Die for manufacturing water-permeable precast block for replacing tunnel non-fine concrete
By designing molds for tunnel construction, including bottom molds, side molds, back molds and arc-shaped pipes, the problem of low stability of sand-free concrete is solved, ensuring the stability of blind pipe parts and improving the forming efficiency of prefabricated blocks .
Patent Information
- Application Number
- CN202420172778.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-24
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-01-24
AI Technical Summary
Existing sand-free concrete has low stability in tunnel construction, which can easily lead to insufficient lining thickness and emptying problems, especially the filling of blind pipes is not firm.
Design a mold including a bottom mold, a side mold, a back mold and a curved tube. These components enclose the forming space of permeable prefabricated blocks to ensure the stability of the blind tube parts and quickly release them through the demolding holes to avoid Lining problem.
The stability of the triangular area above the blind pipe part during tunnel construction is achieved, the problems of insufficient lining thickness and emptying are avoided, and the forming and installation efficiency of prefabricated blocks are improved.
Smart Images

Figure CN221968406U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of waterproofing of water-rich section tunnels, and in particular relates to a mold for making a water-permeable prefabricated block replacing sandless concrete of a tunnel. Background Art
[0002] With the rapid development of infrastructure construction in my country, the number of tunnel construction is increasing, and tunnel construction waterproofing is an important part of it.
[0003] At present, the waterproof design of water-rich tunnels basically has longitudinal blind pipes. Sandless concrete is generally used to fill the triangular area above the blind pipe to ensure that the lining is not hollow. This method has the characteristics of low price, but the sandless concrete is filled on site and has low stability. It is easy for the geotextile and waterproof materials wrapped in the sandless concrete to be not fixed in place or fall off at the construction site, resulting in the sandless concrete falling and concentrating, thereby causing the lining to be insufficient in thickness and hollow. Therefore, a mold for making permeable prefabricated blocks that replace the sandless concrete in tunnels is needed. Utility Model Content
[0004] In order to solve at least one of the above technical problems existing in the prior art, the utility model provides a mold for making a permeable prefabricated block replacing sandless concrete of a tunnel.
[0005] The utility model is implemented by the following technical scheme: a mold for making a permeable prefabricated block replacing sandless concrete for a tunnel, comprising a bottom mold, a side mold, a rear mold and an arc-shaped tube; two side molds are vertically connected to the two sides of a bottom film, the rear end faces of the bottom film and the side molds are both fitted and connected to the rear mold, the arc-shaped tube is buckled and tightly attached to the inner side of the rear mold, the arc-shaped tube, the bottom film and the side molds enclose a space for molding the permeable prefabricated block, and the rear mold is provided with a demoulding hole for ejecting the molded permeable prefabricated block.
[0006] Preferably, the rear mold and the bottom film are arranged at an acute angle, the left and right ends of the arc tube abut against the side molds and the bottom end abuts against the seam between the bottom film and the rear mold.
[0007] Preferably, a section of the upper end of the arc-shaped tube extends out for clamping with the upper end surface of the rear mold.
[0008] Preferably, the cross section of the arc-shaped pipe is a semicircle matching the shape of the drainage blind pipe.
[0009] Preferably, the demoulding holes are arranged on the rear mold at intervals along the length direction of the rear mold, and the distances between the center points and the upper and lower end surfaces of the rear mold are equal.
[0010] Preferably, the vertical cross-section of the rear mold is a parallelogram, the vertical cross-section of the side mold is a triangle, and the end faces of the bottom film and the side mold are both inclined surfaces.
[0011] Preferably, the bottom mold, the side molds and the inner side surfaces of the arc-shaped tube are all coated with a release agent.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] The device has a simple structure and is used to make permeable prefabricated blocks that replace sandless concrete in tunnels through a bottom mold, a side mold, a rear mold and an arc tube. The stability of the triangular area above the blind pipe is ensured, which is convenient for fixation and can avoid the problems of insufficient lining thickness and voiding. At the same time, the molded prefabricated blocks can be quickly ejected through the release agent and the demoulding holes. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 is a side view of the overall structure of this embodiment;
[0016] Figure 2 1 is a top view of the overall structure of this embodiment (without the arc tube);
[0017] Figure 3 It is a front view of the overall structure of this embodiment;
[0018] Figure 4 is a forming diagram of the water permeable prefabricated block of this embodiment;
[0019] Figure 5 is a front view of the installation position of the permeable prefabricated block of this embodiment;
[0020] Figure 6 It is a side view of the installation position of the permeable prefabricated block of this embodiment.
[0021] In the figure: 1- bottom mold; 2- side mold; 3- rear mold; 3.1- demoulding hole; 4- arc tube; 5- water-permeable prefabricated block; 6- rivet; 7- pressure strip; 8- drainage blind pipe. DETAILED DESCRIPTION
[0022] Combined with the drawings in the embodiments of the utility model, the technical solutions in the embodiments of the utility model are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other implementation methods obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification so that people familiar with this technology can understand and read them. They are not used to limit the conditions under which the present invention can be implemented, so they have no substantive technical significance. Any structural modification, change in proportional relationship or adjustment of size should fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention. It should be noted that in this specification, relational terms such as first and second are only used to distinguish one entity from other entities, and do not necessarily require or imply any actual relationship or order between these entities.
[0024] The utility model provides an embodiment:
[0025] like Figures 1 to 6 As shown, a mold for making permeable prefabricated blocks that replace sandless concrete for tunnels includes a bottom mold 1, side molds 2, a rear mold 3 and an arc tube 4; two side molds 2 are vertically connected to the two sides of the bottom membrane 1, the rear end faces of the bottom membrane 1 and the side molds 2 are both fitted and connected to the rear mold 3, the arc tube 4 is buckled and tightly attached to the inner side of the rear mold 3, the arc tube 4, the bottom membrane 1 and the side molds 2 form a space for forming the permeable prefabricated blocks, and the rear mold 3 has a demoulding hole 3.1 for ejecting the formed permeable prefabricated blocks, and a stick can be used to pass through the demoulding hole 3.1 to push the arc tube 4.
[0026] In this embodiment, the vertical section of the rear mold 3 is a parallelogram, the vertical section of the side mold 2 is a triangle, and the end faces of the bottom film 1 and the side mold 2 are both inclined planes, and the cross section of the arc tube 4 is a semicircle that matches the shape of the drainage blind pipe. The rear mold 3 and the bottom film 1 are arranged at an acute angle, and the left and right ends of the arc tube 4 abut on the side mold 2 and the bottom end abuts on the joint between the bottom film 1 and the rear mold 3; the upper end of the arc tube 4 extends a section for clamping with the upper end face of the rear mold 3.
[0027] The demoulding holes 3.1 are arranged on the rear mold 3 at intervals along the length direction of the rear mold 3 and the center points are equidistant from the upper and lower end surfaces of the rear mold 3. The inner surfaces of the bottom mold 1, the side mold 2 and the arc tube 4 are all coated with demoulding agent.
[0028] The bottom form 1, the side form 2, and the rear form are all wooden formworks, and the arc pipe 4 is a PVC pipe, which is made according to the on-site construction requirements and the specifications of the longitudinal drainage blind pipe. The raw materials of the permeable prefabricated block are aggregated crushed stone, cement slurry and polypropylene mesh fiber.
[0029] Specific steps:
[0030] 1. Design and process the template according to construction requirements and specifications of the longitudinal drainage blind pipe;
[0031] 2. Apply release agent, lay polypropylene mesh fiber, put in aggregate gravel, and then pour in cement slurry;
[0032] 3. Equal strength demoulding;
[0033] 4. After passing the quality inspection, it will be transported to the site for installation. One permeable prefabricated block uses two pressure strips, and each pressure strip is fixed with rivets.
[0034] The above is only a preferred specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any changes or substitutions that can be easily thought of by any technician familiar with the technical field within the technical scope disclosed by the utility model should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model shall be based on the protection scope of the claims.
Claims
1. A mold for making a permeable prefabricated block replacing sandless concrete in a tunnel, characterized by: The invention comprises a bottom mold (1), a side mold (2), a rear mold (3) and an arc-shaped tube (4); the two side molds (2) are vertically connected to the two sides of the bottom mold (1); the rear end surfaces of the bottom mold (1) and the side molds (2) are both fitted and connected to the rear mold (3); the arc-shaped tube (4) is buckled and tightly fitted to the inner side of the rear mold (3); the arc-shaped tube (4), the bottom mold (1) and the side molds (2) enclose a space for forming a water-permeable prefabricated block; and the rear mold (3) is provided with a demoulding hole (3.1) for ejecting the formed water-permeable prefabricated block.
2. The mold for making a water-permeable prefabricated block replacing sandless concrete for tunnels according to claim 1, characterized in that: The rear mold (3) and the bottom mold (1) are arranged at an acute angle, and the left and right ends of the arc tube (4) abut against the side mold (2) and the bottom end abuts against the joint between the bottom mold (1) and the rear mold (3).
3. The mold for making a water-permeable prefabricated block replacing sandless concrete for tunnels according to claim 2, characterized in that: The upper end of the arc-shaped tube (4) extends out for a section to be clamped with the upper end surface of the rear mold (3).
4. The mold for making a water-permeable prefabricated block replacing sandless concrete for tunnels according to claim 3, characterized in that: The cross section of the arc-shaped pipe (4) is a semicircle matching the shape of the drainage blind pipe.
5. The mold for making a water-permeable prefabricated block replacing sandless concrete for tunnels according to claim 4, characterized in that: The demoulding holes (3.1) are arranged on the rear mold (3) at intervals along the length direction of the rear mold (3), and the distances between the center points and the upper and lower end surfaces of the rear mold (3) are equal.
6. The mold for making a water-permeable prefabricated block replacing sandless concrete for tunnels according to claim 1, characterized in that: The vertical section of the rear mold (3) is a parallelogram, the vertical section of the side mold (2) is a triangle, and the end faces of the bottom mold (1) and the side mold (2) are both inclined surfaces.
7. The mold for making a permeable prefabricated block replacing sandless concrete for tunnels according to claim 1, characterized in that: The inner surfaces of the bottom mold (1), the side mold (2) and the arc tube (4) are all coated with a release agent.