Crawler bulldozer preheating system and crawler bulldozer
Through inverter technology and remote control, the lithium iron phosphate battery is used to power the crawler bulldozer heater, which solves the problems of high cost, non-environmental protection and inconvenient operation of the existing preheating system, achieving low-cost, environmentally friendly and convenient preheating System, suitable for crawler bulldozers in dusty environments.
Patent Information
- Application Number
- CN202323635653.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-28
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-28
AI Technical Summary
The existing preheating system for crawler bulldozers has high cost, poor performance in dusty environments, is not environmentally friendly and is inconvenient to operate. In particular, the air intake system of the fuel preheater has insufficient filtration capacity, and remote control is not commonly used.
Inverter technology is used to use lithium iron phosphate batteries to power the heater, and remote control is achieved by combining the remote control switch and the mobile phone 4G network. The voltage output by the battery is converted into the voltage required by the heater through the inverter, and the voltage is converted between the generator and the battery. A diode is installed between the two to prevent reverse current flow, and a remote control function is added for easy operation.
It reduces the cost of the preheating system, improves environmental protection, enhances the convenience of operation, alleviates the problem of performance degradation in dusty environments, and enables more flexible operation through remote control.
Smart Images

Figure CN221856823U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of electrical control, in particular to a crawler bulldozer preheating system and a crawler bulldozer. Background Art
[0002] The existing relatively mature crawler bulldozer preheating technology mainly heats the coolant through fuel combustion, and then circulates the coolant in the engine body water channel to heat the engine body, thereby increasing the fluidity of the lubricating oil and avoiding the viscosity of the lubricating oil caused by the low temperature in winter, which causes the engine to be damaged due to poor lubrication.
[0003] However, the disadvantages of the existing technology are: first, the cost is relatively high. Such preheaters usually cost from several thousand to tens of thousands of yuan. For example, the average price of a single preheater of the German Eberspächer brand is more than 10,000 yuan; second, such preheaters do not work well in harsh environments with a lot of dust, mainly due to the poor filtering capacity of the air intake system of such preheaters; third, such products use fuel oil as fuel and are less environmentally friendly; fourth, remote control is not widely used, making operation inconvenient. Utility Model Content
[0004] The purpose of the utility model is to provide a crawler bulldozer preheating system and a crawler bulldozer in order to solve at least one of the above technical problems.
[0005] In the first aspect, an embodiment of the utility model provides a crawler bulldozer preheating system, comprising: a heater, an inverter, a battery and a starting relay; the heater is arranged on the engine oil pan of the crawler bulldozer, and the heater is electrically connected to the output of the inverter; the battery is electrically connected to the input end of the inverter; the two ends of the main contacts of the starting relay are connected to the circuit connecting the positive end of the battery and the input end of the inverter; the control end of the starting relay is connected to a remote control switch, and the remote control switch is wirelessly connected to a remote control terminal; the remote control terminal is used to control the on and off of the remote control switch to control the on and off of the starting relay; the starting relay is used to control the start and stop of the inverter; the inverter is used to convert the output voltage of the battery into the working voltage of the heater; the heater is used to preheat the engine lubricating oil of the crawler bulldozer before starting.
[0006] Furthermore, the number of the heaters is two.
[0007] Furthermore, the battery includes two lithium iron phosphate batteries connected in series.
[0008] Furthermore, the positive terminal of the battery is also electrically connected to the generator of the crawler bulldozer.
[0009] Furthermore, a diode is provided on the connection circuit between the output end of the generator and the positive terminal of the battery.
[0010] Furthermore, the negative terminal of the battery is connected to a grounding wire.
[0011] Furthermore, one end of the control end of the start relay is connected to the output end of the remote control switch, and the other end of the control end of the start relay is connected to a grounding wire.
[0012] Furthermore, the remote control terminal includes a mobile phone; the remote control terminal is communicatively connected to the remote control switch via a 4G network.
[0013] Furthermore, the control end of the starter relay is also connected to a backup power supply in the cab of the crawler bulldozer.
[0014] In a second aspect, an embodiment of the utility model further provides a crawler bulldozer, comprising the crawler bulldozer preheating system described in the first aspect.
[0015] The utility model provides a crawler bulldozer preheating system and a crawler bulldozer, which adopts inverter technology to use a battery to power an electric heater, has strong environmental protection and low cost; adds remote control and is easy to operate; and alleviates the technical problems of high cost, inconvenient operation and environmental pollution in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the implementation methods of the present application or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0017] Figure 1 A schematic diagram of a crawler bulldozer preheating system provided in an embodiment of the utility model.
[0018] In the figure: 1. Engine oil pan, 2. Heater, 3. Remote control switch, 4. Backup power supply in the cab, 5. Starting relay, 6. Generator, 7. Diode, 8. Battery, 9. Grounding wire, 10. Inverter, 11. Remote control terminal. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] Figure 1 Schematic diagram of a crawler bulldozer preheating system provided according to an embodiment of the utility model. Figure 1 As shown, the system includes: a heater 2 , an inverter 10 , a battery 8 and a starter relay 5 .
[0021] Specifically, the heater 2 is arranged on the engine oil pan 1 of the crawler bulldozer, and the heater 2 is electrically connected to the output of the inverter 10; the battery 8 is electrically connected to the input end of the inverter 10; the two ends of the main contact of the starting relay 5 are connected to the positive end of the battery 8 and the input end of the inverter 10 connection circuit; the control end of the starting relay 5 is connected to the remote control switch 3, and the remote control switch 3 is wirelessly connected to the remote control terminal 11.
[0022] Specifically, the remote control terminal 11 is used to control the on and off of the remote control switch 3 to control the on and off of the start relay 5 .
[0023] The starting relay 5 is used to control the start and stop of the inverter 10.
[0024] The inverter 10 is used to convert the output voltage of the battery 8 into an operating voltage of the heater 2 .
[0025] The heater 2 is used for preheating the engine lubricating oil of the crawler bulldozer before starting.
[0026] Preferably, if Figure 1 As shown, the number of heaters 2 is two.
[0027] Preferably, if Figure 1 As shown, the battery 8 includes two lithium iron phosphate batteries connected in series. Optionally, the battery includes two 12V 200Ah lithium iron phosphate batteries.
[0028] Preferably, if Figure 1 As shown, the positive terminal of the battery 8 is also electrically connected to the generator 6 of the crawler bulldozer, and a diode 7 is also provided on the connection circuit between the output end of the generator 6 and the positive terminal of the battery 8. The rated current of the diode 7 is 100A.
[0029] Preferably, the operating voltage of the heater 2 is 220V, and the inverter 10 is a 24V / 5000W inverter. The inverter 10 can convert the 24V DC power output by the battery 8 into a 220V AC power.
[0030] Specifically, in the embodiment of the utility model, two 12V 200Ah lithium iron phosphate batteries are connected in series and connected in parallel with the original vehicle battery, and a 100A diode is used to separate the positive terminal of the additional battery from the positive terminal of the generator of the crawler bulldozer, so as to ensure that the current can only flow from the on-board generator and the original vehicle battery into the additional battery, and cannot flow out in the opposite direction. The purpose of doing so is not only to prevent the current flowing out after the two groups of batteries are connected in parallel from being too large, causing the load such as the starter to be damaged due to excessive current, but also to charge the additional battery through the on-board generator when the engine is operating normally, so as to prepare power reserve for the next preheating system operation. Then, the 24V DC power supply from the two additional lithium iron phosphate batteries is converted into a 220V AC power supply through the inverter inverter step-up, which matches the power supply required by the heating system and is used to power the heating system, and then the conversion connector is used to connect the power supply to the heater harness.
[0031] Preferably, the negative terminal of the battery 8 is connected to a grounding wire 9 .
[0032] Preferably, if Figure 1 As shown, one end of the control end of the start relay 5 is connected to the output end of the remote control switch 3 , and the other end of the control end of the start relay 5 is connected to the grounding wire 9 .
[0033] Optionally, the remote control terminal 11 includes a mobile phone; the remote control terminal 11 is connected to the remote control switch 3 via a 4G network.
[0034] In the embodiment of the utility model, considering the convenience during use, a remote control function is added, that is, the 24V remote control switch 3 controls the on and off of the start relay 5 and then controls the operation of the inverter 10 to realize preheating control. The communication of the remote control switch 3 is realized through the mobile phone 4G network, which is not limited by the region and distance. As long as there is a 4G signal, the preheating system can be controlled anytime and anywhere using the mobile phone APP, and multiple mobile phones can be controlled, which is convenient and reliable.
[0035] Optionally, the operating voltage of the starter relay 5 is DC 24V.
[0036] Preferably, if Figure 1 As shown, the control end of the starter relay 5 is also connected to the backup power supply 4 in the cab of the crawler bulldozer.
[0037] The following is a process for selecting parts for a crawler bulldozer preheating system provided by the embodiment of the utility model:
[0038] 1. Inverter power supply
[0039] First, it is necessary to calculate the output power of the two batteries. Since the additional battery is connected in parallel with the original vehicle battery, in order not to affect the output and function of the original battery, the selected battery must be consistent with the voltage and capacity of the original battery. In addition, considering the limited installation space, the utility model selects a smaller 12V / 200Ah lithium iron phosphate battery as the DC power supply of the inverter.
[0040] 2. Inverter power calculation
[0041] Theoretically, for a battery with a capacity of 12V / 200A, if it is discharged at a current of 200A, the continuous output time is 1 hour. Because the two batteries are connected in series, the voltage will increase to twice the original value, that is, 24V, and the current remains unchanged. Then the power provided by the two 12V / 200Ah batteries in series is P=2×12V×200A=4.8KW.
[0042] The inverter can convert 24V DC voltage into 220V AC voltage, but at the same time the current after inversion will be reduced. This change can be calculated by the power formula P=UI. Because the inversion process is actually an energy conversion process, it is bound to be accompanied by energy loss. The inversion process will have an energy loss of about 10% to 20%. Assuming that the power loss after inversion is 15%, the power after inversion is about P1=4.8KW×85%=4.08KW. The output current after inversion I1=P1 / U1=4.08KW / 220V=20A.
[0043] Because the two original heaters on the equipment will continue to be used, the connection method of the original car heaters must be checked and tested. After inspection and testing, the connection method of the two 220V heaters is connected in parallel, with a total resistance of 11Ω. The rated current allowed to flow into the heater is I2=U1 / R=220V / 11Ω=20A, I1=I2, so the power of the heater is P2=I2 2 R=(20A) 2 ×11Ω=4.4KW. Because the power P2 of the heater is greater than the power P1 after inversion, the smaller power P1=4.08KW should be used as the basic power for selecting the inverter. According to the above calculation, with enough margin, the utility model selects a 24V / 5000W inverter to fully meet the use requirements.
[0044] 3. Calculation of preheating time and energy consumption
[0045] The engine lubricant uses Shell 15W40, which is a four-season lubricant with a capacity of 85L. The mass of each liter of lubricant is 0.75Kg~0.95Kg. Assuming that the mass of 1L of lubricant is 0.95Kg, then the mass of 85L of lubricant M=85L×0.95Kg≈80Kg. The specific heat capacity of lubricant is 1.87KJ / (Kg.℃)~1.88KJ / (Kg.℃), assuming that the specific heat capacity of 15W40 lubricant is 1.88KJ / (Kg.℃). Assuming that the outdoor temperature in Baiyinhua area is low in winter, the lubricant temperature is -25℃. To raise the lubricant temperature to 20℃, the temperature that needs to be raised is 45℃, so the heat that needs to be absorbed is Q=1.88KJ / (Kg.℃)×80Kg×45℃=6768KJ.
[0046] The working time required by the preheating system is t1 = Q / P2 = 6768KJ / 4.08KW≈1659S=27.65min. Then, under ideal conditions, the lubricating oil can be heated to 20°C in the preheater for about 28 minutes. The power consumed by the battery is W1 = P1×t1 / 85% = 4.08KW×27.65min / 85% = 7963KJ, and the total energy that can be provided by two 200Ah batteries is W = U×I×t = 24V×200A×3600S = 17280KJ.
[0047] The energy consumption of a single preheating is η=W1 / W=7963KJ / 17280KJ=46%. It can be seen that the energy consumed by the preheating system once is about 50% of the battery. The energy consumption is large, and the remaining power is not enough to ensure the second preheating, so it is necessary to Figure 1 The battery is shown with additional charging function.
[0048] 4. Accessories selection
[0049] To sum up, the selected accessories are: a 24V / 5000W inverter, two 12V / 200Ah lithium iron phosphate batteries, a 24V4G network remote control switch, a diode with a withstand voltage higher than 24V and a rated current of 100A, a DC 24V starting relay, a heater conversion connector, 2 battery connecting wires, and several other connecting wires, wire tubes, and wiring harness fixing clips. The overall transformation cost is controlled within 5,500 yuan.
[0050] 5. Installation and debugging
[0051] Since the design structure of Komatsu's crawler bulldozer is relatively compact, it is difficult to choose the installation position of two 200Ah batteries. After on-site inspection and communication with the equipment driver, it was determined that the battery should be fixed on the left front maintenance pedal. There is enough space here, and it will not affect the working line of the equipment driver. It is also close to the generator and heater, which is the most suitable position. The inverter is installed on the body near the heater to facilitate the connection and wiring with the heater. A protective cover should be made to prevent dust and water from entering, protect the inverter, and extend the service life of the inverter. A 100A diode is installed on the positive pole of the additional battery and the positive pole of the generator to ensure that the current flows from the generator to the additional battery in one direction. The start relay is installed on the left body of the equipment, close to the heater and inverter. The two ends of the main contact are connected to the positive pole of the additional battery to the 24V input connection line of the inverter to control the start and stop of the inverter. One end of the control end is connected to the output end of the remote control switch, and the other end is connected to the ground wire. The remote control switch is installed in the cab to ensure a good working environment and improve the reliability and sensitivity of the work. The required 24V DC power supply is supplied by the backup power supply in the cab. The routing of all other connecting wires is consistent with the original vehicle wiring harness along the frame to ensure the rationality of the routing. The outside is protected and fixed with a wire tube. The debugging work is mainly to control the remote operation switch through the mobile phone APP. Since the remote control switch is connected to the mobile phone through the mobile phone 4G network for communication, there is no need for traditional frequency matching, and it is easy to achieve connection and set permissions. At this point, the design and optimization of the entire crawler bulldozer intelligent remote control preheating system have been completed, and the trial operation effect is good.
[0052] From the above description, it can be seen that the embodiment of the utility model provides a crawler bulldozer preheating system, which adopts inverter technology and uses batteries to power the electric heater, is environmentally friendly and low in cost; adds remote control, which can be operated directly through a mobile phone, which is convenient and simple; adds anti-reverse charging diode protection equipment and other power loads, alleviating the technical problems of high cost, inconvenient operation and environmental pollution in the prior art.
[0053] The embodiment of the utility model further provides a crawler bulldozer, including the crawler bulldozer preheating system provided by the utility model.
[0054] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0055] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A crawler bulldozer preheating system, characterized in that: include: A heater, an inverter, a battery and a starter relay; the heater is arranged on the engine oil pan of the crawler bulldozer, and the heater is electrically connected to the output of the inverter; the battery is electrically connected to the input end of the inverter; the two ends of the main contact of the starter relay are connected to the circuit connecting the positive end of the battery and the input end of the inverter; the control end of the starter relay is connected to the remote control switch, and the remote control switch is wirelessly connected to the remote control terminal; The remote control terminal is used to control the on and off of the remote control switch to control the on and off of the start relay; The starting relay is used to control the starting and stopping of the inverter; The inverter is used to convert the output voltage of the battery into the operating voltage of the heater; The heater is used to preheat the engine lubricating oil of the crawler bulldozer before starting.
2. The crawler bulldozer preheating system according to claim 1, characterized in that: The number of the heaters is two.
3. The crawler bulldozer preheating system according to claim 1, characterized in that: The storage battery comprises two lithium iron phosphate batteries connected in series.
4. The crawler bulldozer preheating system according to claim 1, characterized in that: The positive terminal of the battery is also electrically connected to the generator of the crawler bulldozer.
5. The crawler bulldozer preheating system according to claim 4, characterized in that: A diode is also arranged on the connection circuit between the output end of the generator and the positive terminal of the battery.
6. The crawler bulldozer preheating system according to claim 1, characterized in that: The negative terminal of the battery is connected to a grounding wire.
7. The crawler bulldozer preheating system according to claim 1, characterized in that: One end of the control end of the start relay is connected to the output end of the remote control switch, and the other end of the control end of the start relay is connected to a grounding wire.
8. The crawler bulldozer preheating system according to claim 1, characterized in that: The remote control terminal includes a mobile phone; the remote control terminal is connected to the remote control switch through a 4G network.
9. The crawler bulldozer preheating system according to claim 1, characterized in that: The control end of the starter relay is also connected to a backup power supply in the cab of the crawler bulldozer.
10. A crawler bulldozer, characterized in that: The crawler bulldozer preheating system comprises the one described in any one of claims 1-9.