Water conservancy construction positioning device

By designing a water conservancy construction positioning device including a fixed plate, electric telescopic legs and a hydraulic cylinder, the problem of inconvenient use of docked pipes in the existing technology is solved, and the simultaneous positioning support and fast and accurate docking of two pipes are achieved, improving the efficiency of the water conservancy construction positioning device. Construction efficiency.

CN221871752UActive Publication Date: 2024-10-22HENAN WUFANG ROAD & BRIDGE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420386484.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2024-10-22
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

The existing water conservancy construction positioning device is inconvenient to use when connecting pipelines. It cannot effectively position and support two pipelines at the same time. It is also difficult to accurately move to the required position during initial installation and requires a lot of effort to adjust.

Method used

A water conservancy construction positioning device including a fixed plate, electric telescopic legs, a workbench and a positioning mechanism is designed. The lifting, rotation and positioning mechanism of the workbench are adjusted through structures such as hydraulic cylinders and spiral plates. The transmitter and receiver are used Determines pipeline axis alignment and emits a beep to simplify operation.

Benefits of technology

It achieves positioning support and position adjustment of two pipelines at the same time, quickly completes pipeline docking, and improves construction efficiency and accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221871752U_ABST
    Figure CN221871752U_ABST
Patent Text Reader

Abstract

A water conservancy construction positioning device effectively solves the problem that a positioning device is inconvenient to use during pipeline butt joint. Comprising a fixing plate, a plurality of electric telescopic legs are arranged at the bottom of the fixing plate, a workbench is arranged above the fixing plate and can ascend, descend and rotate relative to the fixing plate, positioning mechanisms are arranged on the two sides above the workbench, each positioning mechanism comprises a bottom plate, the bottom plates are connected with the workbench through first hydraulic cylinders in a telescopic mode, and a support is arranged above the bottom plates in a sliding mode; a lower positioning ring is fixed on the bracket, and an upper positioning ring is detachably connected above the lower positioning ring; the pipeline positioning and supporting device is simple and ingenious in structure and convenient to use, two pipelines can be positioned and supported at the same time and can be adjusted respectively, the pipelines can be quickly positioned before butt joint, the construction progress is accelerated, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water conservancy construction, in particular to a water conservancy construction positioning device. Background Art

[0002] During the construction of water conservancy projects, it is often necessary to lay pipes, and the docking of pipes has high requirements. The two ends of the docked pipes need to be completely fitted together to ensure the accuracy of the position. Only by completing the docking in this way can the stability of the subsequent use of the pipelines be guaranteed, and defects such as leakage and disconnection can be avoided, the maintenance frequency can be reduced, and the stable operation of the water conservancy project can be ensured.

[0003] In the prior art, when docking pipes, pipe positioning devices are used, which have the following defects when used: some can only position and support one pipe, and two sets of devices are required to complete the docking construction of the two pipes; although some can complete the positioning and support of two pipes at the same time, the two positioning mechanisms move synchronously and always remain on the same axis. However, it is not easy to directly move the pipe to the desired position during the initial installation, but it needs to be adjusted before it can reach the desired position. Therefore, this type of positioning and supporting device requires a lot of effort to fix the pipe on the positioning mechanism when used, which is inconvenient to operate. Utility Model Content

[0004] In order to overcome the defects of the prior art, the utility model provides a water conservancy construction positioning device, which effectively solves the problem that the positioning device is inconvenient to use when pipes are butt-jointed.

[0005] The technical solution to the technical problem is: a water conservancy construction positioning device, including a fixed plate, a plurality of electric telescopic legs are provided at the bottom of the fixed plate, a workbench is provided above the fixed plate, the workbench can be lifted and rotated relative to the fixed plate, positioning mechanisms are provided on both sides above the workbench, the positioning mechanism includes a base plate, the base plate and the workbench are telescopically connected via a first hydraulic cylinder, a bracket is slidably provided above the base plate, a lower positioning ring is fixed on the bracket, and an upper positioning ring is detachably connected above the lower positioning ring.

[0006] Preferably, the bottom of the electric telescopic leg is a sharp-edged structure.

[0007] Preferably, an inner ring is provided above the fixed plate, and an outer ring is provided at the bottom of the workbench and is sleeved on the outside of the inner ring, forming a structure in which the workbench and the fixed plate can rotate relative to each other. A second hydraulic cylinder is provided inside the inner ring, and the second hydraulic cylinder connects the fixed plate and the workbench, forming a structure in which the workbench and the fixed plate can be raised and lowered.

[0008] Preferably, a plurality of levers are evenly extended from the outside of the outer ring, a rotating shaft is rotatably arranged above the fixed plate, a spiral plate is arranged on the rotating shaft, a handwheel is arranged at the end of the rotating shaft, and the rotation of the rotating shaft drives the spiral plate to rotate, so that the outer ring rotates and thus drives the workbench to rotate.

[0009] Preferably, a slide groove is provided above the bottom plate, and the bottom of the bracket slides in the slide groove.

[0010] Preferably, a transmitter is provided on a bracket located on one side of the workbench, and a receiver is provided on a bracket located on the other side of the workbench, and the positions are adjusted into place when the transmitter and the receiver are aligned.

[0011] Preferably, the lower positioning ring and the upper positioning ring are both semicircular structures, and the lower positioning ring and the upper positioning ring are fixedly connected by screws.

[0012] The utility model has a simple and ingenious structure, is easy to use, can position and support two pipes at the same time, and can be adjusted separately, can quickly complete the positioning of the pipes before docking, speed up the construction progress, and improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a structural schematic diagram of the utility model.

[0014] Figure 2 It is a front sectional structural schematic diagram of the utility model.

[0015] Figure 3 It is a side structural schematic diagram of the utility model.

[0016] Figure 4 This utility model Figure 2 Schematic diagram of the cross-sectional structure of AA. DETAILED DESCRIPTION

[0017] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings.

[0018] Depend on Figures 1 to 4 It can be seen that a water conservancy construction positioning device includes a fixed plate 1, a plurality of electric telescopic legs 2 are arranged at the bottom of the fixed plate 1, the bottom of the electric telescopic legs 2 is a pointed ridge structure, which is convenient for inserting into the ground for positioning, a workbench 3 is arranged above the fixed plate 1, the workbench 3 can be lifted and rotated relative to the fixed plate 1, and positioning mechanisms are arranged on both sides above the workbench 3, the positioning mechanism includes a base plate 4, the base plate 4 and the workbench 3 are telescopically connected via a first hydraulic cylinder 5, a bracket 6 is slidably arranged above the base plate 4, a lower positioning ring 7 is fixed on the bracket 6, an upper positioning ring 8 is detachably connected above the lower positioning ring 7, the lower positioning ring 7 and the upper positioning ring 8 are both semicircular structures, and the lower positioning ring 7 and the upper positioning ring 8 are fixedly connected via screws.

[0019] When the utility model is used in a specific way,

[0020] Insert the electric telescopic leg 2 into the ground to fix it, and adjust its length so that the fixing plate 1 is in a horizontal state and suitable for positioning and supporting the pipeline, then rotate the workbench 3 to align it with the pipeline axis, and then adjust the positions of the two positioning mechanisms to fix the two pipelines, and then adjust the positions of the two positioning mechanisms again to make the two pipeline axes coincide, so that the pipelines can be docked.

[0021] When the positioning mechanism is adjusted, the first hydraulic cylinder 5 is used to adjust its height, and the bracket 6 slides on the bottom plate 4 to adjust the horizontal position so that it can be quickly aligned with the pipeline, thereby completing the fixation of the pipeline.

[0022] An inner ring 9 is provided above the fixed plate 1, and an outer ring 10 is provided at the bottom of the workbench 3 and is sleeved on the outside of the inner ring 9, forming a structure in which the workbench 3 and the fixed plate 1 can rotate relative to each other. A second hydraulic cylinder 11 is provided inside the inner ring 9, and the second hydraulic cylinder 11 connects the fixed plate 1 and the workbench 3, forming a structure in which the workbench 3 and the fixed plate 1 can be raised and lowered.

[0023] A plurality of levers 12 are evenly extended from the outside of the outer ring 10, a rotating shaft 13 is rotatably arranged above the fixed plate 1, a spiral plate 14 is arranged on the rotating shaft 13, and a handwheel 15 is arranged at the end of the rotating shaft 13. The rotation of the rotating shaft 13 drives the spiral plate 14 to rotate, so that the outer ring 10 rotates and thus drives the workbench 3 to rotate, and the lever 12 is inserted into the gap of the spiral plate 14. After the spiral plate 14 rotates, it pushes the lever 12 to rotate, so that the outer ring 10 rotates. After the workbench 3 is raised or lowered, the lever 12 can still be inserted into the gap of the spiral plate 14, so that the rotation of the rotating shaft 13 can control the rotation of the workbench 3.

[0024] A slide groove 16 is provided above the base plate 4, and the bottom of the bracket 6 slides in the slide groove 16. A lead screw 19 is provided above the base plate 4, and the bracket 6 is threadedly connected to the lead screw 19. The lead screw 19 is driven by a motor 20, and the motor 20 drives the lead screw 19 to rotate, thereby driving the bracket 6 to slide horizontally in the slide groove 16.

[0025] A transmitter 17 is provided on the bracket 6 located on one side of the workbench 3, and a receiver 18 is provided on the bracket 6 located on the other side of the workbench 3. When the transmitter 17 and the receiver 18 are aligned, the positions are adjusted into place. The transmitter 17 and the receiver 18 are used to determine the relative positions of the two positioning mechanisms, and a prompt sound is issued when they coincide on the same axis, so that the construction personnel can understand this information and then complete the docking construction.

[0026] Compared with the prior art, the utility model has the following beneficial effects: it can position and support two pipelines at the same time, and adjust the positions of the two pipelines respectively, so as to quickly complete the positioning of the pipelines, thereby making the pipeline docking more accurate and efficient, and improving the construction efficiency.

Claims

1. A water conservancy construction positioning device, It is characterized in that The invention comprises a fixed plate (1), a plurality of electrically-operated telescopic legs (2) are arranged at the bottom of the fixed plate (1), a workbench (3) is arranged above the fixed plate (1), the workbench (3) can be lifted and lowered and rotated relative to the fixed plate (1), positioning mechanisms are arranged on both sides above the workbench (3), the positioning mechanisms comprise a bottom plate (4), the bottom plate (4) and the workbench (3) are telescopically connected via a first hydraulic cylinder (5), a bracket (6) is slidably arranged above the bottom plate (4), a lower positioning ring (7) is fixed on the bracket (6), and an upper positioning ring (8) is detachably connected above the lower positioning ring (7).

2. A water conservancy construction positioning device according to claim 1, It is characterized in that The bottom of the electric telescopic leg (2) is a sharp-edged structure.

3. A water conservancy construction positioning device according to claim 1, It is characterized in that An inner ring (9) is provided above the fixed plate (1), and an outer ring (10) is provided at the bottom of the workbench (3) and is sleeved on the outside of the inner ring (9), forming a structure in which the workbench (3) and the fixed plate (1) can rotate relative to each other. A second hydraulic cylinder (11) is provided inside the inner ring (9), and the second hydraulic cylinder (11) connects the fixed plate (1) and the workbench (3), forming a structure in which the workbench (3) and the fixed plate (1) can be raised and lowered.

4. A water conservancy construction positioning device according to claim 3, It is characterized in that A plurality of levers (12) are uniformly extended from the outside of the outer ring (10); a rotating shaft (13) is rotatably arranged above the fixed plate (1); a spiral plate (14) is arranged on the rotating shaft (13); a hand wheel (15) is arranged at the end of the rotating shaft (13); the rotating shaft (13) rotates to drive the spiral plate (14) to rotate, so that the outer ring (10) rotates, thereby driving the workbench (3) to rotate.

5. A water conservancy construction positioning device according to claim 1, It is characterized in that A slide groove (16) is provided above the bottom plate (4), and the bottom of the bracket (6) slides in the slide groove (16).

6. A water conservancy construction positioning device according to claim 1, It is characterized in that A transmitter (17) is provided on the bracket (6) located on one side of the workbench (3), and a receiver (18) is provided on the bracket (6) located on the other side of the workbench (3). When the transmitter (17) and the receiver (18) are aligned, the positions are adjusted into place.

7. A water conservancy construction positioning device according to claim 1, It is characterized in that The lower positioning ring (7) and the upper positioning ring (8) are both semicircular structures, and the lower positioning ring (7) and the upper positioning ring (8) are fixedly connected via screws.