Cement dosage control device for cement mixing pile

By introducing an automated control system and mud converter in the construction of cement mixing piles, the automatic rotation and precise dose control of cement mixing piles are achieved, which solves the problem of cement slurry waste during construction and improves construction efficiency and cement utilization rate.

CN221972388UActive Publication Date: 2024-11-08中庆建设有限责任公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420129857.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-19
Publication Date
2024-11-08
Estimated Expiration
2034-01-19

AI Technical Summary

Technical Problem

During the construction of cement mixing piles, due to the uneven level of the construction team, the failure to completely stop the spraying or a small amount of spraying is caused to waste cement slurry, especially in idle areas and mobile equipment.

Method used

A cement dose control device for cement mixing piles was designed, and an automated control system was used to realize the automatic rotation of cement mixing piles through the synergistic action of mixing pile driving motor and cement mixing pile motor, and the switches of water pipes and mortar pipes were controlled through mud converters. Achieve precise control of cement dose and reduce waste.

Benefits of technology

It improves construction efficiency, reduces human intervention, ensures the utilization rate and construction quality of cement, enhances the flexibility and adaptability of equipment, and avoids the waste of cement slurry.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972388U_ABST
    Figure CN221972388U_ABST
Patent Text Reader

Abstract

The utility model discloses a cement mixing pile cement dosage control device and relates to the field of cement mixing construction. The problems that in the prior art, after guniting is stopped, a pipeline is blocked, guniting is not stopped or a small amount of guniting is carried out in actual construction, and consequently cement paste is wasted in an idling area and when equipment is moved are solved. The device comprises cement mixing pile equipment movable supporting legs, a cement mixing pile drill rod, a cement mixing pile motor, a slurry converter, a mixing pile driving motor, a mortar pipe, a water pipe and a mortar pool. The cement mixing pile equipment movable supporting leg is erected on the original construction ground, a cement mixing pile is fixed to the cement mixing pile equipment foundation platform, and a cement mixing pile motor is arranged above the cement mixing pile and connected with a cement mixing pile drilling rod. The cement mixing pile rotating rod is further connected with a mixing pile driving motor; the slurry converter is arranged on the cement mixing pile and used for controlling opening and closing of water in the water pipe and controlling the mortar pipe to convey cement slurry in the mortar pool. Application to the building field.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of cement mixing construction, and in particular to a cement dosage control device for a cement mixing pile. Background Art

[0002] Cement mixing pile is an engineering technology widely used in soft soil foundation treatment. Its principle is to use cement as the main agent of the curing agent, spray cement into the soil with a mixing pile machine and mix it fully to harden the soft soil and improve the foundation strength. This method was introduced into my country in the 1970s. After more than 40 years of development, it has become a mature technology.

[0003] The construction of cement mixing piles mainly adopts three forms: single-axis, double-axis and three-axis mixing piles. Special deep mixers force soft soil and cement to mix, causing a series of physical and chemical reactions between the two, thereby consolidating the soil and forming cement soil piles with integrity, water stability and certain strength. This process plays an important role in the field of soft soil foundation treatment.

[0004] In the construction of traditional cement mixing piles, spraying should be stopped during the idle mixing section or when moving equipment. However, in actual construction, due to the uneven level of construction team members, some operators did not stop spraying or sprayed a small amount of cement in order to avoid clogging the pipeline after stopping spraying, resulting in waste of cement slurry in the idling area and when moving equipment. Especially when the idling area is large, the waste of cement slurry is very serious. Utility Model Content

[0005] The utility model proposes a cement dosage control device for cement mixing piles to solve the problem that operators do not stop the grouting or only spray a small amount of grouting during actual construction, which causes cement slurry waste in the idling area and when moving equipment in order to avoid clogging the pipeline after stopping the grouting. The device includes:

[0006] Cement mixing pile equipment includes movable legs, cement mixing pile drill rod, cement mixing pile motor, mud converter, mixing pile drive motor, mortar pipe, water pipe, mortar tank;

[0007] The movable legs of the cement mixing pile equipment are erected on the original construction ground and are used to fix the basic platform of the cement mixing pile equipment. The cement mixing pile is fixed on the basic platform of the cement mixing pile equipment. The cement mixing pile motor is arranged above the cement mixing pile and is connected to the cement mixing pile drill rod to drive the cement mixing pile rotating rod to rotate; the cement mixing pile rotating rod is also connected to the mixing pile driving motor, and the mixing pile driving motor is used to provide downward driving power for the cement mixing pile rotating rod; the mud converter is arranged on the cement mixing pile, and is used to control the opening and closing of water in the water pipe, and is also used to control the mortar pipe to transport cement slurry in the mortar pool.

[0008] Furthermore, a preferred embodiment is proposed, wherein the device also includes a bottom support rod, a cement mixing pile bracket and a main support rod, a cement mixing pile bracket is provided at the bottom of the cement mixing pile, and the bottom support rod and the main support rod are used to adjust the cement mixing pile bracket to a vertical state.

[0009] Furthermore, a preferred embodiment is proposed, wherein the device further comprises a bottom fixing bracket of the cement mixing pile, and the bottom fixing bracket of the cement mixing pile is used to fix the cement mixing pile bracket.

[0010] Furthermore, a preferred embodiment is proposed, wherein the device also includes a three-way valve switch controller, and the mud converter controls the opening and closing of the water in the water pipe and the cement slurry in the mortar pipe through the three-way valve switch controller; the three-way valve switch controller is a T-type structure, and the mud converter includes a mud converter interface A, a mud converter interface B and a mud converter interface C; the mud converter interface A, the mud converter interface B and the mud converter interface C are located at the three ports of the T-type structure.

[0011] Furthermore, a preferred embodiment is proposed, wherein the device is also provided with an operating table, the operating table is arranged on the cement mixing pile equipment base platform, the three-way valve switch controller is fixed on the operating table, and the cement mixing pile equipment base platform is also provided with an operator seat.

[0012] Furthermore, a preferred embodiment is proposed, wherein the device further comprises a mud transfer box, wherein the mud transfer box is fixed on the cement mixing pile and connected to the mud converter.

[0013] Furthermore, a preferred embodiment is proposed, wherein the device further comprises an electric box controller, and the electric box controller provides electric energy for the cement mixing pile motor, the mud converter, the mixing pile drive motor, and the three-way valve switch controller.

[0014] Furthermore, a preferred embodiment is proposed, wherein the device further comprises a mortar pump and a mortar mixer, wherein the mortar pump is fixed on the mortar pipe, and the mortar mixer is placed in the mortar pool for mixing the mortar.

[0015] Furthermore, a preferred embodiment is proposed, wherein the device further comprises a water pump, and the water pump is fixed on the water pipe.

[0016] Furthermore, a preferred embodiment is proposed, wherein the device further comprises a water tank, and the water pipe is connected to the water tank for supplying water.

[0017] The utility model is beneficial in that:

[0018] The utility model solves the problem that operators do not stop the grouting or only spray a small amount of grouting during actual construction to avoid clogging of pipelines after stopping the grouting, resulting in waste of cement slurry in idling areas and equipment when moving equipment.

[0019] The cement dosage control device for cement mixing piles described in the utility model introduces automatic control, and realizes automatic rotation of cement mixing piles through the synergistic effect of the mixing pile drive motor and the cement mixing pile motor. This feature significantly improves the convenience of operation, reduces the need for human intervention, reduces the workload of operators, and improves construction efficiency. The mud converter in the device controls the switch of the water pipe to achieve precise control of the cement dosage. This allows the amount of cement used to be adjusted as needed during the construction process, avoids waste, and improves the utilization rate of cement. Precise control of dosage also helps to ensure the stability of construction quality. The device is designed with movable legs so that the device can be freely moved and fixed in a suitable position at the construction site. This enhances the flexibility of the device, making it suitable for different construction environments, while improving the adaptability and efficiency of construction. The mud converter not only controls the switch of the water pipe, but also controls the mortar pipe to transport cement slurry in the mortar pool. This multifunctional design enables the device to complete multiple tasks during the construction process and improves the efficiency of the overall operation.

[0020] In a preferred embodiment of the utility model, by introducing a three-way valve switch controller and a mud converter, accurate control of water and cement slurry in the water pipe and mortar pipe is achieved. This helps to ensure the accurate delivery of cement dosage during the construction of cement mixing piles and improve the quality of the project. The three-way valve switch controller with a T-shaped structure, the design of the mud converter interface A, the mud converter interface B and the mud converter interface C make the operation more intuitive and simple. The staff can easily adjust the flow direction of water and cement slurry through the controller to achieve rapid switching and adjustment. The mud converter controls the opening and closing of water and cement slurry in the water pipe and mortar pipe through the three-way valve switch controller. By adjusting the state of the mud converter interface A, the mud converter interface B and the mud converter interface C, accurate control of the flow direction of water and cement slurry is achieved. The three-way valve switch controller 12 adopts a T-shaped structure, in which the mud converter interface A, the mud converter interface B and the mud converter interface C are located at the three ports of the T-shaped structure. This design makes the structure of the controller more compact and easy to integrate and install. By precisely controlling the flow of water and cement slurry, the accurate dosage of cement is ensured, which helps to improve the construction accuracy of cement mixing piles and thus improve the quality of the project. The intuitive T-shaped structure and simple slurry converter interface are designed to simplify the operation process, allowing workers to more easily control and adjust the cement dosage and improve construction efficiency.

[0021] The utility model is applied to the field of construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 The present invention is a structural schematic diagram of a cement dosage control device for cement mixing piles according to the first embodiment, wherein 1 is the original construction ground; 2 is the movable legs of the cement mixing pile equipment; 3 is the bottom fixed bracket of the cement mixing pile; 4 is the cement mixing pile drill rod; 5 is the cement mixing pile motor; 6 is the mud transfer box; 7 is the mud converter; 8 is the bottom support rod; 9 is the cement mixing pile bracket; 10 is the main support rod; 11 is the mixing pile drive motor; 12 is the three-way valve switch controller; 13 is the operating table; 14 is the operator's seat; 15 is the electric box controller; 16 is the mortar pipe; 17 is the water pipe; 18 is the water pump; 19 is the water tank; 20 is the mortar pump; 21 is the mortar pool; 22 is the mortar mixer;

[0023] Figure 2 This is a schematic diagram of a cement mixing structure according to Embodiment 6;

[0024] Figure 3 This is a schematic diagram of the structure of the operating table described in Embodiment 5;

[0025] Figure 4 This is a three-way valve switch controller stereogram according to the fourth embodiment, 23 is a mud converter interface A; 24 is a mud converter interface B; 25 is a mud converter interface C;

[0026] Figure 5 A top view of the three-way valve switch controller according to Embodiment 4;

[0027] Figure 6 This is a schematic diagram of closing port C of the three-way valve switch controller described in Embodiment 4;

[0028] Figure 7 This is a schematic diagram of closing port B of the three-way valve switch controller according to the fourth embodiment;

[0029] Figure 8 A schematic diagram of the position of the three-way valve switch controller and the mixing pile motor according to the eleventh embodiment;

[0030] Fig. 9 This is a flow chart of a cement dosage control device for cement mixing piles as described in Implementation Example 11. DETAILED DESCRIPTION

[0031] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0032] Implementation method 1, see Figure 1 The present embodiment is described as follows. A cement dosage control device for cement mixing piles according to the present embodiment comprises:

[0033] The cement mixing pile equipment includes movable legs 2, a cement mixing pile drill rod 4, a cement mixing pile motor 5, a mud converter 7, a mixing pile drive motor 11, a mortar pipe 16, a water pipe 17, and a mortar pool 21;

[0034] The movable legs 2 of the cement mixing pile equipment are erected on the original construction ground 1 and are used to fix the basic platform of the cement mixing pile equipment. The cement mixing pile is fixed on the basic platform of the cement mixing pile equipment. The cement mixing pile motor 5 is arranged above the cement mixing pile and is connected to the cement mixing pile drill rod 4 to drive the cement mixing pile rotating rod 4 to rotate; the cement mixing pile rotating rod 4 is also connected to the mixing pile driving motor 11, and the mixing pile driving motor 11 is used to provide downward driving power for the cement mixing pile rotating rod 4; the mud converter 7 is arranged on the cement mixing pile, and is used to control the opening and closing of the water in the water pipe 17, and is also used to control the mortar pipe 16 to transport the cement slurry in the mortar pool 21.

[0035] The cement dosage control device for cement mixing piles described in this embodiment introduces automatic control, and realizes automatic rotation of cement mixing piles through the synergy of the mixing pile drive motor and the cement mixing pile motor. This feature significantly improves the convenience of operation, reduces the need for human intervention, reduces the workload of operators, and improves construction efficiency. The mud converter in the device controls the switch of the water pipe to achieve precise control of the cement dosage. This allows the amount of cement used to be adjusted as needed during the construction process, avoids waste, and improves the utilization rate of cement. Precise control of dosage also helps to ensure the stability of construction quality. The device is designed with movable legs so that the device can be freely moved and fixed in a suitable position at the construction site. This enhances the flexibility of the device, making it suitable for different construction environments, while improving the adaptability and efficiency of construction. The mud converter not only controls the switch of the water pipe, but also controls the mortar pipe to transport cement slurry in the mortar pool. This multifunctional design enables the device to complete multiple tasks during the construction process and improves the efficiency of the overall operation.

[0036] Specifically, at the construction site, first use the movable legs to fix the cement mixing pile equipment foundation platform in the appropriate position to ensure the stability of the equipment. Start the mixing pile drive motor and cement mixing pile motor to realize the automatic rotation of the cement mixing pile and start the mixing process. The automated design reduces the difficulty of operation for operators and improves the efficiency of mixing. The switch of the water pipe is controlled by the mud converter to achieve precise control of the cement dosage. Adjust the dosage as needed to avoid waste and ensure the effective use of cement during construction. The mud converter also controls the mortar pipe to transport the cement slurry in the mortar pool, realizing multi-functional operation and improving the overall efficiency of construction. Avoid the problem of clogging the pipeline when stopping the spraying, and at the same time, through dosage control, reduce the waste of cement slurry and improve resource utilization. The design of the movable legs and automation improves the flexibility and operating efficiency of the equipment, which helps to speed up the construction progress. The characteristics of automatic rotation and dosage control simplify the tasks of operators and reduce the risk of human error.

[0037] Embodiment 2. This embodiment is a further limitation of the cement dosage control device for cement mixing piles described in Embodiment 1. The device also includes a bottom support rod 8, a cement mixing pile bracket 9 and a main support rod 10. A cement mixing pile bracket 9 is provided at the bottom of the cement mixing pile. The bottom support rod 8 and the main support rod 10 are used to adjust the cement mixing pile bracket 9 to a vertical state.

[0038] In this embodiment, the bottom support rod and the main support rod are introduced, and the stability of the entire device can be improved by adjusting the cement mixing pile bracket to a vertical state. This is particularly important for construction under different terrain or construction site conditions, ensuring that the equipment is firmly fixed and improving the reliability of the work. The bottom of the cement mixing pile bracket is provided with a cement mixing pile bracket, which can provide more accurate positioning. This has a positive effect on ensuring the position accuracy and stability of the cement mixing pile during the construction process.

[0039] In this embodiment, by adjusting the bottom support rod and the main support rod, the angle of the cement mixing pile support can be flexibly adjusted to make it vertical. Such a design is based on physical principles and the position of the support is accurately controlled by adjusting the rod.

[0040] A bracket is designed at the bottom of the cement mixing pile, which not only provides stability, but also helps to better position the cement mixing pile and ensure its correct position during construction. By adjusting the support rod, the cement mixing pile bracket is ensured to be in a vertical state, which increases the stability of the equipment and improves the safety of construction. The introduction of the cement mixing pile bracket and support rod can more accurately position the cement mixing pile, avoid errors in the equipment during construction, and improve the accuracy of construction. The bottom support rod and the main support rod can be adjusted to adapt to different terrains or construction site conditions, enhancing the adaptability and flexibility of the device in various environments.

[0041] Embodiment 3: This embodiment further limits the cement dosage control device for cement mixing piles described in Embodiment 2, wherein the device further comprises a bottom fixing bracket 3 of the cement mixing pile, and the bottom fixing bracket 3 of the cement mixing pile is used to fix the cement mixing pile bracket 9.

[0042] The present embodiment introduces the bottom fixing bracket 3 of the cement mixing pile to increase the firmness of the entire cement mixing pile support system. By fixing the bracket, the influence of external factors on the cement mixing pile bracket can be effectively reduced, and the stability of the equipment can be improved. The design of the fixing bracket can make the cement mixing pile bracket more reliably supported. This is very important for ensuring the stability and reliability of the support system when facing vibration or other external forces during construction.

[0043] The introduction of the bottom fixed bracket 3 of the cement mixing pile is based on the physical principle, that is, by increasing the bottom support points, the entire bracket system is more firmly fixed to the ground. This helps to reduce vibration and shaking, and improve the working efficiency and safety of the equipment. The main function of the fixed bracket is to ensure the firm fixation of the cement mixing pile bracket 9. This is achieved by introducing additional support points at the bottom to stabilize the bracket and prevent it from tilting or moving during construction. The main purpose is to improve the stability of the entire cement mixing pile support system through the design of the bottom fixed bracket 3 of the cement mixing pile. This helps to carry out construction more reliably under various construction site conditions. By fixing the cement mixing pile bracket more firmly, the impact of external vibration on the equipment can be reduced, thereby improving the accuracy and efficiency of construction. The improved stability and reliability of the equipment help to ensure safety during construction. The fixed bracket is designed to prevent the equipment from accidentally moving or tilting and reduce potential safety risks.

[0044] Implementation method 4: See Figure 4 , Figure 5 , Figure 6 and Figure 7 This embodiment is a further limitation of the cement dosage control device for cement mixing piles described in Embodiment 1, wherein the device further comprises a three-way valve switch controller 12, and the mud converter 7 controls the opening and closing of the water in the water pipe 17 and the cement slurry in the mortar pipe 16 through the three-way valve switch controller 12; the three-way valve switch controller 12 is a T-shaped structure, and the mud converter 7 comprises a mud converter interface A23, a mud converter interface B24 and a mud converter interface C25; the slurry converter interface A23, the mud converter interface B24 and the mud converter interface C25 are located at the three ports of the T-shaped structure.

[0045] This embodiment can achieve accurate control of water and cement slurry in the water pipe 17 and the mortar pipe 16 by introducing the three-way valve switch controller 12 and the mud converter 7. This helps to ensure the accurate dosage of cement during the construction of cement mixing piles and improve the quality of the project. The design of the three-way valve switch controller 12 with a T-shaped structure, the mud converter interface A23, the mud converter interface B24 and the mud converter interface C25 makes the operation more intuitive and simple. The staff can easily adjust the flow direction of water and cement slurry through the controller to achieve rapid switching and adjustment.

[0046] The mud converter 7 controls the opening and closing of water and cement slurry in the water pipe 17 and the mortar pipe 16 through the three-way valve switch controller 12. By adjusting the states of the mud converter interface A23, the mud converter interface B24 and the mud converter interface C25, precise control of the flow direction of water and cement slurry is achieved. The three-way valve switch controller 12 adopts a T-type structure, in which the mud converter interface A23, the mud converter interface B24 and the mud converter interface C25 are located at the three ports of the T-type structure. This design makes the structure of the controller more compact and easy to integrate and install. By accurately controlling the flow direction of water and cement slurry and ensuring the accurate delivery of cement dosage, it helps to improve the construction accuracy of cement mixing piles, thereby improving the quality of the project. The intuitive T-type structure and simple mud converter interface are designed to simplify the operating process, allowing staff to more easily control and adjust the cement dosage and improve construction efficiency.

[0047] In actual application, the mud converter interface C is closed, and the cement slurry enters the mud converter interface A from the mud converter interface B, and the mixing construction is normal;

[0048] The mud converter interface B is closed, and water flows from the mud converter interface C into the mud converter interface A. When the equipment is idling or moving, the mixing pile pipe is flushed to save cement slurry.

[0049] By installing a remote control electric control system on this valve, the mixing pile operators can control the cement slurry in time according to the actual situation and reduce unnecessary waste of cement slurry.

[0050] Implementation method 5: See Figure 3 This embodiment is a further limitation of the cement dosage control device for cement mixing piles described in Embodiment 4, wherein the device is further provided with an operating table 13, which is arranged on the cement mixing pile equipment base platform, the three-way valve switch controller 12 is fixed on the operating table 13, and an operator seat 14 is also arranged on the cement mixing pile equipment base platform.

[0051] An operating table 13 and an operator's seat 14 are provided so that the operator can operate in a relatively comfortable position. This enhanced human-machine interaction improves the convenience and efficiency of operation. By fixing the three-way valve switch controller 12 on the operating table 13, a centralized control center is formed. The operator can conveniently monitor and adjust the cement dosage of the cement mixing pile in one position, simplifying the control process. An operator's seat 14 is provided to take the operator's comfort into consideration. Providing a seat helps reduce the operator's fatigue and improve work efficiency during long-term operation.

[0052] The operating table 13 serves as a centralized control point on the basic platform of the cement mixing pile equipment. By fixing the three-way valve switch controller 12 on the operating table, centralized control of the cement dosage is achieved. The operator can make adjustments through the controller on the operating table without leaving the operating position. The setting of the operator's seat 14 takes into account the comfort of the operator and provides a relatively comfortable working environment. This helps to improve the operator's work experience and production efficiency. By setting up an operating table on the basic platform of the cement mixing pile equipment and a device for centrally controlling the cement dosage, the convenience and efficiency of the operation are improved, allowing the operator to control and adjust more easily. By setting up an operator's seat, attention is paid to the comfort of the operator, a more comfortable working environment is provided for long-term operation, the fatigue of the operator is reduced, and work efficiency is helped to improve.

[0053] Implementation Method 6: See Figure 2 This embodiment is a further limitation of the cement dosage control device for cement mixing piles described in Embodiment 1, wherein the device further comprises a mud transfer box 6 , which is fixed on the cement mixing pile and connected to a mud converter 7 .

[0054] The introduction of the mud transfer box 6 and the mud converter 7 in this embodiment makes the mud processing more integrated. This can improve the overall production efficiency, reduce scattered mud processing steps, and simplify the operation process. The fixation of the mud transfer box 6 and the connection with the mud converter 7 help to reduce the loss of mud during the transmission process. Through effective mud management, resources can be saved and the yield rate can be improved. Fixing the mud transfer box 6 on the cement mixing pile helps to improve the structural stability of the entire device. Such a design can reduce the possibility of instability of the device due to vibration or other factors.

[0055] The fixation of the mud transfer box 6 and the connection with the mud converter 7 allow the mud processing to be closely integrated with the operation of the cement mixing pile. The mud can be processed directly in the device, avoiding multiple transmission, reverse transportation and other steps, and improving the processing efficiency. Fixing the mud transfer box and connecting the mud converter help reduce the loss of mud during the processing. Stable connection and transmission path can reduce mud leakage and waste. The fixed position of the mud transfer box helps to improve the structural stability of the entire device. During the vibration or operation of the cement mixing pile, the fixed mud transfer box helps to maintain the balance of the entire system. Through the introduction of the mud transfer box and the mud converter, the mud processing process is optimized, the intermediate steps are reduced, and the production efficiency of the entire cement mixing pile cement dosage control device is improved. Reducing the loss of mud helps to reduce production costs and improve resource utilization efficiency. By fixing the mud transfer box, the structural stability of the entire device is increased, and the instability caused by vibration or other factors is reduced. This helps to extend the service life of the device and improve reliability.

[0056] Embodiment 7. This embodiment is a further limitation of the cement dosage control device for cement mixing piles described in embodiment 1. The device also includes an electrical box controller 15, which provides electrical energy for the cement mixing pile motor 5, the mud converter 7, the mixing pile drive motor 11, and the three-way valve switch controller 12.

[0057] The introduction of the electric box controller 15 in this embodiment helps to centrally control the power supply of the cement mixing pile motor 5, the mud converter 7, the mixing pile drive motor 11 and the three-way valve switch controller 12. Such a design can improve the efficiency of power management and reduce energy waste. By connecting different motors and controllers to the electric box controller 15, an integrated control system is realized. This simplifies the operation and improves the operability of the entire cement mixing pile cement dosage control device. The electric box controller 15 provides electrical energy to ensure that each component is supplied with a stable power supply. This helps prevent equipment failure or production interruption caused by unstable power.

[0058] The electric box controller 15 provides electric energy, centrally manages and distributes it to the cement mixing pile motor 5, the mud converter 7, the mixing pile drive motor 11 and the three-way valve switch controller 12. This ensures that each component can obtain sufficient power supply. Connecting each motor and controller to the electric box controller 15 realizes an integrated control system. The electric box controller acts as a central management unit, uniformly coordinating the operation of each component and improving the collaborative working efficiency of the entire device. The electric box controller 15 is designed to ensure a stable supply of electric energy. Through the effective management of the power supply, the adverse effects of power fluctuations on the operation of the equipment are reduced, and the stability of the device is improved.

[0059] Embodiment 8. This embodiment further limits the cement dosage control device for cement mixing piles described in embodiment 1. The device also includes a mortar pump 20 and a mortar mixer 22. The mortar pump 20 is fixed on the mortar pipe 16, and the mortar mixer 22 is placed in the mortar pool 21 for mixing mortar.

[0060] The mortar pump 20 and the mortar mixer 22 are introduced in this embodiment, so that the device has the ability to handle mortar. This provides a comprehensive solution for the production process of cement mixing piles, especially when mortar is needed. The addition of the mortar pump and the mortar mixer expands the functional scope of the device, making it not only limited to the control of cement dosage of cement mixing piles, but also includes the processing and mixing of mortar. The fixing of the mortar pump and the stirring action of the mortar mixer help to flexibly and efficiently handle the mortar, thereby improving the efficiency of the entire cement mixing pile production process.

[0061] The mortar pump 20 is fixed on the mortar pipe 16, and its main function is to transport the mortar from the mortar pool 21 to the required position, which may be a specific position of the mixing pile. Such a design realizes the controlled delivery of the mortar through the mechanical working principle of the pump. The mortar mixer 22 is placed in the mortar pool 21 to mix the mortar to ensure its uniformity and quality. The operation of the mixer ensures that the mortar is fully mixed before use through the principle of mechanical mixing. By introducing a mortar pump and a mortar mixer, this design aims to improve the production process of cement mixing piles and make it more comprehensive and integrated. The functional expansion of the device brings more possibilities for handling mortar, so that the device can adapt to changes in demand more flexibly in different production scenarios. The introduction of a mortar pump and a mortar mixer is intended to ensure the quality and uniformity of the mortar, thereby improving the quality of the final product of the cement mixing pile.

[0062] Embodiment 9: This embodiment further limits the cement dosage control device for cement mixing piles described in Embodiment 1. The device further includes a water pump 18 , and the water pump 18 is fixed on the water pipe 17 .

[0063] In this embodiment, a water pump 18 is introduced and fixed on the water pipe 17, so that the device can control the cement dosage more accurately. The function of the water pump is to transport cement to the required position by mechanical means, thereby ensuring that the amount of cement added can be accurately controlled. The fixation of the water pump and the accuracy of controlling the cement dosage help to improve the production efficiency of cement mixing piles and avoid waste and unnecessary excessive addition.

[0064] The water pump 18 is fixed on the water pipe 17, and its function is to transport cement from the storage location to the required place by mechanical pumping. The operation of the water pump realizes precise control of cement through the principle of mechanical pumping. The main purpose of this design is to ensure the accuracy of cement dosage in the production process of cement mixing piles to avoid excess or deficiency and improve product quality. The fixed design of the water pump simplifies the operation process, reduces the complexity of operation, and helps to improve production efficiency. Accurate cement dosage control helps to avoid excessive use of cement, thereby reducing waste and improving the economic benefits of the production process.

[0065] Embodiment 10: This embodiment further limits the cement dosage control device for cement mixing piles described in Embodiment 1. The device further includes a water tank 19. The water pipe 17 is connected to the water tank 19 for water supply.

[0066] This embodiment is explained in conjunction with the fourth embodiment. During the construction of traditional cement mixing piles, the spraying should be stopped during the idle mixing section or the moving equipment. However, in actual construction, due to the uneven level of construction team personnel, some operators did not stop spraying or sprayed a small amount of cement during the actual construction to avoid clogging the pipeline after stopping the spraying, resulting in the waste of cement slurry in the idling area and the moving equipment. Especially when the idling area is large, the waste of cement slurry is very serious. Therefore, under the premise of ensuring the construction quality, to avoid the waste of cement slurry, this embodiment studies the addition of a set of pressure water tanks in front of the cement slurry equipment of the mixing pile, installing an electric tee above the mixer drill rod, and using an electric remote control three-way valve controller to switch the supply of cement slurry and water in real time, and use water instead of cement slurry to spray, thereby reducing the waste of cement slurry.

[0067] Implementation Method 11: See Figure 8 and Fig. 9 This embodiment provides a specific example of a cement dosage control device for cement mixing piles described in the first embodiment, and is also used to explain the second to tenth embodiments, specifically:

[0068] The movable legs 2 of the cement mixing pile equipment are erected on the original construction ground 1. The bottom support rod 8 and the main support rod 10 adjust the cement mixing pile bracket 9 to a vertical state and are fixed by the bottom fixed bracket 3 of the cement mixing pile. The cement mixing pile motor 5 drives the cement mixing pile rotating rod 4 to rotate and the mixing pile driving motor 11 provides downward driving power. The mud converter 7 adjusts the opening and closing of the water in the water pipe 17 and the cement slurry in the mortar pipe 16 through the valve controller, thereby controlling the closing and opening of the cement slurry at any time to reduce the waste of cement slurry.

[0069] Through the various stages of cement mixing pile construction, the electric remote control is operated in time to control the injection of slurry and water. In the cement mixing pile structure area, the electric remote control three-way valve controller is switched to slurry to ensure the injection of cement slurry in the structure area. In the idling area and when moving equipment, the electric remote control three-way valve controller is switched to water to avoid cement waste. This method is convenient for operators to operate, improves construction efficiency, speeds up construction progress, and prevents blockage of the spraying port, greatly reducing the waste of cement slurry, saving materials, and being low-energy and environmentally friendly.

[0070] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present utility model, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0071] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0072] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A cement dosage control device for cement mixing piles, characterized in that: The device comprises: The cement mixing pile equipment includes movable legs (2), a cement mixing pile drill rod (4), a cement mixing pile motor (5), a mud converter (7), a mixing pile drive motor (11), a mortar pipe (16), a water pipe (17), and a mortar pool (21); The movable legs (2) of the cement mixing pile equipment are erected on the original construction ground (1) and are used to fix the cement mixing pile equipment foundation platform. The cement mixing pile is fixed on the cement mixing pile equipment foundation platform. The cement mixing pile motor (5) is arranged above the cement mixing pile and is connected to the cement mixing pile drill rod (4) and is used to drive the cement mixing pile drill rod (4) to rotate; the cement mixing pile drill rod (4) is also connected to the mixing pile drive motor (11), and the mixing pile drive motor (11) is used to provide downward driving power for the cement mixing pile drill rod (4); the mud converter (7) is arranged on the cement mixing pile and is used to control the opening and closing of water in the water pipe (17), and is also used to control the mortar pipe (16) to transport cement slurry in the mortar pool (21).

2. A cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device further comprises a bottom support rod (8), a cement mixing pile support (9) and a main support rod (10); the cement mixing pile support (9) is provided at the bottom of the cement mixing pile; the bottom support rod (8) and the main support rod (10) are used to adjust the cement mixing pile support (9) to a vertical state.

3. A cement dosage control device for cement mixing piles according to claim 2, characterized in that: The device also comprises a cement mixing pile bottom fixing bracket (3), wherein the cement mixing pile bottom fixing bracket (3) is used to fix the cement mixing pile bracket (9).

4. A cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device further comprises a three-way valve switch controller (12), and the mud converter (7) controls the opening and closing of water in the water pipe (17) and cement slurry in the mortar pipe (16) through the three-way valve switch controller (12); the three-way valve switch controller (12) is a T-shaped structure, and the mud converter (7) comprises a mud converter interface A (23), a mud converter interface B (24) and a mud converter interface C (25); the mud converter interface A (23), the mud converter interface B (24) and the mud converter interface C (25) are located at three ports of the T-shaped structure.

5. A cement dosage control device for cement mixing piles according to claim 4, characterized in that: The device is also provided with an operating table (13), which is arranged on the cement mixing pile equipment base platform, and the three-way valve switch controller (12) is fixed on the operating table (13).

6. The cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device also includes a mud transfer box (6), which is fixed on the cement mixing pile and connected to the mud converter (7).

7. A cement dosage control device for cement mixing piles according to claim 4, characterized in that: The device further comprises an electric box controller (15), and the electric box controller (15) provides electric energy for the cement mixing pile motor (5), the mud converter (7), the mixing pile drive motor (11), and the three-way valve switch controller (12).

8. The cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device further comprises a mortar pump (20) and a mortar mixer (22), wherein the mortar pump (20) is fixed on the mortar pipe (16), and the mortar mixer (22) is placed in the mortar pool (21) and is used for mixing the mortar.

9. The cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device also includes a water pump (18), which is fixed on the water pipe (17).

10. The cement dosage control device for cement mixing piles according to claim 1, characterized in that: The device also includes a water tank (19), and the water pipe (17) is connected to the water tank (19) for supplying water.