New energy battery top cover plate air tightness detection tool
By setting up multi-layer sealing rings and helium pipelines in the airtightness detection toolkit of the new energy battery ceiling, helium replacement and pressurization technology, the problem of micro leakage detection failure in helium detection is solved, and the detection accuracy is improved and recognition capabilities.
Patent Information
- Application Number
- CN202420103186.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-01-16
AI Technical Summary
During the helium inspection process, when the product to be inspected has a micro leakage, the helium atoms fail to diffuse sufficiently, resulting in detection failure. The product to be inspected is molded on the helium inspection to form a confined space, resulting in misjudgment or detection failure.
A new energy battery ceiling airtightness detection tool is designed. By setting up a multi-layer sealing ring between the upper and lower molds of the helium inspection, and using a helium pipeline and a pressure gauge to replace helium, ensuring that helium atoms can be Fully diffuse and amplify the micro leakage phenomenon by pressurizing helium for identification.
It effectively solves the detection failure problem caused by the formation of a confined space by the upper mold of helium detection, improves the detection accuracy, and reduces the misjudgment rate, making micro leakage more easily recognized.
Smart Images

Figure CN221945498U_ABST
Abstract
Description
Technical field:
[0001] The utility model belongs to the technical field of new energy batteries, and more specifically relates to an air tightness detection tool for a new energy battery top cover plate. Background technology:
[0002] At present, the helium inspection of battery top cover plates mainly uses helium as a tracer gas. The helium inspection fixture is evacuated and then helium is filled into the workpiece. Then, the helium leak detector can quickly and accurately determine the leakage of the workpiece with high precision. Basic operation: The operator places the workpiece in a vacuum box, and the vacuum box and the workpiece are automatically sealed. The system can automatically complete the entire process of large leak detection, vacuuming and helium filling, leak detection, and recycling. The production cycle is fast and the leak detection accuracy is high. However, the product was detected to be unqualified many times during the helium inspection process. After eliminating the reasons for the unqualified products. After investigating the reasons, it was found that there are many holes in the structure of the top cover plate and the material strength is low. The existence of pressure will cause it to have slight deformation, resulting in leakage, making the detection results inaccurate, seriously affecting the efficiency of helium inspection, and not conducive to reducing the production and manufacturing costs of new energy battery covers.
[0003] The national utility model patent with patent number 202223056459.2 discloses a helium inspection fixture for new energy battery cover, which solves the above problems very well. Subsequently, the company further developed another generation of helium inspection fixture for new energy battery cover, in which the first sealing ring, the second sealing ring and the third sealing ring are arranged in sequence from the outside to the inside between the lower cavity and the upper cavity. The utility model has the characteristics of strong structural reliability, good air tightness, low failure rate, high detection efficiency, etc., which reduces the error rate of helium detection of new energy battery cover and improves the accuracy and operation efficiency of helium detection.
[0004] However, this design has certain defects. When the product to be inspected has a slight leak, sometimes the helium atoms are not detected in the helium inspection equipment, and the product is misjudged. In addition, the helium inspection upper mold presses the product to be inspected to form a closed space inside, and the helium atoms cannot fully diffuse, resulting in detection failure. The situation for the customer is that some leaking products cannot be detected and identified. Utility model content:
[0005] In order to solve the above problems and overcome the shortcomings of the prior art, the utility model provides a new energy battery top cover plate airtightness detection tool;
[0006] The technical problem to be solved is: when the product to be inspected has a slight leak, sometimes the helium atoms are not detected in the helium inspection equipment, and the product is misjudged. In addition, the helium inspection upper mold presses the product to be inspected to form a closed space inside, and the helium atoms cannot fully diffuse, resulting in detection failure.
[0007] The utility model solves the above technical problems with a specific technical solution: the new energy battery top cover plate airtightness detection tooling comprises a helium detection upper mold and a helium detection lower mold placed up and down, the helium detection upper mold and the helium detection lower mold are connected in a detachable manner, and is characterized in that:
[0008] The lower surface of the helium inspection upper mold is provided with a cavity for the product to be inspected, and the upper surface of the product to be inspected is embedded and matched with the cavity for the product to be inspected.
[0009] The upper end surface of the helium detection lower mold is provided with electrode cavities at both ends, and an explosion-proof valve cavity is provided between the electrode cavities.
[0010] A first air channel is provided in the helium detection lower mold, and the electrode cavity and the explosion-proof valve cavity are connected to the first air channel through internal holes; one end of the first air channel is connected to the helium detection equipment and the vacuum equipment through a three-way and an air valve;
[0011] A second air channel is provided in the helium inspection upper mold, and the second air channel is connected to the cavity of the product to be inspected through an internal channel; one end of the second air channel is connected to the helium pipeline and the vacuum equipment through a three-way and a gas valve, and the other end of the second air channel is connected to the pressure gauge and the exhaust valve through a three-way.
[0012] Furthermore, a first sealing ring, a second sealing ring and a third sealing ring are sequentially arranged between the helium inspection lower mold and the helium inspection upper mold from the outside to the inside.
[0013] Furthermore, the first sealing ring is used for sealing between the helium inspection lower mold and the helium inspection upper mold.
[0014] Furthermore, the second sealing ring is used for sealing between the helium inspection upper mold and the electrode cavity.
[0015] Furthermore, the third sealing ring is used for sealing between the helium inspection upper die and the explosion-proof valve cavity.
[0016] Furthermore, the helium inspection upper die and the helium inspection lower die are detachably connected via bolts or snap fits or buckles.
[0017] The beneficial effects of the utility model are:
[0018] One advantage of the utility model is that a second sealing ring and a third sealing ring are provided between the product to be inspected and the lower die of the helium inspection for sealing, and helium is introduced into the upper die of the helium inspection, so that the pressure and the gravity of the product to be inspected can be used to better achieve sealing, and the need for helium pressurization in subsequent processes can also be met;
[0019] One advantage of the utility model is that the pressure gauge and the exhaust valve are matched to replace the helium through the helium pipeline, and the helium gas flow can play the effect of impact and turbulence, so as to solve the problem that the upper die of the helium inspection forms a closed space inside when pressing the product to be inspected, and the helium atoms cannot fully diffuse, resulting in the failure of the inspection;
[0020] One advantage of the utility model is that providing pressurized helium can help to amplify the micro-leakage phenomenon of the product to be inspected, making it easier to identify. Description of the drawings:
[0021] Attached Figure 1 It is a schematic diagram of the three-dimensional explosion structure of the utility model;
[0022] Attached Figure 2 It is a schematic diagram of the internal cross-section structure of the utility model;
[0023] Attached Figure 3 It is a schematic diagram of a three-dimensional exploded structure of the utility model in the implementation state;
[0024] Attached Figure 4 It is a schematic diagram of the internal cross-sectional structure of the implementation state of the utility model; in the accompanying drawings:
[0025] 1. Helium inspection upper die; 2. Second air channel; 3. Second sealing ring; 4. Product cavity to be inspected; 5. Third sealing ring; 6. First air channel; 7. First sealing ring; 8. Helium inspection lower die; 9. Electrode cavity; 10. Explosion-proof valve cavity. Specific implementation method:
[0026] In the description of the present invention, it should be understood that the terms "center", "upper", "lower", "left", "right", "rear", "lower left", "upper right", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the scope of protection of the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0027] The new energy battery top cover plate air tightness detection tool comprises a helium detection upper mold 1 and a helium detection lower mold 8 placed up and down, the helium detection upper mold 1 and the helium detection lower mold 8 are connected in a detachable manner, and are characterized in that:
[0028] The lower surface of the helium inspection upper mold 1 is provided with a product cavity 4 to be inspected, and the upper surface of the product to be inspected is embedded and matched with the product cavity 4 to be inspected.
[0029] Electrode cavities 9 are provided at both ends of the upper end surface of the helium detection lower mold 8, and an explosion-proof valve cavity 10 is provided between the electrode cavities 9.
[0030] The helium detection lower mold 8 is provided with a first air channel 6, and the electrode cavity 9 and the explosion-proof valve cavity 10 are connected to the first air channel 6 through internal holes; one end of the first air channel 6 is connected to the helium detection equipment and the vacuum equipment through a three-way and an air valve;
[0031] A second air channel 2 is provided in the helium inspection upper mold 1, and the second air channel 2 is connected to the product cavity 4 to be inspected through an internal channel; one end of the second air channel 2 is connected to the helium pipeline and the vacuum equipment through a three-way connection and a gas valve, and the other end of the second air channel 2 is connected to the pressure gauge and the exhaust valve through a three-way connection.
[0032] Furthermore, a first sealing ring 7 , a second sealing ring 3 and a third sealing ring 5 are sequentially arranged between the helium inspection lower mold 8 and the helium inspection upper mold 1 from the outside to the inside.
[0033] Furthermore, the first sealing ring 7 is used for sealing between the helium inspection lower mold 8 and the helium inspection upper mold 1 .
[0034] Furthermore, the second sealing ring 3 is used for sealing between the helium inspection upper mold 1 and the electrode cavity 9 .
[0035] Furthermore, the third sealing ring 5 is used for sealing between the helium inspection upper mold 1 and the explosion-proof valve cavity 10 .
[0036] Furthermore, the helium inspection upper die 1 and the helium inspection lower die 8 are detachably connected via bolts, snap-fits or buckles.
[0037] Specific implementation of the utility model:
[0038] The difference between the utility model and the prior art is that:
[0039] 1 A second sealing ring 3 and a third sealing ring 5 for sealing are arranged between the product to be inspected and the helium inspection lower mold 1, and helium is introduced into the helium inspection upper mold 1, so that the pressure and the gravity of the product to be inspected can be used to better achieve sealing, and the need for helium pressurization in subsequent processes can also be met;
[0040] Furthermore, a second air channel 2 is provided in the helium inspection upper mold 1, and the second air channel 2 is connected to the product cavity 4 to be inspected through an internal hole; one end of the second air channel 2 is connected to the helium pipeline and the vacuum equipment through a three-way and a gas valve, and the other end of the second air channel 2 is connected to the pressure gauge and the exhaust valve through a three-way.
[0041] In this way, the helium can be replaced through the helium pipeline by cooperating with the pressure gauge and the exhaust valve. The helium gas flow can have the effect of impact and turbulence, so as to solve the problem that the upper die of the helium inspection forms a closed space inside when pressing the product to be inspected, and the helium atoms cannot fully diffuse, resulting in detection failure.
[0042] At the same time, pressurized helium can help amplify micro-leakage of the product to be inspected, making it easier to identify;
[0043] It should be noted that the utility model is a new energy battery top cover air tightness detection tooling, when working,
[0044] Embodiment 1:
[0045] Vacuum replacement operation:
[0046] 1. Close the air valves of the first airway 6 and the second airway 2, open the vacuum equipment of the first airway 6 and the second airway 2 respectively, and evacuate the first airway 6 and the second airway 2.
[0047] 2. Close the vacuum and carry out pressure maintenance. At the same time, open the exhaust valve of the second airway 2 and the helium pipeline at the other end, and fill the vacuum second airway 2 with helium. When the pressure reaches the threshold, it means that the helium has been replaced in the second airway 2. The high-pressure helium can disperse the air in the dead corner and fully diffuse. The pressurized helium can help to amplify the micro-leakage of the product to be inspected, making it easier to identify. At this time, close the exhaust valve and the helium pipeline to carry out high-pressure helium pressure maintenance treatment on the second airway 2, and use the pressure and the gravity of the product to be inspected to better achieve sealing.
[0048] 3. At this time, if the helium detection equipment does not detect helium, it means that the quality of the product to be inspected meets the requirements; if the helium detection equipment detects helium, it means that the quality of the product to be inspected does not meet the requirements.
[0049] Embodiment 2:
[0050] Helium replacement operation:
[0051] 1. Close the air valves of the first air channel 6 and the second air channel 2, open the vacuum equipment of the first air channel 6, evacuate the first air channel 6, and close the vacuum to maintain the pressure;
[0052] 2. At the same time, open the exhaust valve of the second airway 2 and the helium pipeline at the other end, directly fill the second airway 2 with helium, use the high-pressure helium to squeeze the air, and discharge the air from the exhaust valve. When the pressure reaches the threshold, it means that the helium has been replaced in the second airway 2. The high-pressure helium can disperse the air in the dead corner and fully diffuse. The pressurized helium can help amplify the micro-leakage of the product to be inspected, making it easier to identify;
[0053] 3. At this time, if the helium detection equipment does not detect helium, it means that the quality of the product to be inspected meets the requirements; if the helium detection equipment detects helium, it means that the quality of the product to be inspected does not meet the requirements.
[0054] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A new energy battery top cover plate air tightness detection tool, comprising a helium detection upper mold (1) and a helium detection lower mold (8) placed up and down, the helium detection upper mold (1) and the helium detection lower mold (8) being connected in a detachable manner, Features: The lower surface of the helium inspection upper mold (1) is provided with a product cavity (4) to be inspected, and the upper surface of the product to be inspected is embedded and matched with the product cavity (4). Electrode cavities (9) are provided at both ends of the upper end surface of the helium detection lower mold (8), and an explosion-proof valve cavity (10) is provided between the electrode cavities (9). A first air channel (6) is provided in the helium detection lower mold (8); the electrode cavity (9) and the explosion-proof valve cavity (10) are connected to the first air channel (6) through internal holes; one end of the first air channel (6) is connected to the helium detection equipment and the vacuum equipment through a three-way and an air valve; A second air channel (2) is provided in the helium inspection upper mold (1), and the second air channel (2) is connected to the product cavity (4) to be inspected through an internal hole; one end of the second air channel (2) is connected to the helium pipeline and the vacuum equipment through a three-way connection and a gas valve, and the other end of the second air channel (2) is connected to a pressure gauge and an exhaust valve through a three-way connection.
2. The new energy battery top cover air tightness detection tooling according to claim 1, Features A first sealing ring (7), a second sealing ring (3) and a third sealing ring (5) are arranged in sequence from outside to inside between the helium detection lower mold (8) and the helium detection upper mold (1).
3. The new energy battery top cover air tightness detection tooling according to claim 2, Features The first sealing ring (7) is used for sealing between the helium inspection lower mold (8) and the helium inspection upper mold (1).
4. The new energy battery top cover air tightness detection tooling according to claim 2, Features The second sealing ring (3) is used for sealing between the helium detection upper mold (1) and the electrode cavity (9).
5. The new energy battery top cover air tightness detection tooling according to claim 2, Features The third sealing ring (5) is used for sealing between the helium detection upper mold (1) and the explosion-proof valve cavity (10).
6. The new energy battery top cover air tightness detection tooling according to claim 1, It is characterized in that The helium detection upper die (1) and the helium detection lower die (8) are detachably connected via bolts or snap fits or buckles.