Hoisting device for steel structure factory building construction
By designing a lifting device for steel structure factory construction that includes a clamping structure and a spring, the problem of low safety in lifting tubular building materials in the existing technology is solved, an efficient and safe lifting process is achieved, and the operation process is simplified. .
Patent Information
- Application Number
- CN202420982085.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-08
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2034-05-08
AI Technical Summary
The existing hoisting devices used in steel structure factory construction are less safe when lifting tubular building materials, there is a risk of falling, and they require manual fixation, which reduces construction efficiency.
A hoisting device including a base plate, a hoist, a support plate, a universal wheel, a clamping structure and a spring is designed. The clamping structure uses lifting tension to fix the tubular building materials, reducing the rope tying time, and automatically releasing it through the spring, simplifying operate.
It improves the safety and efficiency of the lifting process, reduces manual operations, avoids safety hazards such as rope breakage, and simplifies the operation process of lowering tubular building materials.
Smart Images

Figure CN221894545U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hoisting devices, in particular to a hoisting device for steel structure factory building construction. Background Art
[0002] Steel structure factory construction refers to the construction process of factory buildings using steel as the main structural material. Steel structure factory buildings have the advantages of light weight, high strength, good earthquake resistance, and fast construction speed, so they are widely used in the field of industrial construction. The construction process mainly includes design, drawing, material procurement, prefabrication, installation and other links, which require guidance and supervision from experienced engineers and technicians.
[0003] In the prior art, the patent application number CN220098301U discloses a hoisting device for steel structure workshop construction, including a hoisting box, two fixed plates are fixedly connected to the inner side of the hoisting box, a bidirectional motor is fixedly connected between the opposite sides of the two fixed plates, the output shafts on the left and right sides of the bidirectional motor are fixedly connected to threaded rods, the outer sides of the two threaded rods are threadedly connected to threaded blocks, the bottoms of the two threaded blocks are fixedly connected to movable push plates, the outer sides of the two movable push plates are fixedly connected to mounting blocks, the bottom of the hoisting box is movably connected to a hoisting plate, the top of the hoisting plate is fixedly connected to a positioning block, the number of the positioning blocks and the mounting blocks are both two, and the two positioning blocks are movably connected to the two mounting blocks respectively. The hoisting device for steel structure workshop construction achieves the purpose of facilitating the maintenance of the hoisting device, and it is very convenient to disassemble and assemble the hoisting device when it is damaged and needs to be inspected, and the hoisting device can be disassembled and repaired regularly.
[0004] With respect to the above scheme, there are the following technical problems: during the construction of a steel structure factory, various steel materials need to be hoisted to facilitate the construction. At this time, a hoisting device for steel structure factory construction is needed. The hoisting devices for steel structure factory construction in the prior art mostly use ropes to bundle tubular building materials when hoisting tubular building materials. However, this method has the risk of tubular building materials falling and has low safety. At the same time, the tubular building materials need to be manually fixed before they can be hoisted, which reduces work efficiency. Therefore, the hoisting devices for steel structure factory construction in the prior art have the defect of low safety when hoisting tubular building materials. Utility Model Content
[0005] The utility model aims to provide a hoisting device for steel structure factory building construction to solve the problems raised in the above background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a hoisting device for steel structure factory building construction, comprising a base plate and a winch, wherein both ends of the upper surface of the base plate are fixedly connected to a support plate, and four corners of the lower surface of the base plate are fixedly connected to a universal wheel, the winch is fixedly connected to the surface of the support plate, a rope is wound around the surface of the winch, a supporting structure is provided on the upper surface of the base plate, the rope passes around the supporting structure and is fixedly connected to a connecting ring, connecting ropes are fixedly connected to both sides of the connecting ring, and a sleeve is fixedly connected to the end of the connecting rope, a sliding block is provided inside the sleeve, a fixed frame is provided below the sleeve, the bottom end of the sliding block passes through the fixed frame and is provided with a clamping structure, a lower placement block is fixedly connected below the inside of the fixed frame, and the clamping structure clamps the tubular building material above the lower placement block, and the winch is started to reel in the rope, and the rope immediately pulls the connecting ring and the connecting rope upward through the supporting structure, and the connecting rope immediately drives the sleeve and the sliding block to move upward.
[0007] In a preferred embodiment of the present utility model, the supporting structure includes a limiting plate and a limiting roller, the upper surface of the bottom plate is fixedly connected to a supporting column, the side of the supporting column is fixedly connected to a connecting rod, the top of the supporting column and the end of the connecting rod are fixedly connected to a fixing plate, both ends of the surface of the fixing plate are fixedly connected to the lower surface of the limiting plate, the limiting roller is rotatably connected between the limiting plates, the rope passes around the surface of the limiting roller, and the rope is limited by the limiting roller.
[0008] In a preferred embodiment of the present invention, the clamping structure includes a rotating plate and an upper clamping block, the sliding block passes through the fixed frame and is slidably connected to the fixed frame, the bottom end of the sliding block is rotatably connected to the upper surface of the rotating plate, the center position of the rotating plate is fixedly connected with a rotating shaft, the rotating shaft is rotatably connected to the inner wall of the fixed frame, the lower surface of the rotating plate is rotatably connected to the upper surface of the upper clamping block, and the upper surface of the rotating plate away from one end of the upper clamping block is fixedly connected with a spring. The movement of the sliding block lifts one side of the rotating plate upward, and the rotating plate rotates along the rotating shaft, the spring contracts immediately, and the rotating plate drives the upper clamping block to move downward to clamp the tubular building materials and fix the tubular building materials by tension.
[0009] In a preferred embodiment of the utility model, a movable plate is arranged below the fixed frame, and the lower surface of the fixed frame is slidably connected to the movable plate. The movable plate limits the fixed frame to prevent the fixed frame from shaking.
[0010] Beneficial Effects
[0011] The utility model provides a hoisting device for steel structure factory building construction, which has the following beneficial effects:
[0012] 1. The hoisting device for steel structure workshop construction fixes the tubular building materials by the lifting force through the setting of clamping structure when the device is hoisted, which can save the time of tying ropes and reduce manual operation, thereby improving construction efficiency. At the same time, it ensures that the tubular building materials are firmly fixed during the hoisting process, avoiding safety hazards such as loose tying or rope breakage, and ensuring the safety of construction workers.
[0013] 2. The lifting device for steel structure workshop construction can automatically loosen the device after putting down the tubular building materials by setting a spring, eliminating the manual operation steps of workers, saving time and improving work efficiency. Workers no longer need to loosen the clamping structure, but only need to put down the tubular building materials. The operation is more convenient and quick, reducing the complexity of the operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a three-dimensional front view structural diagram of the utility model;
[0015] Figure 2 This is a schematic diagram of the three-dimensional rear view structure of the utility model;
[0016] Figure 3 This is a schematic diagram of the front section structure of the utility model;
[0017] Figure 4 It is a schematic diagram of the side section structure of the fixed frame of the utility model.
[0018] In the figure: 1, bottom plate; 2, winch; 3, support plate; 4, universal wheel; 5, rope; 6, support structure; 7, connecting ring; 8, connecting rope; 9, ring; 10, sliding block; 11, fixed frame; 12, clamping structure; 13, lower placement block; 14, limit plate; 15, limit roller; 16, support column; 17, connecting rod; 18, fixed plate; 19, rotating plate; 20, upper clamping block; 21, rotating shaft; 22, spring; 23, moving plate. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] See also Figure 1-4The utility model provides a technical solution: a hoisting device for steel structure factory building construction, including a base plate 1 and a winch 2, both ends of the upper surface of the base plate 1 are fixedly connected with a support plate 3, the four corners of the lower surface of the base plate 1 are fixedly connected with a universal wheel 4, the winch 2 is fixedly connected to the surface of the support plate 3, a rope 5 is wound around the surface of the winch 2, a supporting structure 6 is arranged on the upper surface of the base plate 1, the supporting structure 6 includes a limiting plate 14 and a limiting roller 15, a supporting column 16 is fixedly connected to the upper surface of the base plate 1, a connecting rod 17 is fixedly connected to the side of the supporting column 16, a fixing plate 18 is fixedly connected to the top of the supporting column 16 and the end of the connecting rod 17, both ends of the surface of the fixing plate 18 are fixedly connected to the lower surface of the limiting plate 14, the limiting roller 15 is rotatably connected between the limiting plates 14, the rope 5 passes around the surface of the limiting roller 15, and the rope 5 is limited by the limiting roller 15.
[0021] The rope 5 passes around the supporting structure 6 and is fixedly connected with a connecting ring 7. Connecting ropes 8 are fixedly connected to both sides of the connecting ring 7. The ends of the connecting rope 8 are fixedly connected with a ring 9. A sliding block 10 is arranged inside the ring 9. A fixed frame 11 is arranged below the ring 9. A movable plate 23 is arranged below the fixed frame 11. The lower surface of the fixed frame 11 is slidably connected to the movable plate 23. The movable plate 23 limits the fixed frame 11 to prevent the fixed frame 11 from shaking. The winch 2 is started to reel in the rope 5. The rope 5 then pulls the connecting ring 7 and the connecting rope 8 upward through the supporting structure 6. The connecting rope 8 then drives the ring 9 and the sliding block 10 to move upward.
[0022] The bottom end of the sliding block 10 passes through the fixed frame 11 and is provided with a clamping structure 12. A lower placement block 13 is fixedly connected to the lower part of the fixed frame 11. The clamping structure 12 clamps the tubular building material above the lower placement block 13. The clamping structure 12 includes a rotating plate 19 and an upper clamping block 20. The sliding block 10 passes through the fixed frame 11 and is slidably connected to the fixed frame 11. The bottom end of the sliding block 10 is rotatably connected to the upper surface of the rotating plate 19. A rotating shaft 21 is fixedly connected to the center position of the rotating plate 19, and the rotating shaft 21 is rotatably connected to the inner wall of the fixed frame 11.
[0023] The movement of the sliding block 10 lifts one side of the rotating plate 19 upward, and the rotating plate 19 rotates along the rotating shaft 21, and the spring 22 contracts immediately. The rotating plate 19 drives the upper clamping block 20 to move downward, clamps the tubular building materials, and fixes the tubular building materials by tension. By setting the clamping structure 12, the tubular building materials can be fixed by the lifting tension when the device is lifted, which can save the time of tying the rope 5 and reduce manual operation, thereby improving construction efficiency. At the same time, it ensures that the tubular building materials are firmly fixed during the lifting process, avoids safety hazards such as loose tying or broken ropes 5, and ensures the safety of construction personnel.
[0024] The lower surface of the rotating plate 19 is rotatably connected to the upper surface of the upper clamping block 20 , and a spring 22 is fixedly connected to the upper surface of the rotating plate 19 at one end away from the upper clamping block 20 .
[0025] After the movable plate 23 is placed on the ground, the pulling force disappears, and the spring 22 immediately pushes one side of the rotating plate 19, and the upper clamping block 20 on the other side of the rotating plate 19 releases the tubular building material. By setting the spring 22, the device can automatically release after the tubular building material is put down, eliminating the manual operation steps of the workers, saving time, and improving work efficiency. The staff no longer need to work hard to loosen the clamping structure 12, and only need to put down the tubular building material. The operation is more convenient and quick, and the complexity of the operation is reduced.
[0026] Instructions for use: First, insert the tubular building material to be hoisted into the interior of the fixed frame 11 and place it above the lower placement block 13. Then start the winch 2 to reel in the rope 5. The rope 5 then pulls the connecting ring 7 and the connecting rope 8 upward through the supporting structure 6. The connecting rope 8 then drives the ring 9 and the sliding block 10 to move upward. The movement of the sliding block 10 lifts one side of the rotating plate 19 upward. The rotating plate 19 rotates along the rotating shaft 21. The spring 22 then contracts. The rotating plate 19 drives the upper clamping block 20 to move downward to clamp the tubular building material and fix it by tension.
[0027] When unloading is required, the movable plate 23 is placed on the ground, the pulling force disappears, and the spring 22 pushes one side of the rotating plate 19, and the upper clamping block 20 on the other side of the rotating plate 19 releases the tubular building material.
[0028] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A hoisting device for steel structure factory building construction, comprising a base plate (1) and a winch (2), characterized in that: The two ends of the upper surface of the base plate (1) are fixedly connected to support plates (3), the four corners of the lower surface of the base plate (1) are fixedly connected to universal wheels (4), the winch (2) is fixedly connected to the surface of the support plate (3), the surface of the winch (2) is wound with a rope (5), the upper surface of the base plate (1) is provided with a support structure (6), the rope (5) passes around the support structure (6) and is fixedly connected to a connecting ring (7), the two sides of the connecting ring (7) are fixedly connected to connecting ropes (8), the ends of the connecting ropes (8) are fixedly connected to a sleeve (9), a sliding block (10) is provided inside the sleeve (9), a fixed frame (11) is provided below the sleeve (9), the bottom end of the sliding block (10) passes through the fixed frame (11) and is provided with a clamping structure (12), the lower part of the fixed frame (11) is fixedly connected to a lower placement block (13), and the clamping structure (12) clamps the tubular building material above the lower placement block (13).
2. A hoisting device for steel structure factory building construction according to claim 1, characterized in that: The support structure (6) comprises a limiting plate (14) and a limiting roller (15); the upper surface of the bottom plate (1) is fixedly connected to a support column (16); and the side surface of the support column (16) is fixedly connected to a connecting rod (17).
3. A hoisting device for steel structure factory building construction according to claim 2, characterized in that: The top end of the support column (16) and the end of the connecting rod (17) are both fixedly connected to a fixing plate (18), and both ends of the surface of the fixing plate (18) are fixedly connected to the lower surface of the limiting plate (14).
4. A hoisting device for steel structure factory building construction according to claim 3, characterized in that: The limiting roller (15) is rotatably connected between the limiting plates (14), and the rope (5) passes around the surface of the limiting roller (15), and the rope (5) is limited by the limiting roller (15).
5. The hoisting device for steel structure factory building construction according to claim 1 is characterized in that: The clamping structure (12) comprises a rotating plate (19) and an upper clamping block (20); the sliding block (10) passes through the fixed frame (11) and is slidably connected to the fixed frame (11); the bottom end of the sliding block (10) is rotatably connected to the upper surface of the rotating plate (19).
6. A hoisting device for steel structure factory building construction according to claim 5, characterized in that: A rotating shaft (21) is fixedly connected to the center of the rotating plate (19), and the rotating shaft (21) is rotatably connected to the inner wall of the fixed frame (11).
7. A hoisting device for steel structure factory building construction according to claim 6, characterized in that: The lower surface of the rotating plate (19) is rotatably connected to the upper surface of the upper clamping block (20), and the upper surface of the rotating plate (19) at one end away from the upper clamping block (20) is fixedly connected to a spring (22).
8. The hoisting device for steel structure factory building construction according to claim 1 is characterized in that: A movable plate (23) is arranged below the fixed frame (11); the lower surface of the fixed frame (11) is slidably connected to the movable plate (23); the movable plate (23) limits the fixed frame (11) to prevent the fixed frame (11) from shaking.
Citation Information
Cited By
Accurate positioning petroleum drilling and production device
CN120251115A