Detachable split nut device in high stress state
By designing a removable flip nut device under high stress conditions, including flip nuts, temporary hoops and nut covers, the problem of nut removal and installation under high stress is solved, and rapid and lossless nut removal and installation is achieved, improving the The construction progress also reduces damage to the screw structure.
Patent Information
- Application Number
- CN202323548841.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2033-12-26
AI Technical Summary
During the coal seam mining process, there are difficulties in disassembling and installing the line tower nut under high stress conditions. The existing technology cannot meet the needs of large-tonnage nut disassembly, and frequent cutting and installation consumes manual labor, affecting the construction progress.
A disassembleable flip nut device under high stress state is designed, including three components: flip nut, temporary hoop and nut cover. The nut is loosened and removed by screwing limit operations and pre-tightening operations. The cover provides annular wrapping force to protect the nut from environmental erosion.
It realizes rapid and non-destructive nut disassembly and installation under high stress conditions, improves construction progress, reduces damage to the screw structure, and has a simple structure and low construction requirements.
Smart Images

Figure CN222084926U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of fasteners, in particular to a detachable split nut device under a high stress state. Background Art
[0002] During the coal mining process, the surface high-voltage power tower will experience uneven subsidence with the evolution of the "three zones". The surface movement will go through three stages: the start-up stage, the active stage, and the attenuation stage. The active period of settlement is 3 to 6 months, accounting for 95% of the total subsidence. According to different geological conditions, the uneven subsidence in the active period is 20mm / d to 500mm / d. The tower foundation is buried in the shallow surface soil layer. The four tower feet are fixed on four independent foundations through bolt structures, controlling the freedom of the tower foot plate in the three directions of x, y, and z. Affected by mining and wind, the bolt structure not only bears shear force but also bears a certain pull-out force. The pull-out force of a single tower foot plate of different specifications of high-voltage transmission towers is about 20 to 200 tons, that is, a single screw rod bears 5 to 50 tons of pull-out force.
[0003] The correction of the wire tower under coal seam mining conditions is frequent. Loosening and installing nuts under high stress is a major problem. On the one hand, the size of the tower foot plate limits the operating space for the removal and installation of the nuts; on the other hand, the magnitude of the removal torque is large, and there are many factors that affect the removal torque: the size of the tightening force directly affects the size of the removal torque. At present, the removal torque can be increased by a torque amplifier on the market, and the maximum range is 20000N·m. It can only remove 10-ton-level wire tower nuts, which cannot meet the current production and construction status.
[0004] At present, in order to solve this problem, the nut structure is directly destroyed on site through hot welding cutting and electrical cutting. On the one hand, high-temperature cutting can easily destroy the strength of the screw; on the other hand, frequent cutting and installation consumes manpower and affects the construction progress. Utility Model Content
[0005] The purpose of the utility model is to provide a detachable split nut device under high stress conditions to solve the above-mentioned problems existing in the prior art.
[0006] Technical solution: A detachable split nut device under high stress state, including three components: a split nut, a temporary hoop and a nut cover. The split nut has a predetermined operating size and is mostly spliced, and can perform corresponding screwing and limiting operations. The temporary hoop has a predetermined operating size and is provided with a through hole adapted to the split nut, and can perform corresponding temporary pre-tightening operations on the split nut. The nut cover has a predetermined operating size and is provided with a recessed receiving cavity of a predetermined size. After completing the corresponding pre-tightening operation, the split nut can be wrapped in the provided recessed receiving cavity.
[0007] In a further embodiment, the split nut is narrow at the top and wide at the bottom, and the wide end of the split nut is a polygon and is divided along two opposite corners of the polygon to present a symmetrical structure.
[0008] In a further embodiment, the upper portion of the nut cover is spherical, and the lower portion is cylindrical; and a raised groove with a predetermined inclination angle is provided at one end of the nut cover cylinder.
[0009] In a further embodiment, the wide end of the split nut is hexagonal, and the split nut is divided along two opposite corners of the hexagon to form two parts that are symmetrical on the left and right.
[0010] Beneficial effects: The utility model relates to a detachable split nut device under high stress state, and relates to the technical field of fasteners, and more specifically to the process of nut removal and installation in the process of tower deviation correction under the background of coal mining, including three components: split nut, temporary hoop and nut cover. The split nut has a predetermined operating size, and is mostly spliced, and can perform corresponding screwing and limiting operations. The temporary hoop has a predetermined operating size, and is provided with a through hole adapted to the split nut, and can perform corresponding temporary pre-tightening operations on the split nut. The nut cover has a predetermined operating size, and is provided with a recessed receiving cavity of a predetermined size, and after completing the corresponding pre-tightening operation, the split nut can be wrapped in the recessed receiving cavity. The present application facilitates the loosening and removal of the nut under high stress conditions through the cooperation between the various components. At the same time, the split nut can also perform a certain pre-tightening operation after installation, and compared with the traditional split nut structure, the force is reasonable, the structure is simple, the construction requirements are not high, and the construction progress is also improved simultaneously. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of the split nut.
[0012] Figure 2 It is a schematic diagram of the structure under temporary pre-tightening state.
[0013] Figure 3 It is a side view in the temporary pre-tensioned state.
[0014] Figure 4 It is a schematic diagram of the structure of the nut when it is in use.
[0015] The reference numerals in the figures are: split nut 1 , temporary hoop 2 , nut cover 3 , raised groove 31 . DETAILED DESCRIPTION
[0016] In the following description, a large number of specific details are given to provide a more thorough understanding of the utility model. However, it is obvious to those skilled in the art that the utility model can be implemented without one or more of these details. In other examples, in order to avoid confusion with the utility model, some technical features known in the art are not described.
[0017] Embodiment 1:
[0018] The detachable split nut 1 device under high stress state proposed in this embodiment realizes rapid and non-destructive disassembly under high stress state in the form of split nut 1, and provides a set of tightening and disassembly methods to ensure the smooth progress of the nut disassembly and installation process during the tower deviation correction process. It includes three components: split nut 1, temporary hoop 2 and nut cover 3. The split nut 1 has a predetermined operating size and is mostly spliced, and can perform corresponding screwing and limiting operations. The temporary hoop 2 has a predetermined operating size and is provided with a through hole adapted to the split nut 1, and can perform corresponding temporary pre-tightening operations on the split nut 1. The nut cover 3 has a predetermined operating size and is provided with a recessed receiving cavity of a predetermined size. After completing the corresponding pre-tightening operation, the split nut 1 can be wrapped in the provided recessed receiving cavity. The split nut 1 is narrow at the top and wide at the bottom, and the wide end of the split nut 1 is a polygon, and is divided along two diagonal angles of the polygon, presenting a symmetrical structure. The split nut 1 structure is narrow at the top and wide at the bottom, and the bottom is widened so that it can withstand greater stress. The upper part of the nut cover 3 is spherical, and the lower part is cylindrical; and a raised groove 31 with a predetermined inclination angle is provided at one end of the cylindrical body of the nut cover 3. The nut cover 3 only provides annular wrapping force and does not directly bear the pull-out force. The pull-out force is still borne by the nut and the screw itself. The nut cover 3 provides a certain protection to prevent the inside of the split nut 1 from rusting due to environmental erosion. The wide end of the split nut 1 is hexagonal, and the split nut 1 is divided along the two opposite corners of the hexagon to form two symmetrical parts. In a further preferred embodiment, the upper part of the split nut 1 can be a common hexagonal nut structure, the bottom is slightly wider, and the nut is divided along the two opposite corners of the hexagon to form a symmetrical structure.
[0019] Embodiment 2:
[0020] On the basis of the first embodiment, a detachable split nut 1 device and an installation and disassembly method under high stress are proposed, which is suitable for the multiple deviation correction process of the surface tower during coal mining, the installation and disassembly of the large-tonnage anti-pulling bolt structure, and the construction is carried out by using this nut structure to speed up the construction progress and reduce the damage to the screw structure. It includes a split nut 1, a nut cover 3, a temporary hoop 2 and other physical structures. Among them, the upper part of the split nut 1 can be a common hexagonal nut structure, the bottom is slightly wider, and the nut is divided along the two diagonals of the hexagon, forming a symmetrical structure. The temporary hoop 2 is a high-strength metal material, and a single split nut 1 is equipped with two hoop clamps, which are placed at the bottom and upper part of the split nut 1 respectively, leaving enough operating space for the torque wrench in the middle, and can be pried and disassembled after the initial tightening. The nut cover 3 is also a high-strength metal material. After removing the temporary hoop 2, it is installed along the internal groove. The upper part of the nut cover 3 is spherical, and the lower part is cylindrical. The middle is hollowed out to facilitate the passage of the screw structure.
[0021] Based on the above embodiments, the working process of the utility model is as follows:
[0022] 1. After installing the tower foot plate, assemble the split nut 1 onto the screw rod on the upper part of the tower foot plate to ensure that the bottoms of the left and right halves of the split nut 1 remain at the same height;
[0023] 2. The temporary hoop 2 is sleeved outside the split nut 1. When the split nut 1 is pre-tightened, the temporary hoop 2 is arranged on both sides of the wrench to ensure the integrity of the split nut 1 when twisting; after the split nut 1 has a certain pre-tightening force, the temporary hoop 2 is pried to remove and the nut cover 3 is installed. The displacement of the tower body causes the stress at the bottom to change, and the downward traction and shear force are gradually transferred to the nut and the tower foot plate. The integrity of the split nut 1 is guaranteed by the constraint of the nut cover 3, and it bears a certain shear force.
[0024] 3. In the second stage of the deviation correction process, the tower body is controlled to be stable, and the nut cover 3 is pried apart along the gap of the split nut 1 to complete the disassembly work. After the second deviation correction is completed, the first step is cycled to complete the installation link of this stage.
[0025] As described above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be interpreted as limiting the present invention itself. Various changes can be made to it in form and detail without departing from the spirit and scope of the present invention defined in the appended claims.
Claims
1. A detachable split nut device under high stress conditions, Features include: Split nuts have predetermined working dimensions and are mostly spliced, allowing for corresponding screwing and limiting operations; A temporary hoop, having a predetermined working size and provided with a through hole adapted to the split nut, capable of performing a corresponding temporary pre-tightening operation on the split nut; The nut cover has a predetermined operating size and is provided with a recessed receiving cavity of a predetermined size. After completing the corresponding pre-tightening operation, the split nut can be wrapped in the recessed receiving cavity.
2. A detachable split nut device under high stress state according to claim 1, Features: The split nut is narrow at the top and wide at the bottom, and the wide end of the split nut is a polygon and is divided along two opposite corners of the polygon to present a symmetrical structure.
3. A detachable split nut device under high stress state according to claim 1, Features: The upper part of the nut cover is spherical, and the lower part is cylindrical; and a protruding groove with a predetermined inclination angle is provided at one end of the cylindrical body of the nut cover.
4. A detachable split nut device under high stress state according to claim 2, Features: The wide end of the split nut is hexagonal, and the split nut is divided along two diagonal corners of the hexagon to form two parts that are symmetrical on the left and right.