Roadway water retaining structure

By setting up sealing walls and reinforcement structures at fault locations in mine tunnels, the problem of fault hysteresis water effluent is solved, the safety and water pressure balance of mine tunnels are improved, and the risk of water barrier wall collapse is avoided.

CN221957641UActive Publication Date: 2024-11-05GENERAL PROSPECTING INSTITUTE OF CHINA NATIONAL ADMINISTRATION OF COAL GEOLOGY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420356482.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-26
Publication Date
2024-11-05
Estimated Expiration
2034-02-26

AI Technical Summary

Technical Problem

In the prior art, the water barrier wall is close to the fault, and the fault is easily lagging behind the water out when it is affected by stress, resulting in the increase in the pressure of the water barrier wall, which leads to the risk of collapse, and reduces the safety of the mine tunnel.

Method used

Set up a sealing wall when filling the fault location of the tunnel. The length of the sealing wall is not less than the fault width, including the inverted frustration cone section and the pressure-bearing section, a waterproof wall and reinforcement wall, and through anchor cables, anchor rods and grouting The holes are reinforced, and the water conduit controls the water flow to form a complete sealing structure.

Benefits of technology

Completely enclosed the fault to avoid lagging water effluent, improve the safety of mine tunnels, maintain the balance of formation stress and water pressure, prevent water damage from spreading, and enhance the stability and sealing of the water barrier wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221957641U_ABST
    Figure CN221957641U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of coal mine water control, and provides a roadway water retaining structure, which comprises a blocking wall filled in a roadway, positioned at the position of a fault of the roadway and used for blocking the position of the fault; the blocking wall extends in the length direction of the roadway, and the length of the blocking wall is larger than or equal to the width of the fault. The utility model provides a roadway water retaining structure which is used for overcoming the defect of lagging water outlet in the prior art, the position of a fault of a roadway is filled with a blocking wall, the fault can be completely sealed in a wall body, a supporting effect is achieved on a rock wall at the fault, and even if the fault is affected by various stresses, the fault can be prevented from falling off. And when the Ordovician limestone water pressure at the coal seam bottom plate is increased, due to the effect of the blocking wall, the problem that fault water outlet is disturbed by the heaving floor phenomenon can be avoided, the problem that the water retaining wall collapses due to the increase of the pressure is solved, and the safety of a mine roadway is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of coal mine water control, in particular to a tunnel water retaining structure. Background Art

[0002] The retaining wall is an important safety facility for waterproofing mine tunnels. When a flood occurs, it can reduce the scope of the disaster, control the harm of water potential, and improve the safety of the mine. The existing technology provides a retaining wall, which is arranged outside the intersection of the tunnel and the fault. The cooperation between the retaining wall and the inner wall of the tunnel can effectively prevent the influence of water discharge from the fault fissure on the tunnel. However, the distance between the fault and the retaining wall is relatively close, and the fault will be affected by various stresses and water discharge will be delayed. In particular, the water pressure of the Ordovician ash at the bottom of the coal seam increases, which is easy to cause bottom drum, and then disturb the fault to discharge water again, which will cause the pressure on the retaining wall to continue to increase, and there is a risk of collapse, which greatly reduces the safety of the mine tunnel. Utility Model Content

[0003] The utility model provides a tunnel water retaining structure to solve the defect of delayed water discharge in the prior art. By filling and setting a blocking wall at the position of the fault in the tunnel, the fault can be completely enclosed in the wall, so that even if the fault is affected by various stresses, the problem of delayed water discharge will not occur, and the problem of disturbing the water discharge of the fault due to the bottom drum phenomenon can be avoided.

[0004] The tunnel water retaining structure provided by the utility model comprises:

[0005] A blocking wall is filled in the tunnel and is located at the position of the fault in the tunnel, and is used to block the position of the fault; the blocking wall extends along the length direction of the tunnel, and the length of the blocking wall is greater than or equal to the width of the fault.

[0006] According to the tunnel water retaining structure provided by the utility model, the blocking wall includes an inverted truncated cone section and a pressure-bearing section. The inverted truncated cone section is arranged at both ends of the pressure-bearing section, and the cross-section of the inverted truncated cone section gradually increases toward the pressure-bearing section.

[0007] The tunnel water retaining structure provided by the utility model further comprises at least one water retaining wall, wherein the extending directions of the water retaining wall and the blocking wall are perpendicular to each other and the water retaining wall is arranged on the blocking wall.

[0008] According to the tunnel water retaining structure provided by the utility model, the water retaining wall includes at least one of a first wall body, a second wall body and a reinforcement wall.

[0009] According to the tunnel water retaining structure provided by the utility model, when the water retaining wall includes the first wall, the second wall and the reinforcement wall, the first wall and the second wall are respectively arranged on both sides of the reinforcement wall, and the first wall, the second wall and the inner wall of the tunnel limit an accommodating space, and the accommodating space is used for casting to form the reinforcement wall.

[0010] According to the tunnel water retaining structure provided by the utility model, when three water retaining walls are provided, two of the water retaining walls are respectively provided at both ends of the blocking wall, and the other water retaining wall is provided on the water-facing side of the blocking wall and between the truncated cone section and the pressure-bearing section.

[0011] According to the tunnel water retaining structure provided by the utility model, a plurality of protrusions are provided at intervals on the outer wall of the blocking wall, and grooves matching the protrusions are provided on the inner wall of the tunnel.

[0012] The tunnel water retaining structure provided by the utility model further comprises a plurality of anchor cables, the anchor cables are staggered and penetrated through the blocking wall, and the two ends of the anchor cables are respectively embedded in the rock strata of the tunnel;

[0013] And / or, it also includes a plurality of anchor rods, which are staggered and penetrated through the blocking wall, and the two ends of the anchor rods are respectively embedded in the rock strata of the tunnel.

[0014] According to the tunnel water retaining structure provided by the utility model, a plurality of grouting holes are arranged at intervals on at least one of the water retaining walls arranged at both ends of the blocking wall, and each of the grouting holes is connected to a corresponding grouting pipe.

[0015] According to the tunnel water retaining structure provided by the utility model, the grouting pipe comprises a long pipe and a short pipe, and the long pipe and the short pipe are alternately arranged along the height direction of the blocking wall.

[0016] The tunnel water retaining structure provided by the utility model also includes a water pipe, which is penetrated by the blocking wall and the water retaining wall, one end of the water pipe is connected to the water channel on the water-facing side of the blocking wall, and the other end of the water pipe is connected to a valve.

[0017] The tunnel water retaining structure provided by the embodiment of the utility model, by filling and setting a blocking wall at the position where the fault of the tunnel is located, and making the length of the blocking wall not less than the width of the fault, can completely seal the fault inside the wall, so that water seepage cannot occur at the fault, thereby realizing the interception and reduction of mine water gushing, and intercepting the water hazard connection between the water gushing area and the safe area; in addition, the blocking wall filled here can support the bottom plate, top plate and side of the tunnel. In other words, this place can be close to the original rock formation state that has not been mined, so that the groundwater in the rock formation at the fault can not flow out from here, and the normal formation stress in the area and the water pressure balance inside the rock formation can be maintained, while protecting the groundwater resources.

[0018] Compared with the prior art, the tunnel water retaining structure provided by the embodiment of the utility model can support the rock wall at the fault by completely enclosing the fault within the wall, so that even if the fault is affected by various stresses, there will be no problem of delayed water discharge. When the water pressure of the Ordovician ash at the bottom of the coal seam increases, due to the effect of the sealing wall, the problem of disturbing the water discharge of the fault due to the bottom drum phenomenon can be avoided, the problem of collapse of the retaining wall due to increased pressure is solved, and the safety of the mine tunnel is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0020] Figure 1 It is a schematic diagram of the overall structure of the tunnel water retaining structure provided by the embodiment of the utility model;

[0021] Figure 2 It is a front view of the retaining wall provided by the embodiment of the utility model.

[0022] Reference numerals:

[0023] 100: blocking wall; 110: inverted truncated cone section; 120: pressure-bearing section; 130: protrusion; 140: groove;

[0024] 200: retaining wall; 210: first wall; 220: second wall; 230: reinforcement wall; 240: grouting hole;

[0025] 300: anchor cable; 310: anchor rod; 400: water pipe; 410: valve. DETAILED DESCRIPTION

[0026] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be clearly and completely described below in conjunction with the drawings in the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] In the description of the embodiments of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.

[0028] In the embodiments of the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0029] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the embodiments of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0030] At present, there is a demand for deeper mining due to the exhaustion of upper resources in the mining area, but the degree of deep hydrogeological exploration is seriously insufficient. Specifically, the deep hydrogeological conditions are not clearly explored, the karst fracture grid is unevenly developed, and the structural exploration is low. For example, at the intersection of the tunnel and the fault, there is a high possibility of water outflow when encountering water-conducting structures. However, even after regional governance of the deep mining area, it cannot be ensured that there will be no water inrush from the structure.

[0031] If there is water inrush after mining, in order to avoid the continuous damage of the water inrush point under the action of water flow, causing the water inrush to increase, and to ensure the safety of mine drainage, it is necessary to adopt certain water retaining means to achieve rapid pressure resistance and water control. The retaining wall is an important safety facility for waterproofing the mine tunnel. When a flood occurs, it can reduce the impact range of the disaster, control the harm of water potential, and improve the safety of the mine. The prior art provides a retaining wall, which is arranged outside the intersection of the tunnel and the fault. The cooperation between the retaining wall and the inner wall of the tunnel can effectively prevent the influence of water outflow from the fault fissure on the tunnel. However, the distance between the fault and the retaining wall is relatively close, and the fault will be affected by various stresses and will have delayed water outflow, especially the increase of the water pressure of the Ordovician ash at the bottom of the coal seam, which is easy to cause bottom drum, and then disturb the fault to discharge water again, which will cause the pressure on the retaining wall to continue to increase, and there is a risk of collapse, which greatly reduces the safety of the mine tunnel.

[0032] Figure 1 It is a schematic diagram of the overall structure of the tunnel water retaining structure provided by an embodiment of the utility model.

[0033] See also Figure 1 The embodiment of the utility model provides a tunnel water retaining structure, which includes a blocking wall 100. The blocking wall 100 is a solid structure. The blocking wall 100 is filled in the tunnel and is located at the position where the fault of the tunnel is located. The shape of the blocking wall 100 corresponds to the shape of the tunnel. Specifically, the cross-sectional shape of the blocking wall 100 corresponds to the cross-sectional shape of the tunnel. The blocking wall 100 extends along the length direction of the tunnel. The length of the blocking wall 100 is not less than the width of the fault. The outer wall of the blocking wall 100 is connected to the inner wall of the tunnel. The blocking wall 100 is suitable for forming a whole with the rock wall of the tunnel to block the position where the fault is located.

[0034] See also Figure 1 It can be understood that the tunnel water retaining structure provided by the embodiment of the utility model, by filling and setting the blocking wall 100 at the position where the fault of the tunnel is located, and making the length of the blocking wall 100 not less than the width of the fault, can completely seal the fault inside the wall, so that no water seepage can occur at the fault, thereby realizing the interception and reduction of mine water gushing, and intercepting the water hazard connection between the water gushing area and the safe area; in addition, the blocking wall 100 is filled here, which can support the bottom plate, top plate and side of the tunnel. In other words, this place can be close to the original rock state of unmined, so that the groundwater in the rock formation at the fault can not flow out from here, and the normal formation stress in the area and the water pressure balance inside the rock formation can be maintained, while protecting groundwater resources.

[0035] Compared with the prior art, the tunnel water retaining structure provided by the embodiment of the utility model can support the rock wall at the fault by completely enclosing the fault within the wall, so that even if the fault is affected by various stresses, there will be no problem of delayed water discharge. When the water pressure of the coal seam floor increases, due to the effect of the sealing wall 100, the problem of disturbing the water discharge of the fault due to the bottom drum phenomenon can be avoided, the problem of collapse of the retaining wall 200 due to increased pressure is solved, and the safety of the mine tunnel is improved.

[0036] Continue reading Figure 1 In an optional embodiment of the utility model, the blocking wall 100 includes an inverted truncated cone section 110 and a pressure-bearing section 120. The inverted truncated cone section 110 is arranged at both ends of the pressure-bearing section 120, and the larger end of the inverted truncated cone section 110 faces the pressure-bearing section 120. In other words, the cross-section of the inverted truncated cone section 110 gradually increases in the direction of the pressure-bearing section 120. It is easy to understand that the inverted truncated cone section 110 can effectively increase the contact area between the wall and the inner wall of the tunnel, that is, the surrounding rock, and can change the force form between the blocking wall 100 and the surrounding rock, thereby improving the stability and sealing of the blocking wall 100, so that both ends of the wall can withstand a certain pressure with both sides of the tunnel.

[0037] Continue reading Figure 1 In an optional embodiment of the present utility model, the tunnel water retaining structure further includes at least one water retaining wall 200. The water retaining wall 200 and the blocking wall 100 extend in directions perpendicular to each other and are arranged on the blocking wall 100. It is easy to understand that the water retaining wall 200 can be embedded in the blocking wall 100 or at the end of the blocking wall 100. Figure 1 The figure shows a case where three retaining walls 200 are provided. Figure 1 Two of the three water retaining walls 200 are respectively arranged at the two ends of the blocking wall 100, and another one of the three blocking walls 100 is embedded between the inverted truncated cone section 110 and the pressure-bearing section 120 of the blocking wall 100, and is arranged on the water-facing side of the blocking wall 100. It is easy to understand that by setting the water retaining wall 200, the blocking wall 100 can be further reinforced, so that the strength of the blocking wall 100 is better, and the sealing and stability of the blocking wall 100 can be improved.

[0038] Furthermore, a water retaining wall 200 is added on the water-facing side of the sealing wall 100. When a large water flow appears on the water-facing side of the sealing wall 100, the sealing and strength of the sealing wall 100 can be improved to prevent water from flowing out of the gap between the sealing wall 100 and the inner wall of the tunnel. In addition, the sealing wall 100 is arranged between the inverted truncated cone section 110 and the pressure-bearing section 120, which can play a good transition role and prevent the overall strength of the sealing wall 100 from being affected by the different force forms between the inverted truncated cone section 110 and the pressure-bearing section 120 and the surrounding rock.

[0039] It should be noted that the position and number of the retaining wall 200 can be adaptively set according to actual conditions, that is, the retaining wall 200 can be one, two, four, or even more, and the retaining wall 200 can be located at the end or the middle of the blocking wall 100; Figure 1 The situation shown in the figure is only an illustrative example given in the embodiment of the present utility model and is not intended to be a specific limitation of the present utility model.

[0040] Continue reading Figure 1 In an optional embodiment of the utility model, the retaining wall 200 includes at least one of the first wall 210, the second wall 220 and the reinforcement wall 230; when the retaining wall 200 includes the first wall 210, the second wall 220 and the reinforcement wall 230, the first wall 210 and the second wall 220 are arranged on both sides of the reinforcement wall 230, and the first wall 210, the second wall 220 and the inner wall of the lane limit an accommodation space, and the accommodation space is used for casting to form the reinforcement wall 230, The first wall 210 and the second wall 220 can be 500mm thick brick walls, with 500mm space between the brick walls, that is, to limit the aforementioned accommodating space, anchor cables 300 and concrete pouring are used between the brick walls to form the aforementioned reinforced wall 230, and the brick model used for the brick wall construction is: length * width * thickness = 240mm * 115mm * 53mm, and the reinforced wall 230 is filled with No. 400 concrete, and the concrete ratio is cement: sand: gravel = 1:1.29:2.88.

[0041] It is easy to understand that by setting the first wall 210, the second wall 220 and the reinforcement wall 230, the overall strength of the water retaining wall 200 can be improved, so that it has better sealing and pressure resistance. Furthermore, the first wall 210, the second wall 220 and the alley are surrounded by an accommodation space, which can provide a suitable mold for the casting of the reinforcement wall 230, so that the formed reinforcement wall 230 has a closer connection with the first wall 210, the second wall 220 and the inner wall of the alley, so that the integrity of the water retaining wall 200 is better. In addition, the reinforcement wall 230 is obtained by filling, which can fill the gap between the first wall 210, the second wall 220 and the alley, so that the overall sealing and strength are greatly improved.

[0042] It should be noted here that in an optional embodiment of the present invention, the reinforcement wall 230 can also be constructed in the same manner as the first wall 210. For example, the first wall 210, the second wall 220 and the reinforcement wall 230 are all brick walls. The setting of the reinforcement wall 230 can be adaptively set according to actual conditions. Similarly, the first wall 210 and the second wall 220 can also be adaptively designed according to actual conditions, and are not limited to the aforementioned brick walls, etc. The detailed implementation method can refer to the prior art, which will not be repeated herein.

[0043] Continue reading Figure 1 In an optional embodiment of the utility model, the outer wall of the blocking wall 100 is provided with a plurality of protrusions 130 at intervals, and the inner wall of the tunnel is provided with grooves 140 adapted to the protrusions 130. Specifically, before the blocking wall 100 is set, the slag on the top plate, two sides and bottom plate of the tunnel can be cleaned to make the hard rock visible. In other words, the surrounding rock of the inner wall of the tunnel is exposed, and then the top plate, two sides and bottom plate of the tunnel are grooved 5 meters in the direction of the fault at both ends of the blocking wall 100, in the direction close to the fault, to form the aforementioned grooves 140, and the grooves are cut into the hard rock 0.5 meters deep. It should be noted that pneumatic picks should be used for groove excavation, and blasting is prohibited to ensure the stability and integrity of the surrounding rock. When the excavation is almost to the designed size, a manuscript or pneumatic pick should be used to cut to the designed size.

[0044] After the groove 140 is formed, grouting is performed on the space here to form the blocking wall 100. It is easy to understand that after the grouting solidifies, the part flowing into the groove 140 can form the aforementioned protrusion 130, and the protrusion 130 is perfectly matched with the groove 140 and has good tightness. It can be understood that by setting the groove 140 and the protrusion 130, the contact area between the blocking wall 100 and the inner wall of the tunnel can be increased. Based on this embedded structure, the connection strength between the blocking wall 100 and the surrounding rock of the tunnel can be greatly improved.

[0045] Continue reading Figure 1 In an optional embodiment of the utility model, the tunnel water retaining structure also includes a plurality of anchor cables 300, and the plurality of anchor cables 300 are staggered and penetrated through the blocking wall 100, and the two ends of the anchor cables 300 are respectively embedded in the rock strata of the tunnel. It is easy to understand that the staggered arrangement of the plurality of anchor cables 300 can form an anchor cable 300 net, and the anchor cable 300 net can greatly improve the integrity and strength of the blocking wall 100, so that it can work under a greater pressure environment.

[0046] See also Figure 1 In this embodiment, multiple anchor cables 300 are arranged in an array along the length direction of the blocking wall 100. Specifically, taking the cross section of the blocking wall 100 as a reference, multiple anchor cables 300 are arranged parallel to the cross section. Taking any one plane as an example, multiple anchor cables 300 are staggered on this plane to form an anchor cable 300 network to reinforce the cross section. In this embodiment, the anchor cable 300 network formed in this way is arranged at intervals in the length direction of the blocking wall 100. The spacing can be set between 1 and 2 meters. More specifically, it can be adaptively set according to actual conditions.

[0047] It should be noted here that the above embodiments are only illustrative examples of the present invention. There are many arrangements of the anchor cable 300 , which can be arranged at any angle with the length direction of the blocking wall 100 , and can be arranged specifically according to actual conditions.

[0048] Continue reading Figure 1 In the embodiment of the utility model, the tunnel water retaining structure also includes a plurality of anchor rods 310. The arrangement of the anchor rods 310 is similar to that of the anchor cables 300 in the aforementioned embodiment. Please refer to the foregoing description, and this embodiment will not be repeated here.

[0049] Figure 2 It is a front view of the retaining wall 200 provided in the embodiment of the utility model.

[0050] See also Figure 1 and Figure 2 In an optional embodiment of the utility model, a plurality of grouting holes 240 are arranged at intervals on at least one of the retaining walls 200 arranged at both ends of the blocking wall 100, and corresponding grouting pipes are arranged in the direction of the blocking wall 100. The grouting holes 240 and the grouting pipes are used for grouting to form the blocking wall 100.

[0051] Taking the case where the water retaining walls 200 are arranged at both ends of the blocking wall 100 as an example, the two water retaining walls 200 are arranged opposite to each other, and a certain space can be formed with the inner wall of the tunnel. By injecting slurry into the space, the aforementioned blocking wall 100 can be obtained after the slurry solidifies. In other words, the water retaining wall 200 can be used as a mold to form the blocking wall 100. It should be noted here that when the water retaining wall 200 is arranged in the blocking wall 100, it is also necessary to adaptively arrange the grouting holes 240 on the water retaining wall 200 to avoid blocking the flow of slurry due to the setting of the water retaining wall 200, which affects the formation of the blocking wall 100.

[0052] The material of the blocking wall 100 can be selected as needed, such as rough stone, cement, water glass, etc. Specifically, rough stone is filled between the two retaining walls 200, and a mixture of cement and water glass is injected through a grouting pipe. After the grouting solidifies, the blocking wall 100 can be formed; the water-cement ratio of cement slurry (mass) is: 1:1, the cement slurry to water glass (volume) is: 1:1, and the water glass concentration value is: 40°Be. When the final pressure of grouting is not less than 4.0Mpa and the stabilization time is not less than 30min, the grouting can be completed. It should be noted that it is necessary to focus on grouting the gap between the retaining wall 200 and the laneway to improve the firmness here. In an optional embodiment of the utility model, after the grouting is completed, a water permeability test can also be carried out to verify its strength. The grouting method can adopt grouting anchor rods or drilling rig drilling grouting, etc.

[0053] In an optional embodiment of the utility model, the grouting pipe includes a long pipe and a short pipe, and the long pipe and the short pipe are alternately arranged along the height direction of the blocking wall 100. Specifically, the length of the grouting pipe can be 3.0m, 4.5m, 6.0m, 9.5m or 10.5m, so that the filling effect can be guaranteed, and the formed blocking wall 100 is more uniform and has better strength. It should be noted that the grouting pipe needs to extend at least 100mm outside the retaining wall 200, and its end is wrapped with plastic cloth to facilitate subsequent grouting work.

[0054] Continue reading Figure 1 and Figure 2 In an optional embodiment of the utility model, the tunnel water retaining structure also includes a water pipe 400, which is passed through the blocking wall 100 and the water retaining wall 200. One end of the water pipe 400 is connected to the water channel on the water-facing side of the blocking wall 100, and the other end of the water pipe 400 is connected to the valve 410. The water pipe 400 should be arranged between grouting, that is, before the blocking wall 100 is formed. The water pipe 400 can be selected as a high-pressure seamless steel pipe. The length of the water pipe 400 is adaptively selected according to the length of the tunnel water retaining structure. A pressure gauge can also be set on the side of the water pipe 400 connected to the valve 410 to monitor the water pressure in the pipe. In actual situations, the water pressure in the water pipe 400 and the water channel can be maintained based on the opening and closing of the pressure gauge and the valve 410 to ensure the safety of the tunnel.

[0055] In an optional embodiment of the utility model, before the construction of the tunnel water retaining structure, the tunnel surrounding rock before and after the fault can be reinforced. Specifically, before the construction of the tunnel water retaining structure, the top plate, two sides and bottom plate of the tunnel within 10m before and after the fault are grout-reinforced to fill the voids, cracks and fault fracture zones to prevent slurry leakage. The method is to use a rock drill to make holes in the top plate, two sides and bottom plate, insert a grouting pipe for grouting, and there are 5 holes in each row. If the top plate is complete, the two sides and the junction of the top plate and the two sides can be reinforced. The hole depth is 2 meters, the diameter of the drill hole is 43mm, the spacing between each row of holes is 2.5 meters, and there are 8 rows in total. Cement and water glass grouting is used.

[0056] The following are optional construction procedures for the tunnel water retaining structure in the embodiment of the utility model: cleaning up the silt and debris in the construction area → digging → constructing the anchor cable eye → grouting and reinforcing the surrounding rock → installing the anchor cable 300 → constructing the water retaining wall 200 (constructing the water-facing side first) → pouring the reinforced wall 230 → filling the water retaining wall 200 with rough stones + pre-buried grouting pipes → grouting → maintenance → cleaning and acceptance. This procedure is only an illustrative example given in the embodiment of the utility model, and is not a specific limitation of the embodiment of the utility model. Specifically, an adaptive design can be made according to actual conditions.

[0057] It should be noted that the technical solutions in various embodiments of the present utility model can be combined with each other, but the basis for the mutual combination is that it can be implemented by ordinary technicians in the field; when the combination of technical solutions is mutually contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist, that is, it does not belong to the protection scope of the present utility model.

[0058] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the utility model.

Claims

1. A tunnel water retaining structure, It is characterized in that include: A blocking wall (100) is filled in the tunnel and located at the location of the fault in the tunnel, and is used to block the location of the fault; the blocking wall (100) extends along the length direction of the tunnel, and the length of the blocking wall (100) is greater than or equal to the width of the fault.

2. The tunnel water retaining structure according to claim 1, It is characterized in that The blocking wall (100) comprises an inverted truncated cone section (110) and a pressure-bearing section (120); the inverted truncated cone section (110) is arranged at both ends of the pressure-bearing section (120); and the cross section of the inverted truncated cone section (110) gradually increases toward the pressure-bearing section (120).

3. The tunnel water retaining structure according to claim 2, It is characterized in that It also comprises at least one water retaining wall (200), wherein the extending directions of the water retaining wall (200) and the blocking wall (100) are perpendicular to each other and the water retaining wall (200) is arranged on the blocking wall (100).

4. The tunnel water retaining structure according to claim 3, It is characterized in that The retaining wall (200) comprises at least one of a first wall (210), a second wall (220) and a reinforcement wall (230).

5. The tunnel water retaining structure according to claim 4, It is characterized in that When the water retaining wall (200) includes the first wall (210), the second wall (220) and the reinforcement wall (230), the first wall (210) and the second wall (220) are respectively arranged on both sides of the reinforcement wall (230), and the first wall (210), the second wall (220) and the inner wall of the tunnel limit an accommodation space, and the accommodation space is used for casting to form the reinforcement wall (230).

6. The tunnel water retaining structure according to claim 3, It is characterized in that When three water retaining walls (200) are provided, two of the water retaining walls (200) are respectively provided at the two ends of the blocking wall (100), and the other water retaining wall (200) is provided on the water-facing side of the blocking wall (100) and between the truncated cone section and the pressure-bearing section (120).

7. The tunnel water retaining structure according to any one of claims 1 to 6, It is characterized in that The outer wall of the blocking wall (100) is provided with a plurality of protrusions (130) at intervals, and the inner wall of the tunnel is provided with grooves (140) matched with the protrusions (130).

8. The tunnel water retaining structure according to any one of claims 1 to 6, It is characterized in that It also includes a plurality of anchor cables (300), wherein the anchor cables (300) are staggered and penetrate the blocking wall (100), and the two ends of the anchor cables (300) are respectively embedded in the rock strata of the tunnel; And / or, it also includes a plurality of anchor rods (310), wherein the anchor rods (310) are staggered and penetrate the blocking wall (100), and the two ends of the anchor rods (310) are respectively embedded in the rock strata of the tunnel.

9. The tunnel water retaining structure according to claim 6, It is characterized in that At least one of the water retaining walls (200) disposed at both ends of the blocking wall (100) is provided with a plurality of grouting holes (240) at intervals, and each of the grouting holes (240) is connected to a corresponding grouting pipe.

10. The tunnel water retaining structure according to claim 9, It is characterized in that The grouting pipe comprises a long pipe and a short pipe, and the long pipe and the short pipe are arranged alternately along the height direction of the blocking wall (100).

11. The tunnel water retaining structure according to any one of claims 3 to 6, It is characterized in that It also comprises a water pipe (400), wherein the water pipe (400) is passed through the blocking wall (100) and the water retaining wall (200), one end of the water pipe (400) is connected to the water channel on the water-facing side of the blocking wall (100), and the other end of the water pipe (400) is connected to a valve (410).