Hanging basket main truss for bridge
By using the positioning grooves, positioning holes and fixed shafts of the vertical rod, horizontal rod and diagonal rod structures in the main truss of the hanging basket for bridges, combined with elastic connection and welding, the installation and installation of the main truss of the hanging basket in the existing technology are solved. It eliminates the tedious problem of disassembly, realizes quick installation and efficient connection, and improves installation efficiency and stability.
Patent Information
- Application Number
- CN202323417341.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-14
AI Technical Summary
The main truss of the existing bridge hanging basket needs to be aligned during installation and disassembly due to the pin connection, which makes the installation and disassembly process relatively cumbersome and time-consuming.
It adopts the structure of vertical poles, horizontal poles and inclined poles, and uses the snap fit of positioning grooves, positioning holes and fixed shafts, combined with elastic connection and welding, to achieve quick installation and disassembly, eliminating tedious installation and disassembly steps.
The sliding fixed shaft drives the spring to move the positioning plate, so that the positioning block is inserted into the positioning hole, realizing quick connection between the horizontal bar, the vertical bar and the inclined bar, significantly saving installation time, and improving the connection stability through the limit rod.
Smart Images

Figure CN221918980U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of bridge construction, and more specifically, to a main truss of a hanging basket for a bridge. Background Art
[0002] When casting a cantilever beam bridge with a larger span, a hanging basket method is used, and the cantilever work is carried out in sections on site. It does not require the erection of a bracket and does not use a large crane. Compared with other methods, the hanging basket construction has the advantages of light structure, simple and convenient assembly, and no pressure. However, the truss nodes are connected by pins, which makes the installation and disassembly more cumbersome and time-consuming. The patent document with the prior art publication number CN215329405U provides a hanging basket main truss for a bridge. The device adopts welding at the main stress-bearing parts and pinning at some parts. It has the advantages of pinning and makes up for the shortcomings and defects of complete pinning. The installation and disassembly speed saves at least twice the time of the hanging basket main truss structure with complete pinning.
[0003] In view of the above-mentioned related technologies, the inventor believes that in the process of connecting the node, the pin shaft needs to be inserted through the pin shaft hole of the rod body and the pin shaft hole of the node seat, and the docking adjustment is inconvenient. Therefore, we propose a main truss for a bridge hanging basket. Utility Model Content
[0004] In order to improve the problems raised in the above background technology, the present application provides a main truss for a bridge hanging basket.
[0005] The present application provides a main truss for a bridge hanging basket, which adopts the following technical solution:
[0006] A main truss of a hanging basket for a bridge comprises a vertical pole, two horizontal poles and two diagonal poles, both ends of the vertical pole are fixedly connected to a first node seat, one end of the horizontal pole is fixedly connected to a second node seat, both ends of the diagonal pole are provided with a positioning groove and two positioning holes, the first node seat and the second node seat are fixedly connected to a fixed shaft, the fixed shaft is snap-fitted with the positioning groove, a positioning plate is provided on one side of the fixed shaft, the positioning plate is elastically connected to the first node seat or the second node seat, and is snap-fitted with the positioning hole.
[0007] By adopting the above technical solution, after one end of the cross bar is clamped with the fixed axis on the first node seat through the positioning groove, the positioning plate is clamped with the positioning hole of the cross bar, and then the positioning grooves at both ends of the diagonal bar are clamped with the fixed axes on the first node seat and the second node seat respectively, and then the diagonal bar is clamped through the positioning plate, so that the vertical bar, cross bar and diagonal bar can be quickly installed to form a truss.
[0008] Optionally, U-shaped plates are welded to the first node seat and the second node seat, and the U-shaped plates are welded to the vertical poles or the horizontal poles.
[0009] By adopting the above technical solution, the first node seat and the vertical pole, the second node seat and the cross bar are welded and connected through the U-shaped plate, eliminating the installation and disassembly steps of the first node seat and the vertical pole, the second node seat and the cross bar, saving time.
[0010] Optionally, a movable plate is fixedly connected to one side of the positioning plate, the positioning plate is slidably connected to the first node seat or the second node seat, the positioning plate is elastically connected to the first node seat or the second node seat via a spring, and positioning blocks are fixedly connected to both ends of the positioning plate, and the positioning blocks are snap-fitted with the positioning holes.
[0011] By adopting the above technical solution, after the fixed shaft slides into the positioning groove, the spring drives the positioning plate to move, so that the positioning block is inserted into the positioning hole, so that the crossbar and the vertical rod, the oblique rod and the vertical rod, and the crossbar are connected and fixed.
[0012] Optionally, a slope is provided at one end of the positioning block.
[0013] By adopting the above technical solution, when the fixed axis slides in the positioning groove, the corners of the cross bar or the oblique bar contact the inclined surface, so that the positioning plate drives the spring to compress. When the positioning block coincides with the positioning hole, the spring resets and drives the positioning block to be inserted into the positioning hole.
[0014] Optionally, a limit rod is disposed on the outer sleeve of the movable plate, a rib plate is hinged on the limit rod, and the rib plate is welded and fixed to the first node seat or the second node seat.
[0015] By adopting the above technical solution, pulling the movable plate can drive the positioning block to cancel the clamping connection with the positioning hole. When the limit rod is rotated to fit with the rib plate, the limit rod limits the sliding of the movable plate, making the movable plate unable to slide, thereby improving the stability of the connection between the positioning block and the positioning hole.
[0016] In summary, the present application includes at least one of the following beneficial technical effects:
[0017] 1. After the fixed shaft slides into the positioning groove, the spring drives the positioning plate to move, so that the positioning block is plugged into the positioning hole, so that the crossbar and the vertical pole, the diagonal pole and the vertical pole, and the crossbar can be quickly connected, saving the docking steps and effectively improving the installation efficiency.
[0018] 2. After the limiting rod is rotated until it fits with the rib plate, the limiting rod limits the sliding of the movable plate, so that the positioning block is stably arranged in the positioning hole, further improving the connection stability of the positioning block to the cross bar or the diagonal bar. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the overall structure of a main truss of a bridge hanging basket according to an embodiment of the present application;
[0020] Figure 2This is a schematic diagram of the diagonal rod and fixed axis structure of a main truss of a bridge hanging basket in an embodiment of the present application;
[0021] Figure 3 This is a schematic diagram of the anatomical structure of the first node seat and the fixed axis of a main truss of a bridge hanging basket according to an embodiment of the present application;
[0022] Figure 4 This is a schematic diagram of the positioning plate, movable plate, and limit rod structure of a main truss of a bridge hanging basket in an embodiment of the present application;
[0023] Explanation of the numbers in the figure: 1. Vertical pole; 2. Cross bar; 3. Diagonal bar; 4. First node seat; 5. Second node seat; 6. U-shaped plate; 7. Positioning groove; 8. Positioning hole; 9. Fixed shaft; 10. Positioning plate; 11. Movable plate; 12. Spring; 13. Positioning block; 14. Limit rod; 15. Rib plate. DETAILED DESCRIPTION
[0024] The present application is further described in detail below in conjunction with the accompanying drawings.
[0025] Reference Figure 1-4 The present application includes a vertical rod 1 and two cross rods 2 and two diagonal rods 3. Both ends of the vertical rod 1 are fixedly connected to a first node seat 4, one end of the cross rod 2 is fixedly connected to a second node seat 5, and both ends of the diagonal rod 3 are provided with a positioning groove 7 and two positioning holes 8. The first node seat 4 and the second node seat 5 are fixedly connected to a fixed shaft 9, the fixed shaft 9 is engaged with the positioning groove 7, and a positioning plate 10 is provided on one side of the fixed shaft 9. The positioning plate 10 is elastically connected to the first node seat 4 or the second node seat 5, and is engaged with the positioning hole 8. After one end of the cross rod 2 is engaged with the fixed shaft 9 on the first node seat 4 through the positioning groove 7, the positioning plate 10 is engaged with the positioning hole 8 of the cross rod. Subsequently, the positioning grooves 7 at both ends of the diagonal rod 3 are respectively engaged with the fixed shafts 9 on the first node seat 4 and the second node seat 5, and then the diagonal rod 3 is engaged through the positioning plate 10, so that the vertical rod 1, the cross rod 2 and the diagonal rod 3 are quickly installed to form a truss.
[0026] Reference Figure 1 , Figure 3 A U-shaped plate 6 is welded to the first node seat 4 and the second node seat 5, and the U-shaped plate 6 is welded to the vertical pole 1 or the cross bar 2. The first node seat 4 and the vertical pole 1, and the second node seat 5 and the cross bar 3 are welded and connected via the U-shaped plate 6, thereby eliminating the steps of installing and disassembling the first node seat 4 and the vertical pole 1, and the second node seat 5 and the cross bar 2, thereby saving time.
[0027] Reference Figure 4A movable plate 11 is fixedly connected to one side of the positioning plate 10, and the positioning plate 10 is slidably connected to the first node seat 4 or the second node seat 5. The positioning plate 10 is elastically connected to the first node seat 4 or the second node seat 5 through a spring 12, and positioning blocks 13 are fixedly connected to both ends of the positioning plate 10. The positioning blocks 13 are snap-fitted with the positioning holes 8. After the fixed shaft 9 slides into the positioning groove 7, the spring 12 drives the positioning plate 10 to move, so that the positioning block 14 is inserted into the positioning hole 8, so that the cross bar 2 is connected and fixed to the vertical bar 1, the diagonal bar 3 is connected to the vertical bar 1, and the cross bar 2 is connected and fixed.
[0028] Reference Figure 4 One end of the positioning block 13 is provided with an inclined surface. When the fixed shaft 9 slides into the positioning groove 7, the corners of the cross bar 2 or the inclined bar 3 contact the inclined surface, so that the positioning plate 10 drives the spring 12 to compress. When the positioning block 13 coincides with the positioning hole 8, the spring 12 resets and drives the positioning block 13 to be inserted into the positioning hole 8.
[0029] Reference Figure 4 The movable plate 11 is outerly provided with a limiting rod 14, and a rib plate 15 is hinged on the limiting rod 14. The rib plate 15 is welded and fixed to the first node seat 4 or the second node seat 5. Pulling the movable plate 11 can drive the positioning block 13 to cancel the clamping connection with the positioning hole 8. When the limiting rod 14 is rotated to fit with the rib plate 15, the limiting rod 14 limits the sliding of the movable plate 11, so that the movable plate 11 cannot slide, thereby improving the stability of the connection between the positioning block 13 and the positioning hole 8.
[0030] After the fixed shaft 9 slides into the positioning groove 7, the spring 12 drives the positioning plate 10 to move, so that the positioning block 13 is plugged into the positioning hole 8, so that the cross bar 2 and the vertical bar 1 and the diagonal bar 3 and the vertical bar 1 and the cross bar 2 can be quickly connected, saving the docking steps and effectively improving the installation efficiency.
[0031] The implementation principle of the main truss of a hanging basket for a bridge in an embodiment of the present application is as follows: the vertical pole 1 is placed vertically, and the left cross bar 2 is clamped with the left fixed axis 9 on the lower first node seat 4 through the positioning groove 7. The spring 12 close to the fixed axis 9 drives the positioning block 13 to be inserted into the positioning hole 8. At this time, the cross bar 2 is connected and fixed to the vertical pole 1. Subsequently, the positioning grooves 7 at both ends of the diagonal bar 3 are respectively clamped with the fixed axis 9 on the left second node seat 5 and the left fixed axis 9 on the upper first node seat 5. The spring 12 drives the positioning block 13 to be inserted into the positioning hole 8. At this time, the diagonal bar 3 is connected and fixed to the vertical pole 1 and the cross bar 2. Similarly, the right cross bar 2 and the diagonal bar 3 are installed to achieve quick installation and connection.
Claims
1. A main truss of a hanging basket for a bridge, comprising a vertical pole (1), two horizontal poles (2), and two diagonal poles (3), wherein both ends of the vertical pole (1) are fixedly connected to a first node seat (4), and one end of the horizontal pole (2) is fixedly connected to a second node seat (5), characterized in that: Both ends of the inclined rod (3) are provided with a positioning groove (7) and two positioning holes (8); the first node seat (4) and the second node seat (5) are fixedly connected with a fixed shaft (9); the fixed shaft (9) is snap-fitted with the positioning groove (7); a positioning plate (10) is provided on one side of the fixed shaft (9); the positioning plate (10) is elastically connected to the first node seat (4) or the second node seat (5), and is snap-fitted with the positioning hole (8).
2. The main truss of a bridge hanging basket according to claim 1, characterized in that: A U-shaped plate (6) is welded to the first node seat (4) and the second node seat (5), and the U-shaped plate (6) is welded to the vertical pole (1) or the horizontal pole (2).
3. The main truss of a bridge hanging basket according to claim 1, characterized in that: A movable plate (11) is fixedly connected to one side of the positioning plate (10), and the positioning plate (10) is slidably connected to the first node seat (4) or the second node seat (5). The positioning plate (10) is elastically connected to the first node seat (4) or the second node seat (5) via a spring (12), and positioning blocks (13) are fixedly connected to both ends of the positioning plate (10), and the positioning blocks (13) are snap-fitted with the positioning holes (8).
4. The main truss of a bridge hanging basket according to claim 3, characterized in that: One end of the positioning block (13) is provided with an inclined surface.
5. The main truss of a bridge hanging basket according to claim 3, characterized in that: The movable plate (11) is provided with a limiting rod (14) on its outer sleeve, a rib plate (15) is hinged on the limiting rod (14), and the rib plate (15) is welded and fixed to the first node seat (4) or the second node seat (5).