Prestressed concrete pipe pile production residual slurry recovery device
By designing a device that automatically adds water to dilute and retarder to delay solidification in the production of prestressed concrete pipe piles, the problem of easy solidification of residual slurry in the existing technology is solved, automatic recovery and processing of residual slurry is realized, and production efficiency is improved.
Patent Information
- Application Number
- CN202420218211.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-30
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-01-30
AI Technical Summary
The existing slurry recovery device for prestressed concrete pipe pile production lacks a slow-solidification function, which causes the residual slurry to easily solidify after being stored for a long time, affecting the recovery efficiency.
A device is designed that includes a recovery tank, a delivery pipe, a top cover and a retarder adding component. It automatically adds water to dilute and retarder through a timer switch to delay the solidification time. It uses coolant to reduce the temperature and combines the scraping component to prevent clogging. Automated slurry recovery and treatment.
It effectively avoids the hardening and solidification of residual slurry, ensures the continuous recovery and treatment of residual slurry, improves production efficiency, and prevents equipment clogging problems.
Smart Images

Figure CN221872484U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete pipe pile production, in particular to a residual slurry recovery device for prestressed concrete pipe pile production. Background Art
[0002] Prestressed concrete pipe piles are a type of prefabricated concrete pile that reflects the progress of contemporary concrete technology and the high-tech level of concrete products. When making prestressed concrete pipe piles, slurry is usually poured into the mold, and it solidifies after being poured. In order to reduce costs, the remaining slurry will be recycled, so a residual slurry recycling device will be used.
[0003] After searching, the patent with announcement number CN218222760U discloses a device for recovering residual slurry in the production of prestressed concrete pipe piles, and its content records "including a box body, the inner wall of the box body is rotatably connected to a first rotating shaft, the outer wall of the first rotating shaft is fixedly connected to multiple groups of symmetrically distributed first crushing knives, a second rotating shaft rotatably connected to the inner wall of the box body is arranged below the first rotating shaft, the outer wall of the second rotating shaft is fixedly connected to multiple groups of symmetrically distributed second crushing knives, the output shaft of the second motor rotates to drive the second rotating shaft to rotate and then drive the second crushing knives to rotate, and at the same time, the rotation of the second rotating shaft drives the first crushing knife to rotate, and the residual slurry is poured into the box body, and the crushed residual slurry falls on the screen..." From the above, it can be seen that the residual slurry recovery device of the patent does not have a slow solidification function, and the residual slurry is prone to solidification when stored for a long time, and there are certain shortcomings. Utility Model Content
[0004] The utility model aims to solve the problems existing in the prior art or related technologies.
[0005] To this end, the technical solution adopted by the utility model is: a prestressed concrete pipe pile production residual slurry recovery device, including a recovery tank, a delivery pipe, a top cover and a retarder adding component, the front end of the recovery tank is provided with a timing switch and a controller, the delivery pipe is arranged on the left side of the recovery tank, the delivery pipe is provided with a first electric valve, the top cover is arranged on the top of the recovery tank, and the retarder adding component includes a vertical pipe arranged at the top end of the top cover, a second electric valve arranged on the vertical pipe and a retarder barrel arranged at the top end of the vertical pipe.
[0006] Preferably, a support rod and a discharge pipe are provided at the bottom of the recovery tank.
[0007] Preferably, an injection pipe and a discharge pipe are sequentially arranged on the rear side of the recovery tank, and a cooling chamber is arranged inside the recovery tank, and the cooling chamber is communicated with the injection pipe and the discharge pipe.
[0008] Preferably, it further comprises a scraping assembly, which comprises a cylinder arranged on the discharge pipe, a round tube arranged at the bottom end of the cylinder and an inclined surface arranged on the inner wall of the round tube.
[0009] Preferably, the first electric valve is electrically connected to the timing switch.
[0010] Preferably, a feed hopper is provided at the top end of the top cover.
[0011] Preferably, it further comprises a stirring assembly, wherein the stirring assembly comprises a reducer arranged at the top end of the top cover, a driving motor arranged at the top end of the reducer and a spiral blade arranged at the bottom end of the reducer.
[0012] Preferably, the controller is electrically connected to the cylinder, the drive motor and the second electric valve.
[0013] By adopting the above technical scheme, the beneficial effects achieved by the utility model are as follows: the delivery pipe arranged in the utility model can be connected to the tap water pipe, and the timing switch arranged can regularly connect the power supply of the first electric valve, the first electric valve connected with the power supply can automatically open the delivery pipe, and after releasing the tap water for a certain period of time, the timing switch can automatically disconnect the power supply of the first electric valve, so as to achieve the effect of automatic and regular water dilution to avoid the hardening of the residual slurry, and at the same time, the controller arranged can control the second electric valve to open, and the retarder in the retarder barrel can be automatically added after opening, that is, the solidification time of the residual slurry can be delayed by adding the retarder, and then the injection pipe arranged can add the coolant, and the added coolant can reduce the temperature of the residual slurry and also delay the solidification time of the residual slurry, and then the cylinder of the scraping assembly arranged can be retractable, and the retractable cylinder can scrape the inner wall of the discharge pipe through the circular pipe to avoid the residual slurry solidified on the inner wall of the discharge pipe clogging the discharge pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of the utility model from one perspective;
[0015] Figure 2 It is a structural schematic diagram of another perspective of the utility model;
[0016] Figure 3 It is a cross-sectional schematic diagram of the recovery tank of the utility model;
[0017] Figure 4 This is a schematic diagram of the structure of the scraping component of the utility model;
[0018] Figure 5 It is a structural schematic diagram of the top cover and the stirring assembly of the utility model.
[0019] Reference numerals:
[0020] 100, recovery tank; 110, support rod; 120, discharge pipe; 130, timer switch; 140, controller; 150, injection pipe; 160, discharge pipe; 170, cooling chamber;
[0021] 200, scraping assembly; 210, cylinder; 220, round tube; 230, inclined plane;
[0022] 300, delivery pipe; 310, first electric valve;
[0023] 400, top cover; 410, feed hopper;
[0024] 500, stirring assembly; 510, reducer; 520, driving motor; 530, spiral blade;
[0025] 600. Retarder adding assembly; 610. Vertical pipe; 620. Second electric valve; 630. Retarder barrel. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model is further described in detail below in combination with specific implementation methods and with reference to the accompanying drawings. It should be noted that the embodiments of the utility model and the features in the embodiments can be combined with each other without conflict.
[0027] The following describes some embodiments of the utility model in conjunction with the accompanying drawings to provide a device for recovering residual slurry from the production of prestressed concrete pipe piles.
[0028] Embodiment 1:
[0029] Reference Figure 1 , Figure 2 Figure 3 and Figure 5 , which is the first embodiment of the utility model, provides a prestressed concrete pipe pile production residual slurry recovery device, including a recovery tank 100, a delivery pipe 300, a top cover 400, a stirring assembly 500 and a retarder adding assembly 600.
[0030] Specifically, a timing switch 130 and a controller 140 are provided at the front end of the recovery tank 100, a support rod 110 and a discharge pipe 120 are provided at the bottom of the recovery tank 100, an injection pipe 150 and a discharge pipe 160 are provided in sequence at the rear side of the recovery tank 100, and a cooling chamber 170 is provided inside the recovery tank 100. The cooling chamber 170 is connected with the injection pipe 150 and the discharge pipe 160. Coolant can be added through the injection pipe 150, and the added coolant will enter the cooling chamber 170, which can reduce the temperature of the residual slurry and delay the solidification time of the residual slurry.
[0031] Specifically, the delivery pipe 300 is arranged on the left side of the recovery tank 100, and a first electric valve 310 is arranged on the delivery pipe 300. The first electric valve 310 is electrically connected to the timing switch 130. The delivery pipe 300 can be connected to the tap water pipe in advance, and then the interval time is set through the timing switch 130. When the time is reached, the timing switch 130 can connect the power supply of the first electric valve 310. The first electric valve 310 connected with the power supply will automatically open the delivery pipe 300. After releasing the tap water for a certain period of time, the timing switch 130 can automatically disconnect the power supply of the first electric valve 310, so as to achieve the effect of automatic regular water dilution to avoid the hardening of the residual slurry.
[0032] Specifically, the top cover 400 is disposed on the top of the recovery tank 100 , and a feed hopper 410 is disposed on the top of the top cover 400 , through which the residual slurry can be put.
[0033] Specifically, the stirring assembly 500 includes a reducer 510 arranged at the top of the top cover 400, a drive motor 520 arranged at the top of the reducer 510, and a spiral blade 530 arranged at the bottom of the reducer 510. At the same time, the controller 140 can control the operation of the drive motor 520. The operating drive motor 520 can drive the spiral blade 530 to stir the residual slurry through the reducer 510 so as to dilute it with water or add a retarder for mixing.
[0034] Specifically, the retarder adding assembly 600 includes a vertical pipe 610 arranged at the top of the top cover 400, a second electric valve 620 arranged on the vertical pipe 610, and a retarder barrel 630 arranged at the top of the vertical pipe 610. The retarder is added to the retarder barrel 630 in advance, and the second electric valve 620 is controlled to open. After opening, the retarder in the retarder barrel 630 enters the recovery tank 100 through the vertical pipe 610, and the solidification time of the residual slurry can be delayed by adding the retarder.
[0035] Embodiment 2:
[0036] Reference Figure 1 and Figure 4 , which is the second embodiment of the utility model, and is different from the first embodiment in that it also includes a scraping assembly 200, the scraping assembly 200 includes a cylinder 210 arranged on the discharge pipe 120, a circular tube 220 arranged at the bottom end of the cylinder 210 and an inclined surface 230 arranged on the inner wall of the circular tube 220, and the cylinder 210 can be controlled to be extended and retracted. The retracted cylinder 210 can scrape the inner wall of the discharge pipe 120 through the circular tube 220 to prevent the solidified residual slurry on the inner wall of the discharge pipe 120 from clogging the discharge pipe 120.
[0037] It should be noted that the controller 140 is electrically connected to the cylinder 210 , the driving motor 520 and the second electric valve 620 , and the controller 140 can control the cylinder 210 , the driving motor 520 and the second electric valve 620 .
[0038] The working principle and use process of the utility model are as follows: when in use, the delivery pipe 300 can be connected to the tap water pipe, and then the interval time can be set through the timer switch 130. When the time is reached, the timer switch 130 can connect the power supply of the first electric valve 310, and the first electric valve 310 connected with the power supply will automatically open the delivery pipe 300. After releasing the tap water for a certain period of time, the timer switch 130 can automatically disconnect the power supply of the first electric valve 310. At the same time, the controller 140 can control the driving motor 520 to operate. The operating driving motor 520 can drive the spiral blade 530 to stir the residual slurry through the reducer 510, so as to achieve automatic and regular water dilution. The effect is achieved to prevent the residual slurry from hardening, and then the second electric valve 620 can be controlled to open through the controller 140. After opening, the retarder in the retarder barrel 630 enters the recovery tank 100 through the vertical pipe 610, and the solidification time of the residual slurry can be delayed by adding the retarder. After that, the coolant can be added through the injection pipe 150, and the added coolant will enter the cooling chamber 170, which can reduce the temperature of the residual slurry and delay the solidification time of the residual slurry. Finally, the cylinder 210 can be controlled to be extended and retracted, and the extended cylinder 210 can scrape the inner wall of the discharge pipe 120 through the circular tube 220 to prevent the residual slurry solidified on the inner wall of the discharge pipe 120 from clogging the discharge pipe 120.
[0039] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and purpose of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
Claims
1. A device for recovering excess slurry from the production of prestressed concrete pipe piles. It is characterized in that include: A recovery tank (100), wherein a timing switch (130) and a controller (140) are provided at the front end of the recovery tank (100); A delivery pipe (300), wherein the delivery pipe (300) is arranged on the left side of the recovery tank (100), and a first electric valve (310) is arranged on the delivery pipe (300); A top cover (400), wherein the top cover (400) is arranged on the top of the recovery tank (100); The retarder adding assembly (600) comprises a vertical pipe (610) arranged at the top of the top cover (400), a second electric valve (620) arranged on the vertical pipe (610), and a retarder barrel (630) arranged at the top of the vertical pipe (610).
2. A prestressed concrete pipe pile production residual slurry recovery device according to claim 1, It is characterized in that A support rod (110) and a discharge pipe (120) are provided at the bottom of the recovery tank (100).
3. A prestressed concrete pipe pile production residual slurry recovery device according to claim 2, It is characterized in that An injection pipe (150) and a discharge pipe (160) are sequentially arranged on the rear side of the recovery tank (100), and a cooling chamber (170) is arranged inside the recovery tank (100), wherein the cooling chamber (170) is communicated with the injection pipe (150) and the discharge pipe (160).
4. A prestressed concrete pipe pile production residual slurry recovery device according to claim 3, It is characterized in that It also includes a scraping assembly (200), which includes a cylinder (210) arranged on the discharge pipe (120), a round tube (220) arranged at the bottom end of the cylinder (210), and an inclined surface (230) arranged on the inner wall of the round tube (220).
5. A prestressed concrete pipe pile production residual slurry recovery device according to claim 4, It is characterized in that The first electric valve (310) is electrically connected to the timing switch (130).
6. A prestressed concrete pipe pile production residual slurry recovery device according to claim 5, It is characterized in that A feed hopper (410) is provided at the top end of the top cover (400).
7. A prestressed concrete pipe pile production residual slurry recovery device according to claim 6, It is characterized in that It also includes a stirring assembly (500), wherein the stirring assembly (500) includes a reducer (510) arranged at the top end of the top cover (400), a driving motor (520) arranged at the top end of the reducer (510), and a spiral blade (530) arranged at the bottom end of the reducer (510).
8. A prestressed concrete pipe pile production residual slurry recovery device according to claim 7, It is characterized in that The controller (140) is electrically connected to the cylinder (210), the drive motor (520) and the second electric valve (620).