Fabricated concrete building
Through the connection of the embedded pipe and steel bars of precast concrete buildings and the design of water stop glue strips, the problems of poor waterproof performance and high alignment accuracy of the prefabricated concrete structure are solved, and construction efficiency and environmental protection are improved.
Patent Information
- Application Number
- CN202420288023.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-07
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-02-07
AI Technical Summary
The existing prefabricated concrete structures have poor waterproof and sealing performance in the joint position, and high alignment accuracy requirements during installation, resulting in low construction efficiency and possible dust and noise pollution.
The prefabricated base plate, prefabricated roof plate and prefabricated wall are connected by embedded pipes and steel bars, combined with the design of water-stop glue strips, improve the waterproof and sealing performance of the joints, and reduce the alignment accuracy requirements through bellows and elastic water-stop glue strips.
It significantly improves the waterproof and sealing performance of prefabricated concrete buildings, simplifies the installation process, improves construction efficiency, reduces dust and noise pollution in on-site construction, and realizes a green and environmentally friendly construction method.
Smart Images

Figure CN221956923U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction, in particular to an assembled concrete building. Background Art
[0002] At present, prefabricated concrete structures have been rapidly developed and widely used in the field of housing construction. However, existing prefabricated concrete structures have problems such as poor waterproof sealing performance at the joints and high positioning accuracy requirements during installation.
[0003] Therefore, there is an urgent need for a prefabricated concrete building to solve the above problems. Utility Model Content
[0004] The utility model aims to provide a prefabricated concrete building, improve the waterproof and airtight performance of the joint position, and reduce the positioning accuracy requirements during the installation process.
[0005] In order to achieve the above object, the utility model provides a prefabricated concrete building, comprising:
[0006] A prefabricated bottom plate, comprising a bottom plate body and a first anti-ridge convexly arranged on the top surface of the bottom plate body, wherein the first anti-ridge extends along the circumferential direction of the bottom plate body, and a plurality of first sleeves extending along the height direction of the prefabricated bottom plate and with the top ends extending to the top surface of the first anti-ridge are pre-buried in the prefabricated bottom plate;
[0007] A prefabricated top plate, in which a plurality of second sleeves extending along the height direction of the prefabricated top plate and with bottom ends extending to the bottom surface of the prefabricated top plate are pre-buried;
[0008] A prefabricated wall, the bottom end of which is arranged on the prefabricated bottom plate, the prefabricated top plate is covered on the top of the prefabricated wall, the prefabricated wall comprises a plurality of prefabricated side plates connected end to end, a plurality of first protruding steel bars arranged at intervals along the length direction of each prefabricated side plate are arranged on the bottom end surface of each prefabricated side plate, a plurality of second protruding steel bars arranged at intervals along the length direction of each prefabricated side plate are arranged on the top end surface, the first protruding steel bars and the second protruding steel bars are extended along the height direction of the prefabricated wall, the first protruding steel bars are inserted into the first sleeve, the second protruding steel bars are inserted into the second sleeve, and the first sleeve and the second sleeve are filled with grouting material;
[0009] Connecting components, two adjacent prefabricated side panels are connected by a plurality of connecting components;
[0010] A water-stop rubber strip is sandwiched between the prefabricated wall and the first anti-ridge, between the prefabricated wall and the prefabricated top plate, and between two adjacent prefabricated side plates.
[0011] As an improvement of the above technical solution, the multiple prefabricated side panels include two first prefabricated side panels and two second prefabricated side panels, the two first prefabricated side panels are spaced apart along a first direction, and the two second prefabricated side panels are spaced apart along a second direction perpendicular to the first direction.
[0012] As an improvement of the above technical solution, the connection component includes:
[0013] A connecting piece, wherein one of the first prefabricated side panel and the second prefabricated side panel is provided with a threaded hole, and the other is provided with a connecting hole corresponding to the threaded hole one by one, and the connecting piece passes through the connecting hole and is screwed to the corresponding threaded hole;
[0014] A fastener is threadedly connected to one end of the connector exposed outside the prefabricated wall and abuts against the prefabricated wall.
[0015] As an improvement of the above technical solution, the connection assembly also includes a plurality of third embedded sleeves embedded in the prefabricated side panels, and the threaded holes are inner holes of the third embedded sleeves.
[0016] As an improvement of the above technical solution, the length of the first prefabricated side panel is greater than that of the second prefabricated side panel, and end faces at both ends of the length direction of the first prefabricated side panel are provided with a plurality of third embedded sleeves arranged at intervals along the height direction of the first prefabricated side panel, and the third embedded sleeves extend along the length direction of the first prefabricated side panel, and both ends of the length direction of the second prefabricated side panel are provided with connecting holes extending along their own thickness direction.
[0017] As an improvement of the above technical solution, the connecting assembly also includes an anchoring end plate embedded in the prefabricated side panel, the middle part of the anchoring end plate is fixedly connected to one end of the corresponding third embedded sleeve extending into the first prefabricated side panel, and the two ends of the anchoring end plate extend in a direction away from the axis of the third embedded sleeve.
[0018] As an improvement of the above technical solution, it also includes steel strips, which are sandwiched between each of the fasteners and the prefabricated wall. There are four steel strips, which are spaced apart along the circumference of the prefabricated wall and extend along the height direction of the prefabricated wall.
[0019] As an improvement of the above technical solution, a door opening is arranged on the prefabricated wall, and a groove corresponding to the door opening is arranged on the first counter-ridge.
[0020] As an improvement of the above technical solution, the bottom end of the groove extends to the top surface of the bottom plate body.
[0021] As an improvement of the above technical solution, both the first sleeve and the second sleeve are corrugated tubes.
[0022] Compared with the prior art, the utility model has the following beneficial effects:
[0023] The prefabricated concrete building of the utility model is formed by splicing a prefabricated bottom plate, a prefabricated top plate and a prefabricated wall. The prefabricated bottom plate, the prefabricated top plate and the prefabricated wall are prefabricated in a factory and are easy to assemble on site. Compared with the cast-in-place structure, the construction efficiency is greatly improved, the construction period is shortened, and the dust and noise pollution during on-site construction are effectively reduced, which is green and environmentally friendly. In addition, a water-stopping rubber strip is sandwiched between the prefabricated wall and the first anti-slope, between the prefabricated wall and the prefabricated top plate, and between two adjacent prefabricated side plates, which effectively improves the waterproof and airtight performance of the prefabricated concrete building at the joint position. In addition, the prefabricated wall and the prefabricated bottom plate are connected by a first sleeve and a first protruding steel bar, and the prefabricated wall and the prefabricated top plate are connected by a second sleeve and a second protruding steel bar, and the water-stopping rubber strip is elastic, so that the positioning accuracy requirement during the installation process is relatively low, thereby further improving the installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural schematic diagram of an assembled concrete building provided by an embodiment of the utility model;
[0025] Figure 2 It is a cross-sectional view of a part of the structure of the assembled concrete building provided by the embodiment of the utility model;
[0026] Figure 3 The utility model provides an explosion-proof method for assembled concrete buildings. Figure 1 ;
[0027] Figure 4 The utility model provides an explosion-proof method for assembled concrete buildings. Figure 2 ;
[0028] Figure 5 It is a structural schematic diagram of a prefabricated bottom plate of an assembled concrete building provided by an embodiment of the utility model;
[0029] Figure 6 It is a structural schematic diagram of a prefabricated top plate of an assembled concrete building provided in an embodiment of the utility model.
[0030] In the figure:
[0031] 1. prefabricated bottom plate; 11. bottom plate body; 12. first counter-ridge; 121. groove; 13. first sleeve;
[0032] 2. Prefabricated top plate; 21. Second casing; 22. Top plate body; 23. Second counter ridge;
[0033] 3. Prefabricated wall; 31. First externally extending steel bar; 32. Second externally extending steel bar; 33. First prefabricated side panel; 34. Second prefabricated side panel; 35. Door opening; 36. Window opening;
[0034] 4. Connecting assembly; 41. Connecting piece; 42. Fastener; 43. Third embedded sleeve; 44. Anchoring end plate;
[0035] 5. Water-stop strip;
[0036] 6. Steel slats. DETAILED DESCRIPTION
[0037] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0038] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0039] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0040] In the description of this embodiment, the terms "upper", "lower", "right" and other directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0041] like Figure 1-Figure 6As shown, an assembled concrete building of an embodiment of the utility model includes a prefabricated bottom plate 1, a prefabricated top plate 2, a prefabricated wall 3, a connection assembly 4 and a waterproof rubber strip 5. The prefabricated bottom plate 1 includes a bottom plate body 11 and a first anti-ridge 12 protruding from the top surface of the bottom plate body 11, the first anti-ridge 12 extends along the circumferential direction of the bottom plate body 11, and a plurality of first sleeves 13 extending along the height direction of the prefabricated bottom plate 1 and the top end extending to the top surface of the first anti-ridge 12 are embedded in the prefabricated bottom plate 1. A plurality of second sleeves 21 extending along the height direction of the prefabricated top plate 2 and the bottom end extending to the bottom surface of the prefabricated top plate 2 are embedded in the prefabricated top plate 2. The bottom ends of the prefabricated walls 3 are all arranged on the prefabricated bottom plate 1, and the prefabricated top plate 2 is covered on the top of the prefabricated wall 3. The prefabricated wall 3 includes a plurality of prefabricated side plates connected end to end, and a plurality of first protruding steel bars 31 arranged at intervals along the length direction of each prefabricated side plate are arranged on the bottom end surface of each prefabricated side plate, and a plurality of second protruding steel bars 32 arranged at intervals along the length direction of each prefabricated side plate are arranged on the top end surface, and the first protruding steel bars 31 and the second protruding steel bars 32 are both extended along the height direction of the prefabricated wall 3, and the first protruding steel bars 31 are inserted into the first sleeve 13, and the second protruding steel bars 32 are inserted into the second sleeve 21. Grouting material is filled in the first sleeve 13 and the second sleeve 21, and the grouting material here is high-strength non-shrinking grouting material. Two adjacent prefabricated side plates are connected by a plurality of connecting components 4. Waterproof rubber strips 5 are sandwiched between the prefabricated wall 3 and the first anti-ridge 12, between the prefabricated wall 3 and the prefabricated top plate 2, and between two adjacent prefabricated side plates. The thickness of the waterproof rubber strips 5 is 20 mm. The first protruding steel bar 31 penetrates the waterproof rubber strips 5 between the prefabricated bottom plate 1 and the prefabricated wall 3, and the second protruding steel bar 32 penetrates the waterproof rubber strips between the prefabricated top plate 2 and the prefabricated wall 3. The prefabricated bottom plate 1, the prefabricated top plate 2 and the prefabricated side plates are all concrete structures.
[0042] The prefabricated concrete building provided in this embodiment has a main building body formed by splicing a prefabricated bottom plate 1, a prefabricated top plate 2 and a prefabricated wall 3. The prefabricated bottom plate 1, the prefabricated top plate 2 and the prefabricated wall 3 are prefabricated in a factory and are easy to assemble on site. Compared with cast-in-place structures, the construction efficiency is greatly improved, the construction period is shortened, and the dust and noise pollution from on-site construction are effectively reduced, which is green and environmentally friendly. In addition, the prefabricated bottom plate 1 is provided with a first anti-ridge 12 extending along the circumference of the bottom plate body 11, and waterstop strips 5 are sandwiched between the prefabricated wall 3 and the first anti-ridge 12, between the prefabricated wall 3 and the prefabricated top plate 2, and between two adjacent prefabricated side plates. The waterstop strip 5 between the prefabricated wall 3 and the first anti-ridge 12 is pressed tightly by the gravity of the prefabricated wall 3 and the prefabricated top plate 2, the waterstop strip 5 between the prefabricated wall 3 and the prefabricated top plate 2 is pressed tightly by the gravity of the prefabricated top plate 2, and the waterstop strip 5 between two adjacent prefabricated side plates is pressed tightly by the pre-tightening force of the connecting component 4, thereby effectively improving the waterproof and airtight performance of the prefabricated concrete building at the joint position. In addition, the prefabricated wall 3 and the prefabricated bottom plate 1 are connected by the first sleeve 13 and the first protruding steel bar 31, and the prefabricated wall 3 and the prefabricated top plate 2 are connected by the second sleeve 21 and the second protruding steel bar 32, and the water stop strip 5 is elastic, so that the positioning accuracy requirements during the installation process are relatively low and the assembly is convenient, thereby further improving the installation efficiency.
[0043] like Figure 6 As shown, in this embodiment, the prefabricated top plate 2 includes a top plate body 22 and a second anti-ridge 23 protruding from the top plate body 22, the second anti-ridge 23 is arranged on the side of the top plate body 22 facing the prefabricated wall 3, and surrounds the top plate body 22. The waterproof rubber strip 5 between the prefabricated top plate 2 and the prefabricated wall 3 is sandwiched between the second anti-ridge 23 and the prefabricated wall 3.
[0044] Specifically, Figure 1-Figure 6 As shown, in this embodiment, the first sleeve 13 and the second sleeve 21 are both corrugated tubes. The corrugated structure of the corrugated tube can improve the connection firmness between the first sleeve 13 and the prefabricated floor and between the second sleeve 21 and the prefabricated top plate 2. At the same time, it can also make the connection between the first sleeve 13 and the second sleeve 21 more firmly after the grouting material is poured into the first sleeve 13 and the second sleeve 21 and solidified. The inner diameter of the first sleeve 13 and the second sleeve 21 needs to be at least 20-30mm larger than the outer diameter of the first protruding steel bar 31 and the second protruding steel bar 32. The first sleeve 13 penetrates the first anti-ridge 12 and the bottom plate body 11, and the second sleeve 21 penetrates the second anti-ridge 23 and the top plate body 22.
[0045] Furthermore, if Figure 1-Figure 4As shown, the plurality of prefabricated side panels include two first prefabricated side panels 33 and two second prefabricated side panels 34. The two first prefabricated side panels 33 are spaced apart along a first direction, and the two second prefabricated side panels 34 are spaced apart along a second direction perpendicular to the first direction. That is, the two first prefabricated side panels 33 and the two second prefabricated side panels 34 are spliced to form a rectangular structure. The prefabricated wall 3 is divided into two first prefabricated side panels 33 and two second prefabricated side panels 34, so that the weight difference between the main components of the prefabricated concrete building, that is, the prefabricated top panel 2, the prefabricated bottom panel 1, the first prefabricated side panel 33 and the second prefabricated side panel 34 is small, which is convenient for transportation and hoisting.
[0046] Furthermore, waterproof glue is applied to the joint between the first prefabricated side panel 33 and the adjacent second prefabricated side panel 34 to further improve the waterproof performance of the prefabricated wall 3 to prevent leakage in the kitchen and bathroom during the later use stage.
[0047] Alternatively, if Figure 1-Figure 4 As shown, the connection assembly 4 includes a connection member 41 and a fastener 42. One of the first prefabricated side panel 33 and the second prefabricated side panel 34 is provided with a threaded hole, and the other is provided with a connection hole corresponding to the threaded hole. The connection member 41 passes through the connection hole and is screwed to the corresponding threaded hole. The fastener 42 is threadedly connected to one end of the connection member 41 exposed outside the prefabricated wall 3 and abuts against the prefabricated wall 3. The connection member 41 passes through the waterproof rubber strip 5 between the first prefabricated side panel 33 and the second prefabricated side panel 34.
[0048] Furthermore, if Figure 2 As shown, the connection assembly 4 also includes a third embedded sleeve 43 embedded in the prefabricated side plate, and the threaded hole is the inner hole of the third embedded sleeve 43. After the connector 41 is inserted into the third embedded sleeve 43 and connected with the third embedded sleeve 43, the threaded hole in the third embedded sleeve 43 should have a redundant length of 2mm-5mm.
[0049] Furthermore, if Figure 1-Figure 4 As shown, the length of the first prefabricated side panel 33 is greater than that of the second prefabricated side panel 34, and a plurality of third embedded sleeves 43 spaced apart along the height direction of the first prefabricated side panel 33 are provided on the end faces at both ends in the length direction of the first prefabricated side panel 33, and the third embedded sleeves 43 extend along the length direction of the first prefabricated side panel 33, and connection holes extending along the thickness direction of the second prefabricated side panel 34 are provided at both ends in the length direction.
[0050] Furthermore, if Figure 2As shown, the connection assembly 4 also includes an anchoring end plate 44 embedded in the prefabricated side plate, the middle of the anchoring end plate 44 is fixedly connected to one end of the corresponding third embedded sleeve 43 extending into the first prefabricated side plate 33, and both ends of the anchoring end plate 44 extend in a direction away from the axis of the third embedded sleeve 43, that is, the anchoring end plate 44 is π-shaped as a whole. The tensile strength of the third embedded sleeve 43 is improved by the anchoring end plate 44, so as to improve the connection firmness between the first prefabricated side plate 33 and the second prefabricated side plate 34.
[0051] Alternatively, if Figure 1-Figure 4 As shown, the prefabricated concrete building provided in this embodiment further includes a steel strip 6, and a steel strip 6 is sandwiched between each fastener 42 and the prefabricated wall 3. There are four steel strips 6, which are arranged at intervals along the circumference of the prefabricated wall 3 and extend along the height direction of the prefabricated wall 3. The pressure of the fastener 42 on the second prefabricated wall 3 is dispersed by providing the steel strips 6.
[0052] Alternatively, if Figure 1-Figure 4 As shown, the prefabricated wall 3 is provided with a door opening 35, and the first counter ridge 12 is provided with a groove 121 corresponding to the door opening 35. Specifically, the door opening 35 is provided on the first prefabricated side plate 33, and the window opening 36 is provided on the second prefabricated side plate 34.
[0053] Furthermore, if Figure 4 and Figure 5 As shown, the bottom end of the groove 121 extends to the top surface of the bottom plate body 11 .
[0054] The process of on-site hoisting operation of the prefabricated concrete building provided in this embodiment is as follows:
[0055] 1. First, conduct on-site measurement and layout, place the prefabricated base plate 1 in place, and paste a 20 mm thick waterproof strip 5 on the first anti-ridge 12.
[0056] 2. Then, high-strength non-shrinkage grouting material is injected into all the first embedded sleeves on the precast base plate 1, and two pieces of reinforced concrete first precast side plates 33 are hoisted above the precast base plate 1 respectively, and the first protruding steel bars 31 are inserted into the first embedded sleeves on the precast base plate 1. After adjusting the verticality of the first precast side plates 33, diagonal braces are set to temporarily fix the first precast side plates 33.
[0057] 3. Next, hoist two second prefabricated side panels 34 with window frames, and similarly insert the first protruding steel bar 31 into the first embedded sleeve on the prefabricated bottom plate 1. Place the waterproof rubber strip 5 between the first prefabricated side panel 33 and the second prefabricated side panel 34, and after adjusting the verticality of the second prefabricated side panel 34, set a diagonal brace on the outside to temporarily fix the second prefabricated side panel 34. Screw the connector 41 into the threaded hole, and then tighten it with the fastener 42.
[0058] 4. Paste a 20mm thick waterproof strip 5 on the top surface of the first prefabricated side panel 33 and the second prefabricated side panel 34, and finally hoist the prefabricated top panel 2 into place. Insert the second protruding steel bars 32 on the top of the first prefabricated side panel 33 and the second prefabricated side panel 34 into the second embedded sleeve on the prefabricated top panel 2, and use high-strength non-shrinkage grouting material to grout all the second embedded sleeves on the prefabricated top panel 2.
[0059] 5. After the overall assembly is completed, waterproof glue is applied to the joint between the first prefabricated side panel 33 and the second prefabricated side panel 34 to prevent leakage during the later use of the kitchen and bathroom.
[0060] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
Claims
1. An assembled concrete building, characterized in that: include: A prefabricated base plate (1), comprising a base plate body (11) and a first anti-ridge (12) protruding from the top surface of the base plate body (11), wherein the first anti-ridge (12) extends along the circumference of the base plate body (11), and a plurality of first sleeves (13) are pre-buried in the prefabricated base plate (1), extending along the height direction of the prefabricated base plate (1) and having their top ends extending to the top surface of the first anti-ridge (12); A prefabricated top plate (2), in which a plurality of second sleeves (21) extending in the height direction of the prefabricated top plate (2) and with the bottom ends extending to the bottom surface of the prefabricated top plate (2) are pre-buried; A prefabricated wall (3), the bottom end of which is arranged on the prefabricated bottom plate (1), the prefabricated top plate (2) is covered on the top of the prefabricated wall (3), the prefabricated wall (3) comprises a plurality of prefabricated side plates connected end to end, a plurality of first protruding steel bars (31) arranged at intervals along the length direction of each prefabricated side plate are arranged on the bottom end surface of each prefabricated side plate, a plurality of second protruding steel bars (32) arranged at intervals along the length direction of each prefabricated side plate are arranged on the top end surface of each prefabricated side plate, the first protruding steel bars (31) and the second protruding steel bars (32) are extended along the height direction of the prefabricated wall (3), the first protruding steel bars (31) are inserted into the first sleeve (13), the second protruding steel bars (32) are inserted into the second sleeve (21), and the first sleeve (13) and the second sleeve (21) are filled with grouting material; Connecting components (4), two adjacent prefabricated side panels are connected via a plurality of connecting components (4); A water-stopping rubber strip (5) is sandwiched between the prefabricated wall (3) and the first anti-ridge (12), between the prefabricated wall (3) and the prefabricated top plate (2), and between two adjacent prefabricated side plates.
2. The prefabricated concrete building according to claim 1, characterized in that: The plurality of prefabricated side panels include two first prefabricated side panels (33) and two second prefabricated side panels (34), wherein the two first prefabricated side panels (33) are spaced apart along a first direction, and the two second prefabricated side panels (34) are spaced apart along a second direction perpendicular to the first direction.
3. The prefabricated concrete building according to claim 2, characterized in that: The connection component (4) comprises: A connecting member (41), wherein one of the first prefabricated side panel (33) and the second prefabricated side panel (34) is provided with a threaded hole, and the other is provided with a connecting hole corresponding to the threaded hole one by one, and the connecting member (41) passes through the connecting hole and is screwed to the corresponding threaded hole; A fastener (42) is threadedly connected to one end of the connecting member (41) exposed outside the prefabricated wall (3), and abuts against the prefabricated wall (3).
4. The prefabricated concrete building according to claim 3, characterized in that: The connection assembly (4) further comprises a third embedded sleeve (43) embedded in the prefabricated side plate, and the threaded hole is an inner hole of the third embedded sleeve (43).
5. The prefabricated concrete building according to claim 4, characterized in that: The length of the first prefabricated side panel (33) is greater than the length of the second prefabricated side panel (34); a plurality of third embedded sleeves (43) are arranged at intervals along the height direction of the first prefabricated side panel (33) on the end surfaces at both ends in the length direction of the first prefabricated side panel (33); the third embedded sleeves (43) extend along the length direction of the first prefabricated side panel (33); and the second prefabricated side panel (34) is provided with connection holes extending along its thickness direction at both ends in the length direction.
6. The prefabricated concrete building according to claim 5, characterized in that: The connection assembly (4) further comprises an anchoring end plate (44) embedded in the prefabricated side plate, wherein a middle portion of the anchoring end plate (44) is fixedly connected to an end of the corresponding third embedded sleeve (43) extending into the first prefabricated side plate (33), and both ends of the anchoring end plate (44) extend in a direction away from the axis of the third embedded sleeve (43).
7. The prefabricated concrete building according to any one of claims 3 to 6, characterized in that: It also includes a steel strip (6), each of which is sandwiched between the fasteners (42) and the prefabricated wall (3), and there are four steel strips (6). The four steel strips (6) are spaced apart along the circumference of the prefabricated wall (3) and extend along the height direction of the prefabricated wall (3).
8. The prefabricated concrete building according to any one of claims 1 to 6, characterized in that: The prefabricated wall (3) is provided with a door opening (35), and the first counter-ridge (12) is provided with a groove (121) corresponding to the door opening (35).
9. The prefabricated concrete building according to claim 8, characterized in that: The bottom end of the groove (121) extends to the top surface of the bottom plate body (11).
10. The prefabricated concrete building according to any one of claims 1 to 6, characterized in that: The first sleeve (13) and the second sleeve (21) are both corrugated tubes.