030] An upper technical interlayer 7, wherein the upper technical interlayer 7 is arranged on the top of the lower technical interlayer 8;

[0031] The embedded enclosure 3 is arranged on one side of the lower technical interlayer 8, and the embedded enclosure 3 includes a first cement mortar leveling layer 11, a first ordinary brick layer 12, reinforced concrete 13, a second ordinary brick layer 14, a second cement mortar leveling layer 15, a small hole 16 and a pressure sensor 17, wherein the first ordinary brick layer 12 is arranged on the left side of the reinforced concrete 13, the second ordinary brick layer 14 is arranged on the right side of the reinforced concrete 13, the first cement mortar leveling layer 11 is arranged on the ordinary The first cement mortar leveling layer 11 is on the left side of the brick layer 12, the second cement mortar leveling layer 15 is arranged on the right side of the second ordinary brick layer 14, and the first cement mortar leveling layer 11 and the second cement mortar leveling layer 15 are both fixedly installed with a pressure sensor 17 on one side, and the small hole 16 is respectively opened in the first cement mortar leveling layer 11, the first ordinary brick layer 12, the reinforced concrete 13, the second ordinary brick layer 14, the second cement mortar leveling layer 15, the small hole 16 and the pressure sensor 17;

[0032] A plurality of cold water pipes 4 are disposed inside the reinforced concrete 13 .

[0033] The thickness of the first cement mortar leveling layer 11 and the second cement mortar leveling layer 15 are both 20 millimeters.

[0034] The thickness of the first ordinary brick layer 12 and the second ordinary brick layer 14 are both 40 millimeters, and the thickness of the reinforced concrete 13 is 200 millimeters.

[0035] The spacing between the plurality of cold water pipes 4 is 200 millimeters.

[0036] The supply and return water temperatures of the cold water pipe 4 are 13°C for supply and 19°C for return. The cold energy can be transferred and stored on the inner side of the building wall. In addition, a certain number of small holes 16 are arranged on the embedded tubular enclosure 3 structure to facilitate the circulation of airflow. As a part of the air-conditioning terminal, the wall structure can directly participate in the cooling process of the air-conditioning system. This structure replaces the original DCC equipment, changes the traditional convection heat exchange mode, and forms a heat exchange mode based on radiation heat exchange. Compared with convection heat exchange, radiation heat exchange is more energy-saving and more comfortable. Radiation heat exchange can use high-temperature refrigerant, which makes it possible to utilize natural cold sources such as high-temperature ground cooling and groundwater. The reinforced concrete 13 (building structure layer) has a low heat transfer coefficient K value, good thermal insulation characteristics, and a certain cold storage capacity. Its cold storage effect will directly affect the cooling performance of the system.

[0037] The air conditioning system installs a solenoid valve on the water supply main of the cold water pipe 4. The heating equipment is located in the main process area 6. The temperature sensor located at the heating equipment determines the size of the equipment's heat generation, and then automatically controls the opening of the solenoid valve to automatically adjust the water flow.

[0038] The air conditioning system is equipped with a temperature collector on one side of the embedded tubular enclosure 3 structure close to the return air channel 9. The temperature collector uploads the collected return air temperature TC to the plant FMCS room. By comparing the relationship between TC and TO=21℃, the plant control console can perform frequency conversion speed regulation on the circulating water pump on the cold and hot source side according to its internal logic. If TC<T0, the circulating water pump frequency conversion speed reduction; if TC>T0, the circulating water pump frequency conversion speed increase;

[0039] The air conditioning system is provided with pressure sensors 17 on both sides of the embedded tubular enclosure 3 structure, and controls the amount of fresh air by comparing the pressure P1 of the lower technical interlayer 8 with the pressure P2 of the return air duct 9. To achieve unidirectional flow of airflow, it is necessary to ensure that P1>P2;

[0040] A certain number of guide blades are arranged in the small holes 16 of the air conditioning system. By controlling the angles of the guide blades, the one-way flow of the airflow is further realized, ensuring that the direction of the return air flow is from the lower technical interlayer 8 to 9 - the return air channel.

[0041] The working principle of a clean air conditioning system suitable for FAB provided by the utility model is as follows:

[0042] The air conditioning system includes a MAU direct current air conditioning system 1, an FFU high efficiency filter 2 and an embedded tubular enclosure 3 structure. The MAU air conditioning system is arranged in a uniformly planned air conditioning room, and outdoor fresh air is sent into the return air duct 9 through primary and secondary efficiency filtration sections, preheating, reheating, surface cooling, chemical filter sections, etc. An FFU is set on the ceiling of the clean room for high-efficiency filtration. The lower technical mezzanine 8 and the return air duct 9 partition wall use an embedded tubular enclosure 3 structure. A certain number of small holes 16 are set on the embedded tubular enclosure 3 structure. The embedded tubular enclosure 3 structure is composed of a cement mortar layer, a brick layer, and a concrete structure layer. The cold water pipe 4 is embedded in the center of the reinforced concrete 13, so that the cold energy can be transmitted and stored inside the building structure. There are a certain number of small holes 16 on the embedded tubular enclosure 3 structure, which can facilitate the cooled airflow to flow into the return air duct 9. Its airflow organization model is as follows: the airflow passing through the MAU is mixed with the cold airflow treated by the embedded tubular enclosure 3 structure in the return air duct 9, and is filtered by the FFU efficiently and sent into the clean room. After taking away the heat and heat dissipation of the machine equipment in the clean room, the airflow eliminates the sensible heat through the embedded tubular enclosure 3 structure, and then enters the return air duct 9 through its small holes 16, and the cycle is repeated.

[0043] Compared with the related art, the clean air conditioning system suitable for FAB provided by the utility model has the following beneficial effects:

[0044] This air-conditioning system can provide a higher temperature and humidity accuracy level, replaces the traditional air-conditioning DCC equipment, reduces the setting of the return air duct area, eliminates indoor sensible heat mainly by radiation heat exchange, and the embedded tubular enclosure 3 structure increases the cold storage capacity of the return air duct 9 due to its structural particularity. The entire system is more energy-efficient. The setting of components such as the temperature collector and the pressure sensor 17 optimizes the control method of the air-conditioning, so that the design working conditions are perfectly matched with the actual operating conditions. This air-conditioning system solves the problem of huge air-conditioning energy consumption in semiconductor factories to a certain extent.

[0045] Second embodiment

[0046] Please refer to Figure 3 and Figure 4 Based on the clean air conditioning system applicable to FAB provided in the first embodiment of the present application, the second embodiment of the present application proposes another clean air conditioning system applicable to FAB. The second embodiment is only a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.

[0047] Specifically, the second embodiment of the present application provides a clean air-conditioning system suitable for FAB, which is different in that a fixed frame 18 is provided on the other side of the air-conditioning room 10, and a metal mesh 181 is fixedly installed on the inner side of the fixed frame 18.

[0048] Side plates 182 are fixedly mounted on the top and bottom of the fixing frame 18 , and mounting bolts 183 are disposed inside both ends of the side plates 182 .

[0049] One end of the mounting bolt 183 is threadedly connected to the inside of one side of the air conditioning room 10 .

[0050] The working principle of a clean air conditioning system suitable for FAB provided by the utility model is as follows:

[0051] When in use, the fixing frame 18 is installed by threading the mounting bolts 183 on one side of the air conditioning room 10 , so that the metal mesh 181 is installed at the air inlet of the MAU DC air conditioning system 1 .

[0052] Compared with the related art, the clean air conditioning system suitable for FAB provided by the utility model has the following beneficial effects:

[0053] By cooperating with each other through structures such as the fixing frame 18, the metal mesh 181, the side panel 182 and the mounting bolts 183, when in use, the metal mesh 181 is set at the air inlet of the MAU DC air-conditioning system 1 to block impurities and prevent external impurities from entering the air inlet of the MAU DC air-conditioning system 1.

[0054] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A clean air conditioning system suitable for FAB, characterized in that: include: An air-conditioning room, wherein the inner side of the air-conditioning room is provided with a MAU direct current air-conditioning system; A return air alley, the return air alley is arranged on one side of the air-conditioning room, a lower technical interlayer is arranged on the inner side of the return air alley, a raised floor is arranged on the top of the lower technical interlayer, a main process area is arranged on the top of the raised floor, and a FFU high-efficiency filter is arranged on the top of the main process area; An upper technical interlayer, the upper technical interlayer being arranged on the top of the lower technical interlayer; Embedded enclosure, the embedded enclosure is arranged on one side of the lower technical interlayer, the embedded enclosure includes a first cement mortar leveling layer, a first ordinary brick layer, reinforced concrete, a second ordinary brick layer, a second cement mortar leveling layer, a small hole and a pressure sensor, the first ordinary brick layer is arranged on the left side of the reinforced concrete, the second ordinary brick layer is arranged on the right side of the reinforced concrete, the first cement mortar leveling layer is arranged on the left side of the ordinary brick layer, the second cement mortar leveling layer is arranged on the right side of the second ordinary brick layer, one side of the first cement mortar leveling layer and the second cement mortar leveling layer are both fixedly installed with a pressure sensor, and the small holes are respectively opened inside the first cement mortar leveling layer, the first ordinary brick layer, the reinforced concrete, the second ordinary brick layer, the second cement mortar leveling layer, the small hole and the pressure sensor; A plurality of cold water pipes are provided inside the reinforced concrete.

2. A clean air conditioning system suitable for FAB according to claim 1, characterized in that: The thickness of the first cement mortar leveling layer and the second cement mortar leveling layer are both 20 mm.

3. A clean air conditioning system suitable for FAB according to claim 1, characterized in that: The thickness of the first ordinary brick layer and the second ordinary brick layer are both 40 millimeters, and the thickness of the reinforced concrete is 200 millimeters.

4. A clean air conditioning system suitable for FAB according to claim 1, characterized in that: The spacing between the plurality of cold water pipes is 200 mm.

5. A clean air conditioning system suitable for FAB according to claim 1, characterized in that: A fixing frame is arranged on the other side of the air-conditioning room, and a metal mesh is fixedly installed on the inner side surface of the fixing frame.

6. A clean air conditioning system suitable for FAB according to claim 5, characterized in that: The top and bottom of the fixing frame are fixedly mounted with side plates, and mounting bolts are arranged inside both ends of the side plates.

7. A clean air conditioning system suitable for FAB according to claim 6, characterized in that: One end of the mounting bolt is threadedly connected to the interior of one side of the air conditioning room.