Guide photoelectric transmission structure of vertical shaft drilling machine
By adopting the photoelectric transmission structure of verticality detection elements and optical modules in the shaft drilling rig, combined with segmented cable discs and connectors, the problem that existing guides cannot effectively maintain the verticality of the drill pipe and the complex layout of underwater cables is solved. It realizes high-precision data transmission and space savings, reducing construction costs and difficulty.
Patent Information
- Application Number
- CN202420065493.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-11
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-01-11
AI Technical Summary
The existing shaft drilling rig guide structure cannot effectively maintain the verticality of the drill rod, and the underwater cable layout is complex and takes up a large space, which increases construction cost and difficulty.
A guided photoelectric transmission structure of a shaft drilling rig is designed, using the verticality detection element on the underwater platform and the optical module on the driving platform to connect through the photoelectric integrated cable, combined with segmented cable discs and connectors to achieve real-time detection and data. The transmission reduces the construction difficulties of wired communication and fixes the optoelectronic integrated cable through the hoop surrounding the drill rod.
It improves the stability and accuracy of data transmission, can detect the verticality of the drill rod in real time, saves space, reduces construction costs and difficulty, and improves the convenience of maintenance.
Smart Images

Figure CN221957572U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of vertical shaft drilling rigs, in particular to a guiding photoelectric transmission structure of a vertical shaft drilling rig. Background Art
[0002] The main component of the shaft drilling rig used for underground excavation is the drill rod. If the drill rod is tilted, it cannot be smoothly removed from the underground. Therefore, in order to monitor whether the drill rod of the shaft drilling rig remains vertical, a guide structure is generally used for guidance. The guide structure currently on the market is simple, including a bearing and a contact plate:
[0003] The guide bearings all use non-standard thrust radial ball bearings without cages, which can freely rotate around the drill pipe relying on resistance, but cannot effectively maintain verticality.
[0004] The diameter of the contact plate is slightly smaller than that of the drill bit, and it mainly plays the role of stabilizing the drill bit. It has limited function and low degree of automation. The contact plate of the original guide can only contact the well wall when the drill bit is greatly deflected.
[0005] In addition, the underwater cable arrangement method used for vertical shaft drilling rigs is mostly a double-line layout, one cable is used for data transmission, and one cable is used for underwater power supply. The cables are both retracted and released using a large winch design, which not only takes up a large space, but also increases construction costs and difficulty. Utility Model Content
[0006] Purpose of the invention: The purpose of the utility model is to address the deficiencies of the prior art and provide a guiding photoelectric transmission structure for a vertical shaft drilling rig that has high integration, high precision, high safety, and can detect the verticality of the drill pipe in real time.
[0007] Technical solution: The utility model discloses a guiding photoelectric transmission structure of a vertical shaft drilling rig, wherein the underwater part of the drill pipe is provided with an underwater platform, and the above-water part of the drill pipe is provided with a driving platform, including:
[0008] An underwater sealing assembly, wherein the underwater sealing assembly is arranged on an underwater platform and a verticality detection element is provided in the underwater sealing assembly;
[0009] An optical module, wherein the optical module is arranged on the driving platform;
[0010] An optoelectronic integrated cable connects a verticality detection element and an optical module.
[0011] Furthermore, a cable drum for winding the optoelectronic integrated cable is provided on the driving platform, and the rotation of the cable drum drives the retraction and extension of the optoelectronic integrated cable.
[0012] Furthermore, the axial ends of the cable drum are rotatably arranged on a bracket, and the bracket is fixed on the driving platform.
[0013] Furthermore, two ends of the optoelectronic integrated cable are respectively connected to the optical module and the optoelectronic verticality detection element through plugs.
[0014] Furthermore, the optical-electric integrated cable is arranged in sections, and each section is connected by a connector.
[0015] Furthermore, the length of each section of the optical-electric integrated cable is 100 meters.
[0016] Furthermore, the connector is fixed by a clamp surrounding the drill pipe.
[0017] Furthermore, the underwater sealing component is constructed as a watertight electronic cabin, and the verticality detection element is constructed as a gyroscope.
[0018] Furthermore, the watertight electronic compartment is electrically connected to the verticality detection element, and the watertight electronic compartment has an external electrical socket.
[0019] Beneficial effects: 1. The utility model sets a verticality detection element on the underwater platform and sets an optical module on the driving platform. The two are connected by an optoelectronic integrated cable, which improves the stability and accuracy of the data and can accurately locate the fault position of the cable during data transmission. In addition, the setting of the optical module can be wirelessly transmitted with the main control system of the industrial computer and the drilling rig, which greatly reduces the construction difficulties caused by the wired communication method.
[0020] 2. The utility model provides a segmented arrangement of the optoelectronic integrated cable, which increases the cable reels for winding each segment and the segmented docking structure through the connector, which not only saves space, but also improves the convenience of repair and maintenance and saves costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the structure of the utility model;
[0022] Figure 2 It is a schematic diagram of the structure above the driving platform. DETAILED DESCRIPTION
[0023] The technical solution of the present invention is described in detail below with reference to the accompanying drawings, but the protection scope of the present invention is not limited to the embodiments.
[0024] A guiding photoelectric transmission structure of a vertical shaft drilling rig, such as Figure 1As shown, it includes an underwater sealing assembly 1, an optical module 2 and an optoelectronic integrated cable 3. It should be noted that multiple drill rods 4 usually need to be coaxially connected to enter underwater, and the number of drill rods 4 is determined according to the adaptability to the underwater construction depth. The length of the drill rod 4 can be continuously extended and connected, and a cutter head is provided at the bottom of the last section of the drill rod 4 for vertical shaft construction. The underwater part of the drill rod 4 is provided with an underwater platform 5, and the above-water part of the drill rod 4 is provided with a driving platform 6, and this part of the structure is the inherent structure of the drill rod 4. The underwater sealing assembly 1 is arranged on the underwater platform 5, and a verticality detection element 7 is provided in the underwater sealing assembly 1; the optical module 2 is arranged on the driving platform 6, and the optoelectronic integrated cable 3 connects the verticality detection element 7 and the optical module 2.
[0025] Specifically, the verticality detection element 7 can be used to detect the verticality of the drilling rig. For example, the verticality detection element 7 can be a seismic gyroscope, which is sealed in the underwater sealing assembly 1. The seismic gyroscope has a dual-axis inclinometer inside. By obtaining the inclination of the underwater platform 5, the dual-axis inclination angle and azimuth of the seismic gyroscope installed at a suitable position of the cutter head at the front of the vertical drilling rig can be obtained, and the real-time dual-axis inclination angle of the cutter head of the vertical drilling rig can be calculated, so as to calculate the coordinate deviation at the position of the cutter head according to the coordinate deviation of the cutter head at the initial position, the length of the drill pipe 4 of the vertical drilling rig, and other parameters.
[0026] In addition, the optoelectronic integrated cable 3 includes an optical fiber core and a power supply core. The optical fiber core is used for data transmission, and the power supply core is used for power supply. Therefore, the transmission cables of the guided optoelectronic transmission structure of the vertical shaft drilling rig in this embodiment can be integrated into one cable, and when the optoelectronic integrated cable 3 breaks underwater, the optical fiber core can be used to accurately locate the break position, thereby repairing the cable.
[0027] In some embodiments, the underwater sealing assembly 1 is constructed as a watertight electronic cabin, which can be placed underwater to create a closed and waterproof working environment inside, and is generally a high-strength stainless steel structure, which can be fixed on the underwater platform 5 by flanges or clamps. The watertight electronic cabin has the function of facilitating the installation and connection of the optoelectronic integrated cable 3 and the verticality detection element 7. The verticality detection element 7 and the watertight electronic cabin are electrically connected, so the optoelectronic integrated cable 3 only needs to be docked to the connector on the watertight electronic cabin to complete the electrical connection with the verticality detection element 7.
[0028] In some embodiments, both ends of the optoelectronic integrated cable 3 are connected to the optical module 2 and the watertight electronic cabin through plugs respectively.
[0029] In some embodiments, since the length of each section of drill pipe 4 is fixed, the drill pipe 4 needs to be continuously connected during the drilling process to adapt to different downhole depths. In order to match the length changes of different numbers of drill pipes 4, the optoelectronic integrated cable 3 is set in sections, and each section of the cable is connected by a connector 8. Exemplarily, the optoelectronic integrated cable 3 adopts a 6-electric 1-optical watertight integrated cable, which is segmented every 100 meters, and the built-in fiber core optical attenuation is less than 0.5dB / km. The connector 8 can be fixed by a clamp 9 surrounding the drill pipe 4. The clamp 9 is at least set on each section of the drill pipe 4, and is evenly distributed along the overall length direction of the drill pipe 4 to ensure that the optoelectronic integrated cable 3 is fixed firmly. Specifically, the connector 8 adopts an optoelectronic integrated watertight connector 8, in which one core is an optical contact and two cores are electrical contacts, which can meet the needs of long-term towing, retracting and releasing in water, and the maximum water pressure resistance reaches 10Mpa. Furthermore, the outside of the connector 8 uses a pressurized cable seal for underwater sealing. When the rubber sealing gasket of the pressurized cable seal is subjected to axial pressure, it expands radially and presses the cable and the inner wall of the connector 8 shell, thereby blocking the fluid and completely sealing.
[0030] In some embodiments, Figure 2 As shown, a cable drum 10 for winding the optical fiber integrated cable 3 is provided on the driving platform 6, and the cable is retracted and released by rotating the cable drum 10. Each cable drum 10 is wound with 100 meters of optical fiber integrated cable 3, and when a drum of optical fiber integrated cable 3 is released, the next cable drum 10 needs to be manually replaced, so that all cables can be prevented from being piled up on the platform and occupying too much space.
[0031] In some embodiments, both axial ends of the cable drum 10 are rotatably arranged on a bracket, and the bracket is fixed on the driving platform 6. Further, the cable drum 10 is controlled by the controller 11 to rotate forward and reverse, so that the optical-electric integrated cable 3 is released or wound.
[0032] In some embodiments, the optical module 2 can use the common SFP optical module 2 on the market, which is mainly used to receive data transmitted by the optoelectronic integrated cable 3 and communicate with the wireless receiver, which is connected to the host computer and the main control system of the drilling rig. For example, the optical module 2 has a built-in battery, a wireless transmitter, optical components, and a watchdog module to realize the conversion and transmission of Ethernet signals / RS485 signals and wireless signals. Among them, the wireless transmitter can use the SX1278 radio frequency wireless transmission module, the optical components are used to monitor the optical fiber signal, and the implementation form of the watchdog module can be the SP706S reset monitoring chip. The watchdog module can make the optical module 2 run stably without downtime, and supports transparent transmission mode and HTTPD Client mode. The wireless receiver is mainly used for wireless data reception, wireless communication with the built-in wireless transmitter of the optical module 2, and also wired communication connection with the host computer. The upper computer is installed with guidance system software, which obtains the dual-axis tilt angle and azimuth of the verticality detection element 7 through communication connection with the wireless receiver, and communicates with the main control system of the drilling rig in real time to determine the real-time working status of the vertical shaft drilling rig and obtain the drilling depth of the vertical shaft drilling rig.
[0033] The verticality detection element 7 of the utility model is powered by the photoelectric integrated cable 3 on the one hand, and transmits the original data measured by itself to the optical module 2 on the other hand through the photoelectric integrated cable. Since the drill rod 4 needs to be frequently docked and extended during the operation of the shaft drilling rig, the segmented design of the photoelectric integrated cable can be extended with the replacement of the drill rod 4, and the length of the photoelectric integrated cable fixed on the drill rod 4 by the clamp 9 during the excavation of the shaft drilling rig also changes in real time, so a small automatic cable drum is used, and the cable drum can be remotely controlled to rotate under the action of the cable drum controller 11. The upper computer obtains the dual-axis tilt angle and azimuth of the verticality detection element 7 installed at a suitable position of the underwater platform 5 at the front of the shaft drilling rig, calculates the real-time dual-axis tilt angle of the cutter head of the shaft drilling rig, and calculates the coordinate deviation at the position of the cutter head according to the coordinate deviation at the initial position of the cutter head, the length of the drill rod 4 of the shaft drilling rig, and other parameters.
[0034] As described above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be construed as limiting the present invention itself. Various changes in form and details may be made without departing from the spirit and scope of the present invention as defined in the appended claims.
Claims
1. A guided photoelectric transmission structure of a vertical shaft drilling rig, wherein the underwater part of the drill pipe is provided with an underwater platform, and the above-water part of the drill pipe is provided with a driving platform, characterized in that: include: An underwater sealing assembly, wherein the underwater sealing assembly is arranged on an underwater platform and a verticality detection element is provided in the underwater sealing assembly; An optical module, wherein the optical module is arranged on the driving platform; An optoelectronic integrated cable connects a verticality detection element and an optical module.
2. The guided photoelectric transmission structure of the shaft drilling rig according to claim 1, characterized in that: The driving platform is provided with a cable drum for winding the optoelectronic integrated cable, and the rotation of the cable drum drives the retraction and extension of the optoelectronic integrated cable.
3. The guided photoelectric transmission structure of the vertical shaft drilling rig according to claim 2, characterized in that: The axial ends of the cable drum are rotatably arranged on a bracket, and the bracket is fixed on a driving platform.
4. The guided photoelectric transmission structure of the shaft drilling rig according to claim 1, characterized in that: The two ends of the photoelectric integrated cable are respectively connected to the optical module and the photoelectric verticality detection element through plugs.
5. The guided photoelectric transmission structure of the shaft drilling rig according to claim 1, characterized in that: The optical-electric integrated cable is arranged in sections, and each section is connected by a connector.
6. The guided photoelectric transmission structure of the vertical shaft drilling rig according to claim 5, characterized in that: The length of each section of the optical-electric integrated cable is 100 meters.
7. The guided photoelectric transmission structure of the vertical shaft drilling rig according to claim 5, characterized in that: The connector is secured by a clamp surrounding the drill pipe.
8. The guided photoelectric transmission structure of the shaft drilling rig according to claim 1, characterized in that: The underwater sealing component is configured as a watertight electronic compartment, and the verticality detection element is configured as a gyroscope.
9. The guided photoelectric transmission structure of the shaft drilling rig according to claim 8, characterized in that: The watertight electronic compartment is electrically connected to the verticality detection element, and the watertight electronic compartment has an external electrical socket.