Detection device for building foundation pit settlement
By designing an automated building foundation pit settlement detection device and using a combination of ranging probes and driving mechanisms, the problem of low detection efficiency and accuracy in the existing technology has been solved, real-time and uniform detection of foundation pit settlement has been achieved, and improved Detection effect.
Patent Information
- Application Number
- CN202420261501.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-02
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-02-02
AI Technical Summary
The existing construction foundation pit settlement detection device is not convenient for automated detection operations, resulting in low efficiency and accuracy, and increasing the work intensity of the staff.
A detection device is designed that includes a main body mechanism and a driving mechanism. The main body mechanism includes a distance measuring probe, a support rod, a support base plate and a connecting frame. The driving mechanism includes an electric motor, screw rod, bearing seat, movable nut and drive motor. Through these The component realizes the automatic movement and distance detection of the ranging probe and avoids manual assisted measurement.
It realizes real-time automated detection of building foundation pit settlement, improves detection accuracy and efficiency, reduces manual errors, and simplifies staff operations.
Smart Images

Figure CN221840399U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of settlement detection, in particular to a detection device for building foundation pit settlement. Background Art
[0002] The building foundation pit is an earth pit excavated at the foundation design position according to the base elevation and foundation plane dimensions. During construction, the excavated foundation pit needs to be tested for settlement. The settlement test is carried out based on the test points and fixed test points set up on the building, and the degree of settlement is expressed in data. All buildings and structures with more than one floor that require the setting of test points in the design, artificial foundations, land foundations, etc., should all have settlement tests. During construction, tests should be carried out and recorded on schedule or by layer until completion.
[0003] The existing patent document with technical disclosure number CN216694966U provides a detection device for building foundation pit settlement. When the foundation pit settles, the horizontal height of the foundation pit drops, so that the self-weight frame is separated from the contact position with the upper surface of the foundation pit. When detecting, the sealing plug is removed by pulling the handle plate, so that the measuring scale can slide out through the limit port, so that the degree of foundation pit settlement can be detected by the sliding measuring scale, so as to achieve the purpose of real-time detection, and overcome the problem that the existing building foundation pit mostly uses a settlement detector for detection when conducting settlement detection. The detector can only perform detection periodically and cannot detect whether the foundation pit has settled and the degree of settlement in real time.
[0004] However, the existing detection device for construction pit settlement is not convenient for automating the detection operation of construction pit settlement when in use. Manual auxiliary adjustment and measurement result in low efficiency and accuracy of foundation pit settlement detection, while increasing the workload of staff and having poor practicality. Utility Model Content
[0005] The utility model aims to provide a detection device for building foundation pit settlement, so as to solve the problem that the existing detection device for building foundation pit settlement proposed in the above background technology is not convenient for automatically realizing the detection operation of building foundation pit settlement when in use.
[0006] To achieve the above object, the utility model provides the following technical solutions: a detection device for construction foundation pit settlement, comprising a main body mechanism and a driving mechanism, wherein the driving mechanism is located above the main body mechanism, the main body mechanism comprises a device body and a distance measuring probe, and the distance measuring probe is located in front of the device body;
[0007] The main structure also includes a support rod, a support base plate and a connecting frame. The support rod is fixedly installed at the left and right ends of the lower end of the device body, the support base plate is fixedly installed at the lower end of the support rod, the connecting frame is movably installed above the device body, and the ranging probe is located in front of the connecting frame.
[0008] Preferably, the driving mechanism comprises a ground spike, the ground spike is movably mounted at the front and rear ends of the upper end of the supporting base plate, and the lower end of the ground spike extends to the bottom of the supporting base plate.
[0009] Preferably, the driving mechanism further comprises an electric motor and a screw rod, wherein the electric motor is fixedly mounted at the left end of the inner end of the device body, and the screw rod is fixedly mounted at the transmission end of the right end of the electric motor.
[0010] Preferably, the driving mechanism also includes a bearing seat and a movable nut, the bearing seat is fixedly mounted on the right end of the inner end of the device body, the right end of the screw rod is rotatably connected to the bearing seat, the movable nut is threadedly connected to the outer end of the screw rod, and the connecting frame is located at the upper end of the movable nut.
[0011] Preferably, the driving mechanism further comprises a driving motor and a threaded rod, wherein the driving motor is fixedly mounted at the rear end of the inner end of the connecting frame, and the threaded rod is fixedly mounted at the transmission end of the front end of the driving motor.
[0012] Preferably, the driving mechanism further comprises a connecting screw block and a connecting plate, the connecting screw block is threadedly connected to the outer end of the threaded rod, the connecting plate is fixedly mounted on the upper end of the connecting screw block, and the ranging probe is located at the front end of the lower end of the connecting plate.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] 1. The detection device for building foundation pit settlement, by installing the main body mechanism, realizes that when the device body is performing the detection operation of the foundation pit settlement, the distance measuring probe can detect the distance between the current position and the upper surface of the foundation pit in real time, thereby realizing the automatic detection of the building foundation pit settlement, without the need for auxiliary measurement by staff, and avoiding the errors caused by traditional manual measurement, thereby improving the automation and detection accuracy of the device body;
[0015] 2. The detection device for building foundation pit settlement is equipped with a driving mechanism so that when the device body is in use, the staff can control the working status of the electric motor and the drive motor through operation, thereby driving the ranging probe to move at a uniform speed, thereby realizing the range settlement detection of the building foundation pit, making it convenient for the staff to grasp the uniformity of the building foundation pit settlement, and improving the detection effect of the device body. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0017] Figure 2 This is a schematic diagram of the three-dimensional structure of the device body of the utility model;
[0018] Figure 3 This is a schematic diagram of the three-dimensional structure of the connecting frame of the utility model;
[0019] Figure 4 It is a schematic diagram of the partial three-dimensional structure of the driving mechanism of the utility model.
[0020] In the figure: 1. Main body; 101. Device body; 102. Distance measuring probe; 103. Support rod; 104. Support base plate; 105. Connecting frame; 2. Driving mechanism; 201. Ground pin; 202. Electric motor; 203. Screw rod; 204. Bearing seat; 205. Movable nut; 206. Driving motor; 207. Threaded rod; 208. Connecting screw block; 209. Connecting plate. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] See also Figure 1 - Figure 4 The utility model provides a technical solution: a detection device for construction foundation pit settlement, comprising a main mechanism 1 and a driving mechanism 2, the driving mechanism 2 is located above the main mechanism 1, the main mechanism 1 comprises a device body 101 and a distance measuring probe 102, the distance measuring probe 102 is located in front of the device body 101;
[0023] The main mechanism 1 also includes a support rod 103, a support base plate 104 and a connecting frame 105. The support rod 103 is fixedly installed at the left and right ends of the lower end of the device body 101, the support base plate 104 is fixedly installed at the lower end of the support rod 103, and the connecting frame 105 is movably installed above the device body 101. The ranging probe 102 is located in front of the connecting frame 105. When the device body 101 is used to detect the settlement of a construction pit, the staff moves the device body 101 to the periphery of the construction pit so that the support base plate 104 is placed on the flat land around the pit. The staff adjusts the position of the ranging probe 102 appropriately through operation. The ranging probe 102 detects the distance between the current position and the upper surface of the pit, and uploads the data to the terminal for recording the distance between the same position and the upper surface of the pit at different times, thereby obtaining the settlement data of the construction pit.
[0024] The driving mechanism 2 includes a ground nail 201, which is movably mounted on the front and rear ends of the upper end of the supporting base plate 104, and the lower end of the ground nail 201 extends to the bottom of the supporting base plate 104. The driving mechanism 2 also includes an electric motor 202 and a screw rod 203. The electric motor 202 is fixedly mounted on the left end of the inner end of the device body 101, and the screw rod 203 is fixedly mounted on the transmission end of the right end of the electric motor 202. The driving mechanism 2 also includes a bearing seat 204 and a movable nut 205. The bearing seat 204 is fixedly mounted on the right end of the inner end of the device body 101, and the right end of the screw rod 203 is rotatably connected to the bearing seat 204. The movable nut 205 is threadedly connected to the outer end of the screw rod 203. The connecting frame 105 is located at the upper end of the movable nut 205. The driving mechanism 2 also includes a driving motor 206 and a threaded rod 207. The driving motor 206 is fixedly mounted on the rear end of the inner end of the connecting frame 105, and the threaded rod 207 is fixedly mounted on the transmission end of the front end of the driving motor 206. The driving mechanism 2 also includes a connecting screw block 208 and a connecting plate 209. The connecting screw block 208 is threadedly connected to the outer end of the threaded rod 207. The connecting plate 209 is fixedly installed on the upper end of the connecting screw block 208. The distance measuring probe 102 is located at the front end of the lower end of the connecting plate 209. The staff uses the ground nail 201 to connect the supporting bottom plate 104 with the ground to complete the installation of the device body 101. When it is necessary to perform detection operations on multiple points of the foundation pit, the staff drives the movable nut 205 to move at a uniform speed on the screw rod 203 by operating the electric motor 202. The movable nut 205 drives the connecting frame 105 to move, thereby driving the distance measuring probe 102 to move left and right for detection. The driving motor 206 drives the connecting screw block 208 to move on the threaded rod 207. The connecting screw block 208 drives the distance measuring probe 102 to move back and forth for detection, completing the distance detection of different positions of the foundation pit. By comparing multiple groups of data, the uniformity of the settlement of the building foundation pit can be judged.
[0025] Working principle: When using the device body 101 to detect the settlement of a building foundation pit, the staff moves the device body 101 to the periphery of the building foundation pit, places the support base plate 104 on the flat land around the foundation pit, and then uses the ground spikes 201 to connect the support base plate 104 to the ground to complete the installation of the device body 101. The staff adjusts the position of the ranging probe 102 appropriately through operation. The ranging probe 102 detects the distance between the current position and the upper surface of the foundation pit, and uploads the data to the terminal for recording the distance between the same position and the upper surface of the foundation pit at different times. Distance, thereby obtaining the settlement data of the building foundation pit. When it is necessary to perform detection operations on multiple points of the foundation pit, the staff operates the electric motor 202 to drive the movable nut 205 to move at a uniform speed on the screw rod 203, and the movable nut 205 drives the connecting frame 105 to move, thereby driving the ranging probe 102 to move left and right for detection. The driving motor 206 drives the connecting screw block 208 to move on the threaded rod 207, and the connecting screw block 208 drives the ranging probe 102 to move back and forth for detection, completing the distance detection of different positions of the foundation pit, and by comparing multiple groups of data, the uniformity of the settlement of the building foundation pit can be judged.
[0026] Finally, it should be noted that the above content is only used to illustrate the technical solution of the utility model, rather than to limit the protection scope of the utility model. Simple modifications or equivalent substitutions of the technical solution of the utility model by ordinary technicians in this field do not deviate from the essence and scope of the technical solution of the utility model.
Claims
1. A device for detecting settlement of a construction foundation pit, comprising a main mechanism (1) and a driving mechanism (2), characterized in that: The driving mechanism (2) is located above the main mechanism (1); the main mechanism (1) comprises a device body (101) and a distance measuring probe (102); the distance measuring probe (102) is located in front of the device body (101); The main body mechanism (1) further comprises a support rod (103), a support base plate (104) and a connecting frame (105); the support rod (103) is fixedly mounted at the left and right ends of the lower end of the device body (101); the support base plate (104) is fixedly mounted at the lower end of the support rod (103); the connecting frame (105) is movably mounted above the device body (101); and the distance measuring probe (102) is located in front of the connecting frame (105).
2. A detection device for construction foundation pit settlement according to claim 1, characterized in that: The driving mechanism (2) comprises a ground pin (201), wherein the ground pin (201) is movably mounted at the front and rear ends of the upper end of the supporting base plate (104), and the lower end of the ground pin (201) extends to below the supporting base plate (104).
3. A detection device for construction foundation pit settlement according to claim 2, characterized in that: The driving mechanism (2) further comprises an electric motor (202) and a screw rod (203), wherein the electric motor (202) is fixedly mounted on the left end of the inner end of the device body (101), and the screw rod (203) is fixedly mounted on the transmission end of the right end of the electric motor (202).
4. A detection device for construction foundation pit settlement according to claim 3, characterized in that: The driving mechanism (2) further comprises a bearing seat (204) and a movable nut (205); the bearing seat (204) is fixedly mounted on the right end of the inner end of the device body (101); the right end of the screw rod (203) is rotatably connected to the bearing seat (204); the movable nut (205) is threadedly connected to the outer end of the screw rod (203); and the connecting frame (105) is located at the upper end of the movable nut (205).
5. A construction foundation pit settlement detection device according to claim 4, characterized in that: The driving mechanism (2) further comprises a driving motor (206) and a threaded rod (207), wherein the driving motor (206) is fixedly mounted at the rear end of the inner end of the connecting frame (105), and the threaded rod (207) is fixedly mounted at the transmission end of the front end of the driving motor (206).
6. A device for detecting construction pit settlement according to claim 5, characterized in that: The driving mechanism (2) further comprises a connecting screw block (208) and a connecting plate (209), wherein the connecting screw block (208) is threadedly connected to the outer end of the threaded rod (207), the connecting plate (209) is fixedly mounted on the upper end of the connecting screw block (208), and the distance measuring probe (102) is located at the front end of the lower end of the connecting plate (209).