Emergency sewage treatment lifting tank
By using submersible sewage pumps and reamers in emergency sewage treatment lifting tanks to combine debris and combine automatic control systems with guide rods, slug plates and floating plates, the problem of garbage blocking water pumps in sewage is solved, and sewage treatment is realized Efficient automation and prevent impurities from influx.
Patent Information
- Application Number
- CN202420558799.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-03-21
AI Technical Summary
During the sewage lifting process of existing emergency sewage treatment lifting tanks, solid debris such as garbage in the sewage can easily block the water pump, affecting the efficiency of sewage treatment operations.
An emergency sewage treatment lifting tank was designed, using a combination of submersible sewage pump and reamer. The reamer crushes the debris entering the pump to avoid blockage. At the same time, it achieves rapid connection through the guide rod and the clamping plate, and the floating plate automatically controls submersible sewage. When the pump is started, the ball valve closes the diversion pipe when the submersible sewage pump is not started to prevent impurities from pouring in.
Effectively prevent water pumps from being blocked, ensure smooth operation of submersible sewage pumps, realize automated control, improve sewage treatment efficiency, and avoid impurities influx.
Smart Images

Figure CN222019665U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sewage treatment, in particular to an emergency sewage treatment lifting tank. Background Art
[0002] In the event of an outbreak, a large number of isolation points and shelter hospitals need to be built to accommodate infected people. According to the local standards of each province and the relevant national standards and specifications, the drainage from isolation points and shelter hospitals must be biochemically treated to meet the discharge standards before it can be discharged into the municipal sewage pipeline. Therefore, an emergency sewage treatment station is set up at the final water use point of each project site, and the sewage is discharged into the municipal sewage network after treatment meets the standards.
[0003] At present, the emergency sewage treatment station is composed of sewage pipelines, septic tanks, disinfection tanks, regulating tanks and drainage pipelines. In order to speed up the construction period and reduce the buried depth of the sewage treatment station, a front lifting tank will be installed at the end of the sewage pipeline to lift the sewage. In the existing technology, a water pump is generally installed inside the lifting tank to lift the sewage. However, when the water pump is operating, solid debris such as garbage in the sewage can easily enter the water pump flow channel and block the water pump, affecting the sewage lifting operation.
[0004] Therefore, there is an urgent need to provide an emergency sewage treatment lifting tank that can prevent water pump clogging when sewage is lifted. Utility Model Content
[0005] In order to overcome the disadvantage that when the existing lifting tank is equipped with a water pump to lift sewage, solid debris such as garbage in the sewage is easy to block the water pump after entering the water pump flow channel, thereby affecting the sewage lifting operation, the utility model provides an emergency sewage treatment lifting tank which can prevent the water pump from being blocked when sewage is lifted.
[0006] In order to solve the above problems, the utility model adopts the following technical solutions: an emergency sewage treatment lifting tank, comprising a supporting base, a collection tank body is installed on the supporting base, a cover plate symmetrically distributed is hinged on the collection tank body, a protective shell is arranged on the supporting base, the collection tank body is located in the protective shell, a feed pipe is connected and communicated with the collection tank body, the end of the feed pipe passes through the protective shell and extends outward to communicate with the end of the sewage pipeline, a submersible sewage pump is installed in the collection tank body, a guide pipe is installed on the submersible sewage pump, a discharge pipe is arranged on the collection tank body, one end of the discharge pipe passes through the protective shell and extends outward to communicate with the septic tank, the other end of the discharge pipe is connected and communicated with the guide pipe, a motor is installed in the submersible sewage pump, and a reamer is arranged on the output shaft of the motor.
[0007] More preferably, the aggregate tank body is made of glass fiber reinforced plastics.
[0008] More preferably, a guide rod is fixedly connected to the feed pipe, and a symmetrically distributed clamping plate is rotatably provided on the guide rod, and a first torsion spring is sleeved on the clamping plate.
[0009] More preferably, a control center is provided outside the discharge pipe, a floating plate is slidably provided inside the collecting tank, a trigger button is provided on the control center through a mounting seat, and a trigger plate is provided on a side of the motor close to the control center.
[0010] More preferably, a plurality of foam boards are embedded in the floating board.
[0011] More preferably, a push rod is provided on the floating plate, a ball valve is provided in the guide tube, a connecting rod is fixedly connected to the ball valve, one end of the connecting rod passes through the guide tube and the aggregate tank body and contacts the push rod, and a second torsion spring is sleeved on the connecting rod.
[0012] More preferably, the feed pipe end cover is provided with a protective shell.
[0013] More preferably, the symmetrically distributed cover plates are commonly provided with latches.
[0014] Compared with the prior art, the utility model has the following technical effects: 1. Through the setting of the motor and the reamer in the submersible sewage pump, the debris in the sewage is chopped by the reamer when entering the flow channel of the submersible sewage pump, which has a certain anti-clogging performance and compresses the sewage at the same time, so that the submersible sewage pump has a larger displacement, ensuring the smooth operation of the submersible sewage pump throughout the whole process.
[0015] 2. By setting the guide rod and the clamping plate instead of the bolt, when the sewage pipe and the feed pipe are connected, the clamping plate will clamp the pipe, so as to realize the quick connection between the sewage pipe and the feed pipe and facilitate the subsequent disassembly.
[0016] 3. The floating plate rises and falls with the sewage level in the aggregate tank. When the sewage in the aggregate tank reaches the start-up water level of the submersible sewage pump, the trigger plate contacts the trigger button on the control center to start the submersible sewage pump, thereby realizing automatic operation of the submersible sewage pump.
[0017] 4. The ball valve can be set to close the diversion pipe when the submersible sewage pump is not started to prevent the influx of sewage and impurities. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a three-dimensional structural schematic diagram of the utility model.
[0019] Figure 2 It is a three-dimensional cross-sectional structural schematic diagram of the support base, aggregate tank body and cover plate of the utility model.
[0020] Figure 3The utility model is a three-dimensional cross-sectional structural schematic diagram of a submersible sewage pump, a motor and a reamer.
[0021] Figure 4 It is a three-dimensional cross-sectional structural schematic diagram of the guide rod, the clamping plate and the first torsion spring of the utility model.
[0022] Figure 5 It is a three-dimensional cross-sectional structural schematic diagram of the material collecting tank body, the guide pipe and the discharge pipe of the utility model.
[0023] Figure 6 It is a three-dimensional cross-sectional structural schematic diagram of the control center, the mounting seat and the trigger plate of the utility model.
[0024] Figure 7 It is a three-dimensional cross-sectional structural schematic diagram of the aggregate tank body, connecting rod and ball valve of the utility model.
[0025] Figure 8 For this utility model Figure 7 Enlarged view of point A in the middle.
[0026] The meanings of the reference numerals in the figure are: 1. Support base, 2. Aggregate tank body, 3. Cover plate, 4. Protective shell, 5. Feed pipe, 6. Submersible sewage pump, 7. Motor, 8. Reamer, 9. Guide pipe, 10. Discharge pipe, 1001. Control center, 11. Float plate, 12. Guide rod, 13. Card plate, 14. First torsion spring, 15. Mounting seat, 16. Trigger button, 17. Trigger plate, 18. Push rod, 19. Connecting rod, 20. Ball valve, 21. Second torsion spring, 22. Protective shell, 23. Latch. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] Example 1
[0029] See also Figure 1 , Figure 2 , Figure 3 and Figure 5, an emergency sewage treatment lifting tank, comprising a support base 1, a collection tank body 2 is installed on the top of the support base 1, the collection tank body 2 is made of glass fiber reinforced plastic, has the characteristics of light weight and high strength, and reduces the production cost, the top of the collection tank body 2 is hinged with two cover plates 3 that are symmetrically distributed on the left and right, and the two cover plates 3 are jointly provided with a latch 23, and the latch 23 is used to fix the two cover plates 3, and a protective shell 4 is provided on the top of the support base 1, the collection tank body 2 is located in the protective shell 4, and the lower front side of the collection tank body 2 is connected and communicated with a feed pipe 5, the end of the feed pipe 5 passes through the protective shell 4 and extends outward to be communicated with the end of the sewage pipeline, and the end of the feed pipe 5 is sleeved with There is a protective shell 22. Before the feed pipe 5 is connected to the sewage pipeline, the protective shell 22 can be used to seal the feed pipe 5 to prevent foreign matter from entering. Two submersible sewage pumps 6 are installed in the aggregate tank body 2. A guide pipe 9 is installed on the submersible sewage pump 6. A discharge pipe 10 is arranged on the upper rear side of the aggregate tank body 2. The rear end of the discharge pipe 10 passes through the protective shell 4 and extends outward to communicate with the septic tank. The front end of the discharge pipe 10 is connected and communicated with the guide pipe 9. A motor 7 is installed at the water inlet of the submersible sewage pump 6. A reamer 8 is arranged on the output shaft of the motor 7. The reamer 8 is driven by the motor 7 to rotate to crush the debris entering the water inlet of the submersible sewage pump 6, thereby preventing blockage.
[0030] In sewage treatment, sewage in the sewage pipeline enters the aggregate tank 2 from the feed pipe 5, is started by the motor 7 and the submersible sewage pump 6, and the submersible sewage pump 6 draws the sewage upward into the guide pipe 9 and then discharges it into the septic tank through the discharge pipe 10, thereby achieving sewage lifting. While the sewage is being pumped into the submersible sewage pump 6, the motor 7 drives the reamer 8 to rotate, so that the debris in the sewage is crushed when entering the flow channel of the submersible sewage pump 6, and at the same time, the sewage is compressed, so that the submersible sewage pump 6 has a larger displacement and has a certain anti-clogging performance, thereby ensuring that the submersible sewage pump 6 runs smoothly throughout the entire process.
[0031] Example 2
[0032] Based on Example 1, please refer to Figure 2 and Figure 4 The front end of the feed pipe 5 is fixedly connected with four uniformly distributed guide rods 12 along the circumferential direction. The guide rods 12 are rotatably provided with card plates 13 that are symmetrically distributed on the left and right. When the feed pipe 5 is connected to the sewage pipeline, the guide rods 12 and the card plates 13 cooperate to replace bolts to achieve quick connection. The upper and lower parts of the card plates 13 are both sleeved with first torsion springs 14, and the two ends of the first torsion spring 14 are respectively connected to the card plates 13 and the guide rods 12.
[0033] By docking the sewage pipe with the feed pipe 5, the guide rod 12 passes through the mounting hole reserved on the sewage pipe, the clamping plate 13 is rotated and closed, and the first torsion spring 14 is deformed. When the sewage pipe moves to the rear of the clamping plate 13, the clamping plate 13 is reset and expanded under the elastic force of the first torsion spring 14 to clamp the pipe, without the need for bolts, to achieve quick connection.
[0034] See also Figure 6 A control center 1001 is arranged outside the discharge pipe 10, and a floating plate 11 is slidingly arranged inside the aggregate tank body 2. The floating plate 11 can rise and fall with the water level in the aggregate tank body 2. Four foam plates are embedded in the floating plate 11. The foam plates are used to increase the buoyancy of the floating plate 11. A trigger button 16 is arranged on the control center 1001 through a mounting seat 15. A trigger plate 17 is arranged on a side of the motor 7 close to the control center 1001, so that the trigger plate 17 can contact the trigger button 16, so that the control center 1001 can start the submersible sewage pump 6.
[0035] After the sewage enters the aggregate tank 2, the float 11 rises with the water level. When the float 11 moves up and the trigger plate 17 contacts the trigger button 16, it means that the sewage in the aggregate tank 2 has reached the start water level of the submersible sewage pump 6. At this time, the control center 1001 controls the submersible sewage pump 6 to start. As the sewage inside the aggregate tank 2 decreases or the sewage stops entering, the float 11 drops accordingly, and the trigger plate 17 disengages from the trigger button 16. The control center 1001 shuts down the submersible sewage pump 6, realizing automatic operation of the submersible sewage pump 6 without the need for personnel supervision.
[0036] See also Figure 7 and Figure 8 A push rod 18 is provided on the top of the floating plate 11, and a ball valve 20 is provided inside the middle and lower section of the guide tube 9. Initially, the ball valve 20 is in a closed state, and a connecting rod 19 is fixedly connected to the ball valve 20. The rear end of the connecting rod 19 passes through the guide tube 9 and the aggregate tank body 2 and contacts the push rod 18. The push rod 18 moves downward to squeeze the connecting rod 19 and rotate to open the ball valve 20. A second torsion spring 21 is sleeved on the rear end of the connecting rod 19, and the two ends of the second torsion spring 21 are respectively connected to the aggregate tank body 2 and the connecting rod 19.
[0037] Initially, when the submersible sewage pump 6 is not started, the ball valve 20 is in a closed state to prevent sewage and impurities from flowing into the guide pipe 9. When the float plate 11 rises, the float plate 11 drives the push rod 18 to move upward, so that the push rod 18 pushes the connecting rod 19, and the connecting rod 19 drives the ball valve 20 to rotate to open the guide pipe 9. The second torsion spring 21 is deformed, and as the submersible sewage pump 6 is subsequently controlled to start, the guide pipe 9 is completely opened.
[0038] The above description is only an example of the implementation of the present invention and is not intended to limit the present invention. Any equivalent replacement made within the principle of the present invention shall be included in the protection scope of the present invention. The contents not elaborated in the present invention belong to the existing technology known to the technicians in this professional field.
Claims
1. An emergency sewage treatment lifting tank, comprising a support base (1), a collection tank body (2) is installed on the support base (1), a cover plate (3) symmetrically distributed is hinged on the collection tank body (2), a protective shell (4) is arranged on the support base (1), the collection tank body (2) is located in the protective shell (4), a feed pipe (5) is connected and communicated with the collection tank body (2), the end of the feed pipe (5) passes through the protective shell (4) and extends outward to communicate with the end of the sewage pipeline, a submersible sewage pump (6) is installed in the collection tank body (2), a guide pipe (9) is installed on the submersible sewage pump (6), a discharge pipe (10) is arranged on the collection tank body (2), one end of the discharge pipe (10) passes through the protective shell (4) and extends outward to communicate with the septic tank, and the other end of the discharge pipe (10) is connected and communicated with the guide pipe (9), wherein: A motor (7) is installed in the submersible sewage pump (6), and a reamer (8) is arranged on the output shaft of the motor (7).
2. The emergency sewage treatment lifting tank according to claim 1, characterized in that: The aggregate tank body (2) is made of glass fiber reinforced plastic.
3. The emergency sewage treatment lifting tank according to claim 1, characterized in that: The feed pipe (5) is fixedly connected with a guide rod (12), and a symmetrically distributed clamping plate (13) is rotatably arranged on the guide rod (12), and a first torsion spring (14) is sleeved on the clamping plate (13).
4. The emergency sewage treatment lifting tank according to claim 1, characterized in that: A control center (1001) is arranged outside the discharge pipe (10), a floating plate (11) is slidably arranged inside the collecting tank body (2), a trigger button (16) is arranged on the control center (1001) via a mounting seat (15), and a trigger plate (17) is arranged on a side of the motor (7) close to the control center (1001).
5. The emergency sewage treatment lifting tank as claimed in claim 4 is characterized in that: A plurality of foam boards are embedded in the floating plate (11).
6. The emergency sewage treatment lifting tank as claimed in claim 4, characterized in that: A push rod (18) is arranged on the floating plate (11), a ball valve (20) is arranged in the guide tube (9), a connecting rod (19) is fixedly connected to the ball valve (20), one end of the connecting rod (19) passes through the guide tube (9) and the collecting tank body (2) and contacts the push rod (18), and a second torsion spring (21) is sleeved on the connecting rod (19).
7. The emergency sewage treatment lifting tank according to claim 1, characterized in that: The end of the feed pipe (5) is covered with a protective shell (22).
8. The emergency sewage treatment lifting tank according to claim 1, characterized in that: The symmetrically distributed cover plates (3) are commonly provided with latches (23).