Overwater temporary buttress for steel truss bridge construction

By designing a detachable temporary water piers structure, using detachable connectors and telescopic support frames, the problems of waste of materials and high manpower in the existing technology are solved, and the construction of steel truss bridges is achieved more stable, flexible and economical. Effect.

CN222043907UActive Publication Date: 2024-11-22中铁大桥局上海工程有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323467486.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-19
Publication Date
2024-11-22
Estimated Expiration
2033-12-19

AI Technical Summary

Technical Problem

The existing temporary water piers need to be removed during disassembly, resulting in waste of materials and high labor consumption and inability to reuse.

Method used

A temporary water pier for steel truss bridge construction was designed, using detachable pillars, support components, beams and connector structures. The telescopic connection of the embedded end plate, node connection ring, support frame and movable plate is formed. The font is built, the support frame and the movable plate can be detachably connected by bolts, the intermediate support and the node connection ring can be detachably connected by bolts, the cross beam and the support end plate can be detachably connected by bolts, and the transverse middle and edge ribs provide auxiliary support.

Benefits of technology

It realizes a more stable and flexible construction of the piers, and the various accessories can be reused, reducing material waste and manpower consumption, saving resources and economic expenditure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222043907U_ABST
    Figure CN222043907U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge construction, and provides an overwater temporary buttress for steel truss bridge construction, which is built in water and used for temporarily supporting a steel truss bridge, and comprises support columns, support components, cross beams, drilling piles and connecting pieces, and the four drilling piles are arranged in the water along the rectangular direction; the upper end of the drilling pile is detachably connected with the lower end of the supporting column through an embedded end plate, a cross beam is erected above the supporting column, a supporting assembly is connected between the cross beam and the supporting column, the supporting column comprises first connecting columns and second connecting columns, every two adjacent first connecting columns are connected through connecting pieces, and every two adjacent second connecting columns are connected through connecting pieces. The first connecting columns on the same side are connected with the second connecting columns above the adjacent first connecting columns through connecting pieces, and the connecting pieces are arranged between the first connecting columns and the second connecting columns in a Z shape. All accessories of the device are detachable, so that the device can be reused, resources are saved, waste is reduced, manpower is saved, and more economic expenditure is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction and provides a temporary supporting pier on water for steel truss bridge construction. Background Art

[0002] Steel truss bridges are made of corresponding steel rods welded together. At present, the construction of steel truss bridge structures across rivers usually adopts large-scale lifting machinery. Generally, temporary piers are built on the water to support them, and large-scale lifting machinery is used to stand on the river bank or the constructed structure to lift the various parts of the steel truss bridge.

[0003] The temporary piers on water in the prior art generally have a supporting column structure of cast bored piles, and then a crossbeam is built on the bored piles and connected by welding. When dismantling, the welded part needs to be cut off and the entire bored pile needs to be broken. The material of the entire bored pile used as the supporting column cannot be reused, and the reuse rate of the accessories after welding is low, resulting in great waste.

[0004] The patent document with application number CN109356021A proposes a temporary water pier and a construction method thereof, including multiple groups of brackets and connection systems, multiple groups of brackets are arranged in parallel and spaced apart and connected into one body through the connection system; each group of brackets includes multiple supporting pipe piles and diagonal braces, multiple supporting pipe piles are arranged in parallel and spaced apart in a straight line and connected into one body through the connection system; the supporting pipe piles include bored piles, main pipes and column heads; the main pipes are arranged vertically, and the lower end of the main pipes is connected to the bored piles through shear keys; the column heads are arranged at the upper end of the main pipes; the diagonal braces are located on both sides of the multiple supporting pipe piles, and one end of the diagonal brace is connected to the main pipe of the outermost supporting pipe pile, and the other end of the diagonal brace is flush with the upper end of the main pipe. Although the supporting pipe piles in this patent are connected to the main pipe structure on the upper part of the bored piles, and then the diagonal braces and the connection system are connected to the main pipe, the connection method is mostly welding. After use, the temporary water pier needs to be disassembled and the bored piles need to be broken. Cutting off a large number of welded parts during the disassembly process is likely to cause material waste and consume manpower. Utility Model Content

[0005] The utility model aims to provide a temporary water pier for the construction of a steel truss bridge, so as to solve the problems raised in the above-mentioned background technology.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] A temporary pier on water for steel truss bridge construction is built in water for temporarily supporting the steel truss bridge, comprising pillars, supporting components, cross beams, bored piles and connecting pieces, four bored piles are arranged in a rectangular position in the water, the upper ends of the bored piles are detachably connected to the lower ends of the pillars through embedded end plates, cross beams are set above the pillars, supporting components are connected between the cross beams and the pillars, and the supporting components are detachably connected to the cross beams and the pillars, the pillars comprise connecting column one and connecting column two, the lower part of the connecting column one is detachably connected to the bored piles through a node connecting ring, the lower part of the connecting column two is detachably connected to the upper part of the connecting column one through a node connecting ring, two adjacent connecting columns one and two adjacent connecting columns two are connected through connecting pieces, the connecting column one on the same side is connected to the connecting column two above the adjacent connecting column one through a connecting piece, the connecting piece forms a Z-shaped arrangement between the connecting column one and the connecting column two, the connecting piece comprises a supporting frame and a movable plate, and the supporting frame and the movable plate are telescopically connected.

[0008] Furthermore, the support assembly includes an intermediate support and an oblique support, the lower ends of the intermediate support and the oblique support are respectively detachably connected to the node connecting ring on the connecting column 2 by bolts, and the upper ends of the intermediate support and the oblique support are respectively detachably connected to the cross beam by bolts; the upper and lower ends of the node connecting ring are provided with connecting ring plates, and four connecting plates are evenly distributed around the node connecting ring along its circumference, and the connecting ring plates at the upper and lower ends of the node connecting ring are connected by connecting plates.

[0009] Furthermore, the connecting member is detachably connected to the connecting plate of the node connecting ring via bolts, and the supporting frame is plugged into and detachably connected to the movable plate via bolts.

[0010] Furthermore, the intermediate support is detachably connected to the connecting plate of the node connecting ring by bolts, the intermediate support includes two support plates arranged at intervals, the support plates include a top plate and two side plates, both ends of the top plate are fixedly connected to the side plates, the side plates are detachably connected to the connecting plate by bolts, and two vertical support ribs are vertically arranged on the top plate.

[0011] Furthermore, the vertical support bars on the two support plates are fixedly connected by transverse center bars, the two transverse center bars are arranged in parallel, and two connecting angle irons are respectively fixed to the lower ends of both sides of the vertical support bars, and the connecting angle irons are detachably connected to the top plate by bolts.

[0012] Furthermore, the diagonal brace includes transverse side reinforcement and diagonal supporting reinforcement. Two diagonal supporting reinforcements are provided. The upper ends of the two diagonal supporting reinforcements are respectively fixed to the two ends of the transverse side reinforcements. The transverse side reinforcements are arranged parallel to the transverse middle reinforcements. Connecting blocks are respectively fixed on both sides of the lower ends of the diagonal supporting reinforcements. The connecting blocks are detachably connected to the connecting plates by bolts.

[0013] Furthermore, a supporting end plate is provided at the upper end of the second connecting column, a cross beam is arranged on the supporting end plate, an upper end plate is provided at the upper end of the first connecting column, the upper end plate and the connecting ring plate on the second connecting column are detachably connected by bolts, and the connecting ring plate on the first connecting column is detachably connected to the embedded end plate by bolts.

[0014] Furthermore, the crossbeam is welded to form an integral steel frame structure, the crossbeam and the supporting end plate are detachably connected by bolts, a plurality of fixed angle irons 1 are arranged on the transverse center reinforcement, a plurality of fixed angle irons 2 are arranged on the transverse side reinforcement, and the crossbeam and the fixed angle irons 1 and 2 are detachably connected by bolts at the same time.

[0015] Compared with the prior art, the utility model has the following beneficial effects:

[0016] 1. The utility model provides a temporary pier on water for use in the construction of a steel truss bridge, which can not only support the crossbeam through pillars, but also provide auxiliary support to the crossbeam through transverse middle reinforcement and transverse side reinforcement. At the same time, the Z-shaped construction is more conducive to the stability of the temporary pier, making the temporary pier more firm and reliable, and can provide better support for the construction of the steel truss bridge.

[0017] 2. The utility model provides a temporary pier on water for use in the construction of a steel truss bridge. Through the telescopic connection of a support frame and a movable plate, it can adapt to the construction of temporary piers of different sizes, and has better adaptability and higher flexibility.

[0018] 3. The utility model provides a temporary water pier for steel truss bridge construction, and each accessory is detachable, so that the device can be reused, saving resources, reducing waste, saving manpower, and saving economic expenditure. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is a structural schematic diagram of a temporary water pier for the construction of a steel truss bridge according to the utility model;

[0020] Figure 2 It is a schematic diagram of the connection state of a node connection ring and a support assembly of a temporary water pier used in the construction of a steel truss bridge according to the utility model;

[0021] Figure 3 It is a side view of the connection state of a node connection ring and a support assembly of a temporary water pier used in the construction of a steel truss bridge of the utility model;

[0022] Figure 4 It is a schematic diagram of the connection state between a temporary water pier support and a bored pile used in the construction of a steel truss bridge of the utility model;

[0023] Figure 5 It is a structural schematic diagram of a temporary water pier connection column 1, a connection column 2 and a node connection ring for use in the construction of a steel truss bridge of the utility model;

[0024] Figure 6 This is a structural schematic diagram of a temporary water pier connection member for use in the construction of a steel truss bridge according to the utility model;

[0025] Figure 7 This is a structural schematic diagram of an intermediate support of a temporary water pier used in the construction of a steel truss bridge according to the utility model;

[0026] Figure 8 This is a structural schematic diagram of a temporary water-based pier diagonal brace for steel truss bridge construction in the utility model;

[0027] Fig. 9 For this utility model Figure 1 Enlarged view of point M.

[0028] In the figure: 1. pillar; 2. support assembly; 3. beam; 4. bored pile; 5. connector; 11. connecting column one; 12. connecting column two; 13. node connecting ring; 22. intermediate support; 23. diagonal brace; 31. connecting through hole one; 32. connecting through hole two; 111. upper end plate; 121. supporting end plate; 131. connecting ring plate; 132. connecting plate; 211. supporting frame; 212. movable plate; 213. plate head; 221. horizontal center reinforcement; 222. vertical support reinforcement; 223. support plate; 224. connecting angle iron; 231. horizontal side reinforcement; 232. diagonal support reinforcement; 233. connecting block. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0030] In the following description of the utility model, it should be noted that the terms "upper", "lower", "left", "right", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, which are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation or be constructed and operated in a specific orientation. The term "connection" only indicates the connection between devices and has no special meaning.

[0031] In addition, the technical fields and installation methods involved in the embodiments of the present invention described below can be combined with each other as long as there is no conflict between them.

[0032] Specific implementation: Please refer to Figure 1-Figure 9A temporary pier on water for steel truss bridge construction is built in water for temporarily supporting the steel truss bridge, including a pillar 1, a support assembly 2, a crossbeam 3, a bored pile 4 and a connector 5. Four bored piles 4 are arranged in a rectangular position in the water. The upper end of the bored pile 4 is detachably connected to the lower end of the pillar 1 through a pre-buried end plate. Every two pillars 1 form a group. A crossbeam 3 is built above each group of pillars 1. The two crossbeams 3 are arranged in parallel. A support assembly 2 is connected between the crossbeam 3 and the pillar 1, and the support assembly 2 is detachably connected to the crossbeam 3 and the pillar 1. The pillar 1 includes a connecting column 11 and a connecting column 2 12. The lower part of the connecting column 11 is connected to the bored pile 4 through a node connecting ring 13. Removable connection, the lower part of the connecting column 12 is detachably connected to the upper part of the connecting column 1 11 through the node connecting ring 13, the node connecting ring 13 is respectively welded on the connecting column 1 11 and the connecting column 2 12, and the two adjacent connecting columns 1 11 and the two adjacent connecting columns 2 12 are connected through the connecting piece 5. The connecting column 1 11 on the same side is connected to the connecting column 2 12 above the adjacent connecting column 1 11 through the connecting piece 5, and the connecting piece 5 forms a Z-shaped arrangement between the connecting column 1 11 and the connecting column 2 12. The Z-shaped construction is more conducive to the stability of the temporary pier. The connecting piece 5 includes a support frame 211 and a movable plate 212, and the support frame 211 and the movable plate 212 are telescopically connected.

[0033] The support assembly 2 includes an intermediate support 22 and an oblique support 23. The lower ends of the intermediate support 22 and the oblique support 23 are detachably connected to the node connection ring 13 on the connecting column 12 by bolts, and the upper ends of the intermediate support 22 and the oblique support 23 are detachably connected to the crossbeam 3 by bolts; the upper and lower ends of the node connection ring 13 are provided with a connection ring plate 131, and four connection plates 132 are evenly distributed around the node connection ring 13 along its circumference. The connection ring plates 131 at the upper and lower ends of the node connection ring 13 are connected by a connection plate 132; the upper end of the connecting column 12 is provided with a support The support end plate 121 and the cross beam 3 are arranged on the support end plate 121. An upper end plate 111 is arranged on the upper end of the connecting column 11. The upper end plate 111 and the node connecting ring 13 on the connecting column 12 are detachably connected by bolts. The connecting ring plate 131 on the connecting column 11 is detachably connected to the embedded end plate by bolts. A plurality of straight through holes are evenly distributed along the circumference of the upper end plate 111, the support end plate 121, the connecting ring plate 131 and the embedded end plate. The connecting ring plate 131 at the upper end of the node connecting ring 13 is reserved for pre-connection, which can provide convenience for other subsequent connections.

[0034] The connecting piece 5 is detachably connected to the connecting plate 132 of the node connecting ring 13 by bolts, and one end of the support frame 211 away from the movable plate 212 is provided with two waist-shaped holes 1 in the vertical direction, and the one end of the movable plate 212 away from the support frame 211 is fixed with a plate head 213, and two waist-shaped holes 2 are provided on the plate head 213 in the vertical direction. The connecting plate 132 is evenly distributed with a number of fixing holes along its vertical direction, and the waist-shaped hole 1 is detachably connected to the fixing hole on one of the node connecting rings 13 by bolts, and the waist-shaped hole 2 is detachably connected to the fixing hole on another corresponding node connecting ring 13 by bolts. The waist-shaped holes can adjust the connection position of the support frame 211 and the movable plate 212 and the node connecting ring 13, and a number of threaded through holes are evenly opened on both sides of the support frame 211, and a number of threaded blind holes are evenly opened on both sides of the movable plate 212. The threaded through holes and the threaded blind holes are detachably connected by bolts, and the telescopic connection between the support frame 211 and the movable plate 212 can adapt to the construction of temporary piers of different sizes, with better adaptability and higher flexibility.

[0035] The middle support 22 is detachably connected to the connecting plate 132 of the node connecting ring 13 by bolts. The middle support 22 includes two spaced support plates 223. The support plate 223 includes a top plate and two side plates. Both ends of the top plate are fixedly connected to the side plates. A plurality of upper through holes are provided on the top plate, and a plurality of side through holes are provided on the side plates. The side through holes are detachably connected to the fixing holes on the connecting plate 132 by bolts. Two vertical support ribs 222 are vertically provided on the top plate. Two connecting angle irons 224 are respectively fixed to the lower ends of both sides of the vertical support ribs 222. The connection method is welding. Holes are provided on the connecting angle irons 224. The holes on the connecting angle irons 224 are detachably connected to the upper through holes on the top plate by bolts. The vertical support ribs 222 on the two support plates 223 are fixedly connected by transverse center ribs 221. The connection method is welding. The two transverse center ribs 221 are arranged in parallel.

[0036] The diagonal brace 23 includes a transverse side reinforcement 231 and a diagonal support reinforcement 232. Two diagonal support reinforcements 232 are provided. The upper ends of the two diagonal support reinforcements 232 are fixedly connected to the two ends of the transverse side reinforcement 231 respectively by welding. The transverse side reinforcement 231 is arranged in parallel with the transverse center reinforcement 221. The transverse center reinforcement 221 and the transverse side reinforcement 231 can be used to provide auxiliary support for the crossbeam 3, so that the temporary pier is more solid and reliable, and can provide better support for the construction of the steel truss bridge. The lower ends of the diagonal support reinforcement 232 are respectively fixed with connecting blocks 233 by welding. A plurality of mounting holes are provided on the connecting block 233. The mounting holes on the connecting block 233 are detachably connected to the fixing holes on the connecting plate 132 by bolts. The transverse center reinforcement 221 and the transverse side reinforcement 231 are both arranged perpendicular to the crossbeam 3.

[0037] The crossbeam 3 is welded to form an integral steel frame structure, a plurality of connecting through holes 1 31 are provided on the upper side of the lower portion of the crossbeam 3, a plurality of connecting through holes 2 32 are provided on the front and rear sides of the lower portion, a straight through hole is provided on the support end plate 121, the connecting through hole 1 31 on the crossbeam 3 is detachably connected to the straight through hole on the support end plate 121 by bolts, a plurality of fixed angle irons 1 are provided on the transverse center rib 221, a plurality of fixed angle irons 2 are provided on the transverse side rib 231, the connection method of the fixed angle irons 1 and 2 are both welding, the fixed angle irons 1 and 2 are both provided with a central through hole, the connecting through hole 2 32 on the crossbeam 3 is detachably connected to the central through holes on the fixed angle irons 1 and 2 respectively by bolts.

[0038] The pillar 1, the supporting assembly 2, the cross beam 3 and the connecting member 5 are all steel structural members.

[0039] The working principle of the device is as follows: first, four bored piles 4 are driven into the water, and pre-buried end plates are pre-buried at the upper ends of the bored piles 4, and the connected connecting column 11 and the node connecting ring 13 are placed on the pre-buried end plates, and the pre-buried end plates and the connecting ring plate 131 at the lower ends of the node connecting ring 13 are connected with bolts, and the connected connecting column 2 12 and another node connecting ring 13 are placed on the connecting column 11, and the connecting ring plate 131 at the lower end of the other node connecting ring 13 is connected with the upper end plate 111 at the upper end of the connecting column 11 with bolts, and after they are all fixed, the connecting piece 5 is installed on the two adjacent node connecting rings 13 on the connecting column 11, and the connecting piece 5 is installed on the two adjacent node connecting rings 13 on the connecting column 2 12, and the connecting piece 5 is installed on the connecting column 11 on the same side and the connecting column 2 12 above the adjacent connecting column 11, so that the connecting piece 5 forms a Z-shaped arrangement between the connecting column 11 and the connecting column 2 12, and the connecting piece 5 is fixed on the connecting piece 13 of the node connecting ring 13. The connecting plate 132 is fixed circumferentially, and the support plate 223 is installed on the node connection ring 13 of the two adjacent connecting columns 12, and another support plate 223 is installed on the opposite side. The support plate 223 is installed on the connecting plate 132 of the node connection ring 13, and the vertical support rib 222 and the transverse middle rib 221 are installed on the support plate 223, and the support plate 223 and the vertical support rib 222 are fixed by connecting the angle iron 224, and the connecting block 233 on the oblique support rib 232 is installed on the connecting column 1 2, the upper end of the oblique support rib 232 is fixed with the transverse side rib 231. During installation, it is necessary to ensure that the transverse side rib 231 is parallel to the transverse middle rib 221 and its upper surface is located in the same plane as the support end plate 121. The beam 3 is placed on the support end plate 121, and the beam 3 and the support end plate 121, the transverse side rib 231, and the transverse middle rib 221 are fixed with bolts. The transverse side rib 231 and the transverse middle rib 221 provide auxiliary support for the beam 3.

[0040] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A temporary pier on water used in the construction of a steel truss bridge. Features: The invention relates to a bridge for temporarily supporting a steel truss constructed in water, comprising a support column (1), a support assembly (2), a cross beam (3), a bored pile (4) and a connecting piece (5). Four bored piles (4) are arranged in a rectangular position in water. The upper end of the bored pile (4) is detachably connected to the lower end of the support column (1) through a pre-buried end plate. A cross beam (3) is arranged above the support column (1). A support assembly (2) is connected between the cross beam (3) and the support column (1). The support assembly (2) and the cross beam (3) and the support column (1) are all detachably connected. The support column (1) comprises a first connecting column (11) and a second connecting column (12). The lower part of the first connecting column (11) is connected through a node connecting ring (13). The connecting column (12) is detachably connected to the bored pile (4); the lower part of the connecting column (12) is detachably connected to the upper part of the connecting column (11) via a node connecting ring (13); two adjacent connecting columns (11) and two adjacent connecting columns (12) are connected via a connecting piece (5); the connecting column (11) on the same side is connected to the connecting column (12) above the adjacent connecting column (11) via a connecting piece (5); the connecting piece (5) is arranged in a Z shape between the connecting column (11) and the connecting column (12); the connecting piece (5) comprises a support frame (211) and a movable plate (212); the support frame (211) and the movable plate (212) are telescopically connected.

2. A temporary water support pier for steel truss bridge construction according to claim 1, Features: The support assembly (2) comprises an intermediate support (22) and an oblique support (23); the lower ends of the intermediate support (22) and the oblique support (23) are respectively detachably connected to the node connection ring (13) on the second connection column (12) by bolts; the upper ends of the intermediate support (22) and the oblique support (23) are respectively detachably connected to the crossbeam (3) by bolts; the upper and lower ends of the node connection ring (13) are both provided with connection ring plates (131); four connection plates (132) are evenly distributed around the node connection ring (13) along its circumference; the connection ring plates (131) at the upper and lower ends of the node connection ring (13) are connected by the connection plates (132).

3. A temporary water pier for steel truss bridge construction according to claim 2, Features: The connecting member (5) is detachably connected to the connecting plate (132) of the node connecting ring (13) by means of bolts, and the supporting frame (211) is plugged into and detachably connected to the movable plate (212) by means of bolts.

4. A temporary water support pier for steel truss bridge construction according to claim 2, Features: The intermediate support (22) is detachably connected to the connecting plate (132) of the node connecting ring (13) by bolts, the intermediate support (22) comprises two spaced support plates (223), the support plates (223) comprise a top plate and two side plates, the two ends of the top plate are fixedly connected to the side plates, the side plates are detachably connected to the connecting plate (132) by bolts, and two vertical support ribs (222) are vertically arranged on the top plate.

5. A temporary water pier for steel truss bridge construction according to claim 4, Features: The vertical supporting ribs (222) on the two supporting plates (223) are fixedly connected via a transverse middle rib (221), the two transverse middle ribs (221) are arranged in parallel, two connecting angle irons (224) are respectively fixed to the lower ends of both sides of the vertical supporting ribs (222), and the connecting angle irons (224) are detachably connected to the top plate via bolts.

6. A temporary water support pier for steel truss bridge construction according to claim 5, Features: The diagonal brace (23) comprises a transverse side rib (231) and a diagonal supporting rib (232). Two diagonal supporting ribs (232) are provided. The upper ends of the two diagonal supporting ribs (232) are respectively fixed to the two ends of the transverse side rib (231). The transverse side rib (231) and the transverse middle rib (221) are arranged in parallel. Connecting blocks (233) are respectively fixed to the two sides of the lower end of the diagonal supporting rib (232). The connecting blocks (233) are detachably connected to the connecting plate (132) by bolts.

7. A temporary water support pier for steel truss bridge construction according to claim 6, Features: The upper end of the second connecting column (12) is provided with a supporting end plate (121), the cross beam (3) is arranged on the supporting end plate (121), the upper end of the first connecting column (11) is provided with an upper end plate (111), the upper end plate (111) and the connecting ring plate (131) on the second connecting column (12) are detachably connected by bolts, and the connecting ring plate (131) on the first connecting column (11) and the embedded end plate are detachably connected by bolts.

8. A temporary water support pier for steel truss bridge construction according to claim 7, Features: The cross beam (3) is welded to form an integral steel frame structure. The cross beam (3) is detachably connected to the support end plate (121) by bolts. A plurality of fixed angle irons (1) are arranged on the transverse middle reinforcement (221). A plurality of fixed angle irons (2) are arranged on the transverse side reinforcement (231). The cross beam (3) is detachably connected to the fixed angle irons (1) and (2) by bolts.