Pipe gallery engineering installation stabilizing structure
By designing flexible top layer, shock absorbing spring and support structure in the pipeline gallery project, the problems of poor stability and poor shock absorption at docking in the existing technology are solved, and the stable fixation and shock absorption effect of pipes of different diameters are achieved. The improvement avoids the settlement of the pipe corridor and simplifies the construction process.
Patent Information
- Application Number
- CN202420427808.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-06
AI Technical Summary
The solidification effect of the docking of the prefabricated parts of the existing pipeline project is poor, and the overall shock absorption and buffering effect is poor, making it easy to settle the pipeline body.
A tube is designed including a mounting frame body, a flexible top layer, a shock absorbing spring, an upper positioning clip, a left positioning clip, a right positioning clip, a fixed bottom support, an adjustment bolt, a force-sharing rod, a first support seat and a second support seat The corridor project has a stable structure, and the upper positioning clamp moves through the telescopic and contraction of the shock absorbing spring, adjust the angle of the positioning clamp, combines the support of the support seat and the force-partitioning rod to achieve adaptive fixation to pipes of different diameters, and passes the card of the connecting seat Joining enhances structural stability.
The stable fixation of pipes of different diameters is achieved, and the compression resistance and service life of the overall structure is improved. At the same time, the shock absorption effect is enhanced through shock absorption springs and support structures, avoiding the settlement of the pipe corridor and saving on-site construction time. .
Smart Images

Figure CN222103102U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipe gallery engineering, in particular to a stable installation structure for pipe gallery engineering. Background Art
[0002] A pipe gallery refers to a place in which many pipelines in chemical and related factories are concentrated together and arranged along the outside of the equipment or factory buildings. It is usually in the air and supported by brackets to form a corridor-like appearance. There are also large-scale equipment pipes laid underground. It is composed of steel or reinforced concrete columns, beams and trusses.
[0003] There are two main construction methods for the installation of existing pipeline corridors. The first is to pour concrete on site, and the second is to cast the corridor in advance and then assemble it at the construction site. The existing pipeline corridor installation has poor stability at the joints when the stable structural prefabricated parts are spliced up and down, and the overall shock-absorbing and buffering effect is not good, which makes it easy for the corridor to sink.
[0004] Therefore, in view of this, the existing structure and deficiencies are studied and improved, and a stable structure for the installation of the pipeline corridor project is proposed. Utility Model Content
[0005] The purpose of the utility model is to provide a stable structure for installing a pipe gallery project to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a stable installation structure for a pipe gallery project, comprising a mounting frame body and a pipeline, the top of the mounting frame body is fixedly connected with a flexible top layer, and the top inner wall of the mounting frame body is fixedly connected with a shock-absorbing spring, the bottom end of the shock-absorbing spring is provided with an upper positioning clamp, the pipeline is provided on the bottom outer wall of the upper positioning clamp, and the left outer wall of the pipeline is connected with a left positioning clamp, the right outer wall of the pipeline is provided with a right positioning clamp, and the bottom outer wall of the pipeline is connected with a fixed bottom support.
[0007] Furthermore, the outer walls of the left positioning clamp and the right positioning clamp are both provided with adjustment bolts, and the side outer walls of the adjustment bolts are connected with force component rods.
[0008] Furthermore, a first support seat is fixed to the bottom outer wall of the adjusting bolt, and a second support seat is provided on the bottom outer wall of the fixed base.
[0009] Furthermore, the bottom outer walls of the first support seat and the second support seat are connected to the bottom inner wall of the mounting frame body, and the top outer wall height of the first support seat is higher than the top outer wall height of the second support seat.
[0010] Furthermore, the left outer wall and the right outer wall of the mounting frame body are both provided with a first extension seat, and the height of the bottom outer wall of the first extension seat is consistent with the height of the bottom outer wall of the mounting frame body.
[0011] Furthermore, the internal threads of the first extension seat are connected with reinforcement bolts, and the reinforcement bolts are symmetrically distributed with the vertical center axis of the mounting frame body as the symmetry axis.
[0012] Furthermore, a first connecting seat is provided on the front outer wall of the mounting frame body, and a second connecting seat is fixed on the rear outer wall of the mounting frame body.
[0013] Furthermore, the outer wall of the first connecting seat is adapted to the outer wall of the second connecting seat, and connecting bolts are provided inside the first connecting seat and the second connecting seat.
[0014] The utility model provides a stable installation structure for a pipe gallery project, which has the following beneficial effects:
[0015] 1. The pipeline corridor project is installed with a stable structure. The shock-absorbing spring is squeezed by pipes of different diameters to produce expansion and contraction and rebound, which drives the position of the upper positioning clamp to move, so as to adapt to pipes with different diameters. Pressure is applied directly above it, and the rotation angle of the left and right positioning clamps is adjusted. The adjusting bolt is tightened to fix the position of the left and right positioning clamps, so as to adjust the contact angle of the left and right positioning clamps with the pipe according to the diameter of the pipe, and pressure is applied to the left and right sides to fix the bottom support to support the pipe.
[0016] 2. The tunnel project has a stable installation structure. The first connecting seat is matched with the second connecting seat. The first connecting seat connected to the outer wall of one mounting frame body is aligned with the second connecting seat connected to the outer wall of another mounting frame body, and the two are connected by snapping. The splicing is convenient, and the on-site construction time is saved, which is convenient for the rapid recovery of the road above the tunnel. The connecting bolts are then nailed into the holes of the first connecting seat and the second connecting seat that are matched with them to enhance the stable connection at the connection node. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a front view structural diagram of a stable structure for installing a pipe gallery project according to the utility model;
[0018] Figure 2 This is a side view structural diagram of a stable structure for installing a pipe gallery project according to the utility model;
[0019] Figure 3 It is a schematic diagram of the three-dimensional structure of a first connecting seat of a stable structure for installing a pipe gallery project according to the utility model.
[0020] In the figure: 1. Mounting frame body; 2. Flexible top layer; 3. Shock-absorbing spring; 4. Upper positioning clamp; 5. Pipeline; 6. Left positioning clamp; 7. Right positioning clamp; 8. Fixed base; 9. Adjustment bolt; 10. Force dividing rod; 11. First supporting seat; 12. Second supporting seat; 13. First extension seat; 14. Reinforcement bolt; 15. First connecting seat; 16. Second connecting seat; 17. Connecting bolt. DETAILED DESCRIPTION
[0021] The following is a further detailed description of the implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but cannot be used to limit the scope of the present invention.
[0022] like Figure 1-Figure 3 As shown, a stable installation structure for a pipe gallery project includes a mounting frame body 1 and a pipe 5, the top of the mounting frame body 1 is fixedly connected with a flexible top layer 2, and the top inner wall of the mounting frame body 1 is fixedly connected with a shock-absorbing spring 3, the bottom end of the shock-absorbing spring 3 is provided with an upper positioning clamp 4, the pipe 5 is arranged on the bottom outer wall of the upper positioning clamp 4, and the left outer wall of the pipe 5 is connected with a left positioning clamp 6, the right outer wall of the pipe 5 is provided with a right positioning clamp 7, and the bottom outer wall of the pipe 5 is connected with a fixed bottom bracket 8, and the outer walls of the left positioning clamp 6 and the right positioning clamp 7 are both provided with adjustment bolts 9, and the adjustment bolts 9 are provided on the outer walls of the left positioning clamp 6 and the right positioning clamp 7. The side outer wall of the whole bolt 9 is connected with a force component rod 10, the bottom outer wall of the adjustment bolt 9 is fixed with a first support seat 11, the bottom outer wall of the fixed bottom bracket 8 is provided with a second support seat 12, the bottom outer walls of the first support seat 11 and the second support seat 12 are connected with the bottom inner wall of the mounting frame body 1, and the top outer wall height of the first support seat 11 is higher than the top outer wall height of the second support seat 12, the left outer wall and the right outer wall of the mounting frame body 1 are both provided with a first extension seat 13, and the bottom outer wall height of the first extension seat 13 is consistent with the bottom outer wall height of the mounting frame body 1;
[0023] The specific operation is as follows: the mounting frame body 1 is placed in the leveled foundation pit, the pipe 5 is installed inside the mounting frame body 1, and the upper, lower, left and right outer walls of the pipe 5 are respectively attached to the upper positioning clip 4, the fixed bottom bracket 8, the left positioning clip 6 and the right positioning clip 7. The top of the flexible top layer 2 is in an arc shape, which can disperse the pressure, increase the pressure resistance of the mounting frame body 1, and increase the service life of the mounting frame body 1;
[0024] The shock absorbing spring 3 connects the mounting frame body 1 and the upper positioning clamp 4, and plays a certain buffering role. The shock absorbing spring 3 is squeezed by the pipes 5 of different diameters to produce expansion and contraction and rebound, thereby driving the position of the upper positioning clamp 4 to move, so as to adapt to the pipes 5 of different diameters and exert pressure on the upper part thereof;
[0025] The left positioning clamp 6 and the right positioning clamp 7 can rotate around the top of the first support seat 11, the adjustment bolt 9 connects the left positioning clamp 6 and the first support seat 11, the adjustment bolt 9 connects the right positioning clamp 7 and the first support seat 11, the rotation angle of the left positioning clamp 6 and the right positioning clamp 7 is adjusted, the adjustment bolt 9 is tightened, and the positions of the left positioning clamp 6 and the right positioning clamp 7 are fixed, so as to adjust the contact angle of the left positioning clamp 6 and the right positioning clamp 7 with the pipe 5 according to the diameter of the pipe 5, and apply pressure to the left and right sides thereof;
[0026] The first support seat 11 supports the bottom of the left positioning clamp 6, the right positioning clamp 7 and the adjusting bolt 9, the force dividing rod 10 supports the side of the left positioning clamp 6, the right positioning clamp 7 and the adjusting bolt 9, the second support seat 12 supports the fixed bottom bracket 8, and the fixed bottom bracket 8 supports the pipeline 5;
[0027] like Figure 1-Figure 3 As shown, the inner thread of the first extension seat 13 is connected with a reinforcing bolt 14, and the reinforcing bolt 14 is symmetrically distributed with the vertical central axis of the mounting frame body 1 as the symmetry axis, the front outer wall of the mounting frame body 1 is provided with a first connecting seat 15, and the rear outer wall of the mounting frame body 1 is fixed with a second connecting seat 16, the outer wall of the first connecting seat 15 is adapted to the outer wall of the second connecting seat 16, and the first connecting seat 15 and the second connecting seat 16 are provided with connecting bolts 17 inside;
[0028] The specific operation is as follows: by screwing the reinforcing bolt 14 into the interior of the first extension seat 13, and then the bottom of the reinforcing bolt 14 enters the interior of the construction ground, the position of the mounting frame body 1 is fixed, and the first connecting seat 15 is adapted to the second connecting seat 16. By aligning the first connecting seat 15 connected to the outer wall of one mounting frame body 1 with the second connecting seat 16 connected to the outer wall of another mounting frame body 1, the two are snap-connected, which is convenient for splicing and saves on-site construction time, and is convenient for the rapid recovery of the road above the pipe gallery. Then, the connecting bolt 17 is nailed into the holes of the first connecting seat 15 and the second connecting seat 16 that are adapted to them. When the bottom of the connecting bolt 17 is drilled into the interior of the construction ground, the positions of the first connecting seat 15 and the second connecting seat 16 are fixed, thereby enhancing the stable connection at the connection node.
[0029] In summary, if Figure 1-Figure 3As shown, the pipe gallery project has a stable installation structure. When in use, first put the mounting frame body 1 into the leveled foundation pit, and the pipe 5 is installed inside the mounting frame body 1. The upper, lower, left and right outer walls of the pipe 5 are respectively attached to the upper positioning clamp 4, the fixed bottom bracket 8, the left positioning clamp 6 and the right positioning clamp 7. The top of the flexible top layer 2 is in an arc shape, which can disperse the pressure. The shock-absorbing spring 3 connects the mounting frame body 1 and the upper positioning clamp 4. The shock-absorbing spring 3 is squeezed by the pipes 5 of different diameters to produce expansion and contraction and rebound, which drives the position of the upper positioning clamp 4 to move and compress the pipe 5 directly above. force, adjust the rotation angle of the left positioning clamp 6 and the adjusting bolt 9, tighten the adjusting bolt 9, fix the position of the left positioning clamp 6 and the adjusting bolt 9, so as to adjust the contact angle of the left positioning clamp 6 and the adjusting bolt 9 with the pipe 5 according to the diameter of the pipe 5, and apply pressure to the left and right sides thereof, the first support seat 11 supports the bottom of the left positioning clamp 6, the right positioning clamp 7 and the adjusting bolt 9, the force dividing rod 10 supports the side of the left positioning clamp 6, the right positioning clamp 7 and the adjusting bolt 9, the second support seat 12 supports the fixed bottom bracket 8, and the fixed bottom bracket 8 supports the pipe 5;
[0030] The position of the mounting frame body 1 is fixed by screwing the reinforcing bolt 14 into the first extension seat 13, and then the bottom of the reinforcing bolt 14 enters into the construction ground. The first connecting seat 15 connected to the outer wall of one mounting frame body 1 is aligned with the second connecting seat 16 connected to the outer wall of another mounting frame body 1, and the two are snap-connected. Then the connecting bolt 17 is nailed into the holes of the first connecting seat 15 and the second connecting seat 16 that are adapted to them. When the bottom of the connecting bolt 17 is drilled into the construction ground, the position of the first connecting seat 15 and the second connecting seat 16 is fixed.
[0031] The embodiments of the present invention are provided for the purpose of illustration and description, and are not intended to be exhaustive or to limit the present invention to the disclosed forms. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described to better illustrate the principles and practical applications of the present invention, and to enable those of ordinary skill in the art to understand the present invention and thereby design various embodiments with various modifications suitable for specific uses.
Claims
1. A stable structure for installing a pipe gallery project, comprising a mounting frame body (1) and a pipe (5), Features: The top of the mounting frame body (1) is fixedly connected to a flexible top layer (2), and the top inner wall of the mounting frame body (1) is fixedly connected to a shock-absorbing spring (3), the bottom end of the shock-absorbing spring (3) is provided with an upper positioning clamp (4), the pipe (5) is provided on the bottom outer wall of the upper positioning clamp (4), and the left outer wall of the pipe (5) is connected to a left positioning clamp (6), the right outer wall of the pipe (5) is provided with a right positioning clamp (7), and the bottom outer wall of the pipe (5) is connected to a fixed bottom bracket (8).
2. A stable structure for installing a pipe gallery project according to claim 1, Features: The outer walls of the left positioning clamp (6) and the right positioning clamp (7) are both provided with adjustment bolts (9), and the side outer walls of the adjustment bolts (9) are connected with force distribution rods (10).
3. A pipe gallery engineering installation stabilization structure according to claim 2, Features: A first support seat (11) is fixed to the bottom outer wall of the adjustment bolt (9), and a second support seat (12) is provided on the bottom outer wall of the fixed base (8).
4. A stable structure for installing a pipe gallery project according to claim 3, Features: The bottom outer walls of the first support seat (11) and the second support seat (12) are connected to the bottom inner wall of the mounting frame body (1), and the top outer wall height of the first support seat (11) is higher than the top outer wall height of the second support seat (12).
5. According to claim 1, a stable structure for installing a pipe gallery project, Features: The left outer wall and the right outer wall of the mounting frame body (1) are both provided with a first extension seat (13), and the height of the bottom outer wall of the first extension seat (13) is consistent with the height of the bottom outer wall of the mounting frame body (1).
6. A stable structure for installing a pipe gallery project according to claim 5, Features: The first extension seat (13) is internally threadedly connected with a reinforcing bolt (14), and the reinforcing bolts (14) are symmetrically distributed with the vertical center axis of the mounting frame body (1) as the symmetry axis.
7. A pipe gallery engineering installation stabilization structure according to claim 1, Features: A first connection seat (15) is provided on the front outer wall of the mounting frame body (1), and a second connection seat (16) is fixed on the rear outer wall of the mounting frame body (1).
8. A pipe gallery engineering installation stabilizing structure according to claim 7, Features: The outer wall of the first connecting seat (15) is matched with the outer wall of the second connecting seat (16), and connecting bolts (17) are arranged inside the first connecting seat (15) and the second connecting seat (16).