Cold water supply system for injection molding production line

By designing a cold water supply system for injection molding production lines, using cold water tanks and circulation pump systems to achieve efficient circulation and temperature control of cold water, the problems of idle equipment and large energy consumption are solved, and product quality and production efficiency are improved.

CN222096909UActive Publication Date: 2024-12-03CHINA UNITED ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421044297.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-14
Publication Date
2024-12-03
Estimated Expiration
2034-05-14

AI Technical Summary

Technical Problem

The existing injection molded cold water supply system has problems such as idle equipment, high energy consumption, and fluctuations in cold water temperature, resulting in unqualified product quality.

Method used

Design a cold water supply system for injection molding production lines, including chiller units, chiller tanks, chiller water circulation pipelines and production chiller water circulation pipelines. It adopts a double-layer structure of chiller tanks and circulation pumps, and uses a chiller water circulation pump and a chiller water circulation pump. Achieve efficient circulation and temperature control of cold water, avoid repeated start and stop of the chiller unit, and eliminate water temperature fluctuations through the bypass pipe.

Benefits of technology

It has achieved improvements in equipment utilization, energy conservation, and stability in product quality, reducing production costs and unqualified rates.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222096909U_ABST
    Figure CN222096909U_ABST
Patent Text Reader

Abstract

According to the cold water supply system for the injection molding production line, one end of a chilled water supply pipe is connected with a water outlet of a water chilling unit, and the other end is connected with a water inlet of a cold water tank; a chilled water supply valve is arranged on the chilled water supply pipe; the other end of the chilled water return pipe is connected with a water inlet of the water chilling unit; a chilled water return valve is arranged on the chilled water return pipe; a chilled water circulating pump is arranged on the chilled water return pipe; one injection molding production line is matched with one production cold water supply branch pipe, and the production cold water supply branch pipe is connected with a water inlet of the injection molding production line; one end of a production cold water supply main pipe is connected with a water outlet of the cold water tank, the other end of the production cold water supply main pipe is connected with each production cold water supply branch pipe, and a production cold water circulating pump is arranged on the production cold water supply main pipe; one injection molding production line is matched with one production cold water return branch pipe, and the production cold water return branch pipe is connected with a water outlet of the injection molding production line.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a cold water supply system for an injection molding production line. Background Art

[0002] During the injection molding production process, the injection mold needs to be cooled to achieve rapid cooling and solidification of the plastic product. In the injection molding production process, cold water supply is a crucial link, which directly affects product quality, production efficiency and energy consumption. At present, the injection molding cold water supply system is mainly configured with the injection molding production line, that is, one injection molding line is equipped with a dedicated chiller. When the injection molding production line is in production, the chiller and the corresponding water pump are turned on to supply cold water to the production line. However, the production load of the injection molding production line is not stable. Sometimes a certain production line needs to be turned on and sometimes it needs to be turned off. For several production lines in the workshop, only some of the production lines remain in production at a certain time, that is, there is a simultaneous use coefficient. The above-mentioned method of the prior art has the following disadvantages: First, the configured chiller cannot always maintain high-load operation, but a part of it is always idle, resulting in a waste of initial investment; second, the chiller needs to be started and stopped with the injection molding line, and it is repeatedly turned on and off, causing the chiller to operate at an inefficient operating point, resulting in high energy consumption; third, due to the existence of production gaps, the water supply temperature of the cold water system fluctuates greatly, which will directly affect many performance parameters of the product such as deformation, surface, dimensional accuracy, strength, etc., resulting in an increase in the product failure rate. Utility Model Content

[0003] The purpose of the utility model is to overcome the above-mentioned deficiencies in the prior art and to provide a cold water supply system for an injection molding production line, which is economical in investment, low in operating costs, energy-saving and environmentally friendly, and can effectively avoid the adverse effects of cold water temperature fluctuations on product quality.

[0004] The technical solution adopted by the utility model to solve the above-mentioned problems is: a cold water supply system for an injection molding production line, including a chiller, characterized in that it also includes a cold water tank, a chilled water circulation pipeline and a production cold water circulation pipeline; the chilled water circulation pipeline includes a chilled water supply pipe, a chilled water return pipe, a chilled water supply valve, a chilled water return valve and a chilled water circulation pump; one end of the chilled water supply pipe is connected to the water outlet of the chiller, and the other end is connected to the water inlet of the cold water tank; a chilled water supply valve is provided on the chilled water supply pipe; one end of the chilled water return pipe is connected to the water outlet of the cold water tank, and the other end is connected to the water inlet of the chiller; a chilled water return valve is provided on the chilled water return pipe; a chilled water circulation pump is provided on the chilled water return pipe; the production cold water circulation pipeline includes a production cold water supply main pipe, a production cold water supply branch pipe, a production cold water return branch pipe, a production cold water return main pipe, a production cold water circulation A circulating pump, a production cold water return valve, a production cold water supply three-way valve and a production cold water bypass pipe; one injection molding production line is equipped with a production cold water supply branch pipe, and the production cold water supply branch pipe is connected to the water inlet of the injection molding production line; one end of the production cold water supply main pipe is connected to the outlet of the cold water tank, and the other end is connected to each production cold water supply branch pipe, and a production cold water circulation pump is provided on the production cold water supply main pipe; one injection molding production line is equipped with a production cold water return branch pipe, and the production cold water return branch pipe is connected to the outlet of the injection molding production line, and a production cold water return valve is provided on the production cold water return branch pipe; one end of the production cold water return main pipe is connected to each production cold water return branch pipe, and the other end is connected to the water inlet of the cold water tank; a production cold water supply three-way valve is provided on the production cold water supply branch pipe, one end of the production cold water bypass pipe is connected to the production cold water supply three-way valve, and the other end is connected to the production cold water return branch pipe.

[0005] The cold water tank of the utility model adopts a cylindrical shape, and the tank body is a double-layer structure, wherein a polyurethane heat-insulating layer is provided in the middle of the double-layer structure.

[0006] The top of the cold water tank of the utility model is provided with a vent hole, a maintenance hole and an equipment hole.

[0007] The cold water tank of the utility model is provided with a first water inlet, a second water inlet, a first water outlet, a second water outlet, an overflow hole, a water replenishment hole and a sewage discharge hole.

[0008] The utility model is provided with a first temperature sensor on the production cold water supply main pipe.

[0009] The cold water tank of the utility model is provided with a temperature measuring hole, in which a second temperature sensor is installed.

[0010] Compared with the prior art, the utility model has the following advantages and effects:

[0011] 1. Multiple injection molding production lines can share a production cold water supply system, using a chiller to centrally supply production cold water. There is no need to configure a dedicated chiller for each production line. The system's one-time investment is reduced, while the equipment idle time is reduced and the utilization rate is improved. Since the efficiency of large-capacity chillers is higher than that of small-capacity chillers, the operating costs of the system are also reduced.

[0012] 2. The cold water tank has a certain amount of cold storage capacity, which can prevent the chiller from repeated start and stop, so that the chiller always maintains a more efficient operating point, saving energy and extending the service life of the chiller.

[0013] 3. Setting a bypass at the water supply and return of the injection molding production line can effectively eliminate the problem of large fluctuations in the water temperature of the cold water inlet, thereby improving product quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.

[0015] Figure 2 It is a schematic structural diagram of a cold water tank according to an embodiment of the utility model. DETAILED DESCRIPTION

[0016] The present invention will be further described in detail below with reference to the accompanying drawings and through examples. The following examples are provided to explain the present invention, but the present invention is not limited to the following examples.

[0017] The embodiment of the utility model includes a chiller 5, a cold water tank 1, a chilled water circulation pipeline and a production cold water circulation pipeline. The cold water tank 1 is cylindrical in shape, the box body is made of 304 stainless steel, the box body is a double-layer structure, and the middle of the double-layer structure is a polyurethane insulation layer with a thickness of 5 cm. A vent 107 is provided on the top of the cold water tank 1 to keep the inside of the water tank connected to the atmosphere and maintain the pressure; a maintenance hole 106 is provided on the top of the cold water tank 1 for entry and use in case of internal failure; an equipment hole 105 is provided on the top of the cold water tank 1, which is reserved for later installation of equipment. The body of the cold water tank 1 is provided with a first water inlet 108, a second water inlet 102, a first water outlet 110 and a second water outlet 101, which are respectively connected to the chilled water circulation pipeline and the production cold water circulation pipeline. An overflow hole 109 is provided at the upper part of the cold water tank 1. When the water level in the water tank exceeds the highest level, the excess water is discharged through the overflow hole 109. A water replenishment hole 104 is provided at the upper part of the cold water tank 1. When the water level in the water tank is low, water is replenished from the outside through the water replenishment hole 104. A sewage hole 111 is provided at the lower part of the cold water tank 1 for emptying during maintenance and water replacement. A temperature measuring hole 103 is provided in the middle of the cold water tank 1. A second temperature sensor 113 is installed in the temperature measuring hole 103. A liquid level display control device 112 is provided on the cold water tank 1, which can automatically adjust the water level and directly observe the internal water level with the naked eye.

[0018] The chilled water circulation pipeline includes a chilled water supply pipe 7, a chilled water return pipe 3, a chilled water supply valve 6, a chilled water return valve 4 and a chilled water circulation pump 2. One end of the chilled water supply pipe 7 is connected to the water outlet of the chiller 5, and the other end is connected to the first water inlet 108 of the cold water tank 1; a chilled water supply valve 6 is provided on the side of the chilled water supply pipe 7 close to the water outlet of the chiller 5. One end of the chilled water return pipe 3 is connected to the first water outlet 110 of the cold water tank 1, and the other end is connected to the water inlet of the chiller 5; a chilled water return valve 4 is provided on the side of the chilled water return pipe 3 close to the water inlet of the chiller 5; a chilled water circulation pump 2 is provided on the pipeline between the chilled water return valve 4 and the first water outlet 110 of the cold water tank 1.

[0019] The production cold water circulation pipeline includes a production cold water supply main pipe 9, a production cold water supply branch pipe 11, a production cold water bypass pipe 16, a production cold water return branch pipe 14, a production cold water return main pipe 17, a production cold water circulation pump 8, a production cold water supply three-way valve 12, and a production cold water return valve 15.

[0020] One injection molding production line 13 is equipped with a production cold water supply branch pipe 11, which is connected to the water inlet of the injection molding production line 13, and a production cold water supply three-way valve 12 is provided on the production cold water supply branch pipe 11; one end of the production cold water supply main pipe 9 is connected to the second water outlet 101 of the cold water tank 1, and the other end is connected to each production cold water supply branch pipe 11, and a production cold water circulation pump 8 is provided on the production cold water supply main pipe 9. A first temperature sensor 10 is provided at the farthest end of the production cold water supply main pipe 9.

[0021] An injection molding production line 13 is equipped with a production cold water return branch pipe 14, which is connected to the water outlet of the injection molding production line 13, and a production cold water return valve 15 is provided on the production cold water return branch pipe 14; one end of the production cold water return main pipe 17 is connected to each production cold water return branch pipe 14, and the other end is connected to the second water inlet 102 of the cold water tank 1; one end of the production cold water bypass pipe 16 is connected to the production cold water supply three-way valve 12, and the other end is connected to the production cold water return branch pipe 14.

[0022] When in use, first inject tap water into the water tank through the water filling hole 104 of the cold water tank 1 until the set standard water level is reached. Then turn on the chilled water circulation pump 2 and the chiller 5, and continuously deliver the cold energy generated by the chiller 5 to the cold water tank 1 through the chilled water circulation until the cold water temperature inside the water tank fed back by the second temperature sensor 113 inside the cold water tank 1 reaches the set value.

[0023] When there is no production on the injection molding production line 13, the state of the production cold water supply three-way valve 12 is that the water inlet passage of the injection molding production line 13 is closed, and the passage of the production cold water bypass pipe 16 is open. The water in the production cold water circulation pipeline will slowly exchange heat with the outside air to increase the temperature. When the cold water temperature in the pipeline fed back by the first temperature sensor 10 at the farthest end of the production cold water supply main pipe 9 exceeds the production cold water temperature fluctuation requirement, the production cold water circulation pump 8 is turned on to force the cold water in the cold water tank 1 to enter the production cold water circulation pipeline, so as to always keep the water temperature in the production cold water to meet the production requirements.

[0024] When the injection molding production line 13 is in production, the production cold water supply three-way valve 12 is actuated to open the water supply passage of the injection molding production line 13, close the passage of the production cold water bypass pipe 16, and start the production cold water circulation pump 8 at the same time, and transport the production cold water in the water tank that meets the production temperature requirements to the injection molding production line 13 for production. After releasing the cold amount, the heated production cold water returns to the cold water tank 1 through the production cold water return branch pipe 14 and the production cold water return main pipe 17. When the cold water temperature inside the water tank fed back by the second temperature sensor 113 inside the cold water tank 1 does not meet the production cold water temperature fluctuation requirements, the chilled water circulation passage is opened to transport the cold amount to the cold water tank 1.

[0025] When the injection molding production line 13 stops production, the corresponding production cold water supply three-way valve 12 is activated again, the water inlet passage of the injection molding production line 13 is closed, and the production cold water bypass pipe 16 is opened. When all injection molding production lines 13 stop production, the production cold water circulation pump 8 is turned off.

[0026] In addition, it should be noted that the shapes and names of the parts and components of the specific embodiments described in this specification may be different, and the above content described in this specification is only an example of the structure of the utility model. All equivalent changes or simple changes made based on the structure, features and principles described in the patent concept of the utility model are included in the protection scope of the utility model patent. Technicians in the technical field of the utility model can make various modifications or supplements to the specific embodiments described or replace them in a similar manner, as long as they do not deviate from the structure of the utility model or exceed the scope defined by the claims, they should all fall within the protection scope of the utility model.

Claims

1. A cold water supply system for an injection molding production line, comprising a chiller, characterized in that: It also includes a cold water tank, a chilled water circulation pipeline and a production cold water circulation pipeline; the chilled water circulation pipeline includes a chilled water supply pipe, a chilled water return pipe, a chilled water supply valve, a chilled water return valve and a chilled water circulation pump; one end of the chilled water supply pipe is connected to the water outlet of the chiller, and the other end is connected to the water inlet of the cold water tank; a chilled water supply valve is provided on the chilled water supply pipe; one end of the chilled water return pipe is connected to the water outlet of the cold water tank, and the other end is connected to the water inlet of the chiller; a chilled water return valve is provided on the chilled water return pipe; a chilled water circulation pump is provided on the chilled water return pipe; the production cold water circulation pipeline includes a production cold water supply main pipe, a production cold water supply branch pipe, a production cold water return branch pipe, a production cold water return main pipe, a production cold water circulation pump, a production cold water return valve, a production cold water supply three-way valve and a production cold water return valve. Water bypass pipe; one injection molding production line is equipped with a production cold water supply branch pipe, which is connected to the water inlet of the injection molding production line; one end of the production cold water supply main pipe is connected to the outlet of the cold water tank, and the other end is connected to each production cold water supply branch pipe, and a production cold water circulation pump is provided on the production cold water supply main pipe; one injection molding production line is equipped with a production cold water return branch pipe, which is connected to the outlet of the injection molding production line, and a production cold water return valve is provided on the production cold water return branch pipe; one end of the production cold water return main pipe is connected to each production cold water return branch pipe, and the other end is connected to the water inlet of the cold water tank; a production cold water supply three-way valve is provided on the production cold water supply branch pipe, one end of the production cold water bypass pipe is connected to the production cold water supply three-way valve, and the other end is connected to the production cold water return branch pipe.

2. The cold water supply system for injection molding production line according to claim 1, characterized in that: The cold water tank is cylindrical in shape, and the tank body is a double-layer structure with a polyurethane heat-insulating layer in the middle of the double-layer structure.

3. The cold water supply system for injection molding production line according to claim 1, characterized in that: The top of the cold water tank is provided with a vent hole, a maintenance hole and an equipment hole.

4. The cold water supply system for injection molding production line according to claim 1, characterized in that: The cold water tank is provided with a first water inlet, a second water inlet, a first water outlet, a second water outlet, an overflow hole, a water replenishment hole and a sewage discharge hole.

5. The cold water supply system for injection molding production line according to claim 1, characterized in that: A first temperature sensor is provided on the production cold water supply main.

6. The cold water supply system for injection molding production line according to claim 1, characterized in that: The cold water tank is provided with a temperature measuring hole, in which a second temperature sensor is installed.