Smoke isolating and collecting device
By using a smoke isolation and collection device with a high-pressure blowing mechanism and a smoke collecting hood on the on-site thermal regeneration unit, the problems of asphalt flue gas isolation and observation are solved, and stable smoke collection and equipment status observation in high-temperature environments are achieved, and construction personnel are protected and environment.
Patent Information
- Application Number
- CN202323449139.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-18
AI Technical Summary
The asphalt flue gas generated during construction of the on-site thermal regeneration unit is difficult to effectively isolate and collect, affecting the health and environment of the operators. At the same time, the existing transparent shell has poor stability and reliability at high temperatures, hindering the observation of the operating status of the equipment.
A smoke isolation and collection device is designed, including a high-pressure blowing mechanism and a smoke collecting hood. A high-intensity air curtain is generated to isolate the smoke by a high-pressure blowing fan, and it is suctioned under the action of a negative pressure source to ensure air tightness and observation position. .
It has achieved a long-term observation that maintains stable airtightness in high-temperature flue gas environment, isolates smoke and does not affect the operating status of the equipment, and protects the health and environment of construction workers.
Smart Images

Figure CN221934956U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of environmental protection technology, and specifically relates to a movable device for isolating and centrally collecting smoke during the on-site hot regeneration construction of asphalt pavement. Background Art
[0002] With the rapid growth of high-grade highways and urban roads in my country and the continuous improvement of road service levels, the application of hot-in-place regeneration units has become more and more widespread. Due to the construction of hot-in-place regeneration units, asphalt fumes will inevitably be generated when the ground is heated and raked. The random diffusion of asphalt fumes affects the health of operators and pollutes the surrounding environment. Therefore, it is imperative to block the asphalt fumes within a certain range during the construction of hot-in-place regeneration equipment and concentrate the fumes for treatment. It is also very important to facilitate the observation of the working status of the working device while blocking the fumes.
[0003] If only a cover connected to a negative pressure source is placed on top of the on-site hot regeneration equipment, although it can also play a certain role in collecting smoke, the cover will seriously hinder the operator from observing the operating status of the equipment. If it is replaced with transparent glass or plastic material, it will be affected by the high temperature of the smoke for a long time, resulting in a significant decrease in connection stability and reliability. Utility Model Content
[0004] In view of the above problems, the utility model proposes a smoke isolation and collection device, which can maintain stable air tightness for a long time under the influence of high-temperature flue gas without affecting the operator's observation of the operating status of the on-site heat regeneration equipment, so as to achieve long-term stable collection of flue gas.
[0005] The technical solution of the utility model is as follows: the smoke isolation and collection device comprises a smoke collecting hood 5 connected to a negative pressure source, and an observation port is provided on the smoke collecting hood 5;
[0006] The smoke isolation and collection device also includes a high-pressure blowing mechanism for air-sealing the observation port, the high-pressure blowing mechanism includes a high-pressure blowing fan 1 and a high-pressure air box 8, the blowing port of the high-pressure blowing fan 1 is connected to the high-pressure air box 8, the high-pressure air box 8 is fixedly mounted on the smoke hood 5 and is located below the observation port, and the top of the high-pressure air box 8 is provided with an air outlet slit arranged along the width direction of the observation port, and the length of the air outlet slit is ≥ the width of the observation port. When in use, the smoke hood 5 can be placed on the in-situ hot regeneration equipment 9, and a thin high-strength wind curtain is generated through the air outlet slit to prevent smoke from leaving the observation port, thereby retaining the observation position of the operator and effectively isolating the smoke. In this way, the smoke isolation and collection device is used to isolate the smoke that is easily generated on the in-situ hot regeneration equipment of the asphalt pavement from the surrounding environment, and a strong and high-speed airflow is used to blow it out at high speed with an airflow sheet with a thickness of 0.5mm to 3mm. A thin high-strength air curtain is formed, which can isolate the smoke from the surrounding environment, and the air curtain will not block the line of sight, so that the staff can observe the working conditions of the local heat regeneration equipment through the air curtain. After the high-strength air curtain isolates the smoke, the smoke gathers in the smoke hood, and finally the smoke is sucked out under the action of the negative pressure source. This case has a simple and reasonable structure, is easy to use, simple to operate, and easy to control. It protects the health of construction workers and the environment, and can leave an observation position for operators.
[0007] An air outlet is provided in the middle of the top surface of the smoke collecting hood 5, and the air outlet is connected to the smoking fan 3 as a negative pressure source through the smoking pipe 4; the observation port is arranged at the rear of the smoke collecting hood 5, and there is a distance between the observation port and the air outlet, and the suction pressure of the smoking fan 3 is less than the blowing pressure of the high-pressure blowing fan 1. That is, the formation of the high-pressure air curtain is ensured, and the problem of the air curtain not being able to be formed due to excessive suction of the negative pressure source or the suction position being too close to the high-pressure air curtain is avoided.
[0008] The outer wall of the smoke collecting hood 5 is fixedly connected with a wind box support foot, and the end of the high-pressure wind box 8 is mounted on the wind box support foot by a bolt 10. Thus, while the high-pressure wind box 8 is fixedly installed, the initial direction of the air outlet slit can be adjusted.
[0009] In order to further facilitate observation by the operator, there are multiple observation ports, and all of them are opened on the same side surface of the smoke hood 5. The high-pressure air box 8 is fixedly installed at the bottom of the side surface of the smoke hood 5, and the length of the air outlet slit on the high-pressure air box 8 is ≥ the sum of the widths of the areas where all observation ports are located.
[0010] In order to enable the above-mentioned air outlet slit to blow out high-pressure airflow evenly and comprehensively, the present case also proposes the following optimization scheme: the air outlet of the high-pressure air blowing fan 1 is connected to the high-pressure air box 8 through the main air blowing pipe 2, the shunt pipe 6 and the air blowing pipe 7 in sequence; the shunt pipe 6 is evenly provided with n upper openings, n being an integer greater than 1; the high-pressure air box 8 is evenly provided with n lower openings; the air blowing pipe 7 has n openings, and the two ends of the air blowing pipe 7 are respectively connected to the upper opening and the lower opening. Therefore, when dealing with air outlet slits of a relatively long length, the arrangement of multiple air blowing pipes can enable high-pressure airflow to be blown out from every part of the air outlet slit to ensure comprehensive coverage of the high-pressure air curtain.
[0011] The utility model uses a smoke isolation and collection device to isolate the smoke that is easily generated on the in-situ hot regeneration equipment of the asphalt pavement from the surrounding environment, and adopts a strong and high-speed airflow to blow out at high speed with an airflow sheet with a thickness of 0.5mm to 3mm. A thin high-strength wind curtain is formed, which can isolate the smoke from the surrounding environment, and the wind curtain will not block the line of sight, so that the staff can observe the working conditions of the in-situ hot regeneration equipment through the wind curtain. After the high-strength wind curtain isolates the smoke, the smoke gathers in the smoke collection hood, and finally the smoke is sucked under the action of the negative pressure source. The present case has a simple and reasonable structure, is easy to use, simple to operate, and easy to control. It protects the health of construction workers and the environment, and can leave an observation position for operators. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 This is the structural diagram of this case.
[0013] Figure 2 This is a partial schematic diagram of the high-pressure air box end in this case.
[0014] Figure 3 This is the front view of the case;
[0015] In the figure, 1 is a high-pressure air blowing fan, 2 is an air blowing main pipe, 3 is a smoke exhaust fan, 4 is a smoke exhaust pipe, 5 is a smoke collecting hood, 6 is a diversion pipe, 7 is an air blowing pipe, 8 is a high-pressure air box, 9 is an on-site heat regeneration device, and 10 is a rotating shaft. DETAILED DESCRIPTION
[0016] In order to clearly illustrate the technical features of this patent, this patent is elaborated in detail below through a specific implementation method and in combination with its accompanying drawings.
[0017] like Figure 1-3As shown, the local heat regeneration equipment 9 will generate a lot of smoke during operation, and the smoke collecting hood 5 will effectively seal the smoke. The high-pressure blowing fan 1 draws the surrounding air into the blowing main pipe 2, and flows to each blowing pipe 7 in the branch pipe 6. According to the wind pressure, wind speed, pipeline wind pressure loss, width and height to be isolated, the power required by the high-pressure fan is calculated, and the blowing pipe 7 is arranged reasonably. The strong and high-speed airflow passes through the high-pressure air box 8 and is blown out at high speed with a 0.5mm to 3mm thick airflow sheet to form a thin high-strength air curtain, which can isolate the smoke from the surrounding environment.
[0018] Preferably, the high-pressure air box 8 can be arranged around the smoke isolation and collection device. The wind curtain generated by the high-pressure air box 8 will not block the line of sight, and the staff can observe the working conditions of the working device in real time through the wind curtain. The high-pressure air box 8 can be easily rotated by the rotating shaft 10 to adjust the air outlet direction of the high-pressure air box 8 before use, and control the air volume of the air curtain entering the smoke collection hood 5 as needed to ensure the smoke isolation effect.
[0019] like Figure 1 As shown, after the smoke isolating and collecting device collects the smoke, the smoke exhaust fan 3 sucks the smoke in the smoke isolating and collecting device 5 out through the smoke exhaust pipe 4 for processing.
[0020] There are many specific implementation ways of the utility model. The above is only the preferred implementation mode of the utility model. It should be pointed out that for ordinary technicians in this technical field, several improvements can be made without departing from the principle of the utility model, and these improvements should also be regarded as the protection scope of the utility model.
Claims
1. A smoke isolation and collection device, characterized in that: The smoke isolation and collection device comprises a smoke collecting hood (5) connected to a negative pressure source, and an observation port is provided on the smoke collecting hood (5); The smoke isolation and collection device further comprises a high-pressure air blowing mechanism for air-sealing the observation port, the high-pressure air blowing mechanism comprising a high-pressure air blowing fan (1) and a high-pressure air box (8), the air blowing port of the high-pressure air blowing fan (1) being connected to the high-pressure air box (8), the high-pressure air box (8) being fixedly mounted on the smoke collecting hood (5) and being located below the observation port, the top of the high-pressure air box (8) being provided with an air outlet slit arranged along the width direction of the observation port, the length of the air outlet slit being ≥ the width of the observation port.
2. A smoke isolation and collection device according to claim 1, characterized in that: An air outlet is provided in the middle of the top surface of the smoke collecting hood (5), and the air outlet is connected to a smoke exhaust fan (3) serving as a negative pressure source via a smoke exhaust pipe (4); the observation port is arranged at the rear of the smoke collecting hood (5), with a distance between the observation port and the air outlet, and the suction pressure of the smoke exhaust fan (3) is lower than the blowing pressure of the high-pressure blowing fan (1).
3. A smoke isolation and collection device according to claim 1, characterized in that: An air box support foot is fixedly connected to the outer wall of the smoke collecting hood (5), and the end of the high-pressure air box (8) is mounted on the air box support foot via a bolt (10).
4. A smoke isolation and collection device according to claim 1, characterized in that: There are a plurality of observation ports, all of which are opened on the same side surface of the smoke collecting hood (5); the high-pressure air box (8) is fixedly mounted on the bottom of the side surface of the smoke collecting hood (5); and the length of the air outlet slit on the high-pressure air box (8) is ≥ the sum of the widths of the areas where all the observation ports are located.
5. The smoke isolation and collection device according to claim 1, characterized in that: The air outlet of the high-pressure air blowing fan (1) is connected to the high-pressure air box (8) in sequence through the main air blowing pipe (2), the shunt pipe (6) and the air blowing pipe (7); the shunt pipe (6) is evenly provided with n upper openings, where n is an integer greater than 1; the high-pressure air box (8) is evenly provided with n lower openings; the air blowing pipe (7) has n openings; and both ends of the air blowing pipe (7) are respectively connected to the upper opening and the lower opening.