Timing drying device for traditional Chinese medicine preparation
By using fine sand to adjust the flow time to trigger the power-off mechanism in the traditional Chinese medicine preparation drying device, combined with a timer, the problem of timer failure affecting the drying effect is solved, and the accuracy and stability of the drying time of traditional Chinese medicine preparations are achieved, improving Improve the reliability of drying effect.
Patent Information
- Application Number
- CN202420447138.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The timing function of the existing traditional Chinese medicine preparation drying device is prone to failure due to timer failure, which affects the drying effect and is difficult to detect in time.
A timing drying device for traditional Chinese medicine preparations including a timing component, a heating component and a stirring component is designed. By using fine sand in the timing component to adjust the flow time, the passive trigger is triggered to disconnect the power supply of the heating component, and dual timing is achieved in combination with the timer. function to ensure the accuracy and stability of drying time.
It effectively avoids the long-time working of the heating component caused by timer failure, ensures the accuracy and quality of the drying time of traditional Chinese medicine preparations, and improves the reliability of the drying effect.
Smart Images

Figure CN221859101U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of preparation of traditional Chinese medicine preparations, in particular to a timing drying device for traditional Chinese medicine preparations. Background Art
[0002] Currently, there are two ways to dry Chinese herbal preparations: oven drying and sun drying. Sun drying is to place the Chinese herbal preparations in the sun to dry. This not only takes a long time to prepare, but also a large number of bacteria will parasitize in the herbs, causing the Chinese medicine to deteriorate and even cause more diseases. Oven drying is to place the Chinese herbal preparations in a drying oven to dry. Compared with sun drying, it has the advantages of being fast and convenient and is currently widely used.
[0003] In the prior art, in order to improve the quality of Chinese medicine preparations after drying, a timing function is often set on the Chinese medicine preparation drying device to achieve the most suitable drying degree. However, this timing function is often set using a timer, and once the timer is powered off or fails, it is not easy to be discovered in time, which will still affect the drying effect of the Chinese medicine preparation. Therefore, it is necessary to improve it so that the device can operate for a long time. Utility Model Content
[0004] The purpose of the utility model is to provide a timed drying device for Chinese medicine preparations to solve the problems raised in the above background technology.
[0005] In order to achieve the above utility model purpose, the utility model adopts the following technical solutions:
[0006] The utility model provides a timed drying device for Chinese medicine preparations, comprising a device box and also comprising:
[0007] A timer, arranged on the side of the device box;
[0008] A timing assembly is arranged on the top of the device box and is used for secondary auxiliary timing;
[0009] A heating assembly is disposed on the top of the device box and is used to heat the interior of the device box;
[0010] A stirring component is arranged inside the device box and is used to stir the Chinese medicine preparation inside the device box;
[0011] Wherein: the timing assembly includes two fixed plates fixed on the top of the device box, and a rotating box is arranged between the two fixed plates; conical cavities are symmetrically opened at the upper and lower ends inside the rotating box, and the two conical cavities are connected by a connecting seam, and the interior of one of the conical cavities is filled with fine sand; the timing assembly also includes an active triggering member arranged inside the conical cavity and a passive triggering member arranged on the top of the device box.
[0012] Preferably, the active trigger member includes a slide plate slidably arranged inside the conical cavity, and a connecting rod extending to the outside of the rotating box is fixed to one end of the slide plate, a connecting ball is fixed to the end of the connecting rod, and a first spring is connected between the slide plate and the inner wall of the conical cavity.
[0013] Preferably, the passive trigger component includes a first connecting plate fixed to the side of the fixed plate, and a sliding rod that passes through the fixed plate and slides between the fixed plates, one end of the sliding rod is connected to a trapezoidal block that cooperates with the connecting ball, and the other end of the sliding rod is connected to a second connecting plate, a second spring is arranged between the second connecting plate and the fixed plate, and a second trigger plate is arranged on the top of the second connecting plate, and a first trigger plate that cooperates with the second trigger plate is arranged on the bottom of the first connecting plate.
[0014] Preferably, rotating rods penetrating the fixed plate are fixed to both left and right sides of the rotating box, and the rotating rods are rotatably connected to the fixed plate.
[0015] Preferably, a gear is sleeved on the end of the rotating rod, the top of the device box is slidably connected to a guide plate through a guide rod, and a rack meshing with the gear is fixed to the top of the guide plate, a first magnet is fixed to the side of the rack, and a second magnet cooperating with the first magnet is arranged on the fixed plate.
[0016] Preferably, the heating assembly includes a fixed box fixed to the top of the device box, and a first chamber and a second chamber are opened inside the fixed box, the bottom of the second chamber is an open structure and is connected to the inside of the device box, and a dustproof net is provided at the bottom of the second chamber, a heating tube is provided above the dustproof net, and a rotating rod that passes through the inside of the first chamber is rotatably connected at the center of the top of the dustproof net, the upper cover of the rotating rod has fan blades located inside the second chamber, and a second motor connected to the rotating rod is installed inside the first chamber.
[0017] Preferably, the stirring assembly includes a first motor installed on the side of the device box, and the output end of the first motor is connected to a rotating shaft that penetrates into the device box, and a rotating plate located inside the device box is arranged outside the rotating shaft.
[0018] Compared with the prior art, one or more of the above technical solutions have the following beneficial effects:
[0019] One of the conical cavities is filled with fine sand, so that the fine sand can enter the other conical cavity through the connecting gap. By changing the size of the connecting gap, the time for the fine sand to completely flow to the other conical cavity can be adjusted. When the fine sand completely flows to the other conical cavity, the active trigger component will drive the passive trigger component to trigger, thereby cutting off the power to the electronic components in the heating assembly. This is combined with a timer for double timing, thereby effectively ensuring the drying time of the traditional Chinese medicine preparation and achieving a better use effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention.
[0021] In addition, the terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0022] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0023] Figure 2 It is a longitudinal sectional view of the device box of the utility model;
[0024] Figure 3 This utility model Figure 2 The enlarged view of point A in the middle;
[0025] Figure 4 It is a structural schematic diagram of the timing component of the utility model;
[0026] Figure 5 This utility model Figure 4 The enlarged view of point B in the middle;
[0027] Figure 6 This utility model Figure 4 Enlarged view of point C in the middle;
[0028] Figure 7 It is a schematic diagram of the side structure of the fixed plate of the utility model;
[0029] In the figure:
[0030] 1. Device box; 2. Timer; 3. Timing assembly; 301. Fixed plate; 302. Rotating box; 303. Conical cavity; 304. Connecting seam; 305. Rotating rod; 306. Slide plate; 307. Connecting rod; 308. Connecting ball; 309. First spring; 310. Sliding rod; 311. Trapezoidal block; 312. Second spring; 313. First connecting plate; 314. Second connecting plate; 315. First trigger sheet ; 316, second trigger piece; 4, stirring assembly; 401, first motor; 402, rotating shaft; 403, rotating plate; 5, heating assembly; 501, fixing box; 502, first chamber; 503, second chamber; 504, dustproof net; 505, heating tube; 506, rotating rod; 507, fan blade; 508, second motor; 6, gear; 7, guide plate; 8, rack; 9, first magnet; 10, second magnet. DETAILED DESCRIPTION
[0031] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0032] See also Figure 1-Figure 7 A timed drying device for Chinese medicine preparations, comprising a device box 1, and also comprising:
[0033] A timer 2 is arranged on the side of the device box 1;
[0034] The timing component 3 is arranged on the top of the device box 1 and is used for secondary auxiliary timing;
[0035] The heating assembly 5 is arranged on the top of the device box 1 and is used to heat the inside of the device box 1;
[0036] A stirring component 4 is disposed inside the device box 1 and is used to stir the Chinese medicine preparation inside the device box 1;
[0037] The timing assembly 3 includes two fixing plates 301 fixed on the top of the device box 1, and a rotating box 302 is arranged between the two fixing plates 301; the rotating box 302 has conical cavities 303 symmetrically opened at the upper and lower ends, and the two conical cavities 303 are connected through a connecting seam 304, and the interior of one of the conical cavities 303 is filled with fine sand; the timing assembly 3 also includes an active triggering member arranged inside the conical cavity 303 and a passive triggering member arranged on the top of the device box 1;
[0038] One of the conical cavities 303 is filled with fine sand, so that the fine sand can enter the other conical cavity 303 through the connecting slit 304. By changing the size of the connecting slit 304, the time for the fine sand to completely flow into the other conical cavity 303 can be adjusted. When the fine sand completely flows into the other conical cavity 303, the active trigger component will drive the passive trigger component to trigger, thereby cutting off the power to the electronic components in the heating component 5. In this way, double timing is performed in combination with the timer 2, thereby effectively ensuring the drying time of the traditional Chinese medicine preparation and achieving a better use effect.
[0039] Furthermore, the active trigger member includes a slide plate 306 slidably arranged inside the conical cavity 303, and a connecting rod 307 penetrating to the outside of the rotating box 302 is fixed at one end of the slide plate 306, a connecting ball 308 is fixed at the end of the connecting rod 307, and a first spring 309 is connected between the slide plate 306 and the inner wall of the conical cavity 303.
[0040] Further, the passive trigger member includes a first connecting plate 313 fixed to the side of the fixed plate 301, and a slide bar 310 penetrating the fixed plate 301 and slidingly matched between the fixed plates 301, one end of the slide bar 310 is connected to a trapezoidal block 311 matched with the connecting ball 308, and the other end of the slide bar 310 is connected to a second connecting plate 314, a second spring 312 is arranged between the second connecting plate 314 and the fixed plate 301, and a second triggering piece 316 is arranged on the top of the second connecting plate 314, and a first triggering piece 315 matched with the second triggering piece 316 is arranged on the bottom of the first connecting plate 313;
[0041] Specifically, when in use, if the fine sand inside the upper conical cavity 303 flows to the lower conical cavity 303 through the connecting slit 304, as the fine sand increases until it is completely inside the second conical cavity 303, the first spring 309 cannot bear the weight of all the fine sand and the slide plate 306, so the first spring 309 is compressed, and the slide plate 306 moves in the direction of the first spring 309, so that the connecting ball 308 and the inclined surface on the trapezoidal block 311 are pressed against each other, and the trapezoidal block 311 drives the slide bar 310 and the second connecting plate 314 to move in the direction away from the connecting ball 308. The second trigger piece 316 at the top of the second connecting plate 314 contacts the first trigger piece 315 at the bottom of the first connecting plate 313. The existing technology allows the two to contact and trigger the switch, and the switch is electrically connected to the electronic components in the heating component 5, so that the electronic components in the heating component 5 are powered off, that is, after the fine sand flows, the heating component 5 is immediately powered off. The flow time of the fine sand is calculated and controlled to be consistent with the drying time, so that the auxiliary timing can be completed, and when the timer 2 fails, the heating component 5 is prevented from always working and affecting the drying effect.
[0042] Furthermore, rotating rods 305 penetrating the fixed plate 301 are fixed on both sides of the rotating box 302, and the rotating rods 305 are rotatably connected to the fixed plate 301; by rotating the rotating rods 305 half a circle, the rotating box 302 can be rotated half a circle, so that the fine sand can be "reset" for long-term recycling.
[0043] Furthermore, a gear 6 is sleeved on the end of the rotating rod 305, and a guide plate 7 is slidably connected to the top of the device box 1 through a guide rod, and a rack 8 meshing with the gear 6 is fixed on the top of the guide plate 7, and a first magnet 9 is fixed on the side of the rack 8, and a second magnet 10 cooperating with the first magnet 9 is arranged on the fixed plate 301; by controlling the guide plate 7 to rise or fall, the rack 8 rises or falls, thereby driving the gear 6 to drive the rotating rod 305 to rotate half a circle, and then rotate the rotating box 302, and through the magnetic attraction between the first magnet 9 and the second magnet 10, the rack 8 can be suspended at a specified position, thereby ensuring that the rotating box 302 can rotate half a circle effectively and stably, thereby ensuring the effective operation of the timing component 3.
[0044] Furthermore, the heating assembly 5 includes a fixed box 501 fixed to the top of the device box 1, and the interior of the fixed box 501 is provided with a first chamber 502 and a second chamber 503, the bottom of the second chamber 503 is an open structure and is connected to the interior of the device box 1, and a dustproof net 504 is arranged at the bottom of the second chamber 503, a heating tube 505 is arranged above the dustproof net 504, and a rotating rod 506 that penetrates into the interior of the first chamber 502 is rotatably connected at the center of the top of the dustproof net 504, and the rotating rod 506 is provided with a fan blade 507 located in the second chamber 503, and a second motor 508 connected to the rotating rod 506 is installed in the interior of the first chamber 502; after starting the second motor 508 and the heating tube 505, the rotating rod 506 drives the fan blade 507 to rotate, so that the fan blade 507 blows the hot air around the heating tube 505 to the interior of the device box 1, thereby completing the heating of the interior of the device box 1.
[0045] Furthermore, the stirring assembly 4 includes a first motor 401 installed on the side of the device box 1, and the output end of the first motor 401 is connected to a rotating shaft 402 that penetrates into the interior of the device box 1, and a rotating plate 403 located inside the device box 1 is arranged outside the rotating shaft 402; after starting the first motor 401, the rotating shaft 402 drives the rotating plate 403 to rotate, thereby completing the stirring of the traditional Chinese medicine preparation, which is convenient for better drying effect.
[0046] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A timed drying device for Chinese medicine preparations, comprising a device box (1), characterized in that: Also includes: A timer (2) is arranged on the side of the device box (1); A timing component (3) is arranged on the top of the device box (1) and is used for secondary auxiliary timing; A heating component (5) is arranged on the top of the device box (1) and is used to heat the interior of the device box (1); A stirring component (4) is arranged inside the device box (1) and is used to stir the traditional Chinese medicine preparation inside the device box (1); The timing assembly (3) comprises two fixing plates (301) fixed on the top of the device box (1), and a rotating box (302) is arranged between the two fixing plates (301); conical cavities (303) are symmetrically opened at the upper and lower ends inside the rotating box (302), and the two conical cavities (303) are connected through a connecting seam (304), and the interior of one of the conical cavities (303) is filled with fine sand; the timing assembly (3) also comprises an active triggering component arranged inside the conical cavity (303) and a passive triggering component arranged on the top of the device box (1).
2. The timed drying device for Chinese medicine preparation according to claim 1, characterized in that: The active triggering member comprises a slide plate (306) slidably arranged inside the conical cavity (303), and a connecting rod (307) penetrating to the outside of the rotating box (302) is fixed at one end of the slide plate (306), a connecting ball (308) is fixed at the end of the connecting rod (307), and a first spring (309) is connected between the slide plate (306) and the inner wall of the conical cavity (303).
3. The timed drying device for Chinese medicine preparation according to claim 2, characterized in that: The passive trigger component includes a first connecting plate (313) fixed to the side of the fixed plate (301), and a sliding rod (310) penetrating the fixed plate (301) and slidingly matched between the fixed plates (301), one end of the sliding rod (310) is connected to a trapezoidal block (311) matched with the connecting ball (308), and the other end of the sliding rod (310) is connected to a second connecting plate (314), a second spring (312) is arranged between the second connecting plate (314) and the fixed plate (301), and a second trigger plate (316) is arranged on the top of the second connecting plate (314), and a first trigger plate (315) matched with the second trigger plate (316) is arranged on the bottom of the first connecting plate (313).
4. The timed drying device for Chinese medicine preparation according to claim 1, characterized in that: A rotating rod (305) penetrating the fixed plate (301) is fixed to both the left and right sides of the rotating box (302), and the rotating rod (305) is rotatably connected to the fixed plate (301).
5. The timed drying device for Chinese medicine preparation according to claim 4, characterized in that: The end of the rotating rod (305) is sleeved with a gear (6), the top of the device box (1) is slidably connected to a guide plate (7) via a guide rod, and a rack (8) meshing with the gear (6) is fixed to the top of the guide plate (7), a first magnet (9) is fixed to the side of the rack (8), and a second magnet (10) cooperating with the first magnet (9) is arranged on the fixed plate (301).
6. The timed drying device for Chinese medicine preparation according to claim 1, characterized in that: The heating component (5) comprises a fixing box (501) fixed to the top of the device box (1), and a first chamber (502) and a second chamber (503) are provided inside the fixing box (501), the bottom of the second chamber (503) is an open structure and is communicated with the inside of the device box (1), and a dustproof net (504) is provided at the bottom of the second chamber (503), a heating tube (505) is provided above the dustproof net (504), and a rotating rod (506) penetrating into the inside of the first chamber (502) is rotatably connected at the center of the top of the dustproof net (504), the rotating rod (506) is provided with a fan blade (507) located inside the second chamber (503), and a second motor (508) connected to the rotating rod (506) is installed inside the first chamber (502).
7. The timed drying device for Chinese medicine preparation according to claim 1, characterized in that: The stirring assembly (4) comprises a first motor (401) installed on the side of the device box (1), and the output end of the first motor (401) is connected to a rotating shaft (402) that passes through the inside of the device box (1), and a rotating plate (403) located inside the device box (1) is arranged outside the rotating shaft (402).