Test tool circuit for energy storage high-voltage box
By designing the energy storage high-voltage box test tooling circuit and using AC220V power supply and switching power supply module for rapid conduction and communication testing, the problem that the energy storage high-voltage box cannot be independently tested is solved, and the production efficiency and debugging simplicity are improved.
Patent Information
- Application Number
- CN202420105109.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-01-16
AI Technical Summary
The energy storage high-voltage box cannot be independently tested and verified after production is completed. It must be assembled on the energy storage system before power-on testing can be performed, resulting in low production efficiency and complicated debugging.
An energy storage high-voltage box test tooling circuit is designed. By connecting the AC220V power supply and the switching power supply module, the fast conduction test and software communication test of the energy storage high-voltage box circuit are realized, simplifying the wiring process.
It realizes rapid testing and verification of energy storage high-voltage boxes, improves production efficiency, and simplifies the debugging process.
Smart Images

Figure CN221841125U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a test fixture circuit for an energy storage high-voltage box, belonging to the technical field of energy storage circuit testing. Background Art
[0002] The current status of energy storage high-voltage box testing is that the energy storage high-voltage box needs to be integrated and assembled into the energy storage system before power-on testing can be performed to verify whether its internal wiring is correct and whether its functions meet the system operation requirements.
[0003] After the energy storage high-voltage box is produced, it cannot be tested and verified first. It needs to be assembled on the energy storage system and then powered on to test whether it meets the system operation requirements. If not, it needs to be removed from the energy storage system and reworked, which seriously affects production efficiency and the debugging of the entire energy storage system. Utility Model Content
[0004] The purpose of the utility model is to provide a test fixture circuit for an energy storage high-voltage box to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above purpose, the utility model adopts the following technical solutions:
[0006] A test fixture circuit for an energy storage high-voltage box, with a power cord triangle plug input end connected to an external AC220V power supply, and an output end connected to the QF1 control switch input end 1 / 3 for powering the entire test circuit;
[0007] The output terminals 2 / 4 of the QF1 control switch are connected to the SMPS248V switching power supply input terminals 1 / 2 and the SMPS124V switching power supply input terminals 1 / 2, and are used to control the power supply of the 24V and 48V switching power supply modules;
[0008] The input terminals 1 / 3 of the QF2 control switch are connected in parallel with the input terminals 1 / 3 of the QF1 control switch, and the output terminals 2 / 4 are connected to the SMPS3110V switching power supply input terminals L / N; used to control the power supply of the 110V switching power supply module;
[0009] The input L / N of the CZ five-hole socket is connected in parallel with the input 1 / 3 of the QF2 control switch, and the output is reserved; used to power external devices such as computers;
[0010] DX2 terminal block 5 / 6 connects the grounding terminals of the power cord triangle plug, CZ five-hole socket, SMPS248V switching power supply, SMPS124V switching power supply, and SMPS3110V switching power supply together; it is used to connect the grounding terminals of components;
[0011] SMPS248V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 7 is connected to SB1 boat switch input terminal A, and output terminal 5 is connected to J11 connector socket terminal 6; used to convert AC220V power supply into DC48V power supply;
[0012] SMPS124V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 6 / 7 is connected to DX1 terminal block 1D / 2D, and output terminal 4 / 5 is connected to DX1 terminal block 3D / 4D; used to convert AC220V power supply into DC24V power supply;
[0013] SMPS3110V switching power supply input terminal L / N is connected to QF2 control switch output terminal 2 / 4, and the output terminal +V is connected Input terminal 1, output terminal -V is connected to input terminal 1 of FU2 fuse; used to convert AC220V power supply into DC110V power supply;
[0014] SB1 boat switch input terminal A is connected to SMPS248V switch output terminal 7, and output terminal A1 is connected to J11 connector socket terminal 5; used to control DC48V+ power output;
[0015] J11 connector socket terminal 1 is connected to HG1 power supply 48V indicator light 1 input terminal X1, terminal 2 is connected to HG2 power supply 48V indicator light 2 input terminal X1, terminal 3 is connected to HG2 power supply 48V indicator light 2 input terminal X2, terminal 4 is connected to HG1 power supply 48V indicator light 1 input terminal X2, terminal 5 is connected to SB1 boat switch output terminal A1, terminal 6 is connected to SMPS248V switch power supply output terminal 5; used to connect the energy storage high-voltage box of the object to be tested;
[0016] HG1 power supply 48V indicator light 1 input terminal X1 is connected to J11 connector socket terminal 1, and input terminal X2 is connected to J11 connector socket terminal 4; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 1;
[0017] HG2 power supply 48V indicator light 2 input terminal X1 is connected to J11 connector socket terminal 2, and input terminal X2 is connected to J11 connector socket terminal 3; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 2;
[0018] DX1 terminal block 1 / 2 connects SMPS124V switching power supply output terminal 6 / 7, J12 connector socket terminal 6 / 16, and SB2 boat switch input terminal A together; terminal block 3 / 4 connects SMPS124V switching power supply output terminal 4 / 5, J12 connector socket terminal 17, and HW1 emergency stop signal 24V indicator light input terminal X2 together; used for DC24V+ / - power supply connection conduction;
[0019] The input terminal A of the SB2 boat switch is connected to the DX1 terminal block 2A, and the output terminal A1 is connected to the J12 connector socket terminal 5; it is used to simulate the sending of a DC24V+ power supply signal to trigger the emergency stop tripping of the energy storage high-voltage box circuit breaker of the object under test;
[0020] HW1 emergency stop signal 24V indicator light: input terminal X1 is connected to terminal 7 of J12 connector socket, and input terminal X2 is connected to terminal block 4A of DX1; it is used to indicate whether the energy storage high-voltage box of the object under test has output emergency stop feedback signal;
[0021] J12 connector socket: Endpoint 1 connects to SB3 boat switch input terminal A1, Endpoint 2 connects to SB4 boat switch input terminal A1, Endpoint 3 connects to HG4 power supply 24V indicator light 2 input terminal X2, Endpoint 4 connects to HG3 power supply 24V indicator light 1 input terminal X2, Endpoint 5 connects to SB2 boat switch output terminal A1, Endpoint 6 connects to DX1 terminal block 2B, Endpoint 7 connects to HW1 emergency stop signal 24V indicator light input terminal X1, Endpoints 8 / 9 connect to USB-CAN box 1 input terminal CAN1H / CAN1L, Endpoints 10 / 11 connect Input terminal CAN2H / CAN2L, endpoint 12 / 13 connects to input terminal CAN1H / CAN1L of USB-CAN box 2, and endpoint 14 / 15 connects to input terminal A / B of USB-485 box; used to connect to the energy storage high-voltage box of the object under test;
[0022] The input terminal A1 of the SB3 boat switch is connected to the terminal 1 of the J12 connector socket, and the output terminal A is connected to the input terminal X1 of the HG3 power supply 24V indicator light 1; it is used to control the DC24V power supply 1 output of the energy storage high-voltage box of the object under test;
[0023] HG3 power supply 24V indicator light 1: input terminal X1 is connected to SB3 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 4; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 1;
[0024] SB4 boat switch: input terminal A1 is connected to terminal 2 of J12 connector socket, and output terminal A is connected to input terminal X1 of HG4 power supply 24V indicator light 2; used to control the output of DC24V power supply 2 of the energy storage high-voltage box of the object under test;
[0025] HG4 power supply 24V indicator light 2: input terminal X1 is connected to SB4 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 3; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 2;
[0026] The input terminal 1 of FU1 fuse is connected to the output terminal +V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT+ copper bar input terminal; it is used for DC110V+ power supply output protection;
[0027] The input terminal 1 of FU2 fuse is connected to the output terminal -V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT- copper bar input terminal; it is used for DC110V- power supply output protection;
[0028] HW2 main negative contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output end of the BAT+ copper bar, and input terminal X2 is connected to the M4 bolt at the output end of the DC- copper bar; it is used to indicate whether the main negative contactor of the energy storage high-voltage box under test is closed;
[0029] HW3 main positive contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output terminal of BAT- copper bar, and input terminal X2 is connected to the M4 bolt at the output terminal of DC+ copper bar; it is used to indicate whether the main positive contactor of the energy storage high-voltage box under test is closed;
[0030] BAT+ copper bar connects FU1 fuse output terminal 2 and HW2 main negative contactor closed 110V indicator light input terminal X1; used to connect the energy storage high-voltage box of the object under test;
[0031] BAT- copper bar connects FU2 fuse output terminal 2 and HW3 main positive contactor closed 110V indicator light input terminal X2; used to connect the energy storage high-voltage box of the object under test;
[0032] The DC+ copper busbar is connected to the input terminal X1 of the 110V indicator light of the main positive contactor of HW3; it is used to connect the energy storage high-voltage box of the object to be tested;
[0033] The DC-copper busbar is connected to the input terminal X2 of the 110V indicator light of the main negative contactor of HW2; it is used to connect the energy storage high-voltage box of the object to be tested;
[0034] The USB extender is connected to the USB ports of USB-CAN box 1, USB-CAN box 2 and USB-485 box; it is used to connect to a computer and communicate with the high-voltage box of the object to be measured through computer program software;
[0035] The input end CAN1H / CAN1L of USB-CAN box 1 is connected to the J12 connector socket endpoint 8 / 9, the input end CAN2H / CAN2L is connected to the J12 connector socket endpoint 10 / 11, and the output end USB interface is connected to the USB expander; used to convert CAN communication signals;
[0036] The input terminal CAN1H / CAN1L of USB-CAN box 2 is connected to the J12 connector socket terminal 12 / 13, and the output terminal USB interface is connected to the USB expander; used to convert CAN communication signals;
[0037] The input terminal A / B of the USB-485 box is connected to the J12 connector socket terminal 14 / 15, and the output USB interface is connected to the USB expander; it is used to convert RS485 communication signals.
[0038] Compared with the prior art, the utility model has the following beneficial effects: the utility model uses circuit wiring to simulate the actual installation wiring environment of the energy storage high-voltage box on the energy storage system, which can quickly complete the connection and is convenient for testing. The utility model only needs to connect the energy storage high-voltage box to the test fixture circuit to quickly complete the conduction test of the energy storage high-voltage box circuit and the communication test of the software, thereby realizing rapid testing and verification of the energy storage high-voltage box and improving production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 This is a circuit schematic diagram of the utility model. DETAILED DESCRIPTION
[0040] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0041] A test fixture circuit for an energy storage high-voltage box, with a power cord triangle plug input end connected to an external AC220V power supply, and an output end connected to the QF1 control switch input end 1 / 3 for powering the entire test circuit;
[0042] The output terminals 2 / 4 of the QF1 control switch are connected to the SMPS248V switching power supply input terminals 1 / 2 and the SMPS124V switching power supply input terminals 1 / 2, and are used to control the power supply of the 24V and 48V switching power supply modules;
[0043] The input terminals 1 / 3 of the QF2 control switch are connected in parallel with the input terminals 1 / 3 of the QF1 control switch, and the output terminals 2 / 4 are connected to the SMPS3110V switching power supply input terminals L / N; used to control the power supply of the 110V switching power supply module;
[0044] The input L / N of the CZ five-hole socket is connected in parallel with the input 1 / 3 of the QF2 control switch, and the output is reserved; used to power external devices such as computers;
[0045] DX2 terminal block 5 / 6 connects the grounding terminals of the power cord triangle plug, CZ five-hole socket, SMPS248V switching power supply, SMPS124V switching power supply, and SMPS3110V switching power supply together; it is used to connect the grounding terminals of components;
[0046] SMPS248V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 7 is connected to SB1 boat switch input terminal A, and output terminal 5 is connected to J11 connector socket terminal 6; used to convert AC220V power supply into DC48V power supply;
[0047] SMPS124V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 6 / 7 is connected to DX1 terminal block 1D / 2D, and output terminal 4 / 5 is connected to DX1 terminal block 3D / 4D; used to convert AC220V power supply into DC24V power supply;
[0048] SMPS3110V switching power supply input terminal L / N is connected to QF2 control switch output terminal 2 / 4, and the output terminal +V is connected Input terminal 1, output terminal -V is connected to input terminal 1 of FU2 fuse; used to convert AC220V power supply into DC110V power supply;
[0049] SB1 boat switch input terminal A is connected to SMPS248V switch output terminal 7, and output terminal A1 is connected to J11 connector socket terminal 5; used to control DC48V+ power output;
[0050] J11 connector socket terminal 1 is connected to HG1 power supply 48V indicator light 1 input terminal X1, terminal 2 is connected to HG2 power supply 48V indicator light 2 input terminal X1, terminal 3 is connected to HG2 power supply 48V indicator light 2 input terminal X2, terminal 4 is connected to HG1 power supply 48V indicator light 1 input terminal X2, terminal 5 is connected to SB1 boat switch output terminal A1, terminal 6 is connected to SMPS248V switch power supply output terminal 5; used to connect the energy storage high-voltage box of the object to be tested;
[0051] HG1 power supply 48V indicator light 1 input terminal X1 is connected to J11 connector socket terminal 1, and input terminal X2 is connected to J11 connector socket terminal 4; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 1;
[0052] HG2 power supply 48V indicator light 2 input terminal X1 is connected to J11 connector socket terminal 2, and input terminal X2 is connected to J11 connector socket terminal 3; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 2;
[0053] DX1 terminal block 1 / 2 connects SMPS124V switching power supply output terminal 6 / 7, J12 connector socket terminal 6 / 16, and SB2 boat switch input terminal A together; terminal block 3 / 4 connects SMPS124V switching power supply output terminal 4 / 5, J12 connector socket terminal 17, and HW1 emergency stop signal 24V indicator light input terminal X2 together; used for DC24V+ / - power supply connection conduction;
[0054] The input terminal A of the SB2 boat switch is connected to the DX1 terminal block 2A, and the output terminal A1 is connected to the J12 connector socket terminal 5; it is used to simulate the sending of a DC24V+ power supply signal to trigger the emergency stop tripping of the energy storage high-voltage box circuit breaker of the object under test;
[0055] HW1 emergency stop signal 24V indicator light: input terminal X1 is connected to terminal 7 of J12 connector socket, and input terminal X2 is connected to terminal block 4A of DX1; it is used to indicate whether the energy storage high-voltage box of the object under test has output emergency stop feedback signal;
[0056] J12 connector socket: Endpoint 1 connects to SB3 boat switch input terminal A1, Endpoint 2 connects to SB4 boat switch input terminal A1, Endpoint 3 connects to HG4 power supply 24V indicator light 2 input terminal X2, Endpoint 4 connects to HG3 power supply 24V indicator light 1 input terminal X2, Endpoint 5 connects to SB2 boat switch output terminal A1, Endpoint 6 connects to DX1 terminal block 2B, Endpoint 7 connects to HW1 emergency stop signal 24V indicator light input terminal X1, Endpoints 8 / 9 connect to USB-CAN box 1 input terminal CAN1H / CAN1L, Endpoints 10 / 11 connect Input terminal CAN2H / CAN2L, endpoint 12 / 13 connects to input terminal CAN1H / CAN1L of USB-CAN box 2, and endpoint 14 / 15 connects to input terminal A / B of USB-485 box; used to connect to the energy storage high-voltage box of the object under test;
[0057] The input terminal A1 of the SB3 boat switch is connected to the terminal 1 of the J12 connector socket, and the output terminal A is connected to the input terminal X1 of the HG3 power supply 24V indicator light 1; it is used to control the DC24V power supply 1 output of the energy storage high-voltage box of the object under test;
[0058] HG3 power supply 24V indicator light 1: input terminal X1 is connected to SB3 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 4; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 1;
[0059] SB4 boat switch: input terminal A1 is connected to terminal 2 of J12 connector socket, and output terminal A is connected to input terminal X1 of HG4 power supply 24V indicator light 2; used to control the output of DC24V power supply 2 of the energy storage high-voltage box of the object under test;
[0060] HG4 power supply 24V indicator light 2: input terminal X1 is connected to SB4 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 3; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 2;
[0061] The input terminal 1 of FU1 fuse is connected to the output terminal +V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT+ copper bar input terminal; it is used for DC110V+ power supply output protection;
[0062] The input terminal 1 of FU2 fuse is connected to the output terminal -V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT- copper bar input terminal; it is used for DC110V- power supply output protection;
[0063] HW2 main negative contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output end of the BAT+ copper bar, and input terminal X2 is connected to the M4 bolt at the output end of the DC- copper bar; it is used to indicate whether the main negative contactor of the energy storage high-voltage box under test is closed;
[0064] HW3 main positive contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output terminal of BAT- copper bar, and input terminal X2 is connected to the M4 bolt at the output terminal of DC+ copper bar; it is used to indicate whether the main positive contactor of the energy storage high-voltage box under test is closed;
[0065] BAT+ copper bar connects FU1 fuse output terminal 2 and HW2 main negative contactor closed 110V indicator light input terminal X1; used to connect the energy storage high-voltage box of the object under test;
[0066] BAT- copper bar connects FU2 fuse output terminal 2 and HW3 main positive contactor closed 110V indicator light input terminal X2; used to connect the energy storage high-voltage box of the object under test;
[0067] The DC+ copper bar is connected to the input terminal X1 of the 110V indicator light of the HW3 main positive contactor; it is used to connect the energy storage high-voltage box of the object to be tested;
[0068] The DC-copper busbar is connected to the input terminal X2 of the 110V indicator light of the main negative contactor of HW2; it is used to connect the energy storage high-voltage box of the object to be tested;
[0069] The USB extender is connected to the USB ports of USB-CAN box 1, USB-CAN box 2 and USB-485 box; it is used to connect to a computer and communicate with the high-voltage box of the object to be measured through computer program software;
[0070] The input end CAN1H / CAN1L of USB-CAN box 1 is connected to the J12 connector socket endpoint 8 / 9, the input end CAN2H / CAN2L is connected to the J12 connector socket endpoint 10 / 11, and the output end USB interface is connected to the USB expander; used to convert CAN communication signals;
[0071] The input terminal CAN1H / CAN1L of USB-CAN box 2 is connected to the J12 connector socket terminal 12 / 13, and the output terminal USB interface is connected to the USB expander; used to convert CAN communication signals;
[0072] The input terminal A / B of the USB-485 box is connected to the J12 connector socket terminal 14 / 15, and the output USB interface is connected to the USB expander; it is used to convert RS485 communication signals.
[0073] The above is a preferred embodiment of the present invention. For ordinary technicians in this field, according to the teachings of the present invention, without departing from the principles and spirit of the present invention, changes, modifications, substitutions and variations made to the implementation methods are still within the scope of protection of the present invention.
Claims
1. A test fixture circuit for an energy storage high voltage box, characterized in that: The input end of the triangle plug with power cord is connected to the external AC220V power supply, and the output end is connected to the input end 1 / 3 of the QF1 control switch to power the entire test circuit; The output terminals 2 / 4 of the QF1 control switch are connected to the SMPS248V switching power supply input terminals 1 / 2 and the SMPS124V switching power supply input terminals 1 / 2, and are used to control the power supply of the 24V and 48V switching power supply modules; The input terminals 1 / 3 of the QF2 control switch are connected in parallel with the input terminals 1 / 3 of the QF1 control switch, and the output terminals 2 / 4 are connected to the input terminals L / N of the SMPS3110V switching power supply; Used to control the power supply of 110V switching power supply module; The input L / N of the CZ five-hole socket is connected in parallel with the input 1 / 3 of the QF2 control switch, and the output is reserved; used to power external devices such as computers; DX2 terminal block 5 / 6 connects the grounding terminals of the power cord triangle plug, CZ five-hole socket, SMPS248V switching power supply, SMPS124V switching power supply, and SMPS3110V switching power supply together; it is used to connect the grounding terminals of components; SMPS248V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 7 is connected to SB1 boat switch input terminal A, and output terminal 5 is connected to J11 connector socket terminal 6; used to convert AC220V power supply into DC48V power supply; SMPS124V switching power supply input terminal 1 / 2 is connected to QF1 control switch output terminal 2 / 4, output terminal 6 / 7 is connected to DX1 terminal block 1D / 2D, and output terminal 4 / 5 is connected to DX1 terminal block 3D / 4D; used to convert AC220V power supply into DC24V power supply; SMPS3110V switching power supply input terminal L / N is connected to QF2 control switch output terminal 2 / 4, and the output terminal +V is connected Input terminal 1, output terminal -V is connected to input terminal 1 of FU2 fuse; used to convert AC220V power supply into DC110V power supply; SB1 boat switch input terminal A is connected to SMPS248V switch output terminal 7, and output terminal A1 is connected to J11 connector socket terminal 5; used to control DC48V+ power output; J11 connector socket terminal 1 is connected to HG1 power supply 48V indicator light 1 input terminal X1, terminal 2 is connected to HG2 power supply 48V indicator light 2 input terminal X1, terminal 3 is connected to HG2 power supply 48V indicator light 2 input terminal X2, terminal 4 is connected to HG1 power supply 48V indicator light 1 input terminal X2, terminal 5 is connected to SB1 boat switch output terminal A1, terminal 6 is connected to SMPS248V switch power supply output terminal 5; used to connect the energy storage high-voltage box of the object to be tested; HG1 power supply 48V indicator light 1 input terminal X1 is connected to J11 connector socket terminal 1, and input terminal X2 is connected to J11 connector socket terminal 4; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 1; HG2 power supply 48V indicator light 2 input terminal X1 is connected to J11 connector socket terminal 2, and input terminal X2 is connected to J11 connector socket terminal 3; it is used to indicate whether the energy storage high-voltage box of the object under test has output 48V power supply 2; DX1 terminal block 1 / 2 connects SMPS124V switching power supply output terminal 6 / 7, J12 connector socket terminal 6 / 16, and SB2 boat switch input terminal A together; terminal block 3 / 4 connects SMPS124V switching power supply output terminal 4 / 5, J12 connector socket terminal 17, and HW1 emergency stop signal 24V indicator light input terminal X2 together; used for DC24V+ / - power supply connection conduction; The input terminal A of the SB2 boat switch is connected to the DX1 terminal block 2A, and the output terminal A1 is connected to the J12 connector socket terminal 5; it is used to simulate the DC24V+ power supply signal to trigger the emergency stop tripping of the energy storage high-voltage box circuit breaker of the object under test; HW1 emergency stop signal 24V indicator light: input terminal X1 is connected to terminal 7 of J12 connector socket, and input terminal X2 is connected to terminal block 4A of DX1; it is used to indicate whether the energy storage high-voltage box of the object under test has output emergency stop feedback signal; J12 connector socket: Endpoint 1 connects to SB3 boat switch input terminal A1, Endpoint 2 connects to SB4 boat switch input terminal A1, Endpoint 3 connects to HG4 power supply 24V indicator light 2 input terminal X2, Endpoint 4 connects to HG3 power supply 24V indicator light 1 input terminal X2, Endpoint 5 connects to SB2 boat switch output terminal A1, Endpoint 6 connects to DX1 terminal block 2B, Endpoint 7 connects to HW1 emergency stop signal 24V indicator light input terminal X1, Endpoints 8 / 9 connect to USB-CAN box 1 input terminal CAN1H / CAN1L, Endpoints 10 / 11 connect Input terminal CAN2H / CAN2L, endpoint 12 / 13 connects to input terminal CAN1H / CAN1L of USB-CAN box 2, and endpoint 14 / 15 connects to input terminal A / B of USB-485 box; used to connect to the energy storage high-voltage box of the object under test; The input terminal A1 of the SB3 boat switch is connected to the terminal 1 of the J12 connector socket, and the output terminal A is connected to the input terminal X1 of the HG3 power supply 24V indicator light 1; it is used to control the DC24V power supply 1 output of the energy storage high-voltage box of the object under test; HG3 power supply 24V indicator light 1: input terminal X1 is connected to SB3 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 4; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 1; SB4 boat switch: input terminal A1 is connected to terminal 2 of J12 connector socket, and output terminal A is connected to input terminal X1 of HG4 power supply 24V indicator light 2; used to control the output of DC24V power supply 2 of the energy storage high-voltage box of the object under test; HG4 power supply 24V indicator light 2: input terminal X1 is connected to SB4 boat switch output terminal A, input terminal X2 is connected to J12 connector socket terminal 3; used to indicate whether the energy storage high-voltage box of the object under test has output 24V power supply 2; The input terminal 1 of FU1 fuse is connected to the output terminal +V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT+ copper bar input terminal; Used for DC110V+ power output protection; The input terminal 1 of FU2 fuse is connected to the output terminal -V of SMPS3110V switching power supply, and the output terminal 2 is connected to the M4 bolt of BAT- copper bar input terminal; Used for DC110V-power output protection; HW2 main negative contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output end of the BAT+ copper bar, and input terminal X2 is connected to the M4 bolt at the output end of the DC- copper bar; it is used to indicate whether the main negative contactor of the energy storage high-voltage box under test is closed; HW3 main positive contactor closed 110V indicator light: input terminal X1 is connected to the M4 bolt at the output terminal of BAT- copper bar, and input terminal X2 is connected to the M4 bolt at the output terminal of DC+ copper bar; it is used to indicate whether the main positive contactor of the energy storage high-voltage box under test is closed; BAT+ copper bar connects FU1 fuse output terminal 2 and HW2 main negative contactor closed 110V indicator light input terminal X1; used to connect the energy storage high-voltage box of the object under test; BAT- copper bar connects FU2 fuse output terminal 2 and HW3 main positive contactor closed 110V indicator light input terminal X2; used to connect the energy storage high-voltage box of the object under test; The DC+ copper busbar is connected to the input terminal X1 of the 110V indicator light of the main positive contactor of HW3; it is used to connect the energy storage high-voltage box of the object to be tested; DC-copper busbar is connected to the input terminal X2 of the 110V indicator light of the main negative contactor of HW2; Used to connect the energy storage high-voltage box of the object to be measured; The USB extender is connected to the USB ports of USB-CAN box 1, USB-CAN box 2 and USB-485 box; it is used to connect to a computer and communicate with the high-voltage box of the object to be measured through computer program software; The input CAN1H / CAN1L of USB-CAN box 1 is connected to the J12 connector socket endpoint 8 / 9, the input CAN2H / CAN2L is connected to the J12 connector socket endpoint 10 / 11, and the output USB interface is connected to the USB extender; Used to convert CAN communication signals; The input CAN1H / CAN1L of USB-CAN box 2 is connected to the J12 connector socket terminal 12 / 13, and the output USB interface is connected to the USB extender; Used to convert CAN communication signals; The USB-485 box input terminals A / B are connected to the J12 connector socket terminals 14 / 15, and the output USB port is connected to the USB extender; Used to convert RS485 communication signals.