Positioning lifting appliance at orifice of large-diameter reinforcement cage
By designing a positioning sling at the opening of the large-diameter steel cage, and using structures such as support columns, hanging components and guardrails, the problem of the steel cage offset during the pouring of concrete is solved, and the strength and construction safety of the cast piles are improved.
Patent Information
- Application Number
- CN202420277340.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-04
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-02-04
AI Technical Summary
During the construction of cast piles, the steel cage is easily deviated due to impact during the concrete cast pile, resulting in the position of the cast pile not being centered, reducing its strength and structural stability.
A large-diameter steel cage hole positioning sling is designed, including support columns, hanging components, guardrails and positioning slots. It is connected to the steel cage through hanging components, and is positioned and surrounded by guardrails and positioning slots to ensure the steel cage. and the filling pipes remain stable when filling the concrete.
It effectively reduces the movement of the steel cage when pouring concrete, improves the strength and structural stability of the cast piles, and improves the safety of construction workers through guardrails, reducing the risk of construction workers falling into drilling.
Smart Images

Figure CN221956735U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of positioning hangers, and in particular to a positioning hanger for an opening of a large-diameter steel cage. Background Art
[0002] The steel cage is a cage-like structure made of steel bars woven or welded in a certain arrangement and spacing, and is often used to reinforce and strengthen concrete components.
[0003] During the construction of bored piles, the casing is first embedded, and then a hole is drilled using a drilling machine until the designed hole depth is reached. The hole is then cleaned to remove impurities such as mud and sand at the bottom of the hole. The steel cage is then placed in the hole to increase the strength and stability of the bored pile, and finally concrete is poured into the hole.
[0004] After the steel cage is placed in the hole, concrete enters the hole through the pouring pipe. During the concrete pouring process, the steel cage is often impacted by the concrete, causing the position of the steel cage to shift. As a result, after the concrete is mixed and poured, the position of the steel cage is not centered, thereby reducing the strength and structural stability of the bored pile. Utility Model Content
[0005] In order to reduce the movement of the steel cage when pouring concrete, the present application provides a positioning hanger for the opening of a large-diameter steel cage.
[0006] The present application provides a large diameter steel cage hole positioning hanger, which adopts the following technical solution:
[0007] A positioning hanger for the opening of a large-diameter steel cage includes a support column, wherein there are multiple support columns distributed along the outer wall of a casing, a hanging assembly is installed on the top of the support column, the steel cage is connected to the support frame through the hanging assembly, a guardrail is arranged between two adjacent support columns, and the multiple guardrails surround the casing.
[0008] By adopting the above technical solution, the crane puts the steel cage into the borehole until only the top of the steel cage is located on the outer wall of the casing. Then the construction personnel connect the hanging assembly to the steel cage, and the hanging assembly lifts the steel cage. Then the crane is evacuated, and the hanging assembly limits the steel bars of the steel cage. Under the action of the hanging assembly, the steel cage is positioned in the middle of the borehole, thereby reducing the movement of the steel cage when pouring concrete, thereby increasing the strength and structural stability of the bored pile, and under the action of the guardrail, the guardrail surrounds the casing, thereby separating the construction personnel from the borehole, thereby improving the safety of the construction personnel passing through the borehole and reducing the situation of the construction personnel falling into the borehole.
[0009] Preferably, the hanging assembly includes a load-bearing rod, the top of the load-bearing rod is connected to the top of the support column, the load-bearing rod passes through the steel cage, and one end of the steel cage is placed on the top surface of the load-bearing rod.
[0010] By adopting the above technical solution, the load-bearing rod is passed through the hole in the outer wall of the steel cage, and the steel bars of the steel cage are placed on the top surface of the load-bearing rod, so that the load-bearing rod lifts the steel cage, and then positions the steel cage so that the steel cage is located in the middle of the steel cage.
[0011] Preferably, the hanging assembly also includes a limiting plate, the bottom surface of the limiting plate is connected to the top surface of the load-bearing rod near one end of the center of the steel cage, a groove is formed between the limiting plate and the load-bearing rod, and one end of the steel cage is located in the groove.
[0012] By adopting the above technical solution, the steel cage is placed in the groove. Under the action of the limiting plate, the limiting plate limits the steel bars of the steel cage, reducing the possibility of the steel cage slipping from the load-bearing rod, thereby improving the connection stability between the steel cage and the hanging assembly.
[0013] Preferably, the load-bearing rod is rotatably connected to the support column.
[0014] By adopting the above technical solution, the load-bearing rod is rotatably connected to the support column, so that the position of the load-bearing rod is more flexible. When the support column is installed, the load-bearing rod contacts the steel cage, and the load-bearing rod can be rotated, thereby reducing the damage of the load-bearing rod to the steel cage.
[0015] Preferably, a base is installed on the bottom surface of the support column, and the base is a trapezoidal base.
[0016] By adopting the above technical solution, under the action of the base, the contact area between the bottom surface of the base and the ground can be increased, thereby increasing the friction between the base and the ground and reducing the movement of the support frame. At the same time, the center of gravity of the support frame can be lowered, thereby reducing the tilting of the support frame.
[0017] Preferably, the side wall of the guardrail is rotatably connected to one side of the support column.
[0018] By adopting the above technical solution, when construction workers need to enter the guardrail for observation, the operator applies an outward force to the guardrail to rotate the guardrail outward, thereby opening the guardrail. When the construction workers come out of the guardrail, an inward force is applied to the guardrail to close the guardrail.
[0019] Preferably, the side wall of the guardrail is provided with a connecting column, and the support column is provided with a mounting groove on a side close to the connecting column, and the connecting column is movably inserted into the mounting groove.
[0020] By adopting the above technical solution, under the action of the connecting column and the installation groove, the connection stability between the guardrail and the supporting column can be improved, and it is convenient for construction workers to open the supporting column and the guardrail.
[0021] Preferably, an arc groove is provided on one side of the support column close to the center of the steel cage, and positioning grooves are formed between the plurality of support columns, and the perfusion pipe is inserted into the positioning grooves.
[0022] By adopting the above technical solution, the pouring pipe is inserted into the positioning groove, and the positioning groove is used to position the pouring pipe so that the pouring pipe remains in the center of the steel cage for concrete pouring, thereby reducing the displacement of the pouring pipe during the concrete pouring process, thereby reducing the impact of the displacement of the pouring pipe on the steel cage during the concrete pouring process.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. The crane puts the steel cage into the borehole until only the top of the steel cage is located on the outer wall of the casing. Then the construction workers connect the hanging assembly to the steel cage, and the hanging assembly lifts the steel cage. Then the crane is evacuated. The hanging assembly limits the steel bars of the steel cage. Under the action of the hanging assembly, the steel cage is positioned in the middle of the borehole, thereby reducing the movement of the steel cage during concrete pouring, thereby increasing the strength and structural stability of the bored pile. In addition, under the action of the guardrail, the guardrail surrounds the casing, thereby separating the construction workers from the borehole, thereby improving the safety of the construction workers passing through the borehole and reducing the situation of the construction workers falling into the borehole.
[0025] 2. Insert the pouring pipe into the positioning groove. Under the action of the positioning groove, position the pouring pipe so that the pouring pipe remains in the center of the steel cage for concrete pouring, thereby reducing the displacement of the pouring pipe during the concrete pouring process, thereby reducing the impact of the displacement of the pouring pipe on the steel cage during the concrete pouring process. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.
[0027] Figure 2 yes Figure 1 A is an enlarged view of the middle image.
[0028] Explanation of the reference numerals in the accompanying drawings: 1. Support frame; 11. Base; 12. Support column; 121. Vertical bar; 122. Horizontal bar; 123. Installation slot; 13. Positioning slot; 2. Hanging assembly; 21. Load-bearing rod; 22. Limiting plate; 23. Groove; 3. Injection pipe; 4. Guardrail; 41. Base; 42. Grid frame; 421. Connecting column; 5. Casing; 6. Steel cage. DETAILED DESCRIPTION
[0029] The following is combined with Figure 1-2 This application is described in further detail.
[0030] The embodiment of the present application discloses a positioning hanger for an opening of a large-diameter steel cage.
[0031] Reference Figure 1 A positioning hanger for the opening of a large-diameter steel cage includes a support frame 1, and the support frame 1 includes a base 11 and a support column 12. In the embodiment of the present application, the base 11 is a trapezoidal seat, and the support column 12 includes a vertical rod 121 and a horizontal rod 122. The bottom surface of the vertical rod 121 is welded to the top surface of the base 11, and the bottom surface of the horizontal rod 122 is fixed to the top surface of the vertical rod 121. The extension direction of the horizontal rod 122 is perpendicular to the long side of the vertical rod 121. After the horizontal rod 122 and the vertical rod 121 are assembled, an inverted "L"-shaped column is formed. Under the action of the base 11, the contact area between the bottom surface of the base 11 and the ground can be increased, thereby increasing the friction between the base 11 and the ground, reducing the movement of the support frame 1, and at the same time, the center of gravity of the support frame 1 can be lowered, thereby reducing the tipping of the support frame 1.
[0032] Reference Figure 2 A hanging assembly 2 is provided on the bottom surface of the middle part of the cross bar 122, and the hanging assembly 2 includes a load-bearing rod 21 and a limiting plate 22. In the embodiment of the present application, the load-bearing rod 21 is an "L"-shaped rod, and the top of the load-bearing rod 21 is rotatably connected to the bottom surface of the cross bar 122, and the bottom surface of the limiting plate 22 is fixed to the top surface of the load-bearing rod 21 away from one end of the vertical rod 121. After the limiting plate 22 is assembled with the load-bearing rod 21, a groove 23 is formed between the limiting plate 22 and the load-bearing rod 21.
[0033] Reference Figure 1 The number of support frames 1 depends on the specific situation. In the embodiment of the present application, the number of support frames 1 is four. The four support frames 1 are distributed in a rectangular shape along the outside of the casing 5. The hanging assembly 2 is located on the outside of the steel cage 6. The crane puts the steel cage 6 into the borehole until only the top of the steel cage 6 is located on the outer wall of the casing 5. Then the construction personnel insert the limit plate 22 through the hole on the outer wall of the steel cage 6, and place the steel bars of the steel cage 6 in the groove 23. The load-bearing rod 21 lifts the steel cage 6, and then the crane is withdrawn. The limit plate 22 limits the steel bars of the steel cage 6 to reduce the situation where the steel cage 6 slips from the load-bearing rod 21. Under the action of the hanging assembly 2, the steel cage 6 is positioned and positioned in the middle of the borehole, thereby reducing the movement of the steel cage 6 when pouring concrete, thereby increasing the strength and structural stability of the cast-in-place pile.
[0034] An arc groove is provided on one side of the cross bar 122 near the center of the steel cage 6, and a positioning groove 13 is formed between the four cross bars 122. The positioning groove 13 is a circular groove. The positioning groove 13 is located in the center of the steel cage 6. The pouring pipe 3 is inserted into the positioning groove 13. Under the action of the positioning groove 13, the pouring pipe 3 is positioned so that the pouring pipe 3 remains located in the center of the steel cage 6 for concrete pouring, thereby reducing the displacement of the pouring pipe 3 during the concrete pouring process, thereby reducing the impact of the displacement of the pouring pipe 3 on the steel cage 6 during the concrete pouring process.
[0035] Reference Figure 1 The side wall of the support column 12 is provided with a guardrail 4, which includes a base 41 and a grid frame 42. The bottom surface of the grid frame 42 is fixed to the top surface of the base 41. The base 41 is placed on the ground. In the embodiment of the present application, the base 41 is a trapezoidal seat, so that the guardrail 4 is placed on the ground more firmly, reducing the shaking of the guardrail 4. The side wall of the grid frame 42 is rotatably connected to the side wall of the support column 12. Under the action of the guardrail 4, the drill hole can be surrounded, thereby separating the construction personnel from the drill hole, thereby improving the safety of the construction personnel passing through the drill hole and reducing the situation of the construction personnel falling into the drill hole.
[0036] A mounting groove 123 is provided on the side of the support column 12 away from the guardrail 4. There are multiple mounting grooves 123, and the multiple mounting grooves 123 are evenly distributed along the vertical direction of the support column 12. The guardrail 4 is located between two adjacent support columns 12. A connecting column 421 is fixed to the side of the grid frame 42 close to the mounting groove 123. The number of connecting columns 421 is consistent with the number of mounting grooves 123. The connecting columns 421 correspond to the mounting grooves 123 one by one. The connecting columns 421 are adapted to be inserted into the mounting grooves 123. The top surface of the connecting column 421 and the bottom surface of the connecting column 421 are respectively abutted against the inner wall of the support column 12, and friction is generated between the connecting column 421 and the support column 12, thereby limiting the connecting column 421, thereby improving the connection stability between the connecting column 421 and the support column 12.
[0037] When construction workers need to enter the guardrail 4 for observation, the operator applies an outward force to the guardrail 4 to rotate the guardrail 4 outward, thereby opening the guardrail 4. When the construction workers come out of the guardrail 4, they apply an inward force to the guardrail 4 and insert the connecting column 421 into the installation groove 123 to close the guardrail 4. Under the action of the connecting column 421 and the installation groove 123, it is convenient for the construction workers to open the support column 12 and the guardrail 4.
[0038] The above are all preferred embodiments of the present application. The embodiments are only explanations of the present application and are not intended to limit the protection scope of the present application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A positioning hanger for the opening of a large diameter steel cage. It is characterized in that The invention comprises a support column (12), wherein the support column (12) is in plurality and the plurality of support columns (12) are distributed along the outer wall of a casing (5), a hanging assembly (2) is installed on the top of the support column (12), a steel cage (6) is connected to the support column (12) via the hanging assembly (2), a guardrail (4) is arranged between two adjacent support columns (12), and the plurality of guardrails (4) surround the casing (5).
2. A large diameter steel cage hole positioning hanger according to claim 1, It is characterized in that The hanging assembly (2) comprises a load-bearing rod (21), the top of the load-bearing rod (21) is connected to the top of the support column (12), the load-bearing rod (21) passes through the steel cage (6), and one end of the steel cage (6) is placed on the top surface of the load-bearing rod (21).
3. A large diameter steel cage hole positioning hanger according to claim 2, It is characterized in that The hanging assembly (2) further comprises a limiting plate (22), the bottom surface of the limiting plate (22) being connected to the top surface of the load-bearing rod (21) near the center end of the steel cage (6), a groove (23) being formed between the limiting plate (22) and the load-bearing rod (21), and one end of the steel cage (6) being located in the groove (23).
4. A large diameter steel cage hole positioning hanger according to claim 2, It is characterized in that The load-bearing rod (21) is rotatably connected to the support column (12).
5. A large diameter steel cage hole positioning hanger according to claim 1, It is characterized in that A base (11) is installed on the bottom surface of the support column (12), and the base (11) is a trapezoidal base.
6. A large diameter steel cage hole positioning hanger according to claim 1, It is characterized in that The side wall of the guardrail (4) is rotatably connected to one side of the support column (12).
7. A large diameter steel cage hole positioning hanger according to claim 1, It is characterized in that The side wall of the guardrail (4) is provided with a connecting column (421), and a mounting groove (123) is provided on a side of the support column (12) close to the connecting column (421), and the connecting column (421) is movably inserted into the mounting groove (123).
8. A large diameter steel cage hole positioning hanger according to claim 1, It is characterized in that The support column (12) is provided with an arc groove on one side close to the center of the steel cage (6), and positioning grooves (13) are formed between the plurality of support columns (12), and the perfusion pipe (3) is inserted into the positioning groove (13).