Combined base of tower crane
By designing a combined base, the threaded rod head and positioning rod set are used to realize the disassembly and stacking of the basic unit, which solves the problem that the existing base is difficult to dismantle and reuse, realizes the convenient disassembly and reuse of the base, and reduces Eliminates material waste and installation costs.
Patent Information
- Application Number
- CN202420484906.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-03-12
AI Technical Summary
The base of the existing crane tower crane is difficult to dismantle and reuse, resulting in waste of concrete and other materials, and the overall fixed structure is troublesome to handle during later construction.
Design a combined base, including a base plate and a basic unit. The base unit can be disassembled and stacked through a threaded rod head and positioning rod set, allowing the load to be adjusted according to needs, and easy to dismantle and reuse after the lifting tower crane is dismantled. .
It realizes the convenient disassembly and reuse of the base, reduces material waste, and reduces the cost of base installation and disassembly, adapting to lifting tower cranes with different load requirements.
Smart Images

Figure CN221854033U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of a lifting tower crane, in particular to a base of a lifting tower crane. Background Art
[0002] Crane tower crane is a common lifting equipment in construction sites, which can be used to lift raw materials such as steel bars, wood, concrete, masonry and steel pipes required for construction. The crane tower crane needs to be fixed on the base during installation, so that the base can bear the weight of the crane tower crane and provide the crane tower crane with anti-shear and anti-overturning capabilities.
[0003] Some existing foundation constructions require excavating a foundation pit first, building a steel cage in the foundation pit, and then pouring concrete into the foundation pit to build the foundation. The crane can only be assembled after the concrete strength of the foundation reaches the set requirements. In this process, the pouring construction of the foundation is time-consuming, and the foundation is an integral fixed structure that is difficult to dismantle. After the later construction is completed, it cannot be transported to other construction sites for reuse, resulting in a waste of concrete and other materials. The foundation can generally only be abandoned on site and simply landfilled; if the elevation of the foundation is large and affects the construction of other building structures, the foundation needs to be specially dismantled, making the later processing of the foundation more troublesome. Utility Model Content
[0004] The utility model aims to provide a combined base for a lifting tower crane, which can solve the problem that the base is difficult to dismantle and reuse.
[0005] To achieve the above-mentioned purpose, a combined base of a lifting tower crane is provided, which includes a base plate and a base unit, the base plate is vertically embedded with a first threaded rod head and a second threaded rod head, the base units are provided with at least two and are arranged in sequence along the vertical direction, and each of the base units includes: a fixing frame, a side surface of the fixing frame is detachably provided with a first fixing plate and a second fixing plate arranged in an upper and lower manner; a counterweight group is arranged on the base plate and located on the side of the fixing frame, and is vertically provided with an assembly through hole coaxially arranged with the second threaded rod head, the top and bottom surfaces of the counterweight group are both recessed with positioning grooves communicating with the assembly through hole, the first fixing plate and the second fixing plate are arranged in the corresponding positioning grooves; a positioning rod group, including a rod barrel and a positioning head, the bottom of the rod barrel has a bearing platform, the top of the positioning head has a first positioning screw, and the bottom has a second positioning screw, the rod barrel is upwardly inserted into the second fixing plate and the assembly through hole, the second positioning screw is downwardly penetrated through the first fixing plate and threadedly inserted into the rod barrel;
[0006] Among them, in adjacent basic units, the first positioning screw of the basic unit located at the bottom is threadedly inserted into the bottom of the rod barrel of the basic unit located at the top; in the basic unit located at the bottom, the fixed frame is connected to the first threaded rod head, and the rod barrel is fitted into the second threaded rod head.
[0007] According to the combined base of a lifting tower crane, the first fixing plate and the second fixing plate are both provided with a first mounting hole having the same width as the assembly through hole, and the top fixing sleeve of the second positioning screw is provided with a positioning cylinder adapted to the first mounting hole.
[0008] According to the combined base of the tower crane, the height of the positioning tube is greater than the thickness of the first fixing plate.
[0009] According to the combined base of the lifting tower crane, a third fixing plate is arranged at the bottom of the fixing frame, and the third fixing plate is provided with a second mounting hole for the first threaded rod head to pass through.
[0010] According to the combined base of a lifting tower crane, the counterweight group includes two counterweight blocks arranged up and down, the top and bottom surfaces of the counterweight blocks are both recessed with the positioning grooves, and the height of the rod barrel is greater than the height of the counterweight blocks.
[0011] According to the described combined base of a lifting tower crane, the counterweight group includes two counterweight blocks arranged up and down, each counterweight block is provided with at least two of the assembly through holes in sequence along the horizontal direction, and the top and bottom surfaces of each counterweight block are recessed with the positioning grooves, and the inner walls of the adjacent positioning grooves of the two counterweight blocks are surrounded to form an assembly through hole, and a positioning strip is provided in the assembly through hole, and both sides of the positioning strip are vertically penetrated with a third mounting hole adapted to the rod barrel.
[0012] According to the combined base of a lifting tower crane, in the uppermost basic unit, a first positioning screw sleeve is provided with a pull rod seat.
[0013] According to the combined base of the tower crane, the fixed frames of adjacent basic units are detachably connected.
[0014] According to the combined base of a lifting tower crane, the first fixing plate and the second fixing plate are both L-shaped and connected to the fixing frame by bolts.
[0015] Beneficial effects: As in the above structure, the basic units are detachable, and multiple basic units can be stacked and arranged according to the use requirements, which can be adapted to the cranes with different load requirements and ensure the stable operation of the cranes carried by them; the base is formed by combining multiple basic units, and the basic units are detachably connected to the bottom plate, and the basic units can be disassembled after the crane is dismantled, so that the base is easy to dismantle and reuse, reducing the waste of materials such as concrete;
[0016] The basic unit is formed by a detachable combination of a fixed frame and a counterweight group. The weight and volume of a single component are small, which makes it easy to install and disassemble. A smaller tonnage crane can be used on site to assist in installation and disassembly, which can reduce the cost of base installation and disassembly.
[0017] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The utility model is further described below in conjunction with the accompanying drawings and embodiments;
[0019] Figure 1 A cross-sectional view of an embodiment of the utility model;
[0020] Figure 2 for Figure 1 AA section view;
[0021] Figure 3 is a side view of the counterweight;
[0022] Figure 4 is a cross-sectional view of the positioning rod assembly;
[0023] Figure 5 is a top view of the fixed frame;
[0024] Figure 6 It is a cross-sectional view of another embodiment of the utility model. DETAILED DESCRIPTION
[0025] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.
[0026] In the description of the present invention, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0027] In the description of the present utility model, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0028] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0029] Reference Figure 1-5 A combined base of a lifting tower crane includes a base plate 10 and a basic unit. The base plate 10 is vertically embedded with a first threaded rod head 11 and a second threaded rod head 12. The basic units are provided with at least two and are arranged in sequence along the vertical direction. Each basic unit includes a fixed frame 20, a counterweight group 30 and a positioning rod group 40. The side of the fixed frame 20 is provided with a first fixing plate 21 and a second fixing plate 22 arranged in an upper and lower manner. The counterweight group 30 is arranged on the bottom plate 10 and is located on the side of the fixed frame. The counterweight group 30 is vertically provided with an assembly through hole 32 coaxially arranged with the second threaded rod head 12. The top and bottom surfaces of the counterweight group 30 are both recessed with a positioning groove 33 connected to the assembly through hole 32. The first fixing plate 21 is arranged in the positioning groove 33 at the top of the counterweight group 30, and the second fixing plate 22 is arranged in the positioning groove 33 at the bottom of the counterweight group 30. The positioning rod group 40 includes a rod barrel 41 and a positioning head 42. The bottom of the rod barrel 41 has a base 411, and the inner wall of the rod barrel 41 has an internal thread. The top of the positioning head 42 has a first positioning screw 421, and the bottom of the positioning head 42 has a second positioning screw 422. The rod barrel 41 is upwardly inserted into the second fixing plate 22 and the assembly through hole 32, and the second positioning screw 422 is downwardly penetrated into the first fixing plate 21 and threadedly inserted into the rod barrel 41. In the adjacent basic units, the first positioning screw 421 of the basic unit at the bottom is threadedly inserted into the bottom of the rod barrel 41 of the basic unit at the top. In the basic unit at the bottom, the first threaded rod head 11 is connected to the fixed frame 20, and the second threaded rod head 12 is inserted into the rod barrel 41.
[0030] In the above solution, the first fixing plate 21 and the second fixing plate 22 are both L-shaped, and the vertical sections thereof are detachably connected to the fixing frame 20 by bolts.
[0031] During construction, firstly, a foundation pit is excavated, then a concrete base plate 10 is built at the bottom of the foundation pit, and then the first basic unit is assembled. Specifically, the rod barrel 41 is first twisted to fit the second threaded rod head 12 and to make the bearing platform 411 contact the base plate 10; the second fixed plate 22 is assembled on the fixed frame 20, and the fixed frame 20 is hoisted into the foundation pit, and the second fixed plate 22 is sleeved on the rod barrel 41; the fixed frame 20 is connected to the first threaded rod head 11; the rod barrel 41 is rotated and adjusted to make the bearing platform 411 press against the second fixed plate 22; the assembly group 30 is hoisted into the foundation pit and sleeved on the rod barrel 41; the first fixed plate 21 is assembled on the fixed frame 20; and the positioning head 42 is installed. After the first basic unit is installed, the remaining basic units are installed in sequence to form a base.
[0032] As in the above structure, the basic units are detachable, and multiple basic units can be stacked and arranged according to the use requirements, which can be adapted to cranes with different load requirements and ensure the stable operation of the cranes it carries; the base is formed by a combination of multiple basic units, and the basic units are detachably connected to the bottom plate 10, and the basic units can be disassembled after the crane is dismantled, so that the base is easy to dismantle and reuse, reducing the waste of materials such as concrete. In addition, the basic unit is formed by a detachable combination of components such as a fixed frame 20 and a counterweight group 30, and the weight and volume of a single component are small, so it is easy to install and disassemble. A small-tonnage crane can be used on site to assist in assembly and disassembly, which can reduce the cost of assembly and disassembly of the base. Furthermore, the counterweight group 30 can adopt a concrete block structure, and the counterweight group 30 has a simple structure and a long service life.
[0033] In this embodiment, the first fixing plate 21 and the second fixing plate 22 are both provided with a first mounting hole 23 having the same width as the assembly through hole 32, and the top of the second positioning screw 422 is fixedly sleeved with a positioning cylinder 423 adapted to the first mounting hole 23. With this structure, the first fixing plate 21 and the second fixing plate 22 can be provided with the same first mounting hole 23, and the structures of the first fixing plate 21 and the second fixing plate 22 can be the same, so as to reduce the types of parts and components and facilitate production, and the positioning cylinder 423 can fill the gap between the inner wall of the first mounting hole 23 of the first fixing plate 21 and the second positioning screw 422 to prevent it from shaking.
[0034] In this embodiment, the height of the positioning tube 423 is greater than the thickness of the first fixing plate 21 , so as to reduce the shear force on the first positioning screw 421 .
[0035] In this embodiment, a third fixing plate 24 is provided at the bottom of the fixing frame 20, and a second mounting hole is provided on the third fixing plate 24 for the first threaded rod head 11 to pass through. During installation, the fixing frame 20 of the first basic unit is hoisted into the foundation pit, the first threaded rod head 11 is passed through its second mounting hole, and then a nut is sleeved on the first threaded rod head 11 and tightened to detachably connect the fixing frame 20 to the bottom plate 10.
[0036] In this embodiment, the counterweight group 30 includes two counterweight blocks 31 arranged in an upper and lower manner, and the top and bottom surfaces of the counterweight blocks 31 are both concavely provided with positioning grooves 33, and the height of the rod barrel 41 is greater than the height of the counterweight blocks 31. Among them, each counterweight block 31 is sequentially provided with at least two assembly through holes 32 in the transverse direction, and in the two counterweight blocks 31 of the counterweight group 30, the inner walls of the adjacent positioning grooves 33 are surrounded to form an assembly through hole. The two counterweight blocks 31 can be positioned transversely by the provided rod barrel 41 to ensure that the counterweight blocks 31 are accurately installed.
[0037] In this embodiment, in the topmost basic unit, the first positioning screw 421 is provided with a tie rod seat 51 and a positioning nut 52 to lock the tie rod seat 51 to the top of the base. The tie rod seat 51 can be rotatably installed with the tie rod, and the tie rod is rotatably connected to the crane to improve the stability of the crane.
[0038] In this embodiment, the fixing frames 20 of adjacent basic units are detachably connected. Specifically, the adjacent fixing frames 20 are detachably connected by vertically inserted bolts to improve the overall stability of the base.
[0039] Reference Figure 6 In some embodiments, two counterweight groups 30 are sequentially arranged on the sides of the fixed frame 20. In order to connect the two counterweight groups 30, a positioning bar 34 is provided in the assembly through hole. Both sides of the positioning bar 34 are vertically penetrated with third mounting holes adapted to the rod barrel 41, that is, the rod barrel 41 of one counterweight group 30 is inserted into one of the third mounting holes of the positioning bar 34, and the rod barrel 41 of the other counterweight group 30 is inserted into the other third mounting hole of the positioning bar 34. Through this structure, multiple counterweight groups 30 can be arranged horizontally as needed, and the counterweight groups 30 are connected to form an integral force-bearing structure through the positioning bar 34. The number of counterweight groups 30 can be increased horizontally when the overall construction height of the base is limited, ensuring that the base can meet the requirements of bearing the corresponding lifting tower.
[0040] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. A combined base for a tower crane, characterized in that: It comprises a bottom plate and a basic unit, wherein the bottom plate is vertically embedded with a first threaded rod head and a second threaded rod head, and the basic units are provided with at least two and are arranged in sequence vertically, and each of the basic units comprises: A fixed frame, wherein a first fixing plate and a second fixing plate arranged in an upper and lower manner are detachably provided on a side of the fixed frame; The counterweight group is arranged on the bottom plate and located on the side of the fixed frame, and is vertically provided with an assembly through hole coaxially arranged with the second threaded rod head. The top and bottom surfaces of the counterweight group are both concavely provided with positioning grooves connected to the assembly through hole, and the first fixing plate and the second fixing plate are arranged in the corresponding positioning grooves; The positioning rod assembly includes a rod barrel and a positioning head, wherein the bottom of the rod barrel has a support platform, the top of the positioning head has a first positioning screw, and the bottom has a second positioning screw, the rod barrel is upwardly inserted into the second fixing plate and the assembly through hole, and the second positioning screw is downwardly penetrated into the first fixing plate and threadedly inserted into the rod barrel; in, Among the adjacent basic units, the first positioning screw of the basic unit located at the bottom is thread-matched and inserted into the bottom of the rod barrel of the basic unit located at the top; In the bottommost basic unit, the fixed frame is connected to the first threaded rod head, and the rod barrel is sleeved on the second threaded rod head.
2. The combined base of a tower crane according to claim 1, characterized in that: The first fixing plate and the second fixing plate are both provided with a first mounting hole having the same width as the assembly through hole, and the top fixing sleeve of the second positioning screw is provided with a positioning cylinder adapted to the first mounting hole.
3. The combined base of a tower crane according to claim 2, characterized in that: The height of the positioning tube is greater than the thickness of the first fixing plate.
4. The combined base of a tower crane according to claim 1, characterized in that: A third fixing plate is disposed at the bottom of the fixing frame, and a second mounting hole for the first threaded rod head to pass through is opened on the third fixing plate.
5. The combined base of a tower crane according to claim 1, characterized in that: The counterweight group includes two counterweight blocks arranged up and down, the top surface and the bottom surface of the counterweight block are both concavely provided with the positioning groove, and the height of the rod barrel is greater than the height of the counterweight block.
6. The combined base of a tower crane according to claim 1, characterized in that: The counterweight group includes two counterweight blocks arranged up and down, each counterweight block is provided with at least two assembly through holes in sequence along the horizontal direction, and the top and bottom surfaces of each counterweight block are recessed with the positioning grooves, and the inner walls of the adjacent positioning grooves of the two counterweight blocks are surrounded to form an assembly through hole, and a positioning strip is provided in the assembly through hole, and both sides of the positioning strip are vertically penetrated with a third mounting hole adapted to the rod barrel.
7. The combined base of a tower crane according to claim 1, characterized in that: In the uppermost basic unit, a first positioning screw sleeve is provided with a pull rod seat.
8. The combined base of a tower crane according to claim 1, characterized in that: The fixing frames of adjacent basic units are detachably connected.
9. The combined base of a tower crane according to claim 1, characterized in that: The first fixing plate and the second fixing plate are both L-shaped and are connected to the fixing frame by bolts.