Bus insulation on-line monitoring device

By designing a busbar insulation online monitoring device and using high-voltage isolation modules and branch current sensors, real-time monitoring of the busbar insulation status is achieved, which solves the problem that traditional methods cannot monitor and locate faults in real time, reduces the occurrence of insulation accidents, and improves efficiency. Equipment safety and operational reliability.

CN221926526UActive Publication Date: 2024-10-29CHENGDU GONGBAILI AUTOMATION EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422239099.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-10-29
Estimated Expiration
2034-09-12

AI Technical Summary

Technical Problem

The traditional busbar insulation status monitoring method cannot monitor in real time, is blind and passive, and cannot detect insulation degradation problems in time, leading to the expansion of faults. In particular, when hot standby equipment is started, faults caused by moisture affect safe production.

Method used

A busbar insulation online monitoring device is designed, including an insulation monitoring host, a high-voltage sampling resistor, a high-voltage isolation module, a DC isolation and harmonic elimination module, and a branch current sensor. The busbar insulation resistance value is calculated through Ohm's law, and the high-voltage isolation module and branch circuit are used. The circuit current sensor realizes real-time monitoring and fault location.

Benefits of technology

It realizes real-time monitoring of the busbar insulation status, reduces the occurrence of insulation accidents, and improves the safety and operational reliability of the equipment. The branch current sensor adopts the magnetic modulation principle to ensure high safety. The high-voltage sampling resistor is connected in a star shape. Guaranteed long-term stable work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221926526U_ABST
    Figure CN221926526U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of bus insulation monitoring, in particular to a bus insulation on-line monitoring device, which adopts the scheme that the bus insulation on-line monitoring device comprises an insulation monitoring host, a high-voltage sampling resistor, a high-voltage isolation module, a direct current blocking and harmonic elimination module and a branch current sensor, the other end of the high-voltage sampling resistor is connected with a high-voltage bus, the insulation monitoring host outputs set direct-current voltage to the high-voltage bus, the high-voltage bus is connected with one end of the direct-current blocking and harmonic elimination module through a primary neutral point of a voltage transformer in a PT cabinet, the other end of the direct-current blocking and harmonic elimination module is grounded, and the branch current sensor is installed at the wire outlet end of a switch cabinet. The direct current flowing through the wire outlet end is detected, the detected direct current is sent to the insulation monitoring host, and the insulation monitoring host calculates the insulation resistance value of the whole bus through the Ohm law according to the voltage on the high-voltage bus and the direct current of the wire outlet end. The bus insulation online monitoring device is suitable for bus insulation online monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of busbar insulation monitoring, in particular to an online busbar insulation monitoring device. Background Art

[0002] Electrical equipment in the power system works under high voltage conditions for a long time, which is prone to equipment failure caused by insulation damage. For the safe operation of the equipment, operation and maintenance personnel need to know the insulation status of the electrical equipment in a timely manner. The traditional approach is to use a megohmmeter or digital megohmmeter to perform insulation testing on a single circuit after the system and equipment are shut down, but these approaches have the following shortcomings:

[0003] The insulation resistance of cold standby equipment can only be measured manually at regular intervals. If the measurement cycle is short, the workload is large; if the measurement cycle is too long, the insulation status of the equipment cannot be well evaluated.

[0004] The insulation status of hot standby equipment cannot be monitored in real time, but most equipment burns out at the moment of startup due to moisture and other reasons, affecting safe production.

[0005] Traditional methods cannot monitor the insulation status of equipment in operation, but wear, aging, and mechanical damage often lead to a gradual degradation of insulation. If insulation degradation problems are not discovered in time, the fault will further expand.

[0006] In summary, traditional insulation status monitoring methods are often blind and passive, and cannot effectively avoid the occurrence of insulation accidents. Utility Model Content

[0007] The utility model aims to overcome the shortcomings of the prior art and provide a busbar insulation online monitoring device, which can monitor the busbar insulation online in real time and reduce the occurrence of insulation accidents.

[0008] The utility model adopts the following technical scheme to achieve the above-mentioned purpose. The utility model provides a busbar insulation online monitoring device, including an insulation monitoring host, a high-voltage sampling resistor, a high-voltage isolation module, a direct current isolation and harmonic elimination module and a branch current sensor. The high-voltage sampling resistor and the high-voltage isolation module are both installed in a PT (Potential Transformer) cabinet. One end of the high-voltage sampling resistor is connected to the insulation monitoring host through the high-voltage isolation module, and the other end of the high-voltage sampling resistor is connected to the high-voltage bus. The insulation monitoring host outputs a set DC voltage to the high-voltage bus. The high-voltage bus is connected to one end of the direct current isolation and harmonic elimination module through the primary neutral point of the voltage transformer in the PT cabinet, and the other end of the direct current isolation and harmonic elimination module is grounded. The branch current sensor is installed at the outlet end of the switch cabinet to detect the DC current flowing through the outlet end, and send the detected DC current to the insulation monitoring host. The insulation monitoring host calculates the insulation resistance value of the entire bus according to the voltage on the high-voltage bus and the DC current at the outlet end through Ohm's law.

[0009] Furthermore, the high-voltage isolation module has a built-in high-voltage switch for disconnecting or closing the connection between the insulation monitoring host and the high-voltage sampling resistor.

[0010] Furthermore, the DC isolation and harmonic elimination module includes a capacitor and a resistor connected in series, one end of the capacitor is connected to the primary neutral point of the voltage transformer, and the other end of the capacitor is grounded through the resistor.

[0011] Furthermore, there are multiple high-voltage sampling resistors, and the multiple high-voltage sampling resistors are connected in a star shape.

[0012] Beneficial effects of the utility model:

[0013] The utility model can effectively avoid the influence of the increase of neutral point voltage on the insulation monitoring host when the busbar is single-phase grounded by introducing a high-voltage isolation module; by introducing a branch current sensor, the insulation status of each branch can be intuitively displayed, which is convenient for maintenance personnel to locate faults more quickly; the branch current sensor adopts the magnetic modulation principle. When measuring the branch current, the sensor does not contact the branch high-voltage cable, and has extremely high safety.

[0014] The utility model discloses a high-voltage sampling resistor which is connected in a star-shaped manner. When the resistor works normally, the temperature rise is extremely small, thereby ensuring the long-term stable operation of the high-voltage sampling resistor. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of a busbar insulation online monitoring device provided by an embodiment of the utility model. DETAILED DESCRIPTION

[0016] In order to make the purpose, technical solution and advantages of the embodiments of the present utility model clearer, the technical solution in the embodiments of the present utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the present utility model.

[0017] The utility model provides a busbar insulation online monitoring device, such as Figure 1 As shown, it includes an insulation monitoring host, a high-voltage sampling resistor, a high-voltage isolation module, a direct current isolation and harmonic elimination module, a branch current sensor and an insulation resistance analysis module.

[0018] Insulation monitoring host: output 1500V DC voltage, applied to the high-voltage bus through the high-voltage isolation module and the high-voltage sampling resistor, and the insulation resistance value of the entire bus is calculated by Ohm's law.

[0019] High-voltage sampling resistor: installed in the PT cabinet, one end is connected to the high-voltage busbar, and the other end is short-circuited and connected to the high-voltage isolation module, which plays the role of isolation and current limiting. It ensures the safety of the 10kV high-voltage system and the insulation monitoring host.

[0020] High-voltage isolation module: installed in the PT cabinet, the built-in high-voltage switch is used to disconnect or close the connection between the insulation monitoring host and the high-voltage sampling resistor. When the AC voltage at the high-voltage sampling resistor end exceeds the set threshold (usually 3000V), the high-voltage switch is locked to protect the safety of the insulation monitoring host.

[0021] DC isolation and harmonic elimination module: The 10kV bus is an IT (Isolation Transformer) ungrounded system with no direct grounding point. Instead, it is grounded through the primary neutral point of the voltage transformer (and only this one grounding point). To prevent overvoltage caused by the ferromagnetic resonance of the transformer, a harmonic elimination device needs to be installed at the primary neutral point of the transformer. In order to make the 1500V DC voltage applied by the device truly act on the bus insulation resistance measurement, a capacitor must be connected in series to the primary grounding line of the voltage transformer. The utility model adopts a DC isolation and harmonic elimination module to achieve the purpose of DC isolation and harmonic elimination. The DC isolation and harmonic elimination module includes a capacitor and a resistor connected in series, one end of the capacitor is connected to the primary neutral point of the voltage transformer, and the other end of the capacitor is grounded through a resistor.

[0022] Branch current sensor: installed at the outgoing line end of the switch cabinet, detects the DC current flowing through the outgoing line and sends it to the insulation monitoring host to evaluate the insulation resistance value of the branch line, so as to quickly locate the insulation fault area.

[0023] Insulation resistance analysis module: It runs on the industrial computer of the measurement and control device. It can monitor the insulation resistance value of the busbar and each branch line in real time, analyze the insulation degradation trend and issue an alarm signal in time.

[0024] Specifically, the high-voltage sampling resistor of the utility model uses a high-quality ceramic resistor of 45MΩ / 150W with a withstand voltage of up to 35kV, and the resistor housing is equipped with a high-voltage insulating shed to effectively increase the creepage distance and avoid the risk of breakdown caused by dust, moisture, etc.

[0025] Specifically, the high-voltage sampling resistor is connected in a star configuration. For a 10kV bus, the phase voltage of the star connection is 6kV. The power borne by a single resistor is 0.8W, which is much smaller than the rated power of 150W of the resistor. The temperature rise of the resistor is extremely small when it works normally, which can ensure the long-term stable operation of the high-voltage sampling resistor.

[0026] Specifically, the connection between the high-voltage sampling resistor and the high-voltage isolation module uses a high-voltage silicone wire with a withstand voltage of 35kV, and the connection between the high-voltage isolation module and the insulation monitoring host uses a high-voltage shielded silicone wire with a withstand voltage of 35kV. This can eliminate the risk of electric shock caused by lead breakdown.

[0027] Specifically, the high-voltage switch inside the high-voltage isolation module is in a disconnected state after being shut down or powered off, which can prevent the risk of electric shock caused by the high voltage being connected in series with the 10kV busbar when the insulation monitoring equipment is being repaired.

[0028] Specifically, when the 10kV system is working normally, the relative ground voltage peak is 8.16kV (10 / 1.732*1.414). The DC voltage applied by the insulation monitoring host is 1.5kV, which is equivalent to the relative ground voltage peak increasing to 9.66kV (8.16+1.5). Since the 9.66kV relative ground voltage is much smaller than the non-fault relative ground voltage of 17.32kV during a single-phase ground fault, the introduction of the insulation online monitoring device will not affect the overall operation safety of the system.

[0029] Working principle of this utility model:

[0030] The utility model insulation monitoring host regards the entire ungrounded system as an equivalent resistance as a whole, including all primary equipment connected to the high-voltage bus, such as busbar, voltage transformer, current transformer, high-voltage motor stator coil, high-voltage circuit breaker, connecting cable, transformer winding, etc. If the neutral point of the primary side of the voltage transformer in the ungrounded system is directly grounded, the grounding method needs to be changed to grounding through the direct current isolation and harmonic elimination module. A 0.47uF high-voltage capacitor is connected in series inside the direct current isolation and harmonic elimination module. The function of the high-voltage capacitor is to prevent the DC voltage generated by the monitoring host from being short-circuited, while ensuring the normal passage of the AC power, and not affecting the normal operation of the direct current isolation and harmonic elimination module.

[0031] The insulation monitoring host generates a DC voltage of 1500V and applies a measurement signal to the 10kV bus through three high-voltage sampling resistors 15MΩ (45MΩ / 3) connected in a star shape at the tail end (the signal generates a 0-100uA DC current and will not affect the system). The uA (microampere) DC current is collected through a precision measurement circuit, and then the insulation resistance value of the bus to ground is calculated according to Ohm's law.

[0032] The branch current sensor installed in each branch is a uA-level high-precision DC current sensor, which can detect the DC current flowing through the corresponding branch. Combined with the bus DC voltage obtained by the insulation monitoring host, the insulation resistance value of the branch to be tested is calculated according to Kirchhoff's law and Ohm's law.

[0033] The high-voltage isolation module plays a protective role in this solution. It has a built-in high-voltage switch and an AC voltage acquisition circuit. The high-voltage switch is connected in series between the common end of the high-voltage sampling resistor and the insulation monitoring host. The AC voltage acquisition circuit can monitor the AC voltage between the common end of the high-voltage sampling resistor and the ground in real time. When the busbar is single-phase grounded and the AC voltage exceeds the set threshold (usually 3000V), the internal high-voltage switch is immediately disconnected to ensure the safety of the insulation monitoring host and prevent the risk of electric shock.

[0034] The above is only a preferred embodiment of the utility model. It should be understood that the utility model is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art do not deviate from the spirit and scope of the utility model, and should be within the scope of protection of the claims attached to the utility model.

Claims

1. A busbar insulation online monitoring device, characterized in that: It includes an insulation monitoring host, a high-voltage sampling resistor, a high-voltage isolation module, a direct current isolation and harmonic elimination module, and a branch current sensor. The high-voltage sampling resistor and the high-voltage isolation module are both installed in a PT cabinet. One end of the high-voltage sampling resistor is connected to the insulation monitoring host through the high-voltage isolation module, and the other end of the high-voltage sampling resistor is connected to the high-voltage bus. The insulation monitoring host outputs a set DC voltage to the high-voltage bus. The high-voltage bus is connected to one end of the direct current isolation and harmonic elimination module through the primary neutral point of the voltage transformer in the PT cabinet, and the other end of the direct current isolation and harmonic elimination module is grounded. The branch current sensor is installed at the outlet end of the switch cabinet to detect the DC current flowing through the outlet end, and send the detected DC current to the insulation monitoring host. The insulation monitoring host calculates the insulation resistance value of the entire bus according to the voltage on the high-voltage bus and the DC current at the outlet end through Ohm's law.

2. The busbar insulation online monitoring device according to claim 1 is characterized in that: The high-voltage isolation module has a built-in high-voltage switch, and the high-voltage switch is connected between the insulation monitoring host and the high-voltage sampling resistor.

3. The busbar insulation online monitoring device according to claim 1, characterized in that: The DC isolation and harmonic elimination module comprises a capacitor and a resistor connected in series, one end of the capacitor is connected to the primary neutral point of the voltage transformer, and the other end of the capacitor is grounded through the resistor.

4. The busbar insulation online monitoring device according to claim 1, characterized in that: There are multiple high-voltage sampling resistors, and the multiple high-voltage sampling resistors are connected in a star shape.