Formwork supporting structure for pipe jacking working well construction

By designing a combined bracket structure with retractable top support and rotary fastener, the problem that the bracket cannot adapt to templates of different sizes in the prior art is solved, and stable support and efficient installation of the work well side formwork is achieved, and construction efficiency is improved. Scope of application.

CN221972483UActive Publication Date: 2024-11-08SHAANXI NONFERROUS CONSTR CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420626172.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-11-08
Estimated Expiration
2034-03-28

AI Technical Summary

Technical Problem

In the existing work well construction, the wall guard formwork bracket cannot adapt to formwork of different sizes and specifications, which limits the scope of application of the support mold structure and affects construction efficiency and stability.

Method used

A combined bracket structure including retractable top support and rotary fastener is designed. Through the combination of horizontal bracket, vertical rod and side template, stable support and adjustment of the opposite side template is achieved, adapting to foundation pits of different sizes, and improving the Scope of application and installation efficiency of brackets.

Benefits of technology

It realizes stable support for side forms with different sizes, simplifies the installation process, improves construction efficiency and scope of application of brackets, and ensures stable casting and construction quality of work wells.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972483U_ABST
    Figure CN221972483U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipe jacking construction, in particular to a formwork structure for pipe jacking working well construction, which comprises a support mechanism and a side formwork. The support mechanism comprises a horizontal support, a vertical rod and a plurality of telescopic jacking supports, and the vertical rod is detachably and fixedly connected with the horizontal support; the end of the horizontal support is connected with one end of the jacking, and the jacking abuts against the side formwork. According to the designed jacking, by changing the position of the adjusting nut on the adjusting screw rod, the distance between the supporting part and the end of the transverse supporting pipe or the end of the longitudinal supporting pipe is changed, the supporting part abuts against the inner wall of the side formwork, adjustment can be conveniently conducted according to the side formworks of foundation pits of different sizes, and the application range of the support is widened; according to the side formwork, the formwork part and the switching part are arranged, in the installation process of the side formwork, the connecting boss is clamped in the connecting groove, connection and fixation of the formwork part and the switching part are achieved, use of additional connecting pieces is avoided, the installation mode is simple, and the installation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of pipe jacking construction, and in particular to a formwork structure for the construction of a pipe jacking working well. Background Art

[0002] Pipe jacking construction is a trenchless construction method, a pipeline burial construction technology that requires no excavation or little excavation. Pipe jacking construction is to use the jacking force generated by the jacking equipment in the working pit to overcome the friction between the pipeline and the surrounding soil, push the pipeline into the soil according to the designed slope, and transport the earth away. After one section of the pipeline is pushed into the soil layer, the second section of the pipeline will be pushed in.

[0003] Before the pipe jacking construction, it is necessary to excavate and pour a working pit. The working pit provides a stable support for the pipe jacking equipment. During the pipe jacking construction, jacking equipment is needed to push the pipe into the soil. These devices are heavy and complex in structure, and require a stable foundation to support them. The working pit provides such a foundation to ensure the stable and reliable operation of the pipe jacking equipment.

[0004] Before the construction of the working pit, the working pit must first be measured and marked out to determine the location of the working pit excavation, and then the foundation pit is excavated. When the excavation reaches a certain depth, the retaining wall is reinforced and the retaining wall formwork and bracket are installed. Finally, concrete is poured in the formwork cavity. After the concrete solidifies, the formwork is removed, and excavation and formwork pouring are continued until the depth of the working pit reaches the designed depth. Finally, concrete is poured at the bottom of the well, and the construction of the working pit is completed.

[0005] In the existing working pit construction process, the wall protection formwork support is usually fixed to the circumferential side wall of the formwork using a transverse back beam, and then the transverse back beam is supported and fixed using diagonal braces. However, since the lengths of the transverse back beam and the diagonal braces are fixed, formworks of different sizes cannot be supported, affecting the applicability of the formwork structure. Utility Model Content

[0006] In order to improve the application scope of the formwork structure, the present application provides a formwork structure for the construction of a jacking pipe working shaft.

[0007] The combined support and template for the construction of a pipe jacking work pit provided in this application adopt the following technical solutions:

[0008] A formwork structure for the construction of a jacking pipe working shaft comprises a support mechanism and a side formwork; the support mechanism comprises a horizontal support, a vertical pole and a plurality of retractable jacking supports, the vertical pole is detachably and fixedly connected to the horizontal support; the end of the horizontal support is connected to one end of the jacking support, and the jacking support abuts against the side formwork.

[0009] By adopting the above technical scheme, when constructing the working pit, the operator first completes the erection of the side formwork on the side wall of the foundation pit, sets the horizontal support in the foundation pit, fixes the vertical pole to the horizontal support so that the vertical pole supports the horizontal support, and adjusts the top support so that the top support is tightly against the inner wall of the side formwork to achieve support for the side formwork; the set top support facilitates the stable support of the side formwork, thereby realizing the casting construction of the working pit.

[0010] In a specific feasible implementation manner, the horizontal support includes a transverse support tube and a longitudinal support tube, the transverse support tube and the longitudinal support tube are welded and fixed, and the transverse support tube and the longitudinal support tube are perpendicular to each other; the top support is inserted into the ends of the transverse support tube and the longitudinal support tube.

[0011] By adopting the above technical solution, the transverse support tube and the longitudinal support tube are welded into a whole. During installation, the horizontal bracket is directly placed in the foundation pit. By adjusting the top support inserted at the end of the transverse support tube and the longitudinal support tube, the abutment of the opposite side formwork is achieved. The designed horizontal bracket reduces the workload of the bracket installation and improves the efficiency of the formwork.

[0012] In a specific possible implementation mode, the vertical pole is vertically arranged, the length direction of the vertical pole is perpendicular to the plane where the horizontal support is located, and the vertical pole is fixedly connected to the transverse support tube or the longitudinal support tube by a rotating fastener.

[0013] By adopting the above technical solution, the designed vertical pole is connected to the horizontal support tube or the longitudinal support tube through a rotating fastener to support the horizontal bracket, thereby improving the stability of the horizontal bracket and facilitating the support of the side formwork by the horizontal bracket.

[0014] In a specific possible implementation manner, a plurality of the horizontal supports are provided, and the plurality of the horizontal supports are evenly distributed along the length direction of the vertical pole.

[0015] By adopting the above technical solution, a plurality of horizontal brackets are arranged in the length direction of the vertical pole, and the horizontal brackets abut against the side formwork at different heights, thereby improving the supporting effect of the side formwork.

[0016] In a specific feasible implementation scheme, the jacking support includes a supporting portion, an adjusting screw and an adjusting nut, one end of the adjusting screw is fixedly connected to the supporting portion and fixedly inserted in the end inner cavity of the transverse support tube or the longitudinal support tube; the adjusting nut is threadedly connected to the adjusting screw, and the adjusting nut abuts against the end of the transverse support tube and the adjusting nut abuts against the end of the longitudinal support tube; the supporting portion abuts against the side template away from one end of the adjusting screw.

[0017] By adopting the above technical solution, the adjusting screw is inserted into the inner cavity of the end of the transverse support tube or the longitudinal support tube, and the adjusting nut is rotated to change the position of the adjusting nut on the adjusting screw, so that the distance between the support part and the end of the transverse support tube or the longitudinal support tube is changed, and the support part abuts against the inner wall of the side formwork. The designed jacking support is convenient for adjustment according to the side formwork of foundation pits of different sizes, thereby improving the application range of the bracket.

[0018] In a specific feasible implementation scheme, the side template includes multiple template parts and transition parts arranged at the four corners of the working well; connecting bosses and connecting grooves are respectively arranged on the two opposite side walls of the template part and the transition part, and the connecting grooves and the connecting bosses can be tightly engaged; the multiple connecting bosses located on the side template are distributed along the circumferential direction of the side template.

[0019] By adopting the above technical scheme, the connecting bosses and connecting grooves provided on the template part and the adapter part can realize the connection and fixation between the template part and the adapter part by engaging the connecting bosses in the connecting grooves during the installation process of the side template, thereby avoiding the use of additional connecting parts, simplifying the installation method, and improving the installation efficiency; multiple template parts are connected in sequence, and four adapter parts provided at the corners fix the template parts of two adjacent sides, thereby realizing the overall installation of the side template and facilitating the pouring of the working well.

[0020] In summary, the present application includes at least one of the following beneficial technical effects:

[0021] 1. The designed jacking support changes the position of the adjusting nut on the adjusting screw, so that the distance between the support part and the end of the horizontal support tube or the longitudinal support tube is changed. The support part abuts against the inner wall of the side formwork, which is convenient for adjustment according to the side formwork of foundation pits of different sizes, thereby improving the application range of the bracket.

[0022] 2. The template part and the adapter part are set. During the installation process of the side template, the connecting boss is engaged in the connecting groove, so the connection and fixation between the template part and the adapter part are achieved, avoiding the use of additional connecting parts, simplifying the installation method, and improving the installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 The present invention is a schematic diagram of the overall structure of a formwork structure used for the construction of a jacking pipe working shaft according to an embodiment.

[0024] Figure 2 The present invention is a schematic diagram of a support mechanism of a formwork structure used for pipe jacking working shaft construction according to an embodiment.

[0025] Figure 3 The present invention is a schematic diagram of a horizontal support of a formwork structure used for the construction of a jacking working shaft according to an embodiment.

[0026] Figure 4 The present invention is a schematic diagram of a jacking support of a formwork structure used for the construction of a jacking pipe working shaft according to an embodiment.

[0027] Figure 5 The present invention is an overall schematic diagram of a side formwork of a formwork structure used for the construction of a jacking working shaft according to an embodiment.

[0028] Figure 6 The present invention is a schematic diagram of a template portion and a transition portion plate of a formwork structure used for the construction of a jacking working shaft in an embodiment.

[0029] Description of the drawings: 1. Bracket mechanism; 11. Horizontal bracket; 111. Horizontal support tube; 112. Longitudinal support tube; 12. Vertical pole; 13. Top support; 131. Support part; 132. Adjusting screw; 133. Adjusting nut; 2. Side template; 21. Template part; 22. Adapter part; 23. Connecting boss; 24. Connecting groove. DETAILED DESCRIPTION

[0030] The following is combined with Figure 1-6 This application is described in further detail.

[0031] The embodiment of the present application discloses a formwork structure for the construction of a pipe jacking working shaft.

[0032] Reference Figure 1 A formwork structure for the construction of a jacking pipe working shaft comprises a support mechanism 1 and a side formwork 2 arranged in the circumferential direction of the support mechanism 1.

[0033] Reference Figure 1 and Figure 2 The support mechanism 1 includes a horizontal support 11, a vertical pole 12 and a top support 13. The vertical pole 12 is vertically arranged. A plurality of horizontal supports 11 are arranged along the height direction of the vertical pole 12. The vertical pole 12 is fixedly connected to the horizontal support 11; a plurality of top supports 13 are arranged at each end of the horizontal support 11, and the top supports 13 are abutted against the side formwork 2; the horizontal supports 11 can be two, three, or four, as long as multiple horizontal supports 11 can achieve stable support of the side formwork 2. In this embodiment, a horizontal support 11 is arranged.

[0034] Reference Figure 2 and Figure 3The horizontal support 11 includes a transverse support tube 111 and a longitudinal support tube 112, which are welded and fixed to each other. The transverse support tube 111 and the longitudinal support tube 112 are perpendicular to each other and are located in the same horizontal plane; the top support 13 is respectively inserted into the cavities at both ends of the transverse support tube 111 and the longitudinal support tube 112; a plurality of vertical poles 12 are connected to the transverse support tube 111 or the longitudinal support tube 112 through a rotating fastener. In this embodiment, a vertical pole 12 is respectively arranged at both ends of the transverse support tube 111 and the longitudinal support tube 112, thereby increasing the supporting stability of the vertical pole 12 on the horizontal support 11.

[0035] Reference Figure 1 and Figure 4 The top support 13 includes a support portion 131, an adjusting screw 132 and an adjusting nut 133; the support portion 131 is fixedly connected to one end of the adjusting screw 132, the adjusting nut 133 is threadedly connected to the adjusting screw 132, and the other end of the adjusting screw 132 is inserted into the end inner cavity of the transverse support tube 111 or the longitudinal support tube 112; the outer diameter of the adjusting nut 133 is larger than the inner diameter of the transverse support tube 111 or the longitudinal support tube 112, the adjusting nut 133 abuts against the end of the transverse support tube 111 or the longitudinal support tube 112, and the support portion 131 abuts against the inner wall of the side template 2.

[0036] Reference Figure 5 and Figure 6 The side formwork 2 includes a plurality of formwork parts 21 and transition parts 22 arranged at four corners, and the plurality of formwork parts 21 are connected to the four transition parts 22 in sequence end to end; the transition part 22 is "L"-shaped, and one side wall of the formwork part 21 and the transition part 22 in the length direction is integrally provided with a connecting boss 23, and the other side wall in the length direction is provided with a connecting groove 24, and the connecting boss 23 is sequentially engaged with the connecting groove 24 on another formwork part 21 or the transition part 22, and at the corner, the formwork part 21 is engaged and fixed with the transition part 22; in particular, for foundation pits of different specifications, it is only necessary to select the appropriate number of formwork parts 21 for splicing according to the length and width of the foundation pit.

[0037] The implementation principle of the formwork structure for the construction of a jacking working pit in the present embodiment is as follows: before the construction of the working pit, the operator first confirms the position of the foundation pit, and then excavates the foundation pit. After excavating to a certain depth, the operator ties the steel cage mesh at the bottom of the foundation pit, and then sets up the side formwork 2 on the inner side of the steel cage mesh. During the setting up, the connecting boss 23 of one formwork part 21 is engaged in the connecting groove 24 of another formwork part 21. At the corner, the adapter part 22 is engaged and connected with two adjacent adapter parts 22, and multiple formwork parts 21 and four adapter parts 22 are connected in sequence until a side formwork 2 connected end to end is formed; after the side formwork 2 is set up, the operator inserts the adjusting screw 132 of the jacking support 13 into the cavities at both ends of the transverse support tube 111 and the longitudinal support tube 112 respectively, and then places the horizontal support 11 at the bottom of the foundation pit, and rotates the adjusting nut 133 so that the support part 131 and the side formwork 2 are connected. The inner wall is pressed tightly, and the adjusting nut 133 is pressed tightly against the end of the horizontal support tube 111 or the longitudinal support tube 112. According to the same method, horizontal brackets 11 are set at different heights of the side formwork 2. Finally, multiple vertical poles 12 are vertically set at the bottom of the foundation pit. Multiple vertical poles 12 are respectively connected to the horizontal support tube 111 or the longitudinal support tube 112 through rotating fasteners. The vertical poles 12 realize the stable support of the horizontal bracket 11, thereby ensuring the support of the side formwork 2 by the horizontal bracket 11; after the bracket is erected, concrete is poured into the pouring cavity between the side formwork 2 and the side wall of the foundation pit. After the concrete is solidified and formed, the rotating fastener is removed, and the adjusting nut 133 is rotated to separate the support part 131 from the side formwork 2, and the horizontal bracket 11, the top support 13 and the vertical pole 12 are removed in turn, the formwork part 21 is separated from the adapter part 22, and the side formwork 2 is removed from the concrete to complete the pouring construction of the working well.

[0038] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A formwork structure for pipe jacking work pit construction, characterized in that: The invention comprises a support mechanism (1) and a side template (2); the support mechanism (1) comprises a horizontal support (11), a vertical rod (12) and a plurality of retractable top supports (13); the vertical rod (12) is detachably fixedly connected to the horizontal support (11); the end of the horizontal support (11) is connected to one end of the top support (13), and the top support (13) is in contact with the side template (2).

2. A formwork structure for pipe jacking work pit construction according to claim 1, characterized in that: The horizontal support (11) comprises a transverse support tube (111) and a longitudinal support tube (112), wherein the transverse support tube (111) and the longitudinal support tube (112) are welded and fixed, and the transverse support tube (111) and the longitudinal support tube (112) are perpendicular to each other; the jacking support (13) is inserted into the ends of the transverse support tube (111) and the longitudinal support tube (112).

3. A formwork structure for pipe jacking work pit construction according to claim 2, characterized in that: The vertical rod (12) is arranged vertically, the length direction of the vertical rod (12) is perpendicular to the plane where the horizontal support (11) is located, and the vertical rod (12) is fixedly connected to the transverse support tube (111) or the longitudinal support tube (112) via a rotating fastener.

4. A formwork structure for pipe jacking work pit construction according to claim 3, characterized in that: A plurality of the horizontal supports (11) are provided, and the plurality of the horizontal supports (11) are evenly distributed along the length direction of the vertical pole (12).

5. A formwork structure for pipe jacking work pit construction according to claim 2, characterized in that: The jacking support (13) comprises a supporting portion (131), an adjusting screw (132) and an adjusting nut (133); one end of the adjusting screw (132) is fixedly connected to the supporting portion (131) and fixedly inserted into the inner cavity of the end of the transverse supporting tube (111) or the longitudinal supporting tube (112); the adjusting nut (133) is threadedly connected to the adjusting screw (132), and the adjusting nut (133) abuts against the end of the transverse supporting tube (111) and the adjusting nut (133) abuts against the end of the longitudinal supporting tube (112); the end of the supporting portion (131) away from the adjusting screw (132) abuts against the side template (2).

6. A formwork structure for pipe jacking work pit construction according to claim 1, characterized in that: The side template (2) comprises a plurality of template parts (21) and transition parts (22) arranged at four corners of the working well; connecting bosses (23) and connecting grooves (24) are respectively arranged on two opposite side walls of the template parts (21) and the transition parts (22); the connecting grooves (24) and the connecting bosses (23) can be tightly engaged; the plurality of connecting bosses (23) located on the side template (2) are distributed along the circumferential direction of the side template (2).

Citation Information

Cited By

  • Turnover pipe jacking well supporting device and construction method thereof

    CN120487152A