Construction waste sorting device

By using the pre-sorting conveyor belt and the sorting scraper to move synchronously in the construction waste sorting device, combined with the screening material removal plate and the removal channel, the problem in the existing technology that wind force is difficult to remove and wet the light materials is solved. It realizes automated light material rejection and sorting, improving the efficiency and effect of construction waste sorting.

CN221869336UActive Publication Date: 2024-10-22ZHEJIANG XITOU ENVIRONMENTAL MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323291504.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-05
Publication Date
2024-10-22
Estimated Expiration
2033-12-05

AI Technical Summary

Technical Problem

When the existing construction waste sorting device handles wet plastic bags and woven bags, it is difficult to effectively discharge the wind, resulting in poor sorting effect, and the sorting pressure of heavy materials is high. The conveying capacity of the fan needs to be increased to achieve cleaning. Effect.

Method used

A construction waste sorting device is designed, including a construction waste air separator and a mixed waste conveyor belt. The pre-sorting conveyor belt and the sorting scraper move synchronously, combined with the screening material removal plate and the clearance channel to remove the mixed waste. The large-volume light materials and light materials adhered to cement are removed, and through the movement of the sorting scraper and the cooperation of the screening material removal plate, the manual sorting pressure is reduced and the sorting effect is improved.

Benefits of technology

Through this device, large-volume light materials and light materials adhering to cement can be automatically removed, reducing the sorting pressure of the air separator on light materials, improving the overall effect of waste sorting, reducing manual intervention, and improving sorting efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221869336U_ABST
    Figure CN221869336U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of construction waste treatment, and particularly relates to a construction waste sorting device which comprises a construction waste winnowing machine and a mixed waste conveying belt, the mixed waste conveying belt is arranged on one side of the construction waste winnowing machine, and a pre-sorting conveying belt is arranged above the mixed waste conveying belt. A plurality of sorting scraping rods are installed on the outer side of the pre-sorting conveying belt, and a screened material removing plate is arranged at the top end of the pre-sorting conveying belt. Mixed waste is conveyed to the building waste winnowing machine through the mixed waste conveying belt, the pre-sorting conveying belt drives the sorting scraping rods and the mixed waste conveying belt to move synchronously, and large-size light materials and part of light materials adhering to cement in the mixed waste can be removed by means of mixed movement of the sorting scraping rods. Furthermore, the light materials on the sorting scraping rod can be removed through cooperation of a screened material removing plate and a receding through groove, the sorted waste materials are discharged to the side face of the equipment, and the sorting pressure of the building waste winnowing machine on the light materials can be reduced through cooperation of all the components.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of construction waste treatment, and in particular relates to a construction waste sorting device. Background Art

[0002] After screening, the construction waste can be reused after recycling and processing. The construction waste includes concrete blocks, sand and gravel, wooden boards, cardboard, plastic bags, woven bags and other waste materials. A construction waste sorting device is needed to separate light materials such as plastic bags and woven bags from heavy materials such as concrete blocks and sand and gravel blocks. The currently used construction waste air separator drives the waste to jump in the processing bin through rollers, and uses the large air volume of the fan to blow the light materials out from the side discharge port. However, in the actual production process, dry plastic bags and woven bags can be discharged after moving with the wind, but a large amount of soil and concrete blocks will be attached to the surface of the plastic bags and woven bags wetted by water, resulting in an increase in the gravity of the plastic bags and woven bags. The plastic bags and woven bags are difficult to be discharged under the action of the wind. It is necessary to greatly increase the delivery capacity of the fan to achieve the effect of cleaning the wet plastic bags and woven bags, and the sorting effect of large-volume wet light materials is still not good, and the sorting effect of construction waste still needs to be improved. Utility Model Content

[0003] The utility model provides a construction waste sorting device, which comprises:

[0004] The utility model provides the following technical solutions: a construction waste sorting device, comprising a construction waste air classifier and a mixed waste conveyor belt, the mixed waste conveyor belt is arranged on one side of the construction waste air classifier, a pre-sorting conveyor belt is arranged above the mixed waste conveyor belt, a plurality of sorting scraper bars are installed on the outer side of the pre-sorting conveyor belt, a screening material removal plate is arranged at the top of the pre-sorting conveyor belt, and a making way slot for making way for the sorting scraper bar is provided on the screening material removal plate.

[0005] Among them, a protective support frame is installed on the outside of the mixed waste conveyor belt, the top height of the protective support frame is lower than the top height of the pre-sorting conveyor belt, and the inner walls on both sides of the protective support frame are fixedly connected with limited gathering arc plates.

[0006] Wherein, a waste intercepting plate is fixedly connected to the inner wall of the protective support frame, one side of the waste intercepting plate extends under the pre-sorting conveyor belt, and the waste intercepting plate does not contact the sorting scraper rod.

[0007] Wherein, the side wall of the pre-sorting conveyor belt is fixedly connected with a support frame, and the support frame passes through the protective support frame and bends downward.

[0008] Among them, a conveyor belt limiting plate for supporting and limiting the pre-sorting conveyor belt is fixedly connected between the support frames.

[0009] Wherein, a connecting and fixing rod is fixedly connected to the bottom end of the screening material removal plate, and the other end of the connecting and fixing rod is fixedly connected to the protective support frame.

[0010] The beneficial effects of the utility model are as follows: the mixed waste is conveyed from the mixed waste conveyor belt to the construction waste air separator, the pre-sorting conveyor belt drives the sorting scraper rod to move synchronously with the mixed waste conveyor belt, and the large volume of light materials and some light materials adhering to cement in the mixed waste can be removed by means of the mixed movement of multiple sorting scraper rods, and the light materials on the sorting scraper rod can be removed by means of the cooperation of the screening material removal plate and the give-way slot, and the sorted waste can be discharged to the side of the equipment, and the cooperation of various components can replace the manual sorting of large volume of light materials, reduce the sorting pressure of the construction waste air separator on light materials, and improve the overall waste sorting effect of the device.

[0011] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the structure of the utility model;

[0013] Figure 2 It is a schematic diagram of the structure of the pre-sorting belt and the screening material removal plate in the utility model;

[0014] Figure 3 It is a structural schematic diagram of the conveyor belt limiting plate in the utility model.

[0015] In the figure: 1. Construction waste air separator; 2. Mixed waste conveyor belt; 21. Protective support frame; 22. Limiting and gathering arc plate; 23. Waste intercepting plate; 3. Pre-sorting conveyor belt; 31. Sorting scraper rod; 32. Support frame; 33. Conveyor belt limiting plate; 4. Screening material removal plate; 41. Make way slot; 42. Connecting fixing rod. DETAILED DESCRIPTION

[0016] See also Figure 1-Figure 3 The utility model provides the following technical solutions: a construction waste sorting device, comprising a construction waste air classifier 1 and a mixed waste conveyor belt 2, the mixed waste conveyor belt 2 is arranged on one side of the construction waste air classifier 1, a pre-sorting conveyor belt 3 is arranged above the mixed waste conveyor belt 2, a plurality of sorting scraper bars 31 are installed on the outer side of the pre-sorting conveyor belt 3, a screening material removal plate 4 is arranged at the top of the pre-sorting conveyor belt 3, and a making way slot 41 is provided on the screening material removal plate 4 for making way for the sorting scraper bar 31.

[0017] In this implementation scheme: the staff adds the mixed waste to the top of the mixed waste conveyor belt 2, and the mixed waste conveyor belt 2 conveys the mixed waste to the construction waste air separator 1. In the process of the mixed waste conveyor belt 2 conveying the mixed waste, the pre-sorting conveyor belt 3 drives the sorting scraper 31 to move synchronously with the mixed waste conveyor belt 2, and the sorting scraper 31 is moved in the mixed waste. After the large volume of light materials and the light materials adhering to the cement come into contact with the sorting scraper 31, they are suspended by the end of the sorting scraper 31, and the light materials follow the movement of the sorting scraper 31. With the help of the mixed movement of multiple sorting scraper bars 31, the large volume of light materials and some of the light materials adhering to the cement in the mixed waste can be removed. As the sorting scraper bar 31 drives the movement of the mixed waste, the sorting scraper The rod 31 enters the clearance groove 41, and the waste is blocked by the screening material removal plate 4. When the sorting scraper rod 31 further moves to the arc plate of the screening material removal plate 4, the screening material removal plate 4 cooperates with the clearance groove 41 to remove the light material on the sorting scraper rod 31, and the sorted waste is discharged to the side of the equipment. The pre-sorting conveyor belt 3 and the screening material removal plate 4 cooperate to reduce the sorting pressure of the construction waste air separator 1 on the light material, and improve the overall waste sorting effect of the device. The surface of the sorting scraper rod 31 is provided with a rough surface and a dent to increase the friction between the sorting scraper rod 31 and the light material. The sorting scraper rod 31 is rubbed and impacted by stones and the like in the waste during use, and the roughness of the outer wall of the sorting scraper rod 31 is further increased.

[0018] A protective support frame 21 is installed on the outside of the mixed waste conveyor belt 2. The top height of the protective support frame 21 is lower than the top height of the pre-sorting conveyor belt 3. The inner walls on both sides of the protective support frame 21 are fixedly connected to the limited gathering arc plates 22. By setting the protective support frame 21, the mixed waste conveyor belt 2 can be supported, and the mixed waste conveyor belt 2 and the waste can be intercepted and protected. The top of the pre-sorting conveyor belt 3 is higher, so that the waste can fall down along the screening material removal plate 4 under the action of gravity, avoiding the waste being intercepted by the protective support frame 21 and making the waste unable to be removed.

[0019] A waste intercepting plate 23 is fixedly connected to the inner wall of the protective support frame 21, and one side of the waste intercepting plate 23 extends under the pre-sorting conveyor belt 3, and the waste intercepting plate 23 does not contact the sorting scraper rod 31; by setting the waste intercepting plate 23, the waste transported on the mixed waste conveyor belt 2 can be intercepted to prevent the waste from entering the pre-sorting conveyor belt 3 and causing a malfunction of the pre-sorting conveyor belt 3. At the same time, the waste intercepting plate 23 does not contact the sorting scraper rod 31, which can prevent the movement of the pre-sorting conveyor belt 3 and the sorting scraper rod 31 from being hindered by the waste intercepting plate 23.

[0020] A support frame 32 is fixedly connected to the side wall of the pre-sorting conveyor belt 3, and the support frame 32 passes through the protective support frame 21 and bends downward; by setting the support frame 32, the pre-sorting conveyor belt 3 and the conveyor belt limit plate 33 can be supported, so that the pre-sorting conveyor belt 3 can be stably located above the mixed waste conveyor belt 2, so that the sorting scraper 31 can sort the waste, and the bottom end of the support frame 32 extends downward and is connected to the support plate at the bottom of the construction waste air separator 1.

[0021] A conveyor belt limiting plate 33 for supporting and limiting the pre-sorting conveyor belt 3 is fixedly connected between the support frames 32; by setting the conveyor belt limiting plate 33, the belt body of the pre-sorting conveyor belt 3 can be supported, so that the pre-sorting conveyor belt 3 can provide hard support for the sorting scraper rod 31, thereby preventing the sorting scraper rod 31 from being squeezed by stones and then squeezing the pre-sorting conveyor belt 3.

[0022] A connecting and fixing rod 42 is fixedly connected to the bottom end of the screening material removal plate 4, and the other end of the connecting and fixing rod 42 is fixedly connected to the protective support frame 21; by setting the connecting and fixing rod 42, the screening material removal plate 4 can be supported and fixed, and the stable position of the screening material removal plate 4 is maintained, so that the position of the giving way slot 41 corresponds to the movement trajectory of the sorting scraper rod 31.

[0023] The working principle and use process of the utility model are as follows: the staff adds the mixed waste to the top of the mixed waste conveyor belt 2, and the mixed waste conveyor belt 2 conveys the mixed waste to the construction waste air separator 1. In the process of the mixed waste conveyor belt 2 conveying the mixed waste, the pre-sorting conveyor belt 3 drives the sorting scraper 31 to move synchronously with the mixed waste conveyor belt 2, and the sorting scraper 31 is moved in the mixed waste, and the large volume of light materials and light materials adhering to cement are suspended from the end of the sorting scraper 31 after contacting the sorting scraper 31. The light materials follow the movement of the sorting scraper rod 31. With the help of the mixed movement of multiple sorting scraper rods 31, the large volume of light materials and some light materials adhering to cement in the mixed waste can be removed. As the sorting scraper rod 31 drives the movement of the mixed waste, the sorting scraper rod 31 enters the give way slot 41, and the waste is blocked by the screening material removal plate 4. When the sorting scraper rod 31 further moves to the arc plate of the screening material removal plate 4, the screening material removal plate 4 removes the light materials on the sorting scraper rod 31 and discharges the sorted waste to the side of the equipment.

Claims

1. A construction waste sorting device, comprising a construction waste air separator (1) and a mixed waste conveyor belt (2), characterized in that: The mixed waste conveyor belt (2) is arranged on one side of the construction waste air separator (1); a pre-sorting conveyor belt (3) is arranged above the mixed waste conveyor belt (2); a plurality of sorting scraper bars (31) are installed on the outer side of the pre-sorting conveyor belt (3); a screening material removal plate (4) is arranged at the top of the pre-sorting conveyor belt (3); and a clearance groove (41) is provided on the screening material removal plate (4) for making way for the sorting scraper bars (31).

2. A construction waste sorting device according to claim 1, characterized in that: A protective support frame (21) is installed on the outside of the mixed waste conveyor belt (2), the top height of the protective support frame (21) is lower than the top height of the pre-sorting conveyor belt (3), and the inner walls on both sides of the protective support frame (21) are fixedly connected to limited position gathering arc plates (22).

3. A construction waste sorting device according to claim 2, characterized in that: A waste interception plate (23) is fixedly connected to the inner wall of the protection support frame (21), one side of the waste interception plate (23) extends under the pre-sorting conveyor belt (3), and the waste interception plate (23) does not contact the sorting scraper (31).

4. A construction waste sorting device according to claim 3, characterized in that: A support frame (32) is fixedly connected to the side wall of the pre-sorting conveyor belt (3), and the support frame (32) passes through the protective support frame (21) and bends downward.

5. A construction waste sorting device according to claim 4, characterized in that: A conveyor belt limiting plate (33) for supporting and limiting the pre-sorting conveyor belt (3) is fixedly connected between the support frames (32).

6. A construction waste sorting device according to claim 5, characterized in that: A connecting and fixing rod (42) is fixedly connected to the bottom end of the screening material removal plate (4), and the other end of the connecting and fixing rod (42) is fixedly connected to the protective support frame (21).