Temporary structure for construction of cross beam platform of main tower

By using a combined structure of bottom support frame, Beret frame foundation layer, triangle bracket group and fixed formwork in the construction of cable-stayed bridge main tower cross beam, the problem of difficulty in welding positioning between steel and triangle bracket is solved, and the construction bearing platform is realized The stable construction and improvement of construction efficiency provide a stable and safe construction platform.

CN221956550UActive Publication Date: 2024-11-05CHINA RAILWAY GUANGZHOU ENG GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420277622.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-11-05
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

In the construction of the main tower beam of cable-stayed bridge, it is difficult to position and align the steel and the triangular bracket weld, which affects the quality of the construction bearing platform and the stable construction of the climbing frame, resulting in a decrease in construction efficiency.

Method used

Adopt a temporary construction structure including the bottom support frame, the base layer of the Beret frame, the triangle bracket group and the shaped formwork. The removable installation of the U-bolt and the fixing nut and the cooperation of the outer limit plates ensures the stable positioning of the triangle bracket group. and fine-tune, shaping templates are set to consolidate the carrier platform and provide a more stable infrastructure.

Benefits of technology

The quality of the construction bearing platform and the stable construction of climbing frames have been improved, the installation and disassembly of the construction platform have been simplified, the construction efficiency and safety have been improved, and a stable and safe temporary operation channel and platform have been provided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956550U_ABST
    Figure CN221956550U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge construction, in particular to a main tower cross beam platform construction temporary structure which comprises a construction bearing platform, the construction bearing platform comprises a bottom supporting frame and a bailey truss foundation layer, and the bottom supporting frame is arranged at the bottom end of the bailey truss foundation layer; the bottom support frame is used for providing stable support for the bailey truss foundation layer; the two ends of the bailey truss foundation layer extend outwards in the longitudinal bridge direction to be provided with triangular bracket sets, the triangular bracket sets are detachably installed on the bailey truss foundation layer, shaping formworks are arranged at the top ends of the bailey truss foundation layer and the triangular bracket sets correspondingly, climbing frames are arranged on the top faces of the shaping formworks, and the climbing frames are arranged on the top faces of the shaping formworks. The climbing frames are located on the two sides of the main tower cross beam respectively. The main tower cross beam construction bearing platform has the advantages that the construction quality of the main tower cross beam construction bearing platform is improved, stable building of a climbing frame is conveniently achieved, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a temporary structure for the construction of a main tower crossbeam platform. Background Art

[0002] A cable-stayed bridge, also known as a cable-tensioned bridge, is a type of bridge in which the main beam is directly pulled onto the bridge tower by many cables. It is a structural system composed of pressure-bearing towers, tensioned cables and bending-bearing beams.

[0003] When constructing the crossbeam of the main tower of a cable-stayed bridge, it is necessary to build temporary climbing frames on both sides of the crossbeam. At present, the construction of temporary climbing frames generally uses a steel pipe frame as the bottom support, and then sets up a steel section on the top of the steel pipe frame to form an initial construction bearing platform at the bottom of the crossbeam; secondly, in order to extend the construction bearing platform, it is necessary to weld triangular brackets at both ends of the steel section, and finally set up a climbing frame above the triangular bracket, so that the climbing frame can be set on both sides of the crossbeam to realize the construction of temporary climbing frames, thereby providing a temporary working channel and construction platform for the constructors.

[0004] However, in the prior art, it is difficult to position and align the steel section and the triangular bracket when welding them, which in turn affects the construction quality of the construction bearing platform, is not conducive to the stable construction of the climbing frame, and leads to a decrease in construction efficiency. Summary of the invention

[0005] In order to improve the construction quality of the construction bearing platform, to facilitate the stable construction of the climbing frame, and to improve the construction efficiency, the present application provides a temporary structure for the construction of the main tower beam platform.

[0006] This application provides a temporary structure for the construction of a main tower beam platform, which adopts the following technical solution:

[0007] A temporary construction structure for a main tower beam platform comprises: a construction bearing platform, wherein the construction bearing platform comprises a bottom support frame and a Bailey frame foundation layer, wherein the bottom support frame is arranged at the bottom end of the Bailey frame foundation layer, and the bottom support frame is used to provide stable support for the Bailey frame foundation layer; both ends of the Bailey frame foundation layer are respectively provided with triangular bracket groups extending outward in a longitudinal bridge direction, and the triangular bracket groups are detachably mounted on the Bailey frame foundation layer, and the top ends of the Bailey frame foundation layer and the triangular bracket groups are respectively provided with shaping templates, and the top surface of the shaping templates is provided with climbing frames, and the climbing frames are respectively located on both sides of the main tower beam.

[0008] By adopting the above technical scheme, under the stable support of the bottom support frame, the Bailey frame foundation layer can be stably set at the bottom of the main tower beam, and then through the Bailey frame foundation layer, a stable foundation is provided for the construction of the bearing platform and the climbing frame; then, the setting of the triangular bracket group enables the construction bearing platform to be extended in the longitudinal direction of the bridge, so as to provide the basic structure and stable bearing function for the construction of the climbing frames on both sides of the beam through the triangular bracket group, and the detachable installation of the triangular bracket group on the Bailey frame foundation layer enables the installation position of the triangular bracket group on the Bailey frame foundation layer to be adjusted and changed, It is beneficial to realize the positioning and installation of the triangular bracket group on the Bailey frame foundation layer, thereby improving the construction quality of the construction bearing platform, so as to realize the stable construction of the climbing frame, and make the installation and disassembly of the temporary construction platform of the main tower beam more convenient, so as to improve the construction efficiency; at the same time, the setting of the finalized template consolidates the overall structure of the construction bearing platform and ensures the flatness of the bearing surface of the construction bearing platform, which is conducive to the more stable construction of the climbing frame and the improvement of construction safety, so as to provide the constructors with a stable and safe temporary working channel and construction platform for the main tower beam through the climbing frame and the construction bearing platform.

[0009] Preferably, a U-shaped bolt and a fixing nut are provided between the Bailey frame base layer and the triangular bracket group, and the U-shaped bolt and the fixing nut are threadedly connected and matched, and the U-shaped bolt and the fixing nut are matched to connect and fix the Bailey frame base layer and the triangular bracket group.

[0010] By adopting the above technical scheme, the triangular bracket group can be detachably installed on the Bailey frame foundation layer through U-bolts and fixing nuts, and it is convenient for the constructor to position and install the triangular bracket group on the Bailey frame foundation layer. At the same time, the installation position of the triangular bracket group on the Bailey frame foundation layer can be fine-tuned, thereby improving the construction quality of the construction bearing platform, facilitating the stable construction of the climbing frame, and making the installation and disassembly of the temporary construction platform of the main tower beam more convenient, thereby improving the construction efficiency.

[0011] Preferably, an outer limit plate is detachably mounted on the side of the U-shaped bolt close to the fixing nut.

[0012] By adopting the above technical solution, the locking effect of the U-bolt and the fixing nut on the triangular bracket group is strengthened through the outer limit plate, so that the triangular bracket group can be more stably locked and fixed on the Bailey frame foundation layer.

[0013] Preferably, the outer limit plates are respectively sleeved on both ends of the U-shaped bolt, and the outer limit plates are located at the bottom end of the fixing nut.

[0014] By adopting the above technical solution, the outer limit plates are respectively sleeved on both ends of the U-bolts to achieve detachable installation of the outer limit plates on the U-bolts, so as to facilitate installation and disassembly of the triangular bracket group on the Bailey frame foundation layer.

[0015] Preferably, the outer limit plates at both ends of the U-shaped bolt are arranged as an integral structure.

[0016] By adopting the above technical scheme, the outer limit plates at both ends of the U-bolt are arranged in an integrated structure, so that the outer limit plates at both ends of the U-bolt can restrain and cooperate with each other, which is conducive to further strengthening the locking effect of the U-bolt and the fixing nut on the triangular bracket, so that the triangular bracket group can be more stably locked and fixed on the Bailey frame foundation layer, providing a more stable foundation for the construction of the climbing frame, thereby improving construction safety.

[0017] Preferably, reinforcement structural layers are respectively provided between the shaping template and the Bailey frame base layer and between the shaping template and the triangular bracket group, and the reinforcement structural layers are used to consolidate the overall structure of the construction bearing platform.

[0018] By adopting the above technical solution, the overall structure of the construction bearing platform can be consolidated and strengthened under the reinforcement effect of the reinforced structural layer, which is conducive to providing a more stable foundation for the construction of the climbing frame, thereby providing a more stable and safe main tower beam temporary working channel and construction platform for the constructors to improve construction safety.

[0019] Preferably, the reinforcement structure layer is a steel reinforcement structure layer.

[0020] By adopting the above technical solution, the overall structure of the construction bearing platform is consolidated and strengthened by steel sections, thereby providing a more stable bearing effect for the constructors.

[0021] Preferably, the steel sections in the reinforcement structure layer and the Bailey frames in the Bailey frame base layer are arranged in a staggered manner horizontally and vertically.

[0022] By adopting the above technical solution, the steel sections and Bailey frames are arranged in a staggered manner horizontally and vertically, thereby improving the connection stability between the reinforcement structure layer and the Bailey frame foundation layer, thereby further consolidating and strengthening the overall structure of the construction bearing platform, so as to provide constructors with a more stable and safe main tower beam temporary working channel and construction platform, thereby further improving construction safety.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] 1. Under the stable support of the bottom support frame, the Bailey frame foundation layer can be stably set at the bottom of the main tower beam, and then through the Bailey frame foundation layer, a stable foundation is provided for the construction of the bearing platform and the climbing frame. Then, the setting of the triangular bracket group allows the construction bearing platform to be extended in the longitudinal direction of the bridge, so as to provide the basic structure and stable bearing function for the construction of the climbing frames on both sides of the beam through the triangular bracket group. In addition, the detachable installation of the triangular bracket group on the Bailey frame foundation layer allows the installation position of the triangular bracket group on the Bailey frame foundation layer to be adjusted and changed, which is conducive to achieving The triangular bracket group is positioned and installed on the Bailey frame foundation layer, thereby improving the construction quality of the construction bearing platform, so as to realize the stable construction of the climbing frame, and make the installation and disassembly of the temporary construction platform of the main tower beam more convenient, so as to improve the construction efficiency. At the same time, the setting of the fixed template consolidates the overall structure of the construction bearing platform and ensures the flatness of the bearing surface of the construction bearing platform, which is conducive to the more stable construction of the climbing frame and the improvement of construction safety, so as to provide the constructors with a stable and safe temporary operation channel and construction platform for the main tower beam through the climbing frame and the construction bearing platform;

[0025] 2. Under the cooperation of U-bolts, fixing nuts and outer limit plates, the triangular bracket group can be detachably installed on the Bailey frame foundation layer, and it is convenient for constructors to stably position and install the triangular bracket group on the Bailey frame foundation layer. At the same time, the installation position of the triangular bracket group on the Bailey frame foundation layer can be fine-tuned, thereby improving the construction quality of the construction bearing platform, facilitating the stable construction of the climbing frame, and making the installation and disassembly of the temporary construction platform of the main tower beam more convenient, thereby improving the construction efficiency;

[0026] 3. Under the reinforcement effect of the reinforced structural layer, the overall structure of the construction bearing platform is consolidated and strengthened, which is conducive to providing a more stable foundation for the construction of the climbing frame, thereby providing a more stable and safe main tower beam temporary working channel and construction platform for the constructors to improve construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall structure of the temporary structure for the main tower beam platform construction in the first embodiment of the present application;

[0028] Figure 2 This is a side view of the temporary structure for the main tower crossbeam platform construction in Example 1 of the present application after hiding one side of the main tower;

[0029] Figure 3 It is the embodiment of the present application Figure 2 A local enlarged schematic diagram of the middle A;

[0030] Figure 4 This is a schematic diagram of the structure after the temporary structure of the main tower crossbeam platform construction in the second embodiment of the present application hides one side of the main tower;

[0031] Figure 5 It is the second embodiment of the present application. Figure 4 A local enlarged schematic diagram of point B in the middle.

[0032] Explanation of the reference numerals: 1. Main tower; 11. Crossbeam; 2. Construction bearing platform; 21. Bottom support frame; 22. Bailey frame foundation layer; 221. Bailey frame; 23. Triangular bracket group; 231. Triangular bracket; 2311. Fixed part; 2312. Extension part; 24. Forming formwork; 25. Reinforcement structure layer; 251. Steel section; 3. Climbing frame; 4. Connecting rod; 5. U-bolt; 6. Fixing nut; 7. External limit plate. DETAILED DESCRIPTION

[0033] The following is combined with Figure 1-5 This application is described in further detail.

[0034] The embodiment of the present application discloses a temporary structure for the construction of a main tower beam platform.

[0035] Embodiment 1

[0036] Reference Figure 1 A temporary structure for the construction of a main tower beam platform includes a construction bearing platform 2, which is arranged at the bottom of the main tower beam 11, and is used to provide a stable bearing effect for the constructors. The construction bearing platform 2 includes a bottom support frame 21 and a Bailey frame foundation layer 22, and the bottom support frame 21 is arranged at the bottom end of the Bailey frame foundation layer 22, and the bottom support frame 21 is used to provide stable support for the Bailey frame foundation layer 22. The two ends of the Bailey frame foundation layer 22 are respectively provided with a triangular bracket group 23 extending outward in the longitudinal direction, and the triangular bracket group 23 can be detachably installed on the Bailey frame foundation layer 22, and the top of the Bailey frame foundation layer 22 and the triangular bracket group 23 are respectively provided with a fixed template 24, and the top surface of the fixed template 24 located at the top of the triangular bracket group 23 is provided with a climbing frame 3, so that the climbing frame 3 is respectively located on both sides of the main tower beam 11, and the climbing frame 3 is used to provide a working channel for the construction of the beam 11 for the constructors.

[0037] Under the stable support of the bottom support frame 21, the Bailey frame foundation layer 22 can be stably set at the bottom of the main tower 1 beam 11, and then through the Bailey frame foundation layer 22, a stable foundation is provided for the construction of the bearing platform 2 and the climbing frame 3; then, the setting of the triangular bracket group 23 enables the construction bearing platform 2 to extend in the longitudinal direction of the bridge, so as to provide a basic structure and stable bearing function for the construction of the climbing frame 3 on both sides of the beam 11 through the triangular bracket group 23, and the detachable installation of the triangular bracket group 23 on the Bailey frame foundation layer 22 enables the installation position of the triangular bracket group 23 on the Bailey frame foundation layer 22 to be adjusted and changed, which is conducive to the positioning and installation of the triangular bracket group 23 on the Bailey frame foundation layer 22, thereby improving the construction quality of the construction bearing platform 2, so as to achieve the stable construction of the climbing frame 3, and make the installation and disassembly of the temporary construction platform of the main tower 1 beam 11 more convenient, thereby improving the construction efficiency. At the same time, the setting of the finalized formwork 24 consolidates the overall structure of the construction bearing platform 2 and ensures the flatness of the bearing surface of the construction bearing platform 2, which is conducive to a more stable construction of the climbing frame 3 and improved construction safety, thereby providing the constructors with a stable and safe temporary working channel and construction platform for the main tower 1 beam 11 through the climbing frame 3 and the construction bearing platform 2.

[0038] Reference Figure 2 The bottom support frame 21 is a steel pipe support frame, which is used to strengthen and consolidate the overall structure of the bottom support frame 21, so that the overall structural stability of the bottom support frame 21 can be improved, thereby providing a more stable support for the construction bearing platform 2 and the climbing frame 3. A connecting rod 4 is arranged at the top of the bottom support frame 21 in the horizontal direction; the Bailey frame foundation layer 22 includes a plurality of Bailey frames 221, and the plurality of Bailey frames 221 are evenly arranged at the top of the connecting rod 4 in the longitudinal direction, so that the connecting rod 4 and the plurality of Bailey frames 221 are arranged in a staggered manner horizontally and vertically, and the plurality of Bailey frames 221 are tightly connected and fixed to each other, and then under the action of the connecting rod 4, the connection between the plurality of Bailey frames 221 is strengthened, thereby improving the overall structural stability of the Bailey frame foundation layer 22, so that the Bailey frame foundation layer 22 can be more stably installed at the top of the bottom support frame 21, and the construction quality of the construction bearing platform 2 is further improved, so as to provide a more stable foundation for the construction of the climbing frame 3, and thus it is conducive to further improving the construction safety.

[0039] Reference Figure 2 and Figure 3The triangular bracket group 23 includes a plurality of triangular brackets 231, and the plurality of triangular brackets 231 are respectively arranged at the ends of the plurality of Bailey frames 221, and the plurality of triangular brackets 231 are tightly connected and fixed to each other. Specifically, the top of the triangular bracket 231 includes a fixing portion 2311 and an extension portion 2312. The fixing portion 2311 at the top of the triangular bracket 231 can be detachably installed on the bottom surface of the Bailey frame 221 near the end, and the extension portion 2312 of the triangular bracket 231 extends outward away from the Bailey frame 221, so that the triangular bracket 231 is installed on the Bailey frame 221 through the fixing portion 2311, and the extension portion 2312 provides a basic structure and a stable bearing function for the construction of the climbing frames 3 on both sides of the beam 11. More specifically, a U-shaped bolt 5 and a fixing nut 6 are provided between the Bailey frame base layer 22 and the triangular bracket group 23. The U-shaped bolt 5 passes through the fixing portion 2311 of the triangular bracket 231 and the bottom surface of the Bailey frame 221 near the end, and the two ends of the U-shaped bolt 5 are respectively threadedly connected to the fixing nut 6. The U-shaped bolt 5 and the fixing nut 6 are used to connect and fix the Bailey frame 221 to the triangular bracket 231.

[0040] When building the construction platform, the triangular bracket 231 is positioned and installed at the end of the Bailey frame 221 through the U-bolt 5, and then the fixing nut 6 is threadedly connected and fixed on the two ends of the U-bolt 5, thereby realizing the stable installation of the triangular bracket group 23 at the end of the Bailey frame base layer 22; when it is necessary to adjust the position of the triangular bracket group 23 or disassemble the triangular bracket group 23, loosen the fixing nut 6, release the threaded connection between the fixing nut 6 and the U-bolt 5, and then disassemble the U-bolt 5, release the limitation of the triangular bracket 231 by the U-bolt 5 and the fixing nut 6, so as to fine-tune the position of the triangular bracket group 23 accordingly; or disassemble the triangular bracket group 23 from the Bailey frame base layer 22, thereby realizing the adjustment and change of the position of the triangular bracket group 23 on the Bailey frame base layer 22, and realizing the disassembly of the triangular bracket group 23. Therefore, the U-bolts 5 and the fixing nuts 6 are used to realize the detachable installation of the triangular bracket group 23 on the Bailey frame foundation layer 22, and it is convenient for the constructor to position and install the triangular bracket group 23 on the Bailey frame foundation layer 22. At the same time, the installation position of the triangular bracket group 23 on the Bailey frame foundation layer 22 can be fine-tuned, thereby improving the construction quality of the construction bearing platform 2, facilitating the stable construction of the climbing frame 3, and making the installation and disassembly of the temporary construction platform of the main tower 1 beam 11 more convenient, thereby improving the construction efficiency.

[0041] Reference Figure 2 and Figure 3In order to strengthen the locking effect of the U-bolt 5 and the fixing nut 6 on the triangular bracket 231, an outer limit plate 7 is detachably installed on the side of the U-bolt 5 close to the fixing nut 6, so that the outer limit plate 7 is located between the fixing nut 6 and the Bailey frame 221, thereby increasing the action area of ​​the fixing nut 6 on the Bailey frame 221 through the outer limit plate 7, and then the triangular bracket 231 is more stably locked and fixed on the Bailey frame 221. Specifically, the outer limit plates 7 are respectively sleeved on both ends of the U-bolt 5, and the outer limit plates 7 are located at the bottom end of the fixing nut 6, so that the outer limit plates 7 are placed between the fixing nut 6 and the Bailey frame 221, thereby realizing the detachable installation of the outer limit plate 7 on the U-bolt 5. Furthermore, the outer limit plates 7 at both ends of the U-shaped bolt 5 are arranged as an integrated structure, so that the outer limit plates 7 at both ends of the U-shaped bolt 5 can be restrained and cooperated with each other, and the action area of ​​the fixing nut 6 on the Bailey frame 221 is further increased, which is conducive to further strengthening the locking effect of the U-shaped bolt 5 and the fixing nut 6 on the triangular bracket 231, so that the triangular bracket 231 can be more stably locked and fixed on the Bailey frame 221, and further realize the stable installation of the triangular bracket group 23 at the end of the Bailey frame base layer 22, so as to provide a more stable foundation for the construction of the climbing frame 3, thereby improving construction safety.

[0042] Reference Figure 2 Furthermore, a reinforcement structure layer 25 is respectively provided between the fixed formwork 24 and the Bailey frame foundation layer 22 and between the fixed formwork 24 and the triangular bracket group 23. The reinforcement structure layer 25 is used to consolidate the overall structure of the construction bearing platform 2, which is conducive to providing a more stable foundation for the construction of the climbing frame 3, thereby providing a more stable and safe temporary working channel and construction platform for the main tower 1 beam 11 for the constructors to improve the construction safety. Specifically, the reinforcement structure layer 25 is a steel reinforcement structure layer 25, that is, the reinforcement structure layer 25 is composed of a plurality of steel sections 251, and the plurality of steel sections 251 are tightly connected and fixed to each other, so as to consolidate and strengthen the overall structure of the construction bearing platform 2 through the steel sections 251, thereby providing a more stable bearing effect for the constructors. More specifically, a plurality of steel sections 251 are evenly arranged in the transverse direction at the bottom end of the forming template 24, so that the steel sections 251 and the Bailey frames 221 as well as the steel sections 251 and the triangular brackets 231 are respectively arranged in a staggered manner horizontally and vertically, so as to improve the connection stability between the reinforcement structure layer 25 and the Bailey frame base layer 22 as well as the reinforcement structure layer 25 and the triangular bracket group 23, thereby further consolidating and strengthening the overall structure of the construction bearing platform 2, so as to provide constructors with a more stable and safe temporary working channel and construction platform for the main tower 1 beam 11, thereby further improving the construction safety.

[0043] Embodiment 2

[0044] Reference Figure 4 and Figure 5The difference between this embodiment and the first embodiment is that the side end of the triangular bracket 231 is set as a fixing part 2311, and the top of the triangular bracket 231 is set as an extension part 2312. The fixing part 2311 of the triangular bracket 231 is tightly fitted with the end of the Bailey frame 221, and the upper side and lower side of the fixing part 2311 of the triangular bracket 231 are respectively fixed to the end of the Bailey frame 221 by U-shaped bolts 5 and fixing nuts 6, so that the top extension part 2312 of the triangular bracket 231 is flush with the top of the Bailey frame 221. In addition, under the limiting action of the fixing nuts 6, the outer limiting plate 7 is abutted against the surfaces of the triangular bracket 231 and the Bailey frame 221, and then the fixing nuts 6 at both ends of the U-shaped bolts 5 increase the action area of ​​the triangular bracket 231 and the Bailey frame 221 respectively through the outer limiting plate 7, so that the locking action of the triangular bracket 231 on the Bailey frame 221 by the cooperation of the U-shaped bolts 5 and the fixing nuts 6 is further strengthened.

[0045] Therefore, under the cooperation of the U-bolt 5, the fixing nut 6 and the outer limit plate 7, the triangular bracket 231 is positioned and installed on the Bailey frame 221 through the fixing portion 2311, and the triangular bracket group 23 is detachably installed at the end of the Bailey frame base layer 22, so that the installation and disassembly of the temporary construction platform of the main tower 1 beam 11 is more convenient, which is beneficial to improve the construction efficiency; secondly, through the extension portion 2312, a basic structure and a stable bearing function are provided for the construction of the climbing frame 3 on both sides of the beam 11, and the detachable installation of the triangular bracket group 23 on the Bailey frame base layer 22 enables the installation position of the triangular bracket group 23 on the Bailey frame base layer 22 to be fine-tuned, thereby improving the construction quality of the construction bearing platform 2, which is beneficial to further realize the stable construction of the climbing frame 3, and then through the climbing frame 3 and the construction bearing platform 2, a stable and safe temporary working channel and construction platform for the main tower 1 beam 11 are provided for the constructors.

[0046] The above are all preferred embodiments of the present application. The embodiments are only explanations of the present application and are not intended to limit the protection scope of the present application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A temporary structure for the construction of a main tower beam platform, characterized in that: The invention comprises a construction bearing platform (2), wherein the construction bearing platform (2) comprises a bottom support frame (21) and a Bailey frame foundation layer (22), wherein the bottom support frame (21) is arranged at the bottom end of the Bailey frame foundation layer (22), and the bottom support frame (21) is used to provide stable support for the Bailey frame foundation layer (22); both ends of the Bailey frame foundation layer (22) are respectively provided with triangular bracket groups (23) extending outward in the longitudinal direction, and the triangular bracket groups (23) are detachably mounted on the Bailey frame foundation layer (22); the top ends of the Bailey frame foundation layer (22) and the triangular bracket groups (23) are respectively provided with shaping templates (24); the top surface of the shaping template (24) is provided with climbing frames (3), and the climbing frames (3) are respectively located on both sides of the cross beam (11) of the main tower (1).

2. A temporary structure for construction of a main tower beam platform according to claim 1, characterized in that: A U-shaped bolt (5) and a fixing nut (6) are provided between the Bailey frame base layer (22) and the triangular bracket group (23); the U-shaped bolt (5) and the fixing nut (6) are threadedly connected and matched; the U-shaped bolt (5) and the fixing nut (6) are matched to connect and fix the Bailey frame base layer (22) and the triangular bracket group (23).

3. A temporary structure for construction of a main tower beam platform according to claim 2, characterized in that: An outer limit plate (7) is detachably mounted on the side of the U-shaped bolt (5) close to the fixing nut (6).

4. A temporary structure for construction of a main tower beam platform according to claim 3, characterized in that: The outer limit plates (7) are respectively sleeved on the two ends of the U-shaped bolt (5), and the outer limit plates (7) are located at the bottom end of the fixing nut (6).

5. A temporary structure for construction of a main tower beam platform according to claim 4, characterized in that: The outer limit plates (7) at both ends of the U-shaped bolt (5) are arranged as an integral structure.

6. A temporary structure for construction of a main tower beam platform according to claim 1, characterized in that: A reinforcement structure layer (25) is respectively provided between the shaping template (24) and the Bailey frame foundation layer (22) and between the shaping template (24) and the triangular bracket group (23), and the reinforcement structure layer (25) is used to consolidate the overall structure of the construction bearing platform (2).

7. A temporary structure for construction of a main tower beam platform according to claim 6, characterized in that: The reinforcement structure layer (25) is a steel reinforcement structure layer (25).

8. A temporary structure for construction of a main tower beam platform according to claim 7, characterized in that: The steel sections (251) in the reinforcement structure layer and the Bailey frames (221) in the Bailey frame foundation layer (22) are arranged in a staggered manner in both the horizontal and vertical directions.