Butt joint hoisting mechanism for pipeline installation
By using the butt lifting mechanism of the guide ring and height adjustment components in the pipeline installation, the problem of butt offset of the pipe body unit is solved, a stable and convenient pipeline installation process is achieved, and construction efficiency and installation accuracy are improved.
Patent Information
- Application Number
- CN202420558490.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-21
AI Technical Summary
During the pipeline installation process, the pipe body unit is prone to offset during docking, resulting in unstable docking and time-consuming and labor-intensive, and the existing technology is difficult to effectively solve this problem.
A butt lifting mechanism is designed, including mounting a guide ring and a support rod at both ends of the pipe body unit. A height adjustment component is provided on the support rod, and a combination of the guide ring and the support rod provide stable support and height adjustment. Ensure that the pipe body unit is at the same installation height for easy docking.
Through the cooperation of the guide ring and the height adjustment assembly, the stable docking of the pipe body unit is achieved, the installation efficiency and operation convenience are improved, the time-consuming and labor-intensive problems are reduced, and the stability and accuracy of docking are ensured.
Smart Images

Figure CN222102953U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pipeline installation, and in particular to a docking and lifting mechanism for pipeline installation. Background Art
[0002] A pipeline is a device connected by pipes, pipe connectors and valves for transporting gas, liquid or fluid with solid particles. It is mainly used in water supply, drainage, heating, gas supply, long-distance transportation of oil and natural gas, water conservancy projects and various industrial installations.
[0003] Pipelines need to be installed before being used in various occasions. Usually, pipelines are assembled by connecting pipe units one by one. After the pipe units are processed in the factory, they are transported to the construction site and then lowered into the pipeline burying trench by hoisting. After placing multiple pipe units in the pipeline burying trench in turn, the adjacent pipe units are connected in turn. Due to the limited space in the pipeline burying trench, workers usually connect the pipe units in the pipeline burying trench in turn by pulling with ropes, and then perform sealing to complete the installation of the pipeline.
[0004] Regarding the above-mentioned related technologies, there are the following defects: the volume of the pipe body unit is large, and the ground in the pipeline burial trench is uneven, which makes it easy for the pipe to shift during the docking process, resulting in unstable docking, requiring multiple adjustments, which is time-consuming and labor-intensive, and needs further improvement. Utility Model Content
[0005] In order to improve the problem that pipe body units are easily offset during the docking process, which makes the docking time-consuming and labor-intensive, the present application provides a docking lifting mechanism for pipeline installation.
[0006] The present application provides a butt-joint lifting mechanism for pipeline installation, which adopts the following technical solution:
[0007] A butt lifting mechanism for pipeline installation comprises: guide rings movably mounted on both ends of a pipe unit and support rods connected to the guide rings, wherein the support rods are provided with a height adjustment component for adjusting the support height of the support rods for the pipe unit.
[0008] By adopting the above technical solution, the guide rings are sleeved on both ends of the pipe body unit, and then the guide rings are connected to lower the pipe body unit into the pipeline burying trench, and the support rods support the pipe body unit in the pipeline burying trench. Finally, the height adjustment component is used to adjust the support height of the pipe body unit so that each pipe body unit is at the same installation height, thereby facilitating the docking between adjacent pipe body units, improving the pipeline installation efficiency, and saving time and effort in operation.
[0009] Optionally, the support rod includes a support base and a support rod body slidably connected to the support base, the guide ring is fixedly connected to one end of the support rod body away from the support base, the sliding direction of the support rod body is consistent with the axial direction of the support rod body, and the height adjustment assembly is arranged on the support base, and the height adjustment assembly is used to drive the support rod body to slide.
[0010] By adopting the above technical solution, the pipeline unit provides support through the support base and the support rod body. The support base is directly placed in the pipeline buried trench with a stable structure. The height adjustment component drives the support rod body to slide, thereby effectively adjusting the installation height of the pipe body unit. The operation is convenient and the structure is reliable.
[0011] Optionally, the height adjustment assembly includes a rotating sleeve and a rotating screw, the rotating sleeve being rotatably connected to the support base, the rotating screw being fixedly connected to one end of the support rod body away from the guide ring, the rotating screw being threadedly connected in the rotating sleeve, and the rotating screw being further provided with a limit member for limiting the rotation of the rotating screw around the rotating sleeve.
[0012] By adopting the above technical solution, the rotation of the rotating screw is limited by the limiter, and then when the rotating screw sleeve is driven to rotate, the rotating screw drives the supporting rod body to produce a relative movement trend. At this time, under the action of the limiter, the rotating screw and the supporting rod body drive the vertical displacement of the tube body unit on the guide ring, thereby effectively realizing the adjustment of the installation height of the tube body unit and facilitating the operation.
[0013] Optionally, the limiting member includes a limiting block, which is fixedly connected to the end of the rotating screw, a guide hole is provided on the support base, a limiting groove is provided on the inner wall of the guide hole, the rotating screw passes through the rotating screw sleeve and extends into the guide hole, and the limiting block is clamped in the limiting groove.
[0014] By adopting the above technical solution, the limit block is clamped in the limit slide groove. When the rotating screw generates a relative movement trend driven by the rotating screw sleeve, the limit block slides along the limit slide groove, thereby causing the rotating screw to slide vertically along the rotating screw sleeve, thereby realizing the adjustment of the support height of the tube body unit. The structure is simple and reliable.
[0015] Optionally, a plurality of rotating handles are arranged on the outer wall of the rotating screw sleeve.
[0016] By adopting the above technical solution, the provided rotating handle is used to facilitate driving the rotating screw sleeve to rotate, and no other tools are needed, which is convenient to use.
[0017] Optionally, a plurality of balls are rotatably connected to the inner wall of the guide ring.
[0018] By adopting the above technical solution, the provided balls effectively provide a guide for the tube unit to slide along the guide ring, reducing the friction between the tube unit and the guide ring, making the movement of the tube unit more convenient, saving time and effort.
[0019] Optionally, a lifting ring is fixedly connected to the top of the guide ring.
[0020] By adopting the above technical solution, the provided lifting ring is convenient for lifting the pipe unit, and the structure is simple and reliable.
[0021] Optionally, a non-slip pad is provided at the bottom of the support base.
[0022] By adopting the above technical solution, the anti-skid pad increases the friction of the support base, so that the structure of the support base is more stable when in use.
[0023] In summary, the present application includes at least one of the following beneficial technical effects of a butt-joint lifting mechanism for pipeline installation:
[0024] 1. Through the guide ring, support rod and height adjustment assembly, the guide ring is movably mounted on the pipe unit, so that after the pipe unit is lowered into the pipeline burial trench, the guide ring and support rod provide support force for the pipe unit, and then the height adjustment assembly is used to adjust the support height of the pipe unit, so that each pipe unit is located at the same installation height, thereby making the adjacent pipe units docking stably, pushing the pipe unit to slide on the guide ring, which is convenient to operate, time-saving and labor-saving, and has high installation accuracy;
[0025] 2. The lifting rings are set up so that the pipeline unit can be lifted directly with the help of the lifting rings. The lifting rings are more stable and more convenient to use than the traditional steel cable binding lifting. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0027] Figure 2 It is a cross-sectional structural schematic diagram of the present application.
[0028] Figure numerals: 1. Tube unit; 2. Guide ring; 3. Support rod; 30. Support base; 31. Support rod body; 4. Height adjustment assembly; 40. Rotating screw sleeve; 41. Rotating screw; 50. Limit block; 51. Guide hole; 52. Limit slide groove; 6. Rotating handle; 7. Ball; 8. Lifting ring; 9. Anti-slip pad. DETAILED DESCRIPTION
[0029] The present application is further described in detail below in conjunction with the accompanying drawings.
[0030] The present application embodiment discloses a butt lifting mechanism for pipe installation, referring to Figure 1 and Figure 2 , including: guide rings 2 movably mounted on both ends of the pipe body unit 1 and support rods 3 connected to the guide rings 2. In this embodiment, the pipe body unit 1 needs to be lowered into the pre-dug pipeline burying trench with the help of a crane or other lifting equipment; the pipe body unit 1 is generally a steel pipe or a concrete pipe, and by mounting the guide rings 2 on both ends of the pipe body unit 1, the guide rings 2 and the support rods 3 are lowered into the pipeline burying trench together, and the support rods 3 abut against the ground of the pipeline burying trench, effectively supporting the pipe body unit 1.
[0031] Afterwards, a height adjustment component 4 is further provided on the support rod 3. The height adjustment component 4 is used to adjust the supporting height of the support rod 3 to the pipe body unit 1, so that multiple pipe body units 1 can be at the same height, thereby effectively aligning the pipe body units 1, and further pushing the pipe body units 1 along the guide ring 2 to connect with each other, thereby conveniently completing the installation of the pipeline and increasing the construction efficiency.
[0032] In order to reduce the friction between the guide ring 2 and the tube unit 1 and facilitate the sliding of the tube unit 1, a plurality of balls 7 are rotatably connected to the inner wall of the guide ring 2. The guiding effect of the balls 7 makes the tube unit 1 slide along the guide ring 2 faster and more labor-saving.
[0033] Reference Figure 1 and Figure 2 In this embodiment, the pipe unit 1 is transported to the construction site by vehicle. Therefore, during the transportation of the pipe unit 1, the guide ring 2 and the support rod 3 are connected to the pipe unit 1, so that the pipe unit 1 can be transported stably, and the rolling of the pipe unit 1 can be reduced. In order to improve the convenience of lifting the pipe unit 1, a lifting ring 8 is fixedly connected to the top of the guide ring 2, and the pipe unit 1 is stably lowered into the pipeline burying trench by using the lifting ring 8. The use of the lifting ring 8 is more stable than the traditional method of tying the pipeline unit with steel cables, which reduces the shaking of the pipe unit 1 during lifting, and the structure is reliable.
[0034] Reference Figure 1 and Figure 2In this embodiment, the support rod 3 includes a support base 30 and a support rod body 31 slidably connected to the support base 30; wherein the guide ring 2 is fixedly connected to the end of the support rod body 31 away from the support base 30 by welding, and the sliding direction of the support rod body 31 is consistent with the axial direction of the support rod body 31, and the height adjustment component 4 is arranged on the support base 30, and the height adjustment component 4 is used to drive the support rod body 31 to slide, thereby effectively adjusting the support height of each pipe body unit 1, so that multiple pipe body units 1 can be located at the same installation height, and the support base 30 is placed in the uneven pipeline burying trench, thereby improving the support stability of the pipeline unit and making the pipe body unit 1 more convenient to connect.
[0035] Reference Figure 1 and Figure 2 In this embodiment, the height adjustment component 4 includes a rotating screw sleeve 40 and a rotating screw rod 41. First, the rotating screw sleeve 40 is rotatably connected to the support base 30 through a bearing, and then the rotating screw rod 41 is fixedly connected to the end of the support rod body 31 away from the guide ring 2, and the rotating screw rod 41 is threadedly connected in the rotating screw sleeve 40. Finally, a limit piece is provided on the rotating screw 41 to limit the rotating screw 41 from rotating around the rotating screw sleeve 40.
[0036] When in use, after the support base 30 is placed in the pipeline buried trench to support the pipe body unit 1, the rotating sleeve 40 is driven to rotate, so that the rotating screw 41 drives the supporting rod body 31 to produce a relative rotation trend. At this time, under the restriction of the limiter, the rotating screw 41 drives the supporting rod body 31 to slide linearly, thereby effectively adjusting the installation height of the pipe body unit 1, so that adjacent pipe body units 1 are aligned, and the convenience of docking installation is improved.
[0037] Reference Figure 1 and Figure 2 In this embodiment, the limiting member includes a limiting block 50, which is fixedly connected to the end of the rotating screw 41. Then, a guide hole 51 is opened on the support base 30, and a limiting slot 52 is opened on the inner wall of the guide hole 51. The rotating screw 41 passes through the rotating screw sleeve 40 and extends into the guide hole 51, and the limiting block 50 is clamped in the limiting slot 52. When the rotating screw sleeve 40 is rotated, the limiting block 50 will have a tendency to slide relatively in the limiting slot 52, thereby effectively limiting the rotation of the rotating screw 41, so that the rotating screw 41 and the support rod body 31 drive the upper tube unit 1 of the guide ring 2 to adjust the height; and in order to conveniently rotate the rotating screw sleeve 40, a plurality of rotating handles 6 are also arranged on the outer wall of the rotating screw sleeve 40. At that time, no other tools are needed, and the worker can just apply a little force to the rotating handle 6, which is convenient to operate.
[0038] Reference Figure 1 and Figure 2In this embodiment, since the pipe unit 1 can improve the transportation stability through the support of the support rod 3, the support base 30 abuts against the bottom wall of the vehicle box of the transport vehicle when the pipe unit 1 is transported; therefore, in order to improve the stability of the support base 30, an anti-skid pad 9 is provided at the bottom of the support base 30, and the anti-skid pad 9 reduces the sliding of the support base 30 during the transportation of the pipe unit 1. In addition, when the support base 30 is placed in the pipeline burying trench, the anti-skid pad 9 is elastic, so that it can effectively adapt to the uneven ground in the pipeline burying trench, further improving the support stability of the pipe unit 1, with a simple structure and high practical value.
[0039] The implementation principle of a docking and lifting mechanism for pipeline installation in an embodiment of the present application is as follows: by movably sleeved the guide ring 2 on both ends of the pipe body unit 1, and then using the lifting ring 8 and the crane to lower the pipe body unit 1 into the pipeline burying trench, at this time, the support base 30 and the support rod body 31 effectively provide support for the pipe body unit 1, and further use the rotating handle 6 to rotate the rotating sleeve 40 to drive the rotating screw 41 and the support rod body 31 to produce a relative rotation trend, and then the limit block 50 slides in the limit groove, effectively allowing the rotating screw 41 and the support rod body 31 to drive the vertical displacement of the pipe body unit 1 together, thereby adjusting the installation height of the pipe body unit 1, so that the pipe body units 1 are at the same height, making docking more convenient and accurate, and the operation is also time-saving and labor-saving.
[0040] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A butt lifting mechanism for pipeline installation, characterized in that: include: A guide ring (2) movably mounted on both ends of the tube unit (1) and a support rod (3) connected to the guide ring (2), wherein the support rod (3) is provided with a height adjustment component (4), and the height adjustment component (4) is used to adjust the support height of the support rod (3) on the tube unit (1); The support rod (3) comprises a support base (30) and a support rod body (31) slidably connected to the support base (30); the guide ring (2) is fixedly connected to one end of the support rod body (31) away from the support base (30); the sliding direction of the support rod body (31) is consistent with the axial direction of the support rod body (31); the height adjustment component (4) is arranged on the support base (30); and the height adjustment component (4) is used to drive the support rod body (31) to slide.
2. A butt-jointed lifting mechanism for pipeline installation according to claim 1, characterized in that: The height adjustment assembly (4) comprises a rotating screw sleeve (40) and a rotating screw rod (41); the rotating screw sleeve (40) is rotatably connected to the support base (30); the rotating screw rod (41) is fixedly connected to one end of the support rod body (31) away from the guide ring (2); the rotating screw rod (41) is threadedly connected in the rotating screw sleeve (40); and a limiting member for limiting the rotating screw rod (41) from rotating around the rotating screw sleeve (40) is also provided on the rotating screw rod (41).
3. A butt-jointed lifting mechanism for pipeline installation according to claim 2, characterized in that: The limiting member comprises a limiting block (50), the limiting block (50) is fixedly connected to the end of the rotating screw (41), a guide hole (51) is provided on the support base (30), a limiting sliding groove (52) is provided on the inner wall of the guide hole (51), the rotating screw (41) passes through the rotating screw sleeve (40) and extends into the guide hole (51), and the limiting block (50) is clamped in the limiting sliding groove (52).
4. A butt-jointed lifting mechanism for pipeline installation according to claim 2, characterized in that: A plurality of rotating handles (6) are arranged on the outer wall of the rotating screw sleeve (40).
5. The butt-jointed lifting mechanism for pipeline installation according to claim 1, characterized in that: A plurality of balls (7) are rotatably connected to the inner wall of the guide ring (2).
6. A butt-jointed lifting mechanism for pipeline installation according to claim 1, characterized in that: The top of the guide ring (2) is fixedly connected with a lifting ring (8).
7. A butt-jointed lifting mechanism for pipeline installation according to claim 1, characterized in that: An anti-slip pad (9) is provided at the bottom of the support base (30).