Thermal generator set system
By introducing a second condenser and energy storage device into the thermal generator set system, the problem of degradation of cooling capacity of the condensation component is solved, the unit is fully launched and safely operated, and the system efficiency is improved through adjustment measures in different seasons and adapted to the new Peak shaving demand for energy generation.
Patent Information
- Application Number
- CN202420216311.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-29
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-01-29
AI Technical Summary
The cooling capacity of the thermal generator set system decreases under high temperatures and strong winds in summer, resulting in a back pressure higher than the design value, affecting the safety and economical operation of the unit. The aging of the turbine equipment leads to an increase in coal consumption rate and a decrease in the quality of condensate. It may even cause the unit to trip and shut down.
Design a thermal generator set system, by setting a second condenser and energy storage device on the exhaust pipe, using low-temperature storage components to exchange heat with the exhaust steam, sharing the back pressure of the first condenser, and achieving full emission. And flexibly adjusts through cooling devices and heating systems in different seasons to improve system efficiency.
It effectively reduces the back pressure of the condensation component, ensures the full operation of the unit, improves the operation safety and economy of the thermal generator set, reduces coal consumption, avoids the unit tripping and shutdown, and realizes the decoupling of the heating system from the thermoelectric in winter. Adapt to the peak-shaving needs of new energy power generation.
Smart Images

Figure CN221973607U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of thermal power generation, in particular to a thermal power generator set system. Background Art
[0002] Common thermal power generation unit systems will have a condensing assembly installed on the exhaust steam pipeline. The condensing assembly can be a direct air-cooled unit or an indirect air-cooled unit. In recent years, the cooling capacity of the air-cooled radiator has decreased due to high temperatures, strong winds, dust, and dirty and scaling of the air-cooled fins in summer, and the back pressure during actual unit operation is higher than the design value. At the same time, factors such as aging of turbine equipment and reduced efficiency increase the exhaust volume of the turbine, resulting in increased operating back pressure of the condensing assembly, limited output of the condensing assembly, increased coal consumption rate, reduced condensate quality, and reduced thermal economy of the power plant. In severe cases, the condensing assembly may even cause the unit to trip and shut down due to a jump in exhaust back pressure. In view of this, there is an urgent need for a way to solve at least one of the above technical problems. Utility Model Content
[0003] One purpose of the utility model is to provide a new technical solution for a thermal power generator system. By improving the thermal power generator system, the condensing unit can achieve full power generation, thereby solving at least one of the above technical problems.
[0004] In one aspect of the present application, a thermal power generation unit system is provided, comprising a first heat exchange circuit, an exhaust steam pipeline, and a first condenser and a second condenser connected to the exhaust steam pipeline, wherein the second condenser is located upstream of a position where the first condenser is connected to the exhaust steam pipeline, and the second condenser is also connected to the first heat exchange circuit, and the first heat exchange circuit is provided with an energy storage device, and the energy storage device comprises a low-temperature storage component and a high-temperature storage component;
[0005] When the second condenser is in operation, the low-temperature medium in the low-temperature storage component can be heated by heat exchange with the exhaust steam in the second condenser through the first heat exchange loop and then flow back to the high-temperature storage component.
[0006] In actual use, when the actual operating back pressure of the first condenser is higher than its designed back pressure, the second condenser is turned on to share the portion that exceeds the designed back pressure of the first condenser. When the second condenser is in operation, the low-temperature medium in the low-temperature storage component can be heated up by heat exchange with the exhaust steam in the second condenser through the first heat exchange circuit, and then refluxed to the high-temperature storage component. Thus, the low-temperature medium entering the second condenser through the low-temperature storage component exchanges heat with the exhaust steam in the second condenser, thereby condensing the exhaust steam. Thus, full operation of the first condenser can be achieved.
[0007] Other features and advantages of the present specification will become apparent from the following detailed description of exemplary embodiments of the present specification with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate embodiments of the specification and, together with the description, serve to explain the principles of the specification.
[0009] Figure 1 It is one of the thermal power generating set systems in the embodiment of the utility model;
[0010] Figure 2 It is the second thermal power generating set system in the embodiment of the utility model.
[0011] Description of reference numerals:
[0012] 101. first condenser; 102. second condenser; 200. exhaust steam pipeline; 201. exhaust steam sub-pipe section; 300. steam turbine unit; 400. energy storage device; 401. cold water area; 402. hot water area; 500. cooling device; 600. first heat exchange circuit; 601. first pipe section; 602. second pipe section; 701. first valve; 702. second valve; 703. third valve; 704. fourth valve; 705. fifth valve; 706. sixth valve; 800. heating system; 801. return water pipeline; 802. heating pipeline; 803. first station of heating network. DETAILED DESCRIPTION
[0013] In order to enable those skilled in the art to better understand the solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0014] like Figure 1 and Figure 2 As shown, the present application provides a thermal power generator system. The thermal power generator system includes a first heat exchange loop 600, an exhaust steam pipeline 200, and a first condenser 101 and a second condenser 102 connected to the exhaust steam pipeline 200, wherein the second condenser 102 is located upstream of the connection position between the first condenser 101 and the exhaust steam pipeline 200. The second condenser 102 is also connected to the first heat exchange loop 600, and the first heat exchange loop 600 is provided with an energy storage device 400, and the energy storage device 400 includes a low-temperature storage component and a high-temperature storage component.
[0015] When the second condenser (102) is in operation, the low-temperature medium in the low-temperature storage component can be heated by heat exchange with the exhaust steam in the second condenser 102 through the first heat exchange loop 600 and then flow back to the high-temperature storage component.
[0016] Specifically, the exhaust steam pipeline 200 includes at least one exhaust steam sub-pipe section 201, and the position where the exhaust steam sub-pipe section 201 connects with the exhaust steam pipeline 200 is located upstream of the position where the first condenser 101 connects with the exhaust steam pipeline 200. The exhaust steam sub-pipe section 201 is connected to the second condenser 102 to condense the exhaust steam.
[0017] In this way, a part of the exhaust steam entering the first condenser 101 can be shared through the exhaust steam sub-pipe section 201. The first condenser 101 includes a direct air cooling unit device or an indirect air cooling unit device. The second condenser 102 can be a high back pressure condenser, or of course, a non-high back pressure condenser, and those skilled in the art can choose by themselves.
[0018] In actual use, when the actual operating back pressure of the first condenser 101 is higher than its designed back pressure, the entire power generation system will be forced to reduce the load, the power generation efficiency of the unit will be reduced, the coal consumption rate will increase, and the quality of condensate will also be reduced. Especially when the unit is performing deep peak regulation, the first condenser 101 will trip and shut down due to the jump of the exhaust steam in the exhaust steam pipeline 200. In order to avoid the above problems, when the actual operating back pressure of the first condenser 101 is higher than its designed back pressure, the second condenser 102 is turned on to share the part that exceeds the designed back pressure of the first condenser 101. Thereby achieving full power generation of the first condenser 101.
[0019] Part of the second condenser 102 is connected to the exhaust steam sub-segment 201, and part of it is connected to the first heat exchange loop 600. The heat exchange medium of the first heat exchange loop 600 exchanges heat with the exhaust steam in the exhaust steam sub-segment 201 through the second condenser 102. The first heat exchange loop 600 is provided with an energy storage device 400. The energy storage device 400 is, for example, a water energy storage device. The low-temperature storage component and the high-temperature storage component included in the energy storage device 400 are respectively the cold water area 401 and the hot water area 402 of the water energy storage device. Specifically, the water energy storage device separates the cold water area 401 and the hot water area 402 by a transition layer. Due to the different temperatures and densities of water, the hot water area 402 is located on the upper side of the cold water area 401. When the amount of hot water in the hot water area 402 increases, the transition layer moves down, and the cold water in the cold water area 401 is discharged. When the amount of cold water in the cold water area 401 increases, the transition layer moves up, and the hot water in the hot water area 402 is discharged. In this way, the energy storage device 400 can realize a heat storage-heat release cycle, or a cold storage-cooling release cycle.
[0020] The energy storage device 400 includes a first working condition. In the first working condition, the cold water area 401 is connected to the inlet end of the second condenser 102, and the hot water area 402 is connected to the outlet end of the second condenser 102. The cold water area 401 exchanges heat with the exhaust steam in the exhaust steam sub-pipe section 201 through the second condenser 102. In the first working condition, the cold water area 401 cools down, while the hot water area 402 stores heat.
[0021] That is, when the second condenser 102 is in operation, the energy storage device 400 is in the first operating state. Thus, the low temperature medium cold water entering the second condenser 102 through the cold water area 401 exchanges heat with the exhaust steam in the second condenser 102, thereby condensing the exhaust steam.
[0022] Embodiment 1
[0023] Taking the first condenser 101 as an example of a direct air cooling system, the cooling capacity of the air cooling radiator is reduced due to high temperatures, strong winds, dust, dirt and scaling of the air cooling fins in summer, and the back pressure during actual unit operation is higher than the design value. The number of non-full-load hours of the unit increases significantly during summer operation, forcing the unit to operate at a reduced load.
[0024] In order to solve this problem, in the summer, the air-cooling system radiator surface is forced to use water spraying to cool down, which causes a certain degree of scaling on the air-cooling radiator surface, thereby reducing the radiator's heat exchange capacity. If this continues for a long time, it will produce a vicious cycle, increase the unit's coal consumption, and significantly reduce economic benefits.
[0025] In this way, when thermal power generating units are operated during the high temperature period in summer, the full load capacity of thermal power generating units is greatly restricted, which seriously affects the safety and economy of thermal power generating units. Especially in areas where direct air cooling systems are concentrated, it will directly affect the safety of power grid operation.
[0026] To this end, in this embodiment, the thermal power generator system further includes a cooling device 500. The cooling device 500 is connected between the low temperature storage component and the high temperature storage component, and the high temperature medium from the high temperature storage component is cooled in the cooling device and then flows back to the low temperature storage component.
[0027] The energy storage device 400 includes a second operating condition. When the second condenser 102 is in a non-operating state, the energy storage device 400 can be in the second operating condition. The second operating condition can be selectively applied to the first specific season described below.
[0028] like Figure 1As shown, in the second working condition, the cold water area 401 is connected to the outlet end of the cooling device 500, and the hot water area 402 is connected to the inlet end of the cooling device 500. Thus, the cold water cooled by the cooling device 500 can be stored in the cold water area 401. The cooling device 500 can be an electric cooling device, such as a cooling tower, or a physical cooling device, such as an underground cooling device. Those skilled in the art can make their own choices.
[0029] In a specific implementation of this embodiment, the first heat exchange loop 600 includes a first pipe section 601 and a second pipe section 602, the first pipe section 601 is connected to the cold water zone 401 and the inlet end of the second condenser 102, and the second pipe section 602 is connected to the outlet end of the hot water zone 402 and the second condenser 102. The first pipe section 601 is provided with a first valve 701 and a second valve 702, and compared with the first valve 701, the second valve 702 is closer to the cold water zone 401. The second pipe section 602 is provided with a third valve 703 and a fourth valve 704, and compared with the fourth valve 704, the third valve 703 is closer to the hot water zone 402. The inlet end of the cooling device 500 is connected between the third valve 703 and the fourth valve 704 through a water inlet pipeline, and the water inlet pipeline is provided with a fifth valve 705. The outlet end of the cooling device 500 is connected between the first valve 701 and the second valve 702 through a drainage pipeline, and the drainage pipeline is provided with a sixth valve 706. The energy storage device 400 is switched between the first working condition and the second working condition by opening and closing the valve.
[0030] In this embodiment, after the cryogenic medium stored in the energy storage device 400 is used up, the energy storage device 400 is disconnected from the second condenser 102. The cooling device 500 is connected to the second condenser 102 via the first heat exchange loop 600. Thus, the cooling device 500 can cool the exhaust steam in the second condenser 102. The cold zone device 500 is, for example, a peak cooling tower. In this way, the cooling device 500 of the present application can play two functions.
[0031] Embodiment 2
[0032] In this embodiment, the exhaust steam of the steam turbine of a conventional thermal power generating unit has a huge heat loss, and a large amount of preheating of the exhaust steam is dissipated into the atmosphere.
[0033] In this embodiment, if Figure 2 As shown, the thermal power generating set system also includes a heating system 800, which is applied in the second specific season described below. The heating system 800 includes a return water pipeline 801 and a heating pipeline 802 respectively connected to a heating network first station 803. The low-temperature medium from the return water pipeline 801 is heated through the heating network first station 803 and discharged from the heating pipeline 802.
[0034] Both the high-temperature storage component and the low-temperature storage component can be connected to the return water pipeline 801. Compared with the low-temperature storage component, the high-temperature storage component is connected to a position closer to the first station 803 of the heating network.
[0035] like Figure 2 As shown, the energy storage device 400 also includes a third operating condition. In the third operating condition, the hot water area 402 and the cold water area 401 of the water energy storage device are both connected to the return pipe 801, and the position where the cold water area 401 is connected to the return pipe 801 is located downstream of the position where the cold water area 401 is connected to the return pipe 801.
[0036] In actual use, when the second condenser 102 is in operation, the heat of the exhaust steam is stored in the hot water area 402 through the water medium in the first heat exchange loop 600. That is, the amount of hot water in the hot water area 402 increases.
[0037] When the second condenser 102 is not working, the first condenser 101 may condense the exhaust steam, and the hot water stored in the hot water area 402 may be discharged to the return water pipeline 801 to increase the temperature of the water downstream of the return water pipeline 801. At this time, the cold water located upstream of the return water pipeline 801 will be replenished to the cold water area 401.
[0038] Embodiment 3
[0039] In this embodiment, the difference from the second embodiment is that when the high-temperature storage component is disconnected from the return water pipeline 801, it can still be connected to the heating pipeline 802.
[0040] like Figure 1 As shown, in the second specific season, the energy storage device 400 also includes a fourth operating condition, in which the hot water area 402 of the water energy storage device can also be connected to the heating pipeline 802. The hot water in the heating pipeline 802 can be stored in the hot water area 402, and the cold water area 401 can be connected to the return water pipeline 801 to discharge the cold water in the cold water area 401 to the return water pipeline 801. In this way, the hot water in the heating pipeline 802 can be stored in the hot water area 402. When the temperature of the water in the heating pipeline 802 is too high, part of the hot water can be stored in the hot water area 402. The cold water in the heating circuit is supplemented to the cold water area 401. In this way, the temperature of the heating system 800 can be quickly adjusted. It can meet the needs of flexible peak regulation.
[0041] As another implementation of this embodiment, the thermal power generating unit system further includes a heating system 800, and the heating system 800 includes a return water pipeline 801 and a heating pipeline 802 respectively connected to the heating network first station 803. The high temperature storage component can be selectively connected to one of the heating pipeline 802 and the return water pipeline 801, and the low temperature storage component is connected to the return water pipeline 801. When the high temperature storage component is connected to the return water pipeline 801, the position where the low temperature storage component is connected to the return water pipeline 801 is located downstream of the position where the high temperature storage component is connected to the return water pipeline 801.
[0042] Embodiment 4
[0043] The present application also provides a control method for a thermal power generator system, which is used for the thermal power generator system described above. The control method includes: when the second condenser 102 is in working state, the first heat exchange loop 600 is connected with the second condenser 102, and the low-temperature medium in the low-temperature storage component can be heated by heat exchange with the exhaust steam in the second condenser 102 through the first heat exchange loop 600, and then flow back to the high-temperature storage component.
[0044] In another embodiment, the control method further comprises:
[0045] When the second condenser 102 is in a non-operating state, the second condenser is disconnected from the first heat exchange loop 600, and the cooling device 500 is connected between the low-temperature storage component and the high-temperature storage component.
[0046] Specifically, the thermal power generator system includes a peak operating condition in a first specific season and a valley operating condition in a first specific season. In the peak operating condition in the first specific season, the second condenser 102 is controlled to be in a working state, and the first heat exchange loop 600 is controlled to be connected with the second condenser 102. The low-temperature medium in the low-temperature storage component can be heated by heat exchange with the exhaust steam in the second condenser 102 through the first heat exchange loop 600 and then flow back to the high-temperature storage component.
[0047] During the off-peak operating condition of the first specific season, the second condenser 102 is controlled to be in a non-operating state, the second condenser 102 is controlled to be disconnected from the first heat exchange loop 600, and the cooling device 500 is controlled to be connected between the low-temperature storage component and the high-temperature storage component.
[0048] Among them, the ambient temperature in the first specific season is relatively high, and relatively high means that the full-power and non-full-power states of the first condenser 101 will be affected by the high ambient temperature. For example, the first specific season is summer. Of course, it can also be part of the time when the ambient temperature is relatively high, such as autumn or spring. Peak operating conditions refer to the operating conditions when the generator set is in high-load power generation operation. Valley operating conditions refer to the operating conditions when the generator set is in low-load power generation operation.
[0049] During the time period with the highest temperature in a day, the first condenser 101 is affected by the ambient temperature and cannot operate at full capacity. In order to avoid the negative impact of the first condenser 101 not operating at full capacity on the entire power generation system. Turn on the second condenser 102, and use the energy storage device 400 to perform heat exchange with the second condenser 102 during valley power generation conditions with the cold water stored in the cold water area 401. In this way, the cost of the second condenser 102 can be reduced, and the operating efficiency of the power plant can be significantly improved. Of course, those skilled in the art can also select the operating conditions of the second condenser 102 according to actual needs.
[0050] Specifically, when the actual back pressure of the first condenser 101 exceeds the preset back pressure under peak conditions, the second condenser 102 is turned on and connected to the energy storage device 400. The second condenser 102 is in working condition, and the energy storage device 400 is controlled to switch to the aforementioned first working condition. That is, the cold water zone 401 is controlled to be connected to the inlet end of the second condenser 102, and the hot water zone 402 is controlled to be connected to the outlet end of the second condenser 102. In this way, the cold water in the cold water zone 401 enters the second condenser 102 and exchanges heat with the exhaust steam in the second condenser 102. After the water temperature rises, it flows back to the hot water zone 402 through the outlet end of the second condenser 102. The cold water stored in advance in the energy storage device 400 is used to cool the exhaust steam in the second condenser 102. In this way, there is no need to use a large amount of high-priced electricity to cool the cold water in the second condenser 102 that exchanges heat with the exhaust steam at peak times.
[0051] Of course, if the second condenser 102 still needs to operate after the cold water in the cold water zone 401 is used up under peak operating conditions, the inlet end of the electric cooling device 500 can be connected to the outlet end of the second condenser 102, and the outlet end of the electric cooling device 500 can be connected to the inlet end of the second condenser 102. When the electric cooling device 500 is connected to the second condenser 102, the electric cooling device 500 is disconnected from the energy storage device 400. As a result, the exhaust steam in the second condenser 102 is directly cooled by the cooling device 500. Even in such a case, the participation of the energy storage device 400 can shorten the operating time of the electric cooling device 500, thereby reducing the operating cost of the second condenser 102.
[0052] The valley period operating condition of the first specific season is usually the summer nights or the time of the day when the temperature is relatively low. During this period, the first condenser 101 is in a full power state. The second condenser 102 is in a non-operating state, and the energy storage device 400 is controlled to switch to the second operating condition. That is, the cold water area 401 is controlled to be connected to the outlet end of the cooling device 500, and the hot water area 402 is connected to the inlet end of the cooling device 500. The cooling device 500 can be a cooling tower or other cooling device 500. The operation of the cooling device 500 requires electricity. Due to the low electricity price under the valley power generation condition, the low electricity price can be used to cool the hot water in the hot water area 402 and store it in the cold water area 401.
[0053] In another specific embodiment, the control method comprises:
[0054] The thermal power generator system includes a peak operating condition in the second specific season and a valley operating condition in the second specific season. In the peak operating condition in the second specific season, both the high-temperature storage component and the low-temperature storage component are controlled to be connected to the return pipe 801. Compared with the low-temperature storage component, the high-temperature storage component is connected to a position closer to the first station 803 of the heating network.
[0055] In the off-peak period of the second specific season, the second condenser 102 is controlled to be in working state. The second specific season refers to a season with low ambient temperature, and low temperature refers to the operating condition in which the heating system 800 of the thermal power generator system needs to start operating. For example, in winter in the north, a thermal power plant needs to use the heating system 800 to heat residents. Of course, it can also be a period when other heating systems 800 need to work.
[0056] In the valley condition of the second specific season, the heat of the heating system 800 is sufficient. The high temperature storage component is controlled to be disconnected from the return water pipeline 801, the high temperature storage component is controlled to be connected to the heating pipeline 802, and the low temperature storage component is controlled to be connected to the return water pipeline 801. The hot water area 402 of the water energy storage device can also be connected to the heating pipeline 802. The hot water in the heating pipeline 802 can be stored in the hot water area 402, and the cold water area 401 can be connected to the return water pipeline 801 to discharge the cold water in the cold water area 401 to the return water pipeline 801. In this way, the hot water in the heating pipeline 802 can be stored in the hot water area 402. When the temperature of the water in the heating pipeline 802 is too high, part of the hot water can be stored in the hot water area 402. The cold water in the heating circuit is supplemented to the cold water area 401. In this way, the temperature of the heating system 800 can be quickly adjusted. It can meet the needs of flexible peak regulation.
[0057] During the peak operating conditions of the second specific season, the heat energy of the heating system 800 is insufficient. At this time, the second condenser 102 is switched to a closed state, and the hot water stored in the hot water area 402 is discharged to the downstream of the return water pipeline 801 to increase the temperature of the water downstream of the return water pipeline 801. This makes up for the lack of heat energy in the heating system 800. In this way, the traditional heating system 800 can be decoupled from the condensing system, avoiding the operation of the heating system 800 being restricted by the heat-to-electricity method, not only utilizing the heat energy of the exhaust steam of the steam turbine unit 300, but also meeting the needs of flexible peak regulation.
[0058] By adopting the implementation mode of the present application, not only can the first condenser 101 be fully powered in summer, but also thermal and electric decoupling can be achieved during the winter heating period, so that the heating system 800 can achieve the deep peak-shaving capability of the thermal power generator system, thereby also being able to achieve a large-scale absorption of new energy power generation.
[0059] In the above technical solution, peak operating conditions and valley operating conditions refer to the peak and valley periods of thermal power generating units. Due to the rapid development of renewable energy power generation, the proportion of renewable energy power generation in China is increasing. For renewable energy power generation, especially wind power and solar power generation, due to its seasonality, intermittency and other shortcomings, it is bound to have an impact on the stable operation of the power grid. When the proportion of renewable energy in the power grid gradually increases, the demand for peak power supply of generator sets also gradually increases. This leads to the need for flexible peaking of thermal power generating units to absorb the growing share of wind power and solar power generation.
[0060] However, in the process of peak load regulation, the heat loss of exhaust steam is huge. Not only does it cause a huge waste of energy, but it also increases coal consumption. Through the method of this application, in winter, not only can the decoupling of the heating system 800 and the thermal power generating unit be achieved, but also the waste of heat of exhaust steam can be avoided by the cooperation between the energy storage device 400 and the thermal system 800.
[0061] This article uses specific examples to illustrate the principles and implementation methods of the utility model. The above examples are only used to help understand the method and core ideas of the utility model. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the utility model, the utility model can also be improved and modified, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
Claims
1. A thermal power generating set system, characterized in that: The invention comprises a first heat exchange circuit (600), an exhaust steam pipeline (200), and a first condenser (101) and a second condenser (102) connected to the exhaust steam pipeline (200), wherein the second condenser (102) is located upstream of a position where the first condenser (101) is connected to the exhaust steam pipeline (200), and the second condenser (102) is also connected to the first heat exchange circuit (600). The first heat exchange circuit (600) is provided with an energy storage device (400), and the energy storage device (400) comprises a low-temperature storage component and a high-temperature storage component. When the second condenser (102) is in operation, the low-temperature medium in the low-temperature storage component can be heated by heat exchange with the exhaust steam in the second condenser (102) through the first heat exchange circuit (600) and then flow back to the high-temperature storage component.
2. The thermal power generating set system according to claim 1, characterized in that: The device also includes a cooling device (500), wherein the cooling device (500) is connected between the low-temperature storage component and the high-temperature storage component, and the high-temperature medium from the high-temperature storage component is cooled in the cooling device and then flows back to the low-temperature storage component.
3. The thermal power generating set system according to claim 2, characterized in that: The energy storage device (400) is disconnected from the second condenser (102), and the cooling device (500) is connected to the second condenser (102) via the first heat exchange circuit (600).
4. The thermal power generating set system according to claim 1, characterized in that: The system also includes a heating system (800), wherein the heating system (800) includes a return pipe (801) and a heating pipe (802) respectively connected to a heating network head station (803), and a low-temperature medium from the return pipe (801) is heated through the heating network head station (803) and discharged from the heating pipe (802); Both the high temperature storage component and the low temperature storage component can be connected to the return water pipeline (801). Compared with the low temperature storage component, the high temperature storage component is connected to a position closer to the heating network head station (803).
5. The thermal power generating set system according to claim 4, characterized in that: When the high-temperature storage component is disconnected from the return water pipeline (801), it can still be connected to the heat supply pipeline (802).
6. The thermal power generating set system according to claim 5, characterized in that: The thermal power generating set system further comprises a heating system (800), wherein the heating system (800) comprises a return water pipeline (801) and a heating pipeline (802) respectively connected to a heating network head station (803); The high-temperature storage component can be selectively connected to one of the heat supply pipeline (802) and the return water pipeline (801), and the low-temperature storage component is connected to the return water pipeline (801); When the high-temperature storage component is connected to the return water pipeline (801), the position where the low-temperature storage component is connected to the return water pipeline (801) is located downstream of the position where the high-temperature storage component is connected to the return water pipeline (801).
7. The thermal power generating set system according to any one of claims 1 to 6, characterized in that: The second condenser (102) is a high back pressure condenser.
8. The thermal power generating set system according to claim 2 or 3, characterized in that: The cooling device (500) is an electric cooling device.
Citation Information
Cited By
Thermal generator set system and control method thereof
CN118257642A